Update on Hangar One by Bryce Bartelma at the August 9, 2012, meeting of the Moffett Restoration Advisory Board.

Published in: Education, Technology, Business
  • Be the first to comment

  • Be the first to like this

Moffett RAB Hangar One Update

  1. 1. Former NAS Moffett FieldHangar 1 Removal Action Update Bryce Bartelma, PG Navy BRAC PMO West August 9, 2012 RAB Meeting 1
  2. 2. Project Objective• Control release of PCBs from Hangar 1 in accordance with EE/CA (July 2008) and Action Memorandum (December 2008)  Demolition of interior structures  Removal of contaminated siding  Application of weather-resistant coating to steel frame 2
  3. 3. Continued Monitoring and Protection Measures• Continued biological activity and nesting deterrents• Maintain storm water and ground surface protection• Navy and NASA air monitoring data demonstrates control of air emissions 3
  4. 4. April 2012 4
  5. 5. July 2012 5
  6. 6. Final Material Removed – July 19, 2012 6
  7. 7. Fixing the Holiday Star • Replacement of electrical components 7
  8. 8. Remaining Tasks • Scaffolding deconstruction • Mezzanine prep and coat • Final touch ups, cleaning and surface soil removal 8
  9. 9. Schedule• Complete Fieldwork and Deconstruct Scaffolding October 2012• Final Cleaning and Demobilize November 2012• Submit After Action Completion Report Winter/Spring 2013 9
  10. 10. Hangar 1 Interactive CD CLICK HERE FOR DEMO 10
  11. 11. Questions? Point of Contact: Scott Anderson BRAC Environmental Coordinator (619) 532-0938 scott.d.anderson@navy.mil 11

×