SlideShare a Scribd company logo
1 of 10
5 steps to writing a project risk
Author: PM Majik
Copyright 2015. All rights reserved. www.pmmajik.com
Contents
1.0 Purpose of this presentation
2.0 Risk title
3.0 Risk detail
4.0 Risk consequence
5.0 Target resolution date
6.0 Mitigating action
7.0 Summary
8.0 PMO resources
Copyright 2015. All rights reserved. www.pmmajik.com
1.0 Purpose of this presentation
The purpose of this presentation is to provide the 5 steps to writing a project risk,
including examples of good and bad.
Unfortunately many project risks are poorly written and as a consequence are not
managed. If risks are not managed they can delay the completion of the project.
5 steps to writing a project risk
1. Risk title
2. Risk detail
3. Risk consequence
4. Target resolution date
5. Mitigating action
Copyright 2015. All rights reserved. www.pmmajik.com
2.0 Risk title
• Each risk needs a title that gives an indication of the nature of the risk.
Poor Title
Resources
•Too generic
•Does not specify resource type
•Does not specify if there are not
enough / too many resources
•Does not specify why they are
needed
Good Title
Lack of resources to develop
website interface
•Title is specific
•Identifies resource type
•Identifies there are not resources
•Specifies what they are needed for
Copyright 2015. All rights reserved. www.pmmajik.com
3.0 Risk detail
• Each risk needs a clear description that explains the risk so that it can be
understood. Avoid project language, technical terms and acronyms.
Poor Risk Detail
There may not be sufficient
resources to complete the project.
•Does not specify resource type
•Does not specify when they are
required
•Does not specify what work needs
to be completed
Good Risk Detail
There may not be sufficient java
developers to complete the
development of the website
interface between September and
October 2014.
•Identifies resource type
•Identifies there are not enough
resources
•Specifies what they are needed for
•Defines when they are needed
Copyright 2015. All rights reserved. www.pmmajik.com
4.0 Risk consequence
• The reason for identifying a project risk is that they usually will have some
form of impact on the project if the risk becomes an issue. Therefore, it is
important to document the consequence so that the reviewers can
understand the consequence to the project if the risk is not managed.
Poor Risk Consequence
Lack of resources may cause delays.
•Generic statement
•Does not explain consequence of
not having the required resources
Good Risk Consequence
Delays to completing the website
interface development by 31st
October 2014. This will directly
delay the testing phase. Each day
delay during development will
extend the completion date of the
project by 1 day.
•Clearly defines consequence that
there will be a delay in the project if
resources not secured.
Copyright 2015. All rights reserved. www.pmmajik.com
5.0 Target resolution date
• This is the date by when the risk needs to be addressed (mitigating action
taken) or accepted (the project is happy to accept the impact if the risk
becomes an issue).
Poor Target Resolution Date
No date specified, TBC (to be
confirmed), TBA (to be advised),
general dates (i.e. end of year, end
of project).
•If there is no clear understanding
when the risk needs to be
addressed, it is usually because it
has not been clearly defined. It is
common to see generic risks
relating to resources and the end
date being set as end of year /
project.
Good Target Resolution Date
This should be the date by when
action needs to be taken to address
the risk. In this example 1st
September 2014 as resources
needed on this date to start work
•Important: try to set real dates as
opposed to ones where it does not
matter. If a date is set and missed
and there is no consequence, it will
mean that other deadlines will not
be taken seriously.
Copyright 2015. All rights reserved. www.pmmajik.com
6.0 Mitigating action
• Defining the risk is only part of what needs to be captured. The project team
should also provide proposed mitigation (the action to be taken to address
the risk).
Poor Mitigating Action
Monitor resources to identify
delays.
•Generic statement that states that
resources will be monitored. This
will probably result in lack of
resources only being known when
it is too late.
Good Mitigating Action
Identify named resources to
complete java website interface
and gain agreement that they will
be available to support
development between September
and October. As contingency,
engage 3rd party provider of java
developers to see if they can
provide resources at short notice
should they be required.
•This mitigating action gains
commitment of the required
resources and also tries to put in
place a back-up plan.Copyright 2015. All rights reserved. www.pmmajik.com
7.0 Summary
Follow these 5 steps to capture and document project risks that can be monitored and
progressed.
Reminder of the list:
1. Risk title
2. Risk detail
3. Risk consequence
4. Target resolution date
5. Mitigating action
Additional Resource
http://www.pmmajik.com/5-steps-write-good-project-risk/
Copyright 2015. All rights reserved. www.pmmajik.com
8.0 PMO resources
If you want more information, visit www.pmmajik.com where you will find lots of project
and PMO resources including the FREE guide, 7 Steps to Set-Up a PMO.
Visit http://www.pmmajik.com/set-pmo/
PM Majik Website
On the PM Majik website you will find over 100 articles that contain practical and
pragmatic tips and insights for designing, mobilising and managing a PMO. New
articles are added weekly. Topic requests are encouraged from the community.
Copyright 2015. All rights reserved. www.pmmajik.com

More Related Content

More from PM Majik

Agile Project Management Roles
Agile Project Management RolesAgile Project Management Roles
Agile Project Management RolesPM Majik
 
