2. You are part of a project team designing a new type of a vehicle. You are about to begin work on
a work package for the braking system of the vehicle and want to review the acceptance criteria
before starting the work.
Where can you find this information?
A. Project management plan
B. Activity attributes
C. Requirements documentation
D. The WBS dictionary
HINT: This document is developed during the Create WBS process.
Question
3. The correct answer is D.
A work package is the lowest level of the WBS and provides a general description of the work to be
completed by this work package. The WBS dictionary supplements the WBS by including more detailed
information for each work package or other WBS components.
The WBS dictionary is an output of the Create WBS process and provides information such as the
description of work, schedule milestones, quality requirements, and acceptance criteria for each work
package.
Therefore, the acceptance criteria for the work package to be completed are described in the WBS
dictionary.
Answer
4. Note, the wording of the question, "You are about to begin work on a work package...", suggests that
project execution has already begun, thus implying the project management plan including all its
components (such as the scope baseline that includes the WBS dictionary) has been finalized and
approved.
Answer
5. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.