TAHAPAN-TAHAPAN DALAMPENGERJAAN BETON
TAHAPAN-TAHAPAN DALAM PENGERJAAN BETON   PERSIAPAN   PENAKARAN   PENGADUKAN   PENGANGKUTAN   PENGECORAN   PEMADATAN...
PERSIAPANSemua peralatan untuk pengadukan dan pengangkutan beton harus bersihRuang yang akan diisi beton harus bebas dari ...
PENAKARANPENAKARAN DARI HASIL RANCANGAN AHRUS MENGIKUTIKENTENTUAN                  YA N G     TERTUANG         DALAM      ...
PENGADUKANSECARA         UMUM       PENGADUKAN                DILAKUKAN        S A M PA ID I D A PAT K A N    S U AT U  S ...
PENGANGKUTAN  A L AT P E N G A N G K U TA N D I B E D A K A N M E N J A D I  2 , YA I T U :  A L AT A N G K U M A N U A L ...
PENGECORAN Campuran yang akan dituangkan harus  ditempatkan sedekat mungkin dengan cetakan  untuk mencegah segregasi kare...
PEMADATAN P E M A D ATA N     DILAKUKAN            SESEGERA MUNGKIN                SETELAH                BETON DITUANGKAN...
PERAWATANPerawatan beton dilakukan setelah beton  mencapai Final Setting, artinya beton  telah mengeras. Perawatan ini dil...
SEKIAN DAN TERIMA KASIH
SOAL POST TEST1. Sebutkan dan jelaskan tahapan-tahapan   pengecoran beton secara berurutan?
Upcoming SlideShare
Loading in …5
×

Tahapan tahapan dalam pengerjaan beton

8,788 views

Published on

Published in: Sports, Business
  • Be the first to comment

  • Be the first to like this

Tahapan tahapan dalam pengerjaan beton

  1. 1. TAHAPAN-TAHAPAN DALAMPENGERJAAN BETON
  2. 2. TAHAPAN-TAHAPAN DALAM PENGERJAAN BETON PERSIAPAN PENAKARAN PENGADUKAN PENGANGKUTAN PENGECORAN PEMADATAN perawatan
  3. 3. PERSIAPANSemua peralatan untuk pengadukan dan pengangkutan beton harus bersihRuang yang akan diisi beton harus bebas dari kotoran-kotoran yang mengganggu.Untuk memudahkan pembukaan acuan, permukaan dalam acuan harus dilapisi dengan bahan khusus, antara lain lapisan minyak mineral, lapisan bahan kimia (form release agent) atau lembaran polyurethen.Pasangan dinding bata yang berhubungan langsung dengan beton harus dibasahi air sampai jenuhTulangan harus dalam keadaan bersih dan bebas dari segala lapisan penutup yang dapat merusak beton atau mengurangi lekatan antara beton dengan tulangan.
  4. 4. PENAKARANPENAKARAN DARI HASIL RANCANGAN AHRUS MENGIKUTIKENTENTUAN YA N G TERTUANG DALAM PA S A L 3.3.2S K . S N I . T- 2 8 - 1 9 9 1 - 0 3 T E N TA N G TATA C A R A P E N G A D U K A ND A N P E N G E C O R A N B E T O N , A S T M C . 6 8 5 S TA N D A R D M A D EB Y V O L U M E T R I C B AT H I N G A N D C O N T I N U O U S M I X I N G , S N I03-2834-2000 TATA CARA P E M B U ATA N RENCANACAMPURAN BETON NORMAL, S E R TA A S T M . 9 4 SEBAGAIBERIKUT :1. BETON YA N G M E M P U N YA I K E K U ATA N TEKAN (F’C) L E B I H B E S A R ATA U S A M A D E N G A N 2 0 M PA P R O P O R S I P E N A K A R A N N YA D I D A S A R K A N ATA S B E R AT.2. BETON YA N G M E M P U N YAI K E K U ATA N TEKAN (F’C) L E B I H K E C I L D AR I 2 0 M PA P R O P O R S I P E N A K A R A N N YA BOLEH MENGGUNAKAN TEKNIK PENAKARAN VOLUME.
  5. 5. PENGADUKANSECARA UMUM PENGADUKAN DILAKUKAN S A M PA ID I D A PAT K A N S U AT U S I FAT YA N G PLASTIS DALAMC A M P U R A N B E O N S E G A R . I N D I K A S I N YA A D A L A H WA R N AADUKAN M E R ATA , KELECAKAN YA N G C U K U P, TA M PA KHOMOGEN.SELAMA PROSES PENGADUKAN, HARUS DILAKUKANP E N D ATA A N R I N C I M E N G E N A I : J U M L A H B AT C H - A D U K YA N G D I H A S I L K A N P R O P O R S I M AT E R I A L PERKIRAAN LOKASI DARI PENUANGAN AKHIR PA D A STRUKTUR WAKTU DAN TA N G G A L PENGADUKAN S E RTA PENUANGANM A C A M - M A C A M P E N G A D U K A N B E T O N P R A C E TA K : PENGADUKAN MANUAL PENGADUKAN DENGAN MESIN
  6. 6. PENGANGKUTAN A L AT P E N G A N G K U TA N D I B E D A K A N M E N J A D I 2 , YA I T U : A L AT A N G K U M A N U A L A L AT A N G K U T S E D E R H A N A A L AT A N G K U T M E S I N
  7. 7. PENGECORAN Campuran yang akan dituangkan harus ditempatkan sedekat mungkin dengan cetakan untuk mencegah segregasi karena pengaliran adukan Penuangan harus dilaksanakan dengan kecepatan penuangan yang diatur sedemikian rupa sehingga campuran beton selalu dalam keadaan plastis Campuran beton yang telah nengeras atau terkotori oleh material asing tidak boleh dituang Penuangan beton harus dilakukan tanpa henti hingga terselesaikannya suatu penampang atau batas-batas penghentian Beton yang dituangkan harus dipadatkan
  8. 8. PEMADATAN P E M A D ATA N DILAKUKAN SESEGERA MUNGKIN SETELAH BETON DITUANGKAN. KEBUTUHAN A L AT P E M A D ATA N SESUAI DENGAN K A PA S I TA S P E N G E C O R A N D A N T I N G K AT K E S U L I TA N P E N G E R J A A N . P E M A D ATA N DIMAKSUDKAN UNTUK MENGHILANGKAN RONGGA-RONGGA UDARA YA N G T E R D A PAT D A L A M B E T O N S E G A R .
  9. 9. PERAWATANPerawatan beton dilakukan setelah beton mencapai Final Setting, artinya beton telah mengeras. Perawatan ini dilakukan agar proses hidrasi selanjutnya tidak mengalami gangguan. Jika hal ini terjadi, beton akan mengalami keretakkan karena kehilangan air yang begitu cepat.
  10. 10. SEKIAN DAN TERIMA KASIH
  11. 11. SOAL POST TEST1. Sebutkan dan jelaskan tahapan-tahapan pengecoran beton secara berurutan?

×