Presentation-IRS Housing Project

8,518 views

Published on

Presentation in respect of IRS Towers, the Housing Project of IRS (Mumbai) Housing Cooperative Society made by the Developer Integrated Spaces Ltd. in the GBM on 27-02-09

Published in: Business, Technology, Real Estate
0 Comments
4 Likes
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total views
8,518
On SlideShare
0
From Embeds
0
Number of Embeds
82
Actions
Shares
0
Downloads
245
Comments
0
Likes
4
Embeds 0
No embeds

No notes for slide

Presentation-IRS Housing Project

  1. 1. P R O J E C T IRS HOUSING COMPLEX, ON PLOT NO. 6, 7 & 8 AT ULWE NODE, NAVI MUMBAI. PROJECT BY SHAH CONSTRUCTION CO. 24/A, Shree Laxmi Nivas, M. G. Road, Ghatkopar (West), Mumbai 400 086 Now Renamed as
  2. 2. LOCATION PLAN
  3. 3. LOCATION – I : PLOT NO. 6, 7 & 8, LOCATION – II : PLOT NO. 80 & 81, LOCATION– III : Plot No. 78, 79, 82, 83 & 41.
  4. 4. DESIGN PROCESS...............
  5. 5. B R I E F : 1 . Wing A & B Stilt + 10 Stories, 4 flats per floor, Total number of flats 80 nos. 2. Wing C Stilt + 4 Stories, 2 flats per floor, Total number of flats 8 nos. OR up to Utilization of 1.50 F.S.I. Whichever is higher. (With provision to consumed 2.00 F. S. I. in future). 3. Total 88 nos. of flats in Wing A, B & C. 4 . Each flat 1007.00 sq. ft. of Carpet area, 3 bedrooms with three toilets. 5 . Gymnasium, Society Office and Meeting Room at Basement Floor Level. 6. Entrance lobby at stilt level. 7. Party terrace with gents & ladies toilets & pantry in Wing A & B. 8. Elec. Substation, Generator room & Security cabin at ground level. 9. Refuge floor on 4 th , 6 th & 8 th floor.
  6. 7. L A Y O U T P L A N SUB STATION GENERATOR ROOM UG TANK, PUMP ROOM & RAIN WATER HARVESTING TANK SECURITY - 1 SECURITY - 2
  7. 8. BASEMENT FLOOR PLAN – ALT. - 1 BASEMENT FLOOR PLAN WING - C WING - A WING - B
  8. 9. TYPICAL FLOOR PLAN (1 st , 3 rd , 5 th , 7 th AND 9th)
  9. 10. TYPICAL FLOOR PLAN (2 nd , AND 10 th )
  10. 11. TYPICAL FLOOR PLAN (4 th , 6 th , AND 8 th )
  11. 12. TERRACE FLOOR PLAN
  12. 13. Post Occupation Plan (8 Entrance Doors )
  13. 14. WING – C ( provision to consume 2.00 F. S. I. in future). WING - C WING - A WING - B
  14. 15. On Gudipadva Both IRS (Mumbai) & Integrated Spaces Ltd. Jointly organized a BHOOMI-POOJAN at Ulwe Node Site for IRS tower I & II.
  15. 20. MOU Signed by IRS (Mumbai) Housing Society for IRS Tower being constructed by Integrated Spaces Ltd. Floor wise Carpet & Built-up Area For Building Wing A proposed on Plot No.6,7&8 along with landing cost to the Flat Purchaser MOU Spread Sheet
  16. 21. P R O J E C T IRS TOWER - I IRS HOUSING COMPLEX, ON PLOT NO. 6, 7 & 8 AT ULWE NODE, NAVI MUMBAI. P R O J E C T B Y Thank You.

×