SlideShare a Scribd company logo
1 of 35
Chittagong City Outer Ring Road Project
Structural Part
Structure
CCORRP
IC Bridge
Sluice
Gate
Box
Culvert
Pipe
Culvert
Slope
Protection
Key Point of Structure
IC BRIDGE
 03 IC Bridge
 IC Bridge at Feeder Road 1
 IC Bridge at Toll Road Connection
 IC Bridge at Feeder Road 3
 Each Bridge Contain
 44 Nos. Pile
 01 Pier
 02 Abutment
 18 Nos. Girder
 2 Desk Slab
SLUICE GATE
 11 Nos. Sluice Gate.
 Total Length 1240 Meter approximate.
 1 nos. @ 6 Vent, 1 nos. @ 5 Vent, 1 nos. @ 4 Vent, 5 nos. @ 3 Vent, 3 nos. @ 2 Vent
 36 nos. Flap Gate.
 Component of Sluice Gate.
 Barrel
 Extended Part
 Apron
 Cut-off wall (MS Sheet Pile)
 Return Wall
 Floor Blocks.
BOX CULVERT
 15 nos. Box Culvert.
 Total 700 Meter approximate.
 3 nos. @ 2 Cell and 12 nos. @ 1 Cell
 Component of Pipe Culvert
 Barrel
 Headwall
 Apron
 Cut-off wall
PIPE CULVERT
 15 nos. Pipe Culvert.
 Total 300 Meter approximate.
 Pipe Inner Diameter 600 mm
 Pipe Outer Diameter 800 mm
 Component of Pipe Culvert
 Concrete Pipe.
 Base Slab
 Headwall
 Wing Wall
 Cut-off Wall
Sequence of Work
IC BRIDGE (Sequence of Work)
PIER
•Piling work at Pier Location (12 Nos.)
•Excavation Up to Pile Cap Bottom Level
•Pile Head Trimming (1st Stage)
•PIT and PDA Test
•Pile head Trimming (2nd Stage)
•Rebar Fabrication for Pile Cap
•Shuttering for Pile Cap
•Concreting of Pile Cap
•Rebar Fabrication for Pier Column
•Shuttering for Pier Column
•Concreting of Pier Column
•Shuttering of Pier Head
•Rebar Fabrication of Pier Head
•Concreting of Pier Head
ABUTMENT
•Removal of Surcharge
•Piling Work at Abutment (16 Nos.)
•Excavation Up to Pile Cap Bottom Level
•Pile Head Trimming (1st Stage)
•PIT and PDA Test
•Pile head Trimming (2nd Stage)
•Rebar Fabrication for Bank Seat
•Shuttering for Bank Seat
•Concreting of Bank Seat
•MSE Wall
OTHERS
•GIRDER
•Fixing of Bottom Shutter
•Rebar Fabrication with Duck Profile
•Side Shuttering
•Concreting
•Stressing
•Grouting
•Lifting and Shifting.
•Desk Slab
•Shuttering
•Rebar Fabrication
•Concreting
•Approach Slab
•Railing
SLUICE GATE (Sequence of Work)
01
•Side protection if any .
•Excavation Up to Required Level
•Sheet Piling for Cut-off Wall
•Levelling and dressing
•Plate test for Bearing capacity.
•Foundation Treatment If Required
•Lean Concrete
•Concreting of Bottom Slab
•Concreting of Web
•Concreting of Top Slab
02
•Concreting of Apron Slab
•Concreting of Extended Part
•Concreting of Wing Wall
•Concreting of Return Wall
•Concreting of Railing.
•Concreting of Trash Rake Frame
•CC Block pitching for Loose Apron
03
•Fabrication of Flip Gate
•Fabrication of Trash Rack
•Fixing of Flip Gate
•Fixing of Trash rack
PIPE CULVERT (Sequence of Work)
01
•Excavation Up to Required Level
•Levelling and dressing
•Plate test for Bearing capacity.
•Foundation Treatment If Required
•Lean Concrete
•Concreting of Cut-off Wall
02
•Concreting of Base Slab
•Placing of Concrete pipe
•Concreting of Head Wall
•Concreting of Wing Wall
Drawings
Sluice Gate Drawing
Sluice Gate Drawing
Sluice Gate Drawing
Sluice Gate Drawing
Sluice Gate Drawing
Sluice Gate Drawing
Sluice Gate Drawing
Plan
Plan
Pipe Culvert
Pipe Culvert
Box Culvert
IC Bridge
IC Bridge
Slope Protection
Slope Protection
Slope Protection
Structure
ID
Location
No. of
Vent
Barrel
Length
(m)
Extended Part
(m)
Apron
(m)
Loose Apron
(m)
Total
Length
(m)
Barrel
Width
(m)
Loose Apron
Width (m)
Barrel (R.L.) Apron (C/S) Apron (S/S)
C/S S/S C/S S/S C/S S/S C/S S/S Bottom Top Bottom Top Bottom Top
CR-01 14+800 6 60.700 1.80 1.80 9.00 24.65 8.30 10.30 116.550 13.650 35 42.55 -0.125 2.900 0.000 4.000 -1.600 3.000
CR-02 13+760 2 78.000 1.80 1.80 9.00 21.45 8.30 10.30 130.650 4.950 24.8 29.15 0.275 3.300 0.400 4.000 -0.800 3.000
CR-03 13+145 2 62.750 1.80 1.80 9.00 21.45 8.30 10.30 115.400 4.950 24.8 29.15 0.275 3.300 0.400 4.000 -0.800 3.000
CR-04 12+310 5 80.200 1.80 1.80 9.00 21.45 8.30 10.30 132.850 11.550 32.3 39.8 -0.425 2.600 -0.300 3.300 -1.500 3.000
CR-05 10+640 3 53.400 1.80 1.80 9.00 17.85 8.30 10.30 102.450 7.100 24.15 33.1 0.275 3.300 0.400 3.300 -0.600 3.500
CR-06 09+520 3 47.600 1.80 1.80 9.00 21.45 8.30 10.30 100.250 7.150 26.85 35.5 -0.425 2.600 -0.300 3.300 -1.500 3.000
CR-07 07+920 3 53.400 1.80 1.80 9.00 24.65 8.30 10.30 109.250 7.150 28.95 36.7 -0.225 2.800 -0.100 4.000 -1.700 3.000
CR-08 05+610 4 55.350 1.80 1.80 9.00 21.45 8.30 10.30 108.000 9.250 29.15 37.65 -0.425 2.600 -0.300 3.300 -1.500 3.000
CR-09 03+745 3 50.200 1.80 1.80 9.00 21.45 8.30 10.30 102.850 7.150 26.85 35.5 -0.425 2.600 -0.300 3.300 -1.500 3.000
CR-10 02+680 3 50.200 1.80 1.80 9.00 21.45 8.30 10.30 102.850 7.150 26.85 35.5 -0.425 2.600 -0.300 3.300 -1.500 3.000
CR-11 01+460 2 62.385 1.80 1.80 9.00 21.45 8.30 10.30 115.035 4.950 24.8 29.15 0.275 3.300 0.400 4.000 -0.800 3.000
Sluice gate

