SlideShare a Scribd company logo
1 of 12
Regulations, Supply Rules and Standards of Electricity
Compiled By :
M.G. Wath
EET, MSEDCL, Nagpur

The Indian Electricity Act, 1910
•
Provided basic framework for electric supply industry in India
•
Growth of the sector through licensees. Licence by State Govt.
•
Provision for licence for supply of electricity in a specified area
•
Legal framework for laying down of wires and other works
•
Provisions laying down relationship between licensee and consumer
The Electricity (Supply) Act, 1948
•
Mandated creation of SEBs
•
Need for the State to step in (through SEBs) to extend electrification (so far
limited to cities) across the country.
Inability of the SEB’s to take the decision on tariff in a professional and
independent manner, which in fact was done by the State Government.
The Electricity Regulatory Commission Act, 1998
• Provision for setting up of Central / State Electricity Regulatory Commission with
powers to determine tariffs
• Constitution of SERC optional for States
• Distancing of Government from tariff determination
The Electricity Conservation Act, 2001
• This act provides legal frame work and Institutional arrangement for embarking
on energy efficiency drive.
• BEE have been established wef 01.03.2002 by merging Energy management
centre of Ministry of power.
• BEE is responsible for implementing the policies of energy conservation activity.
Electricity Act, 2003 - notified on 10th June ‘03
The main objective of EA 2003 are Competition in power generators, Protection of
Consumers interests & provision of Power for all Areas
The main features of EA 2003 are :--





Creates liberal framework for power development
Creates competitive environment
Facilitates private investment
Delicenses generation except for hydro : Captive free from controls
Rural Areas : Stand alone Generation and
Distribution delicenced
 Multiple licensing in Distribution
1





Stringent provisions for controlling theft of electricity
Focus on revenue recovery in cases of unauthorized use of electricity
Obliges States to restructure Electricity Boards
Mandates creation of Regulatory Commissions. Retail tariff to be determined by
regulatory commissions
 Open access in Transmission from outset
 Open access in Distribution to be allowed by SERCs in phases
 Gradual phasing out of cross subsidies

Generation
Any GENCO may establish, operate and maintain a Gen- station without a licence by
complying with the technical standards relating to connectivity with the Grid. Captive
Generation plant should have to use the generation for its own. If there is the another
consumer for utilization of the energy generated by CPP or CGP then the condition is that the
user should have a share of more than 26% in CPP. Second condition is that, more than the
51% of the energy generated is to be utilized for its own or by user who have share in CPP.

For Captive Generation freed:
No license required
Right to open access from plant to destination
“Captive generating plant means a power plant set up by any person to generate
electricity primarily for his own use and includes a power plant set up by any cooperative society or association of persons for generating electricity primarily for
use of members of such co-operative society or association.”
Trading distinct activity permitted with licensing
A person may construct, maintain or operate a CGP and dedicated transmission lines
provided ---1) That the supply of electricity power the CGP through the Grid shall be regulated in the
same manner as the generating station of a generating company.
2) No license will be required for supply of electric generated power a CGP to any license
and to any consumer subject to the regulations made under Sub-Section (2) of Sect.42 .
3) A CGP shall have the right to open access for the purpose of carrying electricity from the
CGP to the destination of use.
4) Open access shall be subject to availability of adequate transmission facility.
Duties of a Generating Company :• To establish, maintain & operate generating stations tie-lines and dedicated
transmission lines.
• The Appropriate Commission may in `extra ordinary circumstances’ give directions to a
generating company to operate and maintain any generating station in accordance with
the directions of the Govt. ‘Extraordinary’ means circumstances arising out of threat to
security of the State, public order or a natural calamity or such other circumstance
arising in public interest.
2
Transmission: Requirment of the Transmission company are ---– License from ERC for transmission
– CTU/STU shall be deemed transmission license (14 proviso)
– National Load Despatch Centre
– Regional Load Despatch Centre, RLDC, will be set up by Central Govt. for each
region
– RLDC/SLDC will be a Govt. company/authority
– SLDC shall comply with the direction of RLDC
– Every licensee, Genco, Gen. station, Sub-station shall comply with the directions
issued by SLDC
– Non Discriminatory open access
– Appropriate Govt. can give direction to RLDC/SLDC for maintaining smooth &
stable supply of electricity.
– Central Govt. to make region – wise demarcation of the country.
– Efficient, economical and integrated transmission.
– To develop voluntary inter-connections and co-ordination facilities for interstate, regional and inter-regional generation and transmission of electricity

National Load Despatch Centre :-- (NLDC)
• Centre to set up a NLDC for optimum scheduling despatch of electricity among the
RLDC’s ( Regional Load Despatch centre)
• The NLDC shall not engage in the business of trading of electricity.
• The NLDC shall be operated by a Govt. Co. or any Authority or Corporation established
under any Central Act.
Regional Load Despatch Centre :-- (RLDC)
• RLDC to be the apex body to ensure integrated operation of power system in the region.
• RLDC shall be operated by a Govt. company or Authority or Corporation.
• RLDC shall engage in the business of generation of electricity or trading in electricity
Functions of RLDC :_
• It will be the apex body to ensure integrated operations of the power system.
• Responsible for the optimum scheduling and dispatch of electricity with in region.
• Monitor grid operations
• Keep account of quantity of electricity transmitted through the regional grid.
• Supervision over Inter-State transmission system.
• Ensure secure and economic operation of the regional grid in accordance with the Grid
standards and Grid operations.
• The RLDC may levy and collect such fee and charges from generating Co. or licensees
engaged in inter-state transmission of elec. as may be specified by the central Govt.

3
Functions of the Central Transmission Utility:
I)
To transmit elec. Through inter-state transmission systems.
II)
To discharge all functions of planning and co-ordination relating to inter-state
transmission system with
a) State Transmission Utilities.
b) Central Govornment
c) Generating Company.
d) Regional power Committees.
III) To ensure development of an efficient, Co-ordinated and economical system of inter-state
transmission lines for smooth flow of electricity from generating stations to the load centers’.
IV) To provide non-discriminatory open access to its transmission system for use by
a) Any licensee or generating Co. on payment of the transmission Charges.
b) Any Consumer, as and when open access is provided, on payment of the
transmission charges and a surcharge thereon.
V) Sur-charge shall be utilized for meeting the requirement of current level of cross-subsidy.
VI) Sur-charge shall not be leviable in case open-access is provided to a person who has
established a CGP for carrying the electricity to the destination of his own use.
Intrastate Transmission :• Transmission within the State
• The State Commission shall establish SLDC for same functions as RLDC
• The SLDC shall be operated by a Govt. Co. or authority or Corporation established under
any State Act. as may be notified by the State Govt.
• Till such time, the State Transmission Utility shall operate as the SLDC.
• No SLDC shall engage in the business of Trading in electricity.

