Successfully reported this slideshow.
We use your LinkedIn profile and activity data to personalize ads and to show you more relevant ads. You can change your ad preferences anytime.

Free PMP Exam Sample Question 185

829 views

Published on

This PMP® Exam Sample Question is taken from the Free PMP Exam Simulator free.pm-exam-simulator.com

Published in: Education, Technology
  • Be the first to comment

Free PMP Exam Sample Question 185

  1. 1. Free PMP® Exam Sample Question PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
  2. 2. 2 The following PMP® Exam Sample Question is taken from the Free PMP Exam Simulator:
  3. 3. 3 PMP® Exam Sample Question On a project, several risk response strategies may be used to effectively manage project risks. The strategy or mix of strategies should be determined when planning for risk responses. Which of the following statements best describes an Accept risk response strategy for negative risks or threats? A.) Adopting less complex processes B.) Purchasing insurance C.) Establishing Contingency Reserves D.) Extending the schedule
  4. 4. 4 A risk acceptance strategy is adopted when it is impossible to eliminate all threats from a project. One of the answer choices is performed in the early stages of planning. All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam- simulator.com and try the PMP® Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI® Registered Education Provider. Hint:
  5. 5. 5 The correct answer is C. Explanation: The most common risk acceptance strategy is to establish contingency reserves, which is normally performed in the planning phase of a project. Answer and Explanation:

×