More Related Content

What's hot

Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road constructionSatish Kambaliya
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever BridgeJeelkumar Patel
 
Industrial training seminar PPT
Industrial training seminar PPTIndustrial training seminar PPT
Industrial training seminar PPTAbhishek Makwana
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGJAPJEETSINGH13
 
Signature bridge presentation
Signature bridge presentationSignature bridge presentation
Signature bridge presentationBhismo Dev
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017ktx500
 
Types of pavement construction procedure
Types of pavement construction procedureTypes of pavement construction procedure
Types of pavement construction procedureBhavik A Shah
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEsrinivas cnu
 
Procedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing methodProcedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing methodeSAT Journals
 
Design and construction of highway (flexible pavement
Design and construction of highway (flexible pavementDesign and construction of highway (flexible pavement
Design and construction of highway (flexible pavementsuraj vishwakarma
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING Ram1239
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONatchitect and design
 

What's hot (20)

Dmc pile
Dmc pileDmc pile
Dmc pile
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
Spine and wing method for box girders
Spine and wing method for box girdersSpine and wing method for box girders
Spine and wing method for box girders
 
Balanced Cantilever Bridge
Balanced Cantilever BridgeBalanced Cantilever Bridge
Balanced Cantilever Bridge
 
Concrete pavement design
Concrete pavement designConcrete pavement design
Concrete pavement design
 
Signature bridge
Signature bridgeSignature bridge
Signature bridge
 
Industrial training seminar PPT
Industrial training seminar PPTIndustrial training seminar PPT
Industrial training seminar PPT
 