Distribution
– License from ERC necessary for distribution & trading of electricity
--- ERC on recommendation of Govt. may exempt any local body panchayat, co-op.
society, NGO from license requirement
– Open access to be introduced by state commission in such phases
– No surcharge for open access to captive plant
– Where ERC has allowed open access under Section 42, such consumers may
enter into a PPA on such terms and conditions (including tariff) as may be agreed
upon by them.
– Open access shall be provided to all consumers who required supply which
exceeds 1MW at any time.
– Forum to establish for redressal of consumer grievances.
– Consumer may file appeal to Ombudsman.
4
Main functions of CERC
Regulate tariff of generating companies owned/ controlled by Central government.
Regulate inter State transmission of electricity and determine their tariff , to regulate
the tariff of other generating companies other than Govt. owned / controlled
companies, if such companies have a composite schemes for generation and sale of
electricity in more than one State
CERC Adjudicate upon disputes involving generating companies or transmission
licensees for above. It also Specify and enforce standards for quality, continuity and
reliability of services by licensees.
Main functions of SERCs
• Determine tariff for generation, supply transmission and wheeling of electricity :
wholesale / bulk / rental/ within the State
• Regulate electricity purchase and procurement process of distribution licensees
including the price for distribution and supply within the State
• Adjudicate upon disputes between licensees and generating companies for above
• Specify and enforce standards for quality, continuity and reliability of services by
licensees
Appellate Tribunal
•
Appeal can be made to the Appellate Tribunal on order of adjudicating officer or ER.
•
Summoning & examining a person
• Requiring discovery & production of documents
• Receiving evidence on affidavits
• Issuing commissions
• Powers of Civil Court
• The Appeal Tribunals shall not be bound by the procedure laid down by the CPCshall be guided by the principles of the natural justice.

Clauses of Electricity Act 2003
LICENSING
Clause No 12. No person shall
(a) transmit electricity; or (b) distribute electricity; or (c) undertake trading in electricity,
unless he is authorised to do so by a licence issued under section 14, or is exempt under
section 13.
Clause No 13.
The Appropriate Commission may, on the recommendations, of the Appropriate Government,
in accordance with the national policy formulated undersection 5 and in public interest, direct,
by notification that subject to suchconditions and restrictions, if any, and for such period or
5
periods, as may bespecified in the notification, the provisions of section 12 shall not apply to
any localauthority, Panchayat Institution, users’ association, co-operative societies,
nongovernmental organizations, or franchisees:

Clause No 14.
The Appropriate Commission may, on application made to it undersection 15, grant any person
licence to any person –
(a) to transmit electricity as a transmission licensee; or
(b) to distribute electricity as a distribution licensee; or
(c) to undertake trading in electricity as an electricity trader,in any area which may be specified
in the licence:
Provided that any person engaged in the business of transmission orsupply of electricity under
the provisions of the repealed laws or any Act specifiedin the Schedule on or before the
appointed date shall be deemed to be a licenseeunder this Act for such period as may be
stipulated in the licence, clearance orapproval granted to him under the repealed laws or such
Act specified in the Schedule, and the provisions of the repealed laws or such Act specified in
the Schedule in respect of such licence shall apply for a period of one year from thedate of
commencement of this Act or such earlier period as may be specified, atthe request of the
licensee, by the Appropriate Commission and thereafter the provisions of this Act shall apply to
such business:
Provided further that the Central Transmission Utility or the StateTransmission Utility shall be
deemed to be a transmission licensee under this Act:
Provided also that in case an Appropriate Government transmits electricity or distributes
electricity or undertakes trading in electricity, whether before or after the commencement of
this Act, such Government shall be deemed to be a licensee under this Act, but shall not be
required to obtain a licence under this Act:
Provided also that the Damodar Valley Corporation, established undersub-section (1) of section
3 of the Damodar Valley Corporation Act, 1948, shall bedeemed to be a licensee under this Act
but shall not be required to obtain a licence under this Act and the provisions of the Damodar
Valley Corporation Act, 1948, in so far as they are not inconsistent with the provisions of this
Act, shall continue to apply to that Corporation:
Provided also that the Government company or the company referred to in sub-section (2) of
section 131 of this Act and the company or companies created in pursuance of the Acts
specified in the Schedule, shall be deemed to be a licensee under this Act:
Provided also that the Appropriate Commission may grant a licence to two or more persons for
distribution of electricity through their own distribution system
within the same area, subject to the conditions that the applicant for grant of licence
Procedure for Grant of Licence within the same area, subject to the conditions
that the applicant for grant of licence within the same area shall, without prejudice to the other
conditions or requirements under this Act, comply with the additional requirements (including
6
the capital adequacy, credit-worthiness, or code of conduct) as may be prescribed by the
Central Government, and no such applicant who complies with all the requirements for grant of
licence, shall be refused grant of licence on the ground that there already exists a licensee in
the same area for the same purpose: Provided also that in a case where a distribution licensee
proposes to undertake distribution of electricity for a specified area within his area of supply
through another person, that person shall not be required to obtain any separate licence from
the concerned State Commission and such distribution licensee shall be responsible for
distribution of electricity in his area of supply:
Provided also that where a person intends to generate and distribute
electricity in a rural area to be notified by the State Government, such person shall
not require any licence for such generation and distribution of electricity, but he
shall comply with the measures which may be specified by the Authority under
section 53:
Provided also that a distribution licensee shall not require a licence to
undertake trading in electricity.

Clause No 15.
(1) Every application under section 14 shall be made in such form and in such manner as
may be specified by the Appropriate Commission and shall be accompanied by such fee as may
be prescribed.
(2) Any person who has made an application for grant of licence shall, within seven days after
making such application, publish a notice of his application with such particulars and in such
manner as may be specified and a licence shall not be granted (i) until the objections, if any, received by the Appropriate Commission in response to
publication of the application have been considered by it:
Provided that no objection shall be so considered unless it is received before the expiration of
thirty days from the date of the publication of such notice as aforesaid;
(ii) until, in the case of an application for a licence for an area including the whole or any part of
any cantonment, aerodrome, fortress, arsenal, dockyard or camp or of any building or place in
the occupation of the Government for defence purposes, the Appropriate Commission has
ascertained that there is no objection to the grant of the licence on the part of the Central
Government.
(3) A person intending to act as a transmission licensee shall, immediately on making the
application, forward a copy of such application to the Central Transmission Utility or the State
Transmission Utility, as the case may be.
(4) The Central Transmission Utility or the State Transmission Utility, as the case may be, shall,
within thirty days after the receipt of the copy of the application referred to in sub-section (3),
send its recommendations, if any, to the Appropriate Commission: Provided that such
recommendations shall not be binding on the Commission.
(5) Before granting a licence under section 14, the Appropriate Commission shall ----7
(a) publish a notice in two such daily newspapers, as that Commission may consider necessary,
stating the name of the person to whom it proposes to issue the licence;
(b) consider all suggestions or objections and the recommendations, if any, of the Central
Transmission Utility or State Transmission Utility, as the case may be.
(6) Where a person makes an application under sub-section (1) of section 14 to act as a
licensee, the Appropriate Commission shall, as far as practicable, within ninety days after
receipt of such application, (a) issue a licence subject to the provisions of this Act and the rules and regulations made
thereunder; or
(b) reject the application for reasons to be recorded in writing if such application does not
conform to the provisions of this Act or the rules and regulations made thereunder or the
provisions of any other law for the time being in force: Provided that no application shall be
rejected unless the applicant has been given an opportunity of being heard.
(7) The Appropriate Commission shall, immediately after issue of licence, forward a copy of the
licence to the Appropriate Government , Authority, local authority, and to such other person as
the Appropriate Commission considers necessary.
(8) A licence shall continue to be in force for a period of twentyfive years unless such licence is
revoked.

