Successfully reported this slideshow.
Wind Energy in Morocco                     Presented by                 M. Mustapha ENZILI           Responsible of Wind D...
Summary•   Wind Energy Potential in Morocco•   Wind Resources Map of Morocco•   Wind atlas of Morocco•   Feasibility studi...
Wind Energy Potantial in       Morocco
Wind Energy Potential in Morocco Morocco has an excellent wind potential mainly in the North & in the South :  - Essaouira...
Wind Energy Potential of Morocco        (Results of study CDER/GTZ - July 2007) Total        Technical Estimated    Estima...
Wind Resource Map of Morocco
New Wind Atlas of Morocco• An international call of tenders will be launched in the next  few months for preparation of a ...
Feasibility studies of Wind Farms           in Morocco
Steps of feasibility studies• Choice of sites• Wind measurement (minimum one year)• Micro-siting (Configuration of windtur...
Wind measurement station      near Tangier
Equipments of wind measurement stations• Measurement station of 60 meters :  - 3 or 4 positions of anemometers  - 2 positi...
Equipments of wind measurement stations
Equipments of wind measurement stations
Complex terrain in the north of Morocco
Desert terrain in the south of Morocco
Calibration of anemometers
Calibration of anemometers• Calibration of anemometers before installation by institutes  specialized• Calibration with me...
Measnet anemometer Calibration procedure• The MEASNET procedure is considered to be the most  internationally accepted pro...
The Members of Measnet• CENER - Centro Nacional de Energias Renovables, Spain• CRES - Centre for Renewable Energy Sources,...
The Members of Measnet• WINDTEST - Grevenbroich GmbH, Germany• Barlovento - Barlovento Recursos Naturales S.L., Spain• NRE...
Certificate of calibration(Anemometer Informations)
Certificate of calibration
Certificate of calibration (Calibration Results)
Certificate of calibration      (Wind tunnel)
Before installation of dataloggers• Before installation of anemometers, make sure that you  introduce slope & offset of ea...
Datalogger configuration
Operation & maintenance of  measurement stations
Operation & maintenance of wind measurement                       stations• Triangular masts :    Easy installation of ma...
Operation & maintenance of wind measurement                       stations• Tubular masts :   Need ‘’tire-fort’’ for inst...
Follow up of measurement stationsCompanyWind FarmCountryProvinceSiteStationLocalisationCoordinate systemYXCoordinate syste...
Informations about dataloggerData Logger      Type & Serial Number   installation date   Disassembly date
Informations about anemometers,                       windvane, etc…Anemometers              Type &                       ...
Informations about dataFiles                         Date        Date        Date        Date        Date        Date     ...
Follow up of measurement stations              Summary      Data  Date        Report       collectionNames         Summary...
Assessment data
Wind Softwares• Assessment data with specialized softwares :  - Alwin (Dewi Institute, Germany)  - Wasp (Risoe Institute, ...
Frequency Distribution
Direction Distribution
Simulation by WASP Software.
Wind Farms in Morocco
Wind Farm of 50 MW               (El Koudia El Baida -Tetouan) Power                 : 50 MW (84 Vestas 600 kW) Start pr...
Wind Farm 50 MW(El Koudia El Baida -Tetouan)
Wind Farm 60 MW                     Cap SIM (Essaouira) Power                       : 60 MW Windturbines                ...
Wind Farm 60 MWCap SIM (Essaouira)
Wind Farm 140 MW                           Tangier Power                      : 140 MW Windturbines               : 165 ...
Wind Farm 140 MW      Tangier
Wind Farm 32 MW            Lafarge (Cements Factory of Tetouan) Power                    : 32 MW                         ...
Wind Farm 32 MWLafarge (Cements Factory of Tetouan)
Wind Farms Programmed (2010-2012)Objective of the Government : Production of 18 % of                            electricit...
Conclusion• Operation & maintenance of wind measurement stations is  very important to have a good data because an increas...
Renewable Energy Development Center (CDER)Thank you for your Attention            m.enzili@cder.org.ma             enzili@...
Upcoming SlideShare
Loading in …5
×