Flyover construction
Flyover constructionFlyover construction
Flyover construction
 
Intership in DMRC
Intership in DMRCIntership in DMRC
Intership in DMRC
 
Industrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERINGIndustrial project report ppt CIVIL ENGINEERING
Industrial project report ppt CIVIL ENGINEERING
 
Signature bridge presentation
Signature bridge presentationSignature bridge presentation
Signature bridge presentation
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
 
Types of pavement construction procedure
Types of pavement construction procedureTypes of pavement construction procedure
Types of pavement construction procedure
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
Procedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing methodProcedure and construction of road under bridge by box pushing method
Procedure and construction of road under bridge by box pushing method
 
Design and construction of highway (flexible pavement
Design and construction of highway (flexible pavementDesign and construction of highway (flexible pavement
Design and construction of highway (flexible pavement
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
 
Metro Work
Metro WorkMetro Work
Metro Work
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 

Viewers also liked (6)

Presentation on Chittagong stock exchange
Presentation on Chittagong stock exchangePresentation on Chittagong stock exchange
Presentation on Chittagong stock exchange
 
Road, Culvert & Bridge Training
Road, Culvert & Bridge TrainingRoad, Culvert & Bridge Training
Road, Culvert & Bridge Training
 
Ch 27 culverts
Ch 27   culvertsCh 27   culverts
Ch 27 culverts
 
STRUCTURAL DESIGN OF PIPE CULVERT TO BS EN 1295-1
STRUCTURAL DESIGN OF PIPE CULVERT TO BS EN 1295-1STRUCTURAL DESIGN OF PIPE CULVERT TO BS EN 1295-1
STRUCTURAL DESIGN OF PIPE CULVERT TO BS EN 1295-1
 
Cu07821 7 culverts new
Cu07821 7 culverts newCu07821 7 culverts new
Cu07821 7 culverts new
 
Minor Project Report On Construction of Pipe Culvert
Minor Project Report  On Construction of  Pipe CulvertMinor Project Report  On Construction of  Pipe Culvert
Minor Project Report On Construction of Pipe Culvert
 

Similar to Chittagong City Outer Ring Road Project

. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
.   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro.....   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....IndraNathMishra2
 
A_MukherjeePresn for engineers good file
A_MukherjeePresn for engineers good fileA_MukherjeePresn for engineers good file
A_MukherjeePresn for engineers good fileZiad Salem
 
MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)sufiyan shaikh
 
28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimationimaduddin91
 
Ppt of pre casting yard
Ppt of pre casting yardPpt of pre casting yard
Ppt of pre casting yardRavinder Singh
 
JH Company catalog(English version) 20151109
JH Company catalog(English version) 20151109JH Company catalog(English version) 20151109
JH Company catalog(English version) 20151109Trade Marketing Inc.
 
Ship design project Final presentation
Ship design project Final presentationShip design project Final presentation
Ship design project Final presentationKifayath Chowdhury
 
Ppt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadPpt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadLachhmikant. Prasad
 
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanHDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanIndiaMART InterMESH Limited
 
Capstone Final Presentation
Capstone Final PresentationCapstone Final Presentation
Capstone Final PresentationChris Schultz
 
Steel Bridge for a construction of highway bridge in Nepal
Steel Bridge for a construction of highway bridge in NepalSteel Bridge for a construction of highway bridge in Nepal
Steel Bridge for a construction of highway bridge in NepalPoudel Dinesh
 
Ready rackner for qs
Ready rackner for qsReady rackner for qs
Ready rackner for qsHiren Thakkar
 
PNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxPNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxstilliegeorgiana
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectJill Reeves
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectJill Reeves
 
American insert-flange-catalog
American insert-flange-catalogAmerican insert-flange-catalog
American insert-flange-catalogChiragShah127
 
CONCRETE FILLED STEEL TUBULAR COLUMNS USING GS SHEET
CONCRETE FILLED STEEL TUBULAR COLUMNS USING GS SHEETCONCRETE FILLED STEEL TUBULAR COLUMNS USING GS SHEET
CONCRETE FILLED STEEL TUBULAR COLUMNS USING GS SHEETAL AMIN AZIZ
 

Similar to Chittagong City Outer Ring Road Project (20)

. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
.   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro.....   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
 