THEFT OF ELECTRICITY
Clause No : 126 ---- Extension of unauthorized load
(1) If on an inspection of any place or premises or after inspection of the equipments, gadgets,
machines, devices found connected or used, or after inspection of records maintained by any
person, the assessing officer comes to the conclusion that such person is indulging in
unauthorized use of electricity, he shall provisionally assess to the best of his judgement the
electricity charges payable by such person or by any other person benefited by such use.
(2) The order of provisional assessment shall be served upon the person in occupation or
possession or in charge of the place or premises in such manner as may be prescribed.
(3) The person, on whom a notice has been served under subsection (2) shall be entitled to file
objections, if any, against the provisional assessment before the assessing officer, who may,
after affording a reasonable opportunity of hearing to such person, pass a final order of
assessment of the electricity charges payable by such person.
(4) Any person served with the order of provisional assessment, may, accept such assessment
and deposit the assessed amount with the licensee within seven days of service of such
provisional assessment order upon him Provided that in case the person deposits the assessed
amount he shall not be subjected to any further liability or any action by any authority
whatsoever.
(5) If the assessing officer reaches to the conclusion that unauthorised use of electricity has
taken place, it shall be presumed that such unauthorized use of electricity was continuing for a
period of three months immediately preceding the date of inspection in case of domestic and
agricultural services and for a period of six months immediately preceding the date of
8
inspection for all other categories of services, unless the onus is rebutted by the person,
occupier or possessor of such premises or place.
(6) The assessment under this section shall be made at a rate equal to one-and-half times the
tariff rates applicable for the relevant category of services specified in sub-section (5).

Explanation.- For the purposes of this section,(a) “ assessing officer” means an officer of a State Government or Board or licensee, as the case
may be, designated as such by the State Government
(b) “ unauthorised use of electricity” means the usage of electricity –
(i) by any artificial means; or
(ii) by a means not authorised by the concerned person or authority or licensee; or
(iii) through a tampered meter; or
(iv) for the purpose other than for which the usage of electricity was authorised.

Clause No 127. :: Appeal
(1) Any person aggrieved by a final order made under section 126 may, within thirty days of the
said order, prefer an appeal in such form, verified in such manner and be accompanied by such
fee as may be specified by the State Commission, to an appellate authority as may be
prescribed.
(2) No appeal against an order of assessment under sub-section (1) shall be entertained unless
an amount equal to one third of the assessed amount is deposited in cash or by way of bank
draft with the licensee and documentary evidence of such deposit has been enclosed along
with the appeal.
(3) The appellate authority referred to in sub-section (1) shall dispose of the appeal after
hearing the parties and pass appropriate order and send copy of the order to the assessing
officer and the appellant.
(4) The order of the appellate authority referred to in sub-section (1) passed under sub-section
(3) shall be final.
(5)No appeal shall lie to the appellate authority referred to in subsection (1) against the final
order made with the consent of the parties.
(6) When a person default in making payment of assessed amount, he, in addition to the
assessed amount shall be liable to pay, on the expiry of thirt ydays from the date of order of
assessment, an amount of interest at the rate of sixteen per cent per annum compounded
every six months.
Clause No 135 :- theft of Electricity
(1) Whoever, dishonestly, -(a) taps, makes or causes to be made any connection with overhead, underground or
under water lines or cables, or service wires, or service facilities of a licensee; or
(b) tampers a meter, installs or uses a tampered meter, current reversing transformer,
loop connection or any other device or method which interferes with accurate or proper
9
registration, calibration or metering of electric current or otherwise results in a manner
whereby electricity is stolen or wasted; or
(c)damages or destroys an electric meter, apparatus, equipment, or wire or causes or
allows any of them to be so damaged or destroyed as to interfere with the proper or accurate
metering of electricity, so as to abstract or consume or use electricity shall be punishable with
imprisonment for a term which may extend to three years or with fine or with both, Provided
that in a case where the load abstracted, consumed, or used or attempted abstraction or
attempted consumption or attempted use (i) does not exceed 10 kilowatt, the fine imposed on first conviction shall not be less than three
times the financial gain on account of such theft of electricity and in the event of second or
subsequent conviction the fine imposed shall not be less than six times the financial gain on
account of such theft of electricity;
(ii) exceeds 10 kilowatt, the fine imposed on first conviction shall not be less than three times
the financial gain on account of such theft of electricity and in the event of second or
subsequent conviction, the sentence shall be imprisonment for a term not less than six months
but which may extend to five years and with fine not less than six times the financial gain on
account of such theft of electricity Provided further that if it is proved that any artificial means
or means not authorized by the Board or licensee exist for the abstraction, consumption or use
of electricity by the consumer, it shall be presumed, until the contrary is proved, that any
abstraction, consumption or use of electricity has been dishonestly caused by such consumer.
(2) Any officer authorized in this behalf by the State Government may (a) enter, inspect, break open and search any place or premises in which he has reason to
believe that electricity has been, is being, or is likely to be, used unauthorized;
(b) search, seize and remove all such devices, instruments, wires and any other facilitator or
article which has been, is being, or is likely to be, used for unauthorized use of electricity;
(c) examine or seize any books of account or documents which in his opinion shall be useful for
or relevant to, any proceedings in respect of the offence under sub-section (1) and allow the
person from whose custody such books of account or documents are seized to make copies
thereof or take extracts the reform in his presence.
(3) The occupant of the place of search or any person on his behalf shall remain present during
the search and a list of all things seized in the course of such search shall be prepared and
delivered to such occupant or person who shall sign the list:
Provided that no inspection, search and seizure of any domestic places or domestic premises
shall be carried out between sunset and sunrise except in the presence of an adult male
member occupying such premises.
(4) The provisions of the Code of Criminal Procedure, 1973, relating to search and seizure shall
apply, as far as may be, to searches and seizure under this Act.

10
Electricity Rules 2005
Rule 3
No power plant shall qualify as captive power plant unless :-- not less than 26% of ownership is held by captive user.
- not less than 51% electricity generated in plant is consumed for captive use.
Rule 4 __
Distribution System shall also includes :Electric lines, S/S, Electrical Plants that are primarily maintained for the purpose of
distributing the electricity in area of supply.
Rule 5
•
NDLC/RLDC/SLDC
Give direction for maintaining the availability of transmission system to transmission
company and Transmission licensee shall comply with such directions.
Rule 6
Surcharge under section 38
surcharge on the transmission charges may be fixed by the Central commission.
Rule 7 CGRF and Ombudsman : - Distribution licensee shall establish forum for grievances of consumer shall consist of
officer of the licensee
- Ombudsman to be appointed by state commission. The obmbudsman shall consider
the representative of consumer.
Rule 8 Tariff for generating company under section 79 :Tariff determined by central commission can not be change by state commission
State commission may decide whether to do PPA with that generating company on the basis of
tariff decided by central commission
Rule 9 : Inter State treading licence :-Licence issued by central to trader for inter state operation shall do
trading in intra state. No saperate permission from state commission is required
Rule 10 :
The appeal against order passed by appropriate commission after come into force may be filed
within 25 days from the date notified by the central government, on which the Appellate
Tribunal come into operation.
Rule 11 : Jurisdiction of the court:-jurisdiction of the court shall not be barred till such time special court is constituted.
Rule 12 : Cognizance of the offence :The police shall take cognizance of the offence punishable under act on the complaint made to
the police in writing by the authorized persons of the utulity or Govt bodies.
Rule 13 : Issue of orders and practice direction :
The central Government may from time to time issue and
practice directions in regards to the implementation of these rules and matter incidental or
ancillary thereto as the central government may consider appropriate.
11
Other Legal provisions:
Industrial Dispute Act, 1947
Provision for instigation and settlement of industrial dispute between –
a. Employees and Employers
b. Employees and Workman
c. Workmen and Workmen
With the rights of representation by the registered trade unions or associations of the
employees. It also aims for good relations between employer and workmen.
Factory Act, 1948
This act lays down the basic requirement regarding------Staff, health, safety, welfare, working hours, annual leave with wages, special provisions
and penaulties and procedures etc.
State government are empowered to make rules and regulations regarding arrangement
for the welfare of the workers.
Prior approval from government is necessary for new installation of the factory or foe
the extension of the existing factory.
It also obligatory to govt, to see that, all the factories are registered and obtain a license
for working which is renewed periodically.
The Trade Union Act, 1926
This act covers the registration of the trade unions after fulfilling the requisite
conditions. It deals in details with rights and liabilities of the trade unions, their recognisations,
power to make regulations, procedures etc.
The workman Compensation Act : 1923
This act was design for the payment of the compensation by certain class of employer to
the worker in case of injury during accident.
Compensations has to be ascertain as per provisions of this act.
Indian Contract act, 1872 :
It covers mainly the communication, acceptance, revocation of proposals, contract and
performance of contract.
Standards :
Every State electricity regulatory commission under section 57 of EA 2003
Has issued guaranteed standard of services to be provided to the consumers
Time response to the consumer for their complaint.
Max time for restoration of supply after fault.
Time for providing new supply to the consumer.
Advance notice for supply interruptions.
Responding to the billing complaints.
Investigating of the complaints regarding system parameters like voltage, frequency,
harmonics etc.
National and international standards for electrical equipments are fraimed . the aim of which
is to obtain the uniformity of equipment on national and international basis for the benefit of
the consumer and publics.
12