PMO (Project Management Office) Meaning
PMO (Project Management Office) MeaningPMO (Project Management Office) Meaning
PMO (Project Management Office) MeaningPM Majik
 
How to create and use a project RACI matrix
How to create and use a project RACI matrixHow to create and use a project RACI matrix
How to create and use a project RACI matrixPM Majik
 
8 project management reports you need for your project
8 project management reports you need for your project8 project management reports you need for your project
8 project management reports you need for your projectPM Majik
 
5 steps project change control process
5 steps project change control process5 steps project change control process
5 steps project change control processPM Majik
 
PMO standardisation - simple tracking process
PMO standardisation - simple tracking processPMO standardisation - simple tracking process
PMO standardisation - simple tracking processPM Majik
 
5 tips for PMO Template design
5 tips for PMO Template design5 tips for PMO Template design
5 tips for PMO Template designPM Majik
 
Core project V PMO templates
Core project V PMO templatesCore project V PMO templates
Core project V PMO templatesPM Majik
 
Challenges to getting a role in a project management office (and how they can...
Challenges to getting a role in a project management office (and how they can...Challenges to getting a role in a project management office (and how they can...
Challenges to getting a role in a project management office (and how they can...PM Majik
 

More from PM Majik (9)

Agile Project Management Roles
Agile Project Management RolesAgile Project Management Roles
Agile Project Management Roles
 
PMO (Project Management Office) Meaning
PMO (Project Management Office) MeaningPMO (Project Management Office) Meaning
PMO (Project Management Office) Meaning
 
How to create and use a project RACI matrix
How to create and use a project RACI matrixHow to create and use a project RACI matrix
How to create and use a project RACI matrix
 
8 project management reports you need for your project
8 project management reports you need for your project8 project management reports you need for your project
8 project management reports you need for your project
 
5 steps project change control process
5 steps project change control process5 steps project change control process
5 steps project change control process
 
PMO standardisation - simple tracking process
PMO standardisation - simple tracking processPMO standardisation - simple tracking process
PMO standardisation - simple tracking process
 
5 tips for PMO Template design
5 tips for PMO Template design5 tips for PMO Template design
5 tips for PMO Template design
 
Core project V PMO templates
Core project V PMO templatesCore project V PMO templates
Core project V PMO templates
 
Challenges to getting a role in a project management office (and how they can...
Challenges to getting a role in a project management office (and how they can...Challenges to getting a role in a project management office (and how they can...
Challenges to getting a role in a project management office (and how they can...
 

Recently uploaded

digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingrajputmeenakshi733
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerAggregage
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfJamesConcepcion7
 
Data Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and TemplatesData Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and TemplatesAurelien Domont, MBA
 
Interoperability and ecosystems: Assembling the industrial metaverse
Interoperability and ecosystems:  Assembling the industrial metaverseInteroperability and ecosystems:  Assembling the industrial metaverse
Interoperability and ecosystems: Assembling the industrial metaverseSiemens
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdfChris Skinner
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...Aggregage
 
Psychic Reading | Spiritual Guidance – Astro Ganesh Ji
Psychic Reading | Spiritual Guidance – Astro Ganesh JiPsychic Reading | Spiritual Guidance – Astro Ganesh Ji
Psychic Reading | Spiritual Guidance – Astro Ganesh Jiastral oracle
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...SOFTTECHHUB
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOne Monitar
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifeBhavana Pujan Kendra
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers referencessuser2c065e
 
14680-51-4.pdf Good quality CAS Good quality CAS
14680-51-4.pdf  Good  quality CAS Good  quality CAS14680-51-4.pdf  Good  quality CAS Good  quality CAS
14680-51-4.pdf Good quality CAS Good quality CAScathy664059
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 

Recently uploaded (20)

digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketing
 
Driving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon HarmerDriving Business Impact for PMs with Jon Harmer
Driving Business Impact for PMs with Jon Harmer
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptxThe Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
The Bizz Quiz-E-Summit-E-Cell-IITPatna.pptx
 
WSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdfWSMM Media and Entertainment Feb_March_Final.pdf
WSMM Media and Entertainment Feb_March_Final.pdf
 
Data Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and TemplatesData Analytics Strategy Toolkit and Templates
Data Analytics Strategy Toolkit and Templates
 
Interoperability and ecosystems: Assembling the industrial metaverse
Interoperability and ecosystems:  Assembling the industrial metaverseInteroperability and ecosystems:  Assembling the industrial metaverse
Interoperability and ecosystems: Assembling the industrial metaverse
 
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
20220816-EthicsGrade_Scorecard-JP_Morgan_Chase-Q2-63_57.pdf
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
Strategic Project Finance Essentials: A Project Manager’s Guide to Financial ...
 