Capacity building 2010 day 1 wind energy in morocco

806 views

Published on

Capacity Building in the Field of Wind Energy, Stage II
29 March - 2 April, 2010

  • Be the first to comment

Capacity building 2010 day 1 wind energy in morocco

  1. 1. Wind Energy in Morocco Presented by M. Mustapha ENZILI Responsible of Wind DepartmentRenewable Energy Development Center (CDER - Morocco)RECREE Wind Energy Building Capacity Program Rabat-Tangier, Morocco 29 March - 2 April, 2010
  2. 2. Summary• Wind Energy Potential in Morocco• Wind Resources Map of Morocco• Wind atlas of Morocco• Feasibility studies of windfarms• Wind measurement stations• Calibration of anemometers• Operation & maintenance of wind measurement stations• Follow up of wind measurement stations• Softwares for micrositing• Conclusion
  3. 3. Wind Energy Potantial in Morocco
  4. 4. Wind Energy Potential in Morocco Morocco has an excellent wind potential mainly in the North & in the South : - Essaouira, Tangier & Tetouan with an annual average between 9.5 & 11 m/s at 40 meters. - Tarfaya, Taza & Dakhla with an annual average between 7.5 m/s & 9.5 m/s at 40 meters. Wind Potential of Morocco :• Total Potential : 7936 TWh/year (2645 GW)• Technical Potential : 4896 TWh/year (1632 GW)• Wind Atlas of Morocco published in 1986, 1995 and updated in 2008.• More than 50 measurements stations installed by CDER between 1990 & 2009
  5. 5. Wind Energy Potential of Morocco (Results of study CDER/GTZ - July 2007) Total Technical Estimated Estimated EstimatedPotential Potential capacity capacity capacity to install to install to install in 2010 in 2012 in 20202,645,310 1,632,030 563 1,065 3,258 MW MW MW MW MW7,936 TWh 4,896 TWh 1.9 TWh 3.4 TWh 9.9 TWh Potential estimated to be installed : - until 2012 : 1000 MW to 2000 MW - until 2020 : 4000 MW to 7000 MW
  6. 6. Wind Resource Map of Morocco
  7. 7. New Wind Atlas of Morocco• An international call of tenders will be launched in the next few months for preparation of a new wind atlas of Morocco with a high resolution• In two years, possibility to access to the new wind atlas of Morocco directly via the web• We can zoom on different regions of Morocco• We can change some parameters
  8. 8. Feasibility studies of Wind Farms in Morocco
  9. 9. Steps of feasibility studies• Choice of sites• Wind measurement (minimum one year)• Micro-siting (Configuration of windturbines in site) : with Wasp, Windpro, WindFarm softwares or others• Production estimation• Economic & Financial feasibility• Civil Work study• Grid integration study• Impact Environmental (Impact of the project around the site, visual impact, Noise, Photomontage & Carbon Credit)
  10. 10. Wind measurement station near Tangier
  11. 11. Equipments of wind measurement stations• Measurement station of 60 meters : - 3 or 4 positions of anemometers - 2 positions of windvane• GSM system for transmission of data• Equipments of wind measurement stations : - Anemometers - Pressure, temperature & humidity - Dataloggers with a capacity of one year of data• Measurement of data for one year minimum
  12. 12. Equipments of wind measurement stations
  13. 13. Equipments of wind measurement stations
  14. 14. Complex terrain in the north of Morocco
  15. 15. Desert terrain in the south of Morocco
  16. 16. Calibration of anemometers
  17. 17. Calibration of anemometers• Calibration of anemometers before installation by institutes specialized• Calibration with measnet procedures• Measnet : Measuring Network of Wind Energy Institutes
  18. 18. Measnet anemometer Calibration procedure• The MEASNET procedure is considered to be the most internationally accepted procedure.• The MEASNET Quality Evaluation Program is based on the objective of continuously improving quality in measurements.• The “Reference Measurement Procedure” on which MEASNET Measurement Procedure is based is : IEC 61400-12-1:2005(E)
  19. 19. The Members of Measnet• CENER - Centro Nacional de Energias Renovables, Spain• CRES - Centre for Renewable Energy Sources, Greece• DEWI - Deutsches Windenergie-Institut GmbH, Germany• ECN - Energieonderzoek Centrum Nederland, The Netherlands• RISØ - National Laboratory, Denmark• TRIPOD Wind Energy ApS - TRIPOD Wind Energy ApS, Denmark• WindGuard - Deutsche WindGuard Wind Tunnel Services GmbH, Germany• WINDTEST - Kaiser-Wilhelm-Koog GmbH, Germany
  20. 20. The Members of Measnet• WINDTEST - Grevenbroich GmbH, Germany• Barlovento - Barlovento Recursos Naturales S.L., Spain• NREL - National Renewable Energy Laboratory, USA
  21. 21. Certificate of calibration(Anemometer Informations)
  22. 22. Certificate of calibration
  23. 23. Certificate of calibration (Calibration Results)
  24. 24. Certificate of calibration (Wind tunnel)