More Related Content

What's hot

Introduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) MechanismIntroduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) MechanismSpark Network
 
Electricity act 2003 INDIA
Electricity act 2003 INDIAElectricity act 2003 INDIA
Electricity act 2003 INDIAArpan Khanra
 
Presentation on captive power plants
Presentation on captive power plantsPresentation on captive power plants
Presentation on captive power plantsJay Ranvir
 
Electric Vehicles in Smart Grid
Electric Vehicles in Smart GridElectric Vehicles in Smart Grid
Electric Vehicles in Smart GridIRJET Journal
 
Indian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorIndian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorVijay Menghani
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-StationTowfiqur Rahman
 
MicroGrid and Energy Storage System COMPLETE DETAILS NEW PPT
MicroGrid and Energy Storage System COMPLETE DETAILS NEW PPTMicroGrid and Energy Storage System COMPLETE DETAILS NEW PPT
MicroGrid and Energy Storage System COMPLETE DETAILS NEW PPT Abin Baby
 
Photovoltaic in buildings for EV charging and grid support
Photovoltaic in buildings for EV charging and grid supportPhotovoltaic in buildings for EV charging and grid support
Photovoltaic in buildings for EV charging and grid supportMAYANK ACHARYA
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Gensol Engineering Limited
 
The implementation of Efficient Management of Electrical Energy Regulations 2008
The implementation of Efficient Management of Electrical Energy Regulations 2008The implementation of Efficient Management of Electrical Energy Regulations 2008
The implementation of Efficient Management of Electrical Energy Regulations 2008ZAINI ABDUL WAHAB
 
Electric Vehicle Concept and Power Management Strategies
Electric Vehicle Concept and Power Management StrategiesElectric Vehicle Concept and Power Management Strategies
Electric Vehicle Concept and Power Management Strategiescountoot
 
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission ProjectsTariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission ProjectsAmitava Nag
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationAmeen San
 

What's hot (20)

Ee09 801 eed ppt
Ee09 801 eed pptEe09 801 eed ppt
Ee09 801 eed ppt
 
Introduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) MechanismIntroduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) Mechanism
 
Electricity act 2003 INDIA
Electricity act 2003 INDIAElectricity act 2003 INDIA
Electricity act 2003 INDIA
 
Presentation on captive power plants
Presentation on captive power plantsPresentation on captive power plants
Presentation on captive power plants
 
Restructuring of power grid
Restructuring of power gridRestructuring of power grid
Restructuring of power grid
 
Restructuring and Privatization
Restructuring and PrivatizationRestructuring and Privatization
Restructuring and Privatization
 
Electric Vehicles in Smart Grid
Electric Vehicles in Smart GridElectric Vehicles in Smart Grid
Electric Vehicles in Smart Grid
 
Electricity policies
Electricity policiesElectricity policies
Electricity policies
 
Indian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power SectorIndian Regulatory Framework Of Power Sector
Indian Regulatory Framework Of Power Sector
 
Tariff policy
Tariff policyTariff policy
Tariff policy
 
Typical layout of a Sub-Station
Typical layout of a Sub-StationTypical layout of a Sub-Station
Typical layout of a Sub-Station
 
MicroGrid and Energy Storage System COMPLETE DETAILS NEW PPT
MicroGrid and Energy Storage System COMPLETE DETAILS NEW PPTMicroGrid and Energy Storage System COMPLETE DETAILS NEW PPT
MicroGrid and Energy Storage System COMPLETE DETAILS NEW PPT
 
Photovoltaic in buildings for EV charging and grid support
Photovoltaic in buildings for EV charging and grid supportPhotovoltaic in buildings for EV charging and grid support
Photovoltaic in buildings for EV charging and grid support
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019
 
The implementation of Efficient Management of Electrical Energy Regulations 2008
The implementation of Efficient Management of Electrical Energy Regulations 2008The implementation of Efficient Management of Electrical Energy Regulations 2008
The implementation of Efficient Management of Electrical Energy Regulations 2008
 
Electric Vehicle Concept and Power Management Strategies
Electric Vehicle Concept and Power Management StrategiesElectric Vehicle Concept and Power Management Strategies
Electric Vehicle Concept and Power Management Strategies
 
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission ProjectsTariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
Tariff Based Competitive Bidding (TBCB) for Intra-State Transmission Projects
 
Indian Electricity Grid Code
Indian Electricity Grid CodeIndian Electricity Grid Code
Indian Electricity Grid Code
 
Grid tie solar power system
Grid tie solar power systemGrid tie solar power system
Grid tie solar power system
 
Application of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage RegulationApplication of Capacitors to Distribution System and Voltage Regulation
Application of Capacitors to Distribution System and Voltage Regulation
 

Viewers also liked (20)

Electricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardElectricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forward
 
Energy Conservation Act 2001
Energy Conservation Act 2001Energy Conservation Act 2001
Energy Conservation Act 2001
 
National Building Code 2005
National Building Code 2005National Building Code 2005
National Building Code 2005
 
Electrical Systems in a Building
Electrical Systems in a BuildingElectrical Systems in a Building
Electrical Systems in a Building
 
Trg slides safety
Trg slides safetyTrg slides safety
Trg slides safety
 
The Economics of Regulation
The Economics of RegulationThe Economics of Regulation
The Economics of Regulation
 
1892 indian councils act
1892 indian councils act1892 indian councils act
1892 indian councils act
 
Boilers (A basic approach)
Boilers (A basic approach)Boilers (A basic approach)
Boilers (A basic approach)
 
Fire Safety Dip. OSH
Fire Safety Dip. OSHFire Safety Dip. OSH
Fire Safety Dip. OSH
 
Regulatory regime
Regulatory regimeRegulatory regime
Regulatory regime
 
Fire services act 1988.
Fire services act 1988.Fire services act 1988.
Fire services act 1988.
 
1861 act
1861 act1861 act
1861 act
 
Boiler act 1923
Boiler act 1923Boiler act 1923
Boiler act 1923
 
Environment Protection Act , 1986.
Environment Protection Act , 1986.Environment Protection Act , 1986.
Environment Protection Act , 1986.
 