A_MukherjeePresn for engineers good file
A_MukherjeePresn for engineers good fileA_MukherjeePresn for engineers good file
A_MukherjeePresn for engineers good file
 
MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)MAIN CANOPY BAJAJ HR(22.09.2016)
MAIN CANOPY BAJAJ HR(22.09.2016)
 
Team 19
Team 19Team 19
Team 19
 
Brochure ENG (1)
Brochure ENG (1)Brochure ENG (1)
Brochure ENG (1)
 
28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation28725680 qarghayi-anp-estimation
28725680 qarghayi-anp-estimation
 
Ppt of pre casting yard
Ppt of pre casting yardPpt of pre casting yard
Ppt of pre casting yard
 
JH Company catalog(English version) 20151109
JH Company catalog(English version) 20151109JH Company catalog(English version) 20151109
JH Company catalog(English version) 20151109
 
Ship design project Final presentation
Ship design project Final presentationShip design project Final presentation
Ship design project Final presentation
 
Ppt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadPpt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasad
 
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanHDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
 
Capstone Final Presentation
Capstone Final PresentationCapstone Final Presentation
Capstone Final Presentation
 
Steel Bridge for a construction of highway bridge in Nepal
Steel Bridge for a construction of highway bridge in NepalSteel Bridge for a construction of highway bridge in Nepal
Steel Bridge for a construction of highway bridge in Nepal
 
main_brochure
main_brochuremain_brochure
main_brochure
 
Ready rackner for qs
Ready rackner for qsReady rackner for qs
Ready rackner for qs
 
PNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docxPNGE 310Class 21Overbalanced Drilling• Mos.docx
PNGE 310Class 21Overbalanced Drilling• Mos.docx
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
 
American insert-flange-catalog
American insert-flange-catalogAmerican insert-flange-catalog
American insert-flange-catalog
 
CONCRETE FILLED STEEL TUBULAR COLUMNS USING GS SHEET
CONCRETE FILLED STEEL TUBULAR COLUMNS USING GS SHEETCONCRETE FILLED STEEL TUBULAR COLUMNS USING GS SHEET
CONCRETE FILLED STEEL TUBULAR COLUMNS USING GS SHEET
 

