9. IC BRIDGE (Sequence of Work)
PIER
•Piling work at Pier Location (12 Nos.)
•Excavation Up to Pile Cap Bottom Level
•Pile Head Trimming (1st Stage)
•PIT and PDA Test
•Pile head Trimming (2nd Stage)
•Rebar Fabrication for Pile Cap
•Shuttering for Pile Cap
•Concreting of Pile Cap
•Rebar Fabrication for Pier Column
•Shuttering for Pier Column
•Concreting of Pier Column
•Shuttering of Pier Head
•Rebar Fabrication of Pier Head
•Concreting of Pier Head
ABUTMENT
•Removal of Surcharge
•Piling Work at Abutment (16 Nos.)
•Excavation Up to Pile Cap Bottom Level
•Pile Head Trimming (1st Stage)
•PIT and PDA Test
•Pile head Trimming (2nd Stage)
•Rebar Fabrication for Bank Seat
•Shuttering for Bank Seat
•Concreting of Bank Seat
•MSE Wall
OTHERS
•GIRDER
•Fixing of Bottom Shutter
•Rebar Fabrication with Duck Profile
•Side Shuttering
•Concreting
•Stressing
•Grouting
•Lifting and Shifting.
•Desk Slab
•Shuttering
•Rebar Fabrication
•Concreting
•Approach Slab
•Railing
10. SLUICE GATE (Sequence of Work)
01
•Side protection if any .
•Excavation Up to Required Level
•Sheet Piling for Cut-off Wall
•Levelling and dressing
•Plate test for Bearing capacity.
•Foundation Treatment If Required
•Lean Concrete
•Concreting of Bottom Slab
•Concreting of Web
•Concreting of Top Slab
02
•Concreting of Apron Slab
•Concreting of Extended Part
•Concreting of Wing Wall
•Concreting of Return Wall
•Concreting of Railing.
•Concreting of Trash Rake Frame
•CC Block pitching for Loose Apron
03
•Fabrication of Flip Gate
•Fabrication of Trash Rack
•Fixing of Flip Gate
•Fixing of Trash rack
11. PIPE CULVERT (Sequence of Work)
01
•Excavation Up to Required Level
•Levelling and dressing
•Plate test for Bearing capacity.
•Foundation Treatment If Required
•Lean Concrete
•Concreting of Cut-off Wall
02
•Concreting of Base Slab
•Placing of Concrete pipe
•Concreting of Head Wall
•Concreting of Wing Wall