Building bye laws
Building bye lawsBuilding bye laws
Building bye laws
 
Radiation Protection
Radiation ProtectionRadiation Protection
Radiation Protection
 
The companies-act-1956-ppt-
The companies-act-1956-ppt-The companies-act-1956-ppt-
The companies-act-1956-ppt-
 
national builiding codes
national builiding codesnational builiding codes
national builiding codes
 
Environment Act, 1986
Environment Act, 1986Environment Act, 1986
Environment Act, 1986
 
Enviornmental protection Act 1986
Enviornmental protection Act 1986Enviornmental protection Act 1986
Enviornmental protection Act 1986
 

Similar to Regulations, Supply Rules and Standards of Electricity

Electricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptxElectricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptxmsounak95
 
Power grid operation in India
Power grid operation in IndiaPower grid operation in India
Power grid operation in IndiaMahim Srivastava
 
Environmental show of the south 2014 new entrants in electricity generation
Environmental show of the south 2014 new entrants in electricity generationEnvironmental show of the south 2014 new entrants in electricity generation
Environmental show of the south 2014 new entrants in electricity generationTNenergy
 
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNADay-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNAIPPAI
 
New Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyNew Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyTNenergy
 
Presentation on IEA 2003.pptx
Presentation on IEA 2003.pptxPresentation on IEA 2003.pptx
Presentation on IEA 2003.pptxMaheshThombare9
 
Glen Wright - Legal and Regulatory Aspects of RE
Glen Wright - Legal and Regulatory Aspects of REGlen Wright - Legal and Regulatory Aspects of RE
Glen Wright - Legal and Regulatory Aspects of REANUECI
 
2012 Reenergize the Americas 4A: Alejando Peraza Garcia
2012 Reenergize the Americas 4A: Alejando Peraza Garcia2012 Reenergize the Americas 4A: Alejando Peraza Garcia
2012 Reenergize the Americas 4A: Alejando Peraza GarciaReenergize
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Headway Solar
 
Electricity Act.ppt
Electricity Act.pptElectricity Act.ppt
Electricity Act.pptvaasuchetu
 
WIRES - Transmission 101 - April 21 2015
WIRES - Transmission 101 - April 21 2015WIRES - Transmission 101 - April 21 2015
WIRES - Transmission 101 - April 21 2015Adriann McCoy
 
roof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptxroof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptxsonu1811
 
Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...
Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...
Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...Emmanuel Aondowase Anchaver
 
Cerc communication regulations, 2017 ppt
Cerc communication regulations, 2017 pptCerc communication regulations, 2017 ppt
Cerc communication regulations, 2017 pptSiddharth Arora
 
Tapping potential of waste heat to power and energy conservation
Tapping potential of waste heat to power and energy conservationTapping potential of waste heat to power and energy conservation
Tapping potential of waste heat to power and energy conservationIPPAI
 

Similar to Regulations, Supply Rules and Standards of Electricity (20)

Captive gen
Captive genCaptive gen
Captive gen
 
IEGC.pptx
IEGC.pptxIEGC.pptx
IEGC.pptx
 
Electricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptxElectricity Act (Amendment) Bill 2022.pptx
Electricity Act (Amendment) Bill 2022.pptx
 
Connectivity
ConnectivityConnectivity
Connectivity
 
Power grid operation in India
Power grid operation in IndiaPower grid operation in India
Power grid operation in India
 
Environmental show of the south 2014 new entrants in electricity generation
Environmental show of the south 2014 new entrants in electricity generationEnvironmental show of the south 2014 new entrants in electricity generation
Environmental show of the south 2014 new entrants in electricity generation
 
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNADay-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
Day-3, Mr. SC Shrivastav connectivity MTOA & lTA and concept of GNA
 
New Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee ValleyNew Entrants in Electric Generation in Tennessee Valley
New Entrants in Electric Generation in Tennessee Valley
 
Presentation on IEA 2003.pptx
Presentation on IEA 2003.pptxPresentation on IEA 2003.pptx
Presentation on IEA 2003.pptx
 
Glen Wright - Legal and Regulatory Aspects of RE
Glen Wright - Legal and Regulatory Aspects of REGlen Wright - Legal and Regulatory Aspects of RE
Glen Wright - Legal and Regulatory Aspects of RE
 
DSM.pptx
DSM.pptxDSM.pptx
DSM.pptx
 
2012 Reenergize the Americas 4A: Alejando Peraza Garcia
2012 Reenergize the Americas 4A: Alejando Peraza Garcia2012 Reenergize the Americas 4A: Alejando Peraza Garcia
2012 Reenergize the Americas 4A: Alejando Peraza Garcia
 
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
Policy on Net Metering for Grid Interactive Roof-Top Solar Photo Voltaic Powe...
 
Electricity Act.ppt
Electricity Act.pptElectricity Act.ppt
Electricity Act.ppt
 
WIRES - Transmission 101 - April 21 2015
WIRES - Transmission 101 - April 21 2015WIRES - Transmission 101 - April 21 2015
WIRES - Transmission 101 - April 21 2015
 
roof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptxroof top solar for net metering and gross metering.pptx
roof top solar for net metering and gross metering.pptx
 
Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...
Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...
Potential Effects of the Eligible Customer Declaration in the Nigerian Electr...
 
Republic act no 9136 (2001)
Republic act no 9136 (2001)Republic act no 9136 (2001)
Republic act no 9136 (2001)
 
Cerc communication regulations, 2017 ppt
Cerc communication regulations, 2017 pptCerc communication regulations, 2017 ppt
Cerc communication regulations, 2017 ppt
 
Tapping potential of waste heat to power and energy conservation
Tapping potential of waste heat to power and energy conservationTapping potential of waste heat to power and energy conservation
Tapping potential of waste heat to power and energy conservation
 

Recently uploaded

Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Manik S Magar
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfMounikaPolabathina
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersRaghuram Pandurangan
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxLoriGlavin3
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demoHarshalMandlekar2
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersNicole Novielli
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenHervé Boutemy
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 

Recently uploaded (20)

Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!Anypoint Exchange: It’s Not Just a Repo!
Anypoint Exchange: It’s Not Just a Repo!
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
What is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdfWhat is DBT - The Ultimate Data Build Tool.pdf
What is DBT - The Ultimate Data Build Tool.pdf
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Generative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information DevelopersGenerative AI for Technical Writer or Information Developers
Generative AI for Technical Writer or Information Developers
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptxA Deep Dive on Passkeys: FIDO Paris Seminar.pptx
A Deep Dive on Passkeys: FIDO Paris Seminar.pptx
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demo
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software Developers
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
DevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache MavenDevoxxFR 2024 Reproducible Builds with Apache Maven
DevoxxFR 2024 Reproducible Builds with Apache Maven
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 

