  1. 1. Earned Value ManagementProject ManagementExamplePlannedTask 1 (1 week). Res1 (20€/h) & Res2 (30€/h)Start: Feb’1Ramon Costa i Pujo, 2010. www.pgpsi.comtwitter: RamonCostaPGPSI. www.linkedin.com/in/ramoncosta
  2. 2. Earned Value ManagementProject ManagementCase A. Current Date / Status Date: Feb ‘04Work done as plannedTable “Earned Value”Table “Earned Value Cost Indicators”Table “Earned Value Cost Indicators”Ramon Costa i Pujo, 2010. www.pgpsi.comtwitter: RamonCostaPGPSI. www.linkedin.com/in/ramoncosta
  3. 3. Earned Value ManagementProject ManagementCase B. Current Date: Feb ‘04DelayedTable “Earned Value”Table “Earned Value Cost Indicators”Table “Earned Value Schedule Indicators”Ramon Costa i Pujo, 2010. www.pgpsi.comtwitter: RamonCostaPGPSI. www.linkedin.com/in/ramoncosta
  4. 4. Earned Value ManagementProject ManagementCase B. Current / Status Date: Feb’04AdvancedTable “Earned Value”Table “Earned Value Cost Indicators”Table “Earned Value Schedule Indicators”Ramon Costa i Pujo, 2010. www.pgpsi.comtwitter: RamonCostaPGPSI. www.linkedin.com/in/ramoncosta

×