Hello everyone! Test your PMP exam preparation and answer this Free PMP® Exam Sample Question of the week. For more of this free PMP exam sample question visit: https://free.pm-exam-simulator.com/free-pmp-exam-simulator
2. You are managing a project dealing with a limited amount of resources. Trying to optimize the
resources, you have applied a resource management technique which resulted in the critical path
of the project schedule to increase. Which resource management technique have you applied?
A. Resource compromising
B. Resource leveling
C. Resource estimating
D. Resource smoothing
HINT: This technique adjusts activity schedules based on the resource constraints.
Question
3. The correct answer is B.
Resource leveling is a resource optimization technique in which start and finish dates are
adjusted based on resource constraints with the goal of balancing demand for resources with the
available supply. Resource leveling can be used when shared or critically required resources are
only available at certain times, or in limited quantities, or over-allocated. Resource leveling can
often cause the original critical path to increase.
Answer
4. All our questions are updated to the latest
A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the
PM Exam Simulator free for 7 days.
We are a trusted and experienced education provider.