Regulations, Supply Rules and Standards of Electricity

  • 1. Regulations, Supply Rules and Standards of Electricity Compiled By : M.G. Wath EET, MSEDCL, Nagpur The Indian Electricity Act, 1910 • Provided basic framework for electric supply industry in India • Growth of the sector through licensees. Licence by State Govt. • Provision for licence for supply of electricity in a specified area • Legal framework for laying down of wires and other works • Provisions laying down relationship between licensee and consumer The Electricity (Supply) Act, 1948 • Mandated creation of SEBs • Need for the State to step in (through SEBs) to extend electrification (so far limited to cities) across the country. Inability of the SEB’s to take the decision on tariff in a professional and independent manner, which in fact was done by the State Government. The Electricity Regulatory Commission Act, 1998 • Provision for setting up of Central / State Electricity Regulatory Commission with powers to determine tariffs • Constitution of SERC optional for States • Distancing of Government from tariff determination The Electricity Conservation Act, 2001 • This act provides legal frame work and Institutional arrangement for embarking on energy efficiency drive. • BEE have been established wef 01.03.2002 by merging Energy management centre of Ministry of power. • BEE is responsible for implementing the policies of energy conservation activity. Electricity Act, 2003 - notified on 10th June ‘03 The main objective of EA 2003 are Competition in power generators, Protection of Consumers interests & provision of Power for all Areas The main features of EA 2003 are :--     Creates liberal framework for power development Creates competitive environment Facilitates private investment Delicenses generation except for hydro : Captive free from controls Rural Areas : Stand alone Generation and Distribution delicenced  Multiple licensing in Distribution 1
  • 2.     Stringent provisions for controlling theft of electricity Focus on revenue recovery in cases of unauthorized use of electricity Obliges States to restructure Electricity Boards Mandates creation of Regulatory Commissions. Retail tariff to be determined by regulatory commissions  Open access in Transmission from outset  Open access in Distribution to be allowed by SERCs in phases  Gradual phasing out of cross subsidies Generation Any GENCO may establish, operate and maintain a Gen- station without a licence by complying with the technical standards relating to connectivity with the Grid. Captive Generation plant should have to use the generation for its own. If there is the another consumer for utilization of the energy generated by CPP or CGP then the condition is that the user should have a share of more than 26% in CPP. Second condition is that, more than the 51% of the energy generated is to be utilized for its own or by user who have share in CPP. For Captive Generation freed: No license required Right to open access from plant to destination “Captive generating plant means a power plant set up by any person to generate electricity primarily for his own use and includes a power plant set up by any cooperative society or association of persons for generating electricity primarily for use of members of such co-operative society or association.” Trading distinct activity permitted with licensing A person may construct, maintain or operate a CGP and dedicated transmission lines provided ---1) That the supply of electricity power the CGP through the Grid shall be regulated in the same manner as the generating station of a generating company. 2) No license will be required for supply of electric generated power a CGP to any license and to any consumer subject to the regulations made under Sub-Section (2) of Sect.42 . 3) A CGP shall have the right to open access for the purpose of carrying electricity from the CGP to the destination of use. 4) Open access shall be subject to availability of adequate transmission facility. Duties of a Generating Company :• To establish, maintain & operate generating stations tie-lines and dedicated transmission lines. • The Appropriate Commission may in `extra ordinary circumstances’ give directions to a generating company to operate and maintain any generating station in accordance with the directions of the Govt. ‘Extraordinary’ means circumstances arising out of threat to security of the State, public order or a natural calamity or such other circumstance arising in public interest. 2
  • 3. Transmission: Requirment of the Transmission company are ---– License from ERC for transmission – CTU/STU shall be deemed transmission license (14 proviso) – National Load Despatch Centre – Regional Load Despatch Centre, RLDC, will be set up by Central Govt. for each region – RLDC/SLDC will be a Govt. company/authority – SLDC shall comply with the direction of RLDC – Every licensee, Genco, Gen. station, Sub-station shall comply with the directions issued by SLDC – Non Discriminatory open access – Appropriate Govt. can give direction to RLDC/SLDC for maintaining smooth & stable supply of electricity. – Central Govt. to make region – wise demarcation of the country. – Efficient, economical and integrated transmission. – To develop voluntary inter-connections and co-ordination facilities for interstate, regional and inter-regional generation and transmission of electricity National Load Despatch Centre :-- (NLDC) • Centre to set up a NLDC for optimum scheduling despatch of electricity among the RLDC’s ( Regional Load Despatch centre) • The NLDC shall not engage in the business of trading of electricity. • The NLDC shall be operated by a Govt. Co. or any Authority or Corporation established under any Central Act. Regional Load Despatch Centre :-- (RLDC) • RLDC to be the apex body to ensure integrated operation of power system in the region. • RLDC shall be operated by a Govt. company or Authority or Corporation. • RLDC shall engage in the business of generation of electricity or trading in electricity Functions of RLDC :_ • It will be the apex body to ensure integrated operations of the power system. • Responsible for the optimum scheduling and dispatch of electricity with in region. • Monitor grid operations • Keep account of quantity of electricity transmitted through the regional grid. • Supervision over Inter-State transmission system. • Ensure secure and economic operation of the regional grid in accordance with the Grid standards and Grid operations. • The RLDC may levy and collect such fee and charges from generating Co. or licensees engaged in inter-state transmission of elec. as may be specified by the central Govt. 3
  • 4. Functions of the Central Transmission Utility: I) To transmit elec. Through inter-state transmission systems. II) To discharge all functions of planning and co-ordination relating to inter-state transmission system with a) State Transmission Utilities. b) Central Govornment c) Generating Company. d) Regional power Committees. III) To ensure development of an efficient, Co-ordinated and economical system of inter-state transmission lines for smooth flow of electricity from generating stations to the load centers’. IV) To provide non-discriminatory open access to its transmission system for use by a) Any licensee or generating Co. on payment of the transmission Charges. b) Any Consumer, as and when open access is provided, on payment of the transmission charges and a surcharge thereon. V) Sur-charge shall be utilized for meeting the requirement of current level of cross-subsidy. VI) Sur-charge shall not be leviable in case open-access is provided to a person who has established a CGP for carrying the electricity to the destination of his own use. Intrastate Transmission :• Transmission within the State • The State Commission shall establish SLDC for same functions as RLDC • The SLDC shall be operated by a Govt. Co. or authority or Corporation established under any State Act. as may be notified by the State Govt. • Till such time, the State Transmission Utility shall operate as the SLDC. • No SLDC shall engage in the business of Trading in electricity. Distribution – License from ERC necessary for distribution & trading of electricity --- ERC on recommendation of Govt. may exempt any local body panchayat, co-op. society, NGO from license requirement – Open access to be introduced by state commission in such phases – No surcharge for open access to captive plant – Where ERC has allowed open access under Section 42, such consumers may enter into a PPA on such terms and conditions (including tariff) as may be agreed upon by them. – Open access shall be provided to all consumers who required supply which exceeds 1MW at any time. – Forum to establish for redressal of consumer grievances. – Consumer may file appeal to Ombudsman. 4
  • 5. Main functions of CERC Regulate tariff of generating companies owned/ controlled by Central government. Regulate inter State transmission of electricity and determine their tariff , to regulate the tariff of other generating companies other than Govt. owned / controlled companies, if such companies have a composite schemes for generation and sale of electricity in more than one State CERC Adjudicate upon disputes involving generating companies or transmission licensees for above. It also Specify and enforce standards for quality, continuity and reliability of services by licensees. Main functions of SERCs • Determine tariff for generation, supply transmission and wheeling of electricity : wholesale / bulk / rental/ within the State • Regulate electricity purchase and procurement process of distribution licensees including the price for distribution and supply within the State • Adjudicate upon disputes between licensees and generating companies for above • Specify and enforce standards for quality, continuity and reliability of services by licensees Appellate Tribunal • Appeal can be made to the Appellate Tribunal on order of adjudicating officer or ER. • Summoning & examining a person • Requiring discovery & production of documents • Receiving evidence on affidavits • Issuing commissions • Powers of Civil Court • The Appeal Tribunals shall not be bound by the procedure laid down by the CPCshall be guided by the principles of the natural justice. Clauses of Electricity Act 2003 LICENSING Clause No 12. No person shall (a) transmit electricity; or (b) distribute electricity; or (c) undertake trading in electricity, unless he is authorised to do so by a licence issued under section 14, or is exempt under section 13. Clause No 13. The Appropriate Commission may, on the recommendations, of the Appropriate Government, in accordance with the national policy formulated undersection 5 and in public interest, direct, by notification that subject to suchconditions and restrictions, if any, and for such period or 5
