Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
2. You are using Microsoft Project as a tool to manage the project. All the activities have been
recorded and the Work Breakdown Structure has been prepared. Your project team wants to use
different units of work for different resources. Which document establishes the information
regarding units of measurement for resources on a project?
A. Enterprise Environmental Factors
B. Cost Management Plan
C. Project Charter
D. Performance Measurement Documents
HINT: Units of measurement are contained in one of the Project Management Plan's subsidiary
plans.
Question
3. The correct answer is B.
The Cost Management Plan establishes units of measurement such as staff hours, staff days, and
staff weeks.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.