Psychic Reading | Spiritual Guidance – Astro Ganesh Ji
Psychic Reading | Spiritual Guidance – Astro Ganesh JiPsychic Reading | Spiritual Guidance – Astro Ganesh Ji
Psychic Reading | Spiritual Guidance – Astro Ganesh Ji
 
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
How To Simplify Your Scheduling with AI Calendarfly The Hassle-Free Online Bo...
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in Life
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
14680-51-4.pdf Good quality CAS Good quality CAS
14680-51-4.pdf  Good  quality CAS Good  quality CAS14680-51-4.pdf  Good  quality CAS Good  quality CAS
14680-51-4.pdf Good quality CAS Good quality CAS
 
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 

5 steps to writing an effective project risk

  • 1. 5 steps to writing a project risk Author: PM Majik Copyright 2015. All rights reserved. www.pmmajik.com
  • 2. Contents 1.0 Purpose of this presentation 2.0 Risk title 3.0 Risk detail 4.0 Risk consequence 5.0 Target resolution date 6.0 Mitigating action 7.0 Summary 8.0 PMO resources Copyright 2015. All rights reserved. www.pmmajik.com
  • 3. 1.0 Purpose of this presentation The purpose of this presentation is to provide the 5 steps to writing a project risk, including examples of good and bad. Unfortunately many project risks are poorly written and as a consequence are not managed. If risks are not managed they can delay the completion of the project. 5 steps to writing a project risk 1. Risk title 2. Risk detail 3. Risk consequence 4. Target resolution date 5. Mitigating action Copyright 2015. All rights reserved. www.pmmajik.com
  • 4. 2.0 Risk title • Each risk needs a title that gives an indication of the nature of the risk. Poor Title Resources •Too generic •Does not specify resource type •Does not specify if there are not enough / too many resources •Does not specify why they are needed Good Title Lack of resources to develop website interface •Title is specific •Identifies resource type •Identifies there are not resources •Specifies what they are needed for Copyright 2015. All rights reserved. www.pmmajik.com
  • 5. 3.0 Risk detail • Each risk needs a clear description that explains the risk so that it can be understood. Avoid project language, technical terms and acronyms. Poor Risk Detail There may not be sufficient resources to complete the project. •Does not specify resource type •Does not specify when they are required •Does not specify what work needs to be completed Good Risk Detail There may not be sufficient java developers to complete the development of the website interface between September and October 2014. •Identifies resource type •Identifies there are not enough resources •Specifies what they are needed for •Defines when they are needed Copyright 2015. All rights reserved. www.pmmajik.com
  • 6. 4.0 Risk consequence • The reason for identifying a project risk is that they usually will have some form of impact on the project if the risk becomes an issue. Therefore, it is important to document the consequence so that the reviewers can understand the consequence to the project if the risk is not managed. Poor Risk Consequence Lack of resources may cause delays. •Generic statement •Does not explain consequence of not having the required resources Good Risk Consequence Delays to completing the website interface development by 31st October 2014. This will directly delay the testing phase. Each day delay during development will extend the completion date of the project by 1 day. •Clearly defines consequence that there will be a delay in the project if resources not secured. Copyright 2015. All rights reserved. www.pmmajik.com
  • 7. 5.0 Target resolution date • This is the date by when the risk needs to be addressed (mitigating action taken) or accepted (the project is happy to accept the impact if the risk becomes an issue). Poor Target Resolution Date No date specified, TBC (to be confirmed), TBA (to be advised), general dates (i.e. end of year, end of project). •If there is no clear understanding when the risk needs to be addressed, it is usually because it has not been clearly defined. It is common to see generic risks relating to resources and the end date being set as end of year / project. Good Target Resolution Date This should be the date by when action needs to be taken to address the risk. In this example 1st September 2014 as resources needed on this date to start work •Important: try to set real dates as opposed to ones where it does not matter. If a date is set and missed and there is no consequence, it will mean that other deadlines will not be taken seriously. Copyright 2015. All rights reserved. www.pmmajik.com
  • 8. 6.0 Mitigating action • Defining the risk is only part of what needs to be captured. The project team should also provide proposed mitigation (the action to be taken to address the risk). Poor Mitigating Action Monitor resources to identify delays. •Generic statement that states that resources will be monitored. This will probably result in lack of resources only being known when it is too late. Good Mitigating Action Identify named resources to complete java website interface and gain agreement that they will be available to support development between September and October. As contingency, engage 3rd party provider of java developers to see if they can provide resources at short notice should they be required. •This mitigating action gains commitment of the required resources and also tries to put in place a back-up plan.Copyright 2015. All rights reserved. www.pmmajik.com
  • 9. 7.0 Summary Follow these 5 steps to capture and document project risks that can be monitored and progressed. Reminder of the list: 1. Risk title 2. Risk detail 3. Risk consequence 4. Target resolution date 5. Mitigating action Additional Resource http://www.pmmajik.com/5-steps-write-good-project-risk/ Copyright 2015. All rights reserved. www.pmmajik.com
  • 10. 8.0 PMO resources If you want more information, visit www.pmmajik.com where you will find lots of project and PMO resources including the FREE guide, 7 Steps to Set-Up a PMO. Visit http://www.pmmajik.com/set-pmo/ PM Majik Website On the PM Majik website you will find over 100 articles that contain practical and pragmatic tips and insights for designing, mobilising and managing a PMO. New articles are added weekly. Topic requests are encouraged from the community. Copyright 2015. All rights reserved. www.pmmajik.com