  • 6. periods, as may bespecified in the notification, the provisions of section 12 shall not apply to any localauthority, Panchayat Institution, users’ association, co-operative societies, nongovernmental organizations, or franchisees: Clause No 14. The Appropriate Commission may, on application made to it undersection 15, grant any person licence to any person – (a) to transmit electricity as a transmission licensee; or (b) to distribute electricity as a distribution licensee; or (c) to undertake trading in electricity as an electricity trader,in any area which may be specified in the licence: Provided that any person engaged in the business of transmission orsupply of electricity under the provisions of the repealed laws or any Act specifiedin the Schedule on or before the appointed date shall be deemed to be a licenseeunder this Act for such period as may be stipulated in the licence, clearance orapproval granted to him under the repealed laws or such Act specified in the Schedule, and the provisions of the repealed laws or such Act specified in the Schedule in respect of such licence shall apply for a period of one year from thedate of commencement of this Act or such earlier period as may be specified, atthe request of the licensee, by the Appropriate Commission and thereafter the provisions of this Act shall apply to such business: Provided further that the Central Transmission Utility or the StateTransmission Utility shall be deemed to be a transmission licensee under this Act: Provided also that in case an Appropriate Government transmits electricity or distributes electricity or undertakes trading in electricity, whether before or after the commencement of this Act, such Government shall be deemed to be a licensee under this Act, but shall not be required to obtain a licence under this Act: Provided also that the Damodar Valley Corporation, established undersub-section (1) of section 3 of the Damodar Valley Corporation Act, 1948, shall bedeemed to be a licensee under this Act but shall not be required to obtain a licence under this Act and the provisions of the Damodar Valley Corporation Act, 1948, in so far as they are not inconsistent with the provisions of this Act, shall continue to apply to that Corporation: Provided also that the Government company or the company referred to in sub-section (2) of section 131 of this Act and the company or companies created in pursuance of the Acts specified in the Schedule, shall be deemed to be a licensee under this Act: Provided also that the Appropriate Commission may grant a licence to two or more persons for distribution of electricity through their own distribution system within the same area, subject to the conditions that the applicant for grant of licence Procedure for Grant of Licence within the same area, subject to the conditions that the applicant for grant of licence within the same area shall, without prejudice to the other conditions or requirements under this Act, comply with the additional requirements (including 6
  • 7. the capital adequacy, credit-worthiness, or code of conduct) as may be prescribed by the Central Government, and no such applicant who complies with all the requirements for grant of licence, shall be refused grant of licence on the ground that there already exists a licensee in the same area for the same purpose: Provided also that in a case where a distribution licensee proposes to undertake distribution of electricity for a specified area within his area of supply through another person, that person shall not be required to obtain any separate licence from the concerned State Commission and such distribution licensee shall be responsible for distribution of electricity in his area of supply: Provided also that where a person intends to generate and distribute electricity in a rural area to be notified by the State Government, such person shall not require any licence for such generation and distribution of electricity, but he shall comply with the measures which may be specified by the Authority under section 53: Provided also that a distribution licensee shall not require a licence to undertake trading in electricity. Clause No 15. (1) Every application under section 14 shall be made in such form and in such manner as may be specified by the Appropriate Commission and shall be accompanied by such fee as may be prescribed. (2) Any person who has made an application for grant of licence shall, within seven days after making such application, publish a notice of his application with such particulars and in such manner as may be specified and a licence shall not be granted (i) until the objections, if any, received by the Appropriate Commission in response to publication of the application have been considered by it: Provided that no objection shall be so considered unless it is received before the expiration of thirty days from the date of the publication of such notice as aforesaid; (ii) until, in the case of an application for a licence for an area including the whole or any part of any cantonment, aerodrome, fortress, arsenal, dockyard or camp or of any building or place in the occupation of the Government for defence purposes, the Appropriate Commission has ascertained that there is no objection to the grant of the licence on the part of the Central Government. (3) A person intending to act as a transmission licensee shall, immediately on making the application, forward a copy of such application to the Central Transmission Utility or the State Transmission Utility, as the case may be. (4) The Central Transmission Utility or the State Transmission Utility, as the case may be, shall, within thirty days after the receipt of the copy of the application referred to in sub-section (3), send its recommendations, if any, to the Appropriate Commission: Provided that such recommendations shall not be binding on the Commission. (5) Before granting a licence under section 14, the Appropriate Commission shall ----7
  • 8. (a) publish a notice in two such daily newspapers, as that Commission may consider necessary, stating the name of the person to whom it proposes to issue the licence; (b) consider all suggestions or objections and the recommendations, if any, of the Central Transmission Utility or State Transmission Utility, as the case may be. (6) Where a person makes an application under sub-section (1) of section 14 to act as a licensee, the Appropriate Commission shall, as far as practicable, within ninety days after receipt of such application, (a) issue a licence subject to the provisions of this Act and the rules and regulations made thereunder; or (b) reject the application for reasons to be recorded in writing if such application does not conform to the provisions of this Act or the rules and regulations made thereunder or the provisions of any other law for the time being in force: Provided that no application shall be rejected unless the applicant has been given an opportunity of being heard. (7) The Appropriate Commission shall, immediately after issue of licence, forward a copy of the licence to the Appropriate Government , Authority, local authority, and to such other person as the Appropriate Commission considers necessary. (8) A licence shall continue to be in force for a period of twentyfive years unless such licence is revoked. THEFT OF ELECTRICITY Clause No : 126 ---- Extension of unauthorized load (1) If on an inspection of any place or premises or after inspection of the equipments, gadgets, machines, devices found connected or used, or after inspection of records maintained by any person, the assessing officer comes to the conclusion that such person is indulging in unauthorized use of electricity, he shall provisionally assess to the best of his judgement the electricity charges payable by such person or by any other person benefited by such use. (2) The order of provisional assessment shall be served upon the person in occupation or possession or in charge of the place or premises in such manner as may be prescribed. (3) The person, on whom a notice has been served under subsection (2) shall be entitled to file objections, if any, against the provisional assessment before the assessing officer, who may, after affording a reasonable opportunity of hearing to such person, pass a final order of assessment of the electricity charges payable by such person. (4) Any person served with the order of provisional assessment, may, accept such assessment and deposit the assessed amount with the licensee within seven days of service of such provisional assessment order upon him Provided that in case the person deposits the assessed amount he shall not be subjected to any further liability or any action by any authority whatsoever. (5) If the assessing officer reaches to the conclusion that unauthorised use of electricity has taken place, it shall be presumed that such unauthorized use of electricity was continuing for a period of three months immediately preceding the date of inspection in case of domestic and agricultural services and for a period of six months immediately preceding the date of 8