Chittagong City Outer Ring Road Project

  • 1. Chittagong City Outer Ring Road Project Structural Part
  • 3. Key Point of Structure
  • 4. IC BRIDGE  03 IC Bridge  IC Bridge at Feeder Road 1  IC Bridge at Toll Road Connection  IC Bridge at Feeder Road 3  Each Bridge Contain  44 Nos. Pile  01 Pier  02 Abutment  18 Nos. Girder  2 Desk Slab
  • 5. SLUICE GATE  11 Nos. Sluice Gate.  Total Length 1240 Meter approximate.  1 nos. @ 6 Vent, 1 nos. @ 5 Vent, 1 nos. @ 4 Vent, 5 nos. @ 3 Vent, 3 nos. @ 2 Vent  36 nos. Flap Gate.  Component of Sluice Gate.  Barrel  Extended Part  Apron  Cut-off wall (MS Sheet Pile)  Return Wall  Floor Blocks.
  • 6. BOX CULVERT  15 nos. Box Culvert.  Total 700 Meter approximate.  3 nos. @ 2 Cell and 12 nos. @ 1 Cell  Component of Pipe Culvert  Barrel  Headwall  Apron  Cut-off wall
  • 7. PIPE CULVERT  15 nos. Pipe Culvert.  Total 300 Meter approximate.  Pipe Inner Diameter 600 mm  Pipe Outer Diameter 800 mm  Component of Pipe Culvert  Concrete Pipe.  Base Slab  Headwall  Wing Wall  Cut-off Wall
  • 9. IC BRIDGE (Sequence of Work) PIER •Piling work at Pier Location (12 Nos.) •Excavation Up to Pile Cap Bottom Level •Pile Head Trimming (1st Stage) •PIT and PDA Test •Pile head Trimming (2nd Stage) •Rebar Fabrication for Pile Cap •Shuttering for Pile Cap •Concreting of Pile Cap •Rebar Fabrication for Pier Column •Shuttering for Pier Column •Concreting of Pier Column •Shuttering of Pier Head •Rebar Fabrication of Pier Head •Concreting of Pier Head ABUTMENT •Removal of Surcharge •Piling Work at Abutment (16 Nos.) •Excavation Up to Pile Cap Bottom Level •Pile Head Trimming (1st Stage) •PIT and PDA Test •Pile head Trimming (2nd Stage) •Rebar Fabrication for Bank Seat •Shuttering for Bank Seat •Concreting of Bank Seat •MSE Wall OTHERS •GIRDER •Fixing of Bottom Shutter •Rebar Fabrication with Duck Profile •Side Shuttering •Concreting •Stressing •Grouting •Lifting and Shifting. •Desk Slab •Shuttering •Rebar Fabrication •Concreting •Approach Slab •Railing
  • 10. SLUICE GATE (Sequence of Work) 01 •Side protection if any . •Excavation Up to Required Level •Sheet Piling for Cut-off Wall •Levelling and dressing •Plate test for Bearing capacity. •Foundation Treatment If Required •Lean Concrete •Concreting of Bottom Slab •Concreting of Web •Concreting of Top Slab 02 •Concreting of Apron Slab •Concreting of Extended Part •Concreting of Wing Wall •Concreting of Return Wall •Concreting of Railing. •Concreting of Trash Rake Frame •CC Block pitching for Loose Apron 03 •Fabrication of Flip Gate •Fabrication of Trash Rack •Fixing of Flip Gate •Fixing of Trash rack
  • 11. PIPE CULVERT (Sequence of Work) 01 •Excavation Up to Required Level •Levelling and dressing •Plate test for Bearing capacity. •Foundation Treatment If Required •Lean Concrete •Concreting of Cut-off Wall 02 •Concreting of Base Slab •Placing of Concrete pipe •Concreting of Head Wall •Concreting of Wing Wall
  • 13.
  • 21.
  • 22. Plan
  • 23. Plan
  • 24.
  • 28.
  • 31.
  • 35. Structure ID Location No. of Vent Barrel Length (m) Extended Part (m) Apron (m) Loose Apron (m) Total Length (m) Barrel Width (m) Loose Apron Width (m) Barrel (R.L.) Apron (C/S) Apron (S/S) C/S S/S C/S S/S C/S S/S C/S S/S Bottom Top Bottom Top Bottom Top CR-01 14+800 6 60.700 1.80 1.80 9.00 24.65 8.30 10.30 116.550 13.650 35 42.55 -0.125 2.900 0.000 4.000 -1.600 3.000 CR-02 13+760 2 78.000 1.80 1.80 9.00 21.45 8.30 10.30 130.650 4.950 24.8 29.15 0.275 3.300 0.400 4.000 -0.800 3.000 CR-03 13+145 2 62.750 1.80 1.80 9.00 21.45 8.30 10.30 115.400 4.950 24.8 29.15 0.275 3.300 0.400 4.000 -0.800 3.000 CR-04 12+310 5 80.200 1.80 1.80 9.00 21.45 8.30 10.30 132.850 11.550 32.3 39.8 -0.425 2.600 -0.300 3.300 -1.500 3.000 CR-05 10+640 3 53.400 1.80 1.80 9.00 17.85 8.30 10.30 102.450 7.100 24.15 33.1 0.275 3.300 0.400 3.300 -0.600 3.500 CR-06 09+520 3 47.600 1.80 1.80 9.00 21.45 8.30 10.30 100.250 7.150 26.85 35.5 -0.425 2.600 -0.300 3.300 -1.500 3.000 CR-07 07+920 3 53.400 1.80 1.80 9.00 24.65 8.30 10.30 109.250 7.150 28.95 36.7 -0.225 2.800 -0.100 4.000 -1.700 3.000 CR-08 05+610 4 55.350 1.80 1.80 9.00 21.45 8.30 10.30 108.000 9.250 29.15 37.65 -0.425 2.600 -0.300 3.300 -1.500 3.000 CR-09 03+745 3 50.200 1.80 1.80 9.00 21.45 8.30 10.30 102.850 7.150 26.85 35.5 -0.425 2.600 -0.300 3.300 -1.500 3.000 CR-10 02+680 3 50.200 1.80 1.80 9.00 21.45 8.30 10.30 102.850 7.150 26.85 35.5 -0.425 2.600 -0.300 3.300 -1.500 3.000 CR-11 01+460 2 62.385 1.80 1.80 9.00 21.45 8.30 10.30 115.035 4.950 24.8 29.15 0.275 3.300 0.400 4.000 -0.800 3.000 Sluice gate