  25. 25. Before installation of dataloggers• Before installation of anemometers, make sure that you introduce slope & offset of each anemometer in the datalogger configuration• If you change an anemometer, you should introduce the new Slope & Offset.
  26. 26. Datalogger configuration
  27. 27. Operation & maintenance of measurement stations
  28. 28. Operation & maintenance of wind measurement stations• Triangular masts :  Easy installation of masts & equipements  Easy operation & maintenance of Anemometers, Windvanes, cables, etc….
  29. 29. Operation & maintenance of wind measurement stations• Tubular masts :  Need ‘’tire-fort’’ for installation of the mast  Need to disassemble the mast to repair or change the measuring instruments
  30. 30. Follow up of measurement stationsCompanyWind FarmCountryProvinceSiteStationLocalisationCoordinate systemYXCoordinate systemYXElevation (m)Date installationLast data
  31. 31. Informations about dataloggerData Logger Type & Serial Number installation date Disassembly date
  32. 32. Informations about anemometers, windvane, etc…Anemometers Type & Calibration installation Height Serial Disassembly date Slope( Offset Comments date Number m/s) (m/s) 60 50 30Windvanes Type & installation Disassembly Height Serial Offset (º) Comments date date Number 54 48
  33. 33. Informations about dataFiles Date Date Date Date Date Date DateName Files reception reception reception reception reception reception data data data data data data data Row StaReport (problems) Date of Date Description of Incident repair
  34. 34. Follow up of measurement stations Summary Data Date Report collectionNames Summary Chang.technicians Report GSM or PC Log. Next visit Comments
  35. 35. Assessment data
  36. 36. Wind Softwares• Assessment data with specialized softwares : - Alwin (Dewi Institute, Germany) - Wasp (Risoe Institute, Denmark) - WindPro (EMD Institute, Denmark) - WindFarm (Garrad Hassan, Great Britain) - or others softwares• Micro-siting (Configuration of windturbines in site)• Production estimation of windfarms
  37. 37. Frequency Distribution
  38. 38. Direction Distribution
  39. 39. Simulation by WASP Software.
  40. 40. Wind Farms in Morocco
  41. 41. Wind Farm of 50 MW (El Koudia El Baida -Tetouan) Power : 50 MW (84 Vestas 600 kW) Start production : 8/2000 Production : 200 GWh/year (Average) Wind measurement : CDER Operator : CED (EDF-Paribas-Germa/France) (selled to Theolia in december 2007) BOT for 20 years Average wind speed : - 10 m/s (at 40 meters) - 11 m/s (at 40 meters) in the best location in the site
  42. 42. Wind Farm 50 MW(El Koudia El Baida -Tetouan)
  43. 43. Wind Farm 60 MW Cap SIM (Essaouira) Power : 60 MW Windturbines : 71 Gamesa (G52-850 kW) Start production : 04/2007 Production estimated : 210 GWh/year Avearage wind speed (40 m) : 9.45 m/s Wind measurements : CDER Operator : ONE Project Cost : 800 millions DH (72 Millions Euro)
  44. 44. Wind Farm 60 MWCap SIM (Essaouira)
  45. 45. Wind Farm 140 MW Tangier Power : 140 MW Windturbines : 165 Gamesa (850 kW) Start production : 04/2009 (107 MW) Production estimated : 526,5 GWh/year Average wind speed (40 m) : 9 m/s Wind measurements : CDER Operator : ONE Project Cost : 2875 millions DH (250 Millions Euro)
  46. 46. Wind Farm 140 MW Tangier
  47. 47. Wind Farm 32 MW Lafarge (Cements Factory of Tetouan) Power : 32 MW - 10 MW (12 * 850 kW in 09/2005) - 10 MW (5 * 2 MW in 09/2008) - 12 MW (6 * 2 MW in 06/2009) Start production : 9/2005 Production estimated : 115 GWh/year (2009) Wind energy Production : - For use in the neigbouring cement factory in Tetouan - To transmit any electricity not consumed there to its other productions sites elsewhere in the country (Casablanca), via the ONE grid - Extra energy selled to ONE-grid Project Cost : 496 millions DH (44 MEuro)
  48. 48. Wind Farm 32 MWLafarge (Cements Factory of Tetouan)
  49. 49. Wind Farms Programmed (2010-2012)Objective of the Government : Production of 18 % of electricity from Renewable Energy (included Hydro) in 2012Wind Farms Programmed : 1333 MW until 2012Wind Farms installed : 253 MWProjects programmed :- Wind Farm 140 MW (Tangier) : - Start production of 107 MW in April 2009 - In construction 33 MW (April 2010)- Wind Farm 300 MW (Tarfaya) : BOT (Call of tenders, selection before 12/2009) - 200 MW (September 2011) - 100 MW (October 2012)- Self-producers projects : 1000 MW (2010-2012)
  50. 50. Conclusion• Operation & maintenance of wind measurement stations is very important to have a good data because an increase of 50-75% of wind speed, increases of 300-500% the power PV = 0,37 V3 (PV : Power of wind in W/m2 V : Wind speed in m/s)• Necessary to follow up wind measurement stations by GSM systems• Each month, it’s necessary to visit measurement stations & verification of anemometers, windvanes, cables of masts, etc….• After collection of data, it’s necessary to make verification of all anemometers data to detect a possible any default