  • 9. inspection for all other categories of services, unless the onus is rebutted by the person, occupier or possessor of such premises or place. (6) The assessment under this section shall be made at a rate equal to one-and-half times the tariff rates applicable for the relevant category of services specified in sub-section (5). Explanation.- For the purposes of this section,(a) “ assessing officer” means an officer of a State Government or Board or licensee, as the case may be, designated as such by the State Government (b) “ unauthorised use of electricity” means the usage of electricity – (i) by any artificial means; or (ii) by a means not authorised by the concerned person or authority or licensee; or (iii) through a tampered meter; or (iv) for the purpose other than for which the usage of electricity was authorised. Clause No 127. :: Appeal (1) Any person aggrieved by a final order made under section 126 may, within thirty days of the said order, prefer an appeal in such form, verified in such manner and be accompanied by such fee as may be specified by the State Commission, to an appellate authority as may be prescribed. (2) No appeal against an order of assessment under sub-section (1) shall be entertained unless an amount equal to one third of the assessed amount is deposited in cash or by way of bank draft with the licensee and documentary evidence of such deposit has been enclosed along with the appeal. (3) The appellate authority referred to in sub-section (1) shall dispose of the appeal after hearing the parties and pass appropriate order and send copy of the order to the assessing officer and the appellant. (4) The order of the appellate authority referred to in sub-section (1) passed under sub-section (3) shall be final. (5)No appeal shall lie to the appellate authority referred to in subsection (1) against the final order made with the consent of the parties. (6) When a person default in making payment of assessed amount, he, in addition to the assessed amount shall be liable to pay, on the expiry of thirt ydays from the date of order of assessment, an amount of interest at the rate of sixteen per cent per annum compounded every six months. Clause No 135 :- theft of Electricity (1) Whoever, dishonestly, -(a) taps, makes or causes to be made any connection with overhead, underground or under water lines or cables, or service wires, or service facilities of a licensee; or (b) tampers a meter, installs or uses a tampered meter, current reversing transformer, loop connection or any other device or method which interferes with accurate or proper 9
  • 10. registration, calibration or metering of electric current or otherwise results in a manner whereby electricity is stolen or wasted; or (c)damages or destroys an electric meter, apparatus, equipment, or wire or causes or allows any of them to be so damaged or destroyed as to interfere with the proper or accurate metering of electricity, so as to abstract or consume or use electricity shall be punishable with imprisonment for a term which may extend to three years or with fine or with both, Provided that in a case where the load abstracted, consumed, or used or attempted abstraction or attempted consumption or attempted use (i) does not exceed 10 kilowatt, the fine imposed on first conviction shall not be less than three times the financial gain on account of such theft of electricity and in the event of second or subsequent conviction the fine imposed shall not be less than six times the financial gain on account of such theft of electricity; (ii) exceeds 10 kilowatt, the fine imposed on first conviction shall not be less than three times the financial gain on account of such theft of electricity and in the event of second or subsequent conviction, the sentence shall be imprisonment for a term not less than six months but which may extend to five years and with fine not less than six times the financial gain on account of such theft of electricity Provided further that if it is proved that any artificial means or means not authorized by the Board or licensee exist for the abstraction, consumption or use of electricity by the consumer, it shall be presumed, until the contrary is proved, that any abstraction, consumption or use of electricity has been dishonestly caused by such consumer. (2) Any officer authorized in this behalf by the State Government may (a) enter, inspect, break open and search any place or premises in which he has reason to believe that electricity has been, is being, or is likely to be, used unauthorized; (b) search, seize and remove all such devices, instruments, wires and any other facilitator or article which has been, is being, or is likely to be, used for unauthorized use of electricity; (c) examine or seize any books of account or documents which in his opinion shall be useful for or relevant to, any proceedings in respect of the offence under sub-section (1) and allow the person from whose custody such books of account or documents are seized to make copies thereof or take extracts the reform in his presence. (3) The occupant of the place of search or any person on his behalf shall remain present during the search and a list of all things seized in the course of such search shall be prepared and delivered to such occupant or person who shall sign the list: Provided that no inspection, search and seizure of any domestic places or domestic premises shall be carried out between sunset and sunrise except in the presence of an adult male member occupying such premises. (4) The provisions of the Code of Criminal Procedure, 1973, relating to search and seizure shall apply, as far as may be, to searches and seizure under this Act. 10
  • 11. Electricity Rules 2005 Rule 3 No power plant shall qualify as captive power plant unless :-- not less than 26% of ownership is held by captive user. - not less than 51% electricity generated in plant is consumed for captive use. Rule 4 __ Distribution System shall also includes :Electric lines, S/S, Electrical Plants that are primarily maintained for the purpose of distributing the electricity in area of supply. Rule 5 • NDLC/RLDC/SLDC Give direction for maintaining the availability of transmission system to transmission company and Transmission licensee shall comply with such directions. Rule 6 Surcharge under section 38 surcharge on the transmission charges may be fixed by the Central commission. Rule 7 CGRF and Ombudsman : - Distribution licensee shall establish forum for grievances of consumer shall consist of officer of the licensee - Ombudsman to be appointed by state commission. The obmbudsman shall consider the representative of consumer. Rule 8 Tariff for generating company under section 79 :Tariff determined by central commission can not be change by state commission State commission may decide whether to do PPA with that generating company on the basis of tariff decided by central commission Rule 9 : Inter State treading licence :-Licence issued by central to trader for inter state operation shall do trading in intra state. No saperate permission from state commission is required Rule 10 : The appeal against order passed by appropriate commission after come into force may be filed within 25 days from the date notified by the central government, on which the Appellate Tribunal come into operation. Rule 11 : Jurisdiction of the court:-jurisdiction of the court shall not be barred till such time special court is constituted. Rule 12 : Cognizance of the offence :The police shall take cognizance of the offence punishable under act on the complaint made to the police in writing by the authorized persons of the utulity or Govt bodies. Rule 13 : Issue of orders and practice direction : The central Government may from time to time issue and practice directions in regards to the implementation of these rules and matter incidental or ancillary thereto as the central government may consider appropriate. 11
  • 12. Other Legal provisions: Industrial Dispute Act, 1947 Provision for instigation and settlement of industrial dispute between – a. Employees and Employers b. Employees and Workman c. Workmen and Workmen With the rights of representation by the registered trade unions or associations of the employees. It also aims for good relations between employer and workmen. Factory Act, 1948 This act lays down the basic requirement regarding------Staff, health, safety, welfare, working hours, annual leave with wages, special provisions and penaulties and procedures etc. State government are empowered to make rules and regulations regarding arrangement for the welfare of the workers. Prior approval from government is necessary for new installation of the factory or foe the extension of the existing factory. It also obligatory to govt, to see that, all the factories are registered and obtain a license for working which is renewed periodically. The Trade Union Act, 1926 This act covers the registration of the trade unions after fulfilling the requisite conditions. It deals in details with rights and liabilities of the trade unions, their recognisations, power to make regulations, procedures etc. The workman Compensation Act : 1923 This act was design for the payment of the compensation by certain class of employer to the worker in case of injury during accident. Compensations has to be ascertain as per provisions of this act. Indian Contract act, 1872 : It covers mainly the communication, acceptance, revocation of proposals, contract and performance of contract. Standards : Every State electricity regulatory commission under section 57 of EA 2003 Has issued guaranteed standard of services to be provided to the consumers Time response to the consumer for their complaint. Max time for restoration of supply after fault. Time for providing new supply to the consumer. Advance notice for supply interruptions. Responding to the billing complaints. Investigating of the complaints regarding system parameters like voltage, frequency, harmonics etc. National and international standards for electrical equipments are fraimed . the aim of which is to obtain the uniformity of equipment on national and international basis for the benefit of the consumer and publics. 12