SlideShare a Scribd company logo
1 of 30
Download to read offline
AGM Management Presentation
June 18, 2015
Orbite © TSX: ORT OTCQX: EORBF
Certain information contained in this document may include "forward-looking information". Without limiting the
foregoing, the information and any forward-looking information may include statements regarding projects, costs,
objectives and future returns of the Company or hypotheses underlying these items. In this document, words such as
"may", "would", "could", "will", "likely", "believe", "expect", "anticipate", "intend", "plan", "estimate" and similar words and
the negative form thereof are used to identify forward-looking statements. Forward-looking statements should not be
read as guarantees of future performance or results, and will not necessarily be accurate indications of whether, or the
times at or by which, such future performance will be achieved. Forward-looking statements and information are based
on information available at the time and/or the Company management's good-faith beliefs with respect to future events
and are subject to known or unknown risks, uncertainties, assumptions and other unpredictable factors, many of which
are beyond the Company's control. These risks uncertainties and assumptions include, but are not limited to, those
described in the section of the Management's Discussion and Analysis (MD&A) entitled "Risk and Uncertainties" as filed
on March 31, 2015 on SEDAR.
The Company does not intend, nor does it undertake, any obligation to update or revise any forward-looking information
or statements contained in this document to reflect subsequent information, events or circumstances or otherwise,
except as required by applicable laws.
Annual and Special Meeting of Shareholders
2
Orbite © TSX: ORT OTCQX: EORBF
TSX: ORT OTCQX: EORBF
This time last year...
We anticipated:
• Construction to start July 2014, plant
commercial Q1 2015
• Formalization commercial relationship
with waste monetization partner in H1
of 2015
• Commencement of engineering and
conversion HPA plant to 5tpd and
chloride process
• Name change effective end of
September 2014
3
Orbite © TSX: ORT OTCQX: EORBF
TSX: ORT OTCQX: EORBF
What happened
Replace picture with
decomposer being
dropped in or
schematic cross
section
Started construction in July,
calcinator installation in
September
Identified defects with supplied
refractory materials
Supplier-based delay in shipping
replacement refractory materials
Identified design, capacity and
longevity issues with legacy plant
4
Orbite © TSX: ORT OTCQX: EORBF
TSX: ORT OTCQX: EORBF
However, substantial progress was made
• Materially reengineered HPA1, led to
increased budget
• Identified and ordered new refractory
solution
• Progressed with non-calcination
system related elements of plant
• First commercial samples produced
and shipped (4N8)
• Raised funds at terms better than
Series Y through CREDE
5
Orbite © TSX: ORT OTCQX: EORBF
TSX: ORT OTCQX: EORBF
Where we are today
Significant progress
towards
commercialization
Positioned well to
pursue waste
monetization initiative
• Near fully capitalized for plant completion
• Commercial in Q4 2015
• Engineering for 5tpd upgrade and
conversion to HCl process ongoing
• Obtained red mud related patents in
Canada and U.S.
• Waste monetization partnership
discussions ongoing with various parties
• TSX approved technology/industrial
listing
6
Orbite © TSX: ORT OTCQX: EORBF
TSX: ORT OTCQX: EORBF
A look back before looking ahead
Why HPA1
• Opportunity: HPA selling at up
to $100,000 per tonne
• Technology: hydroxide process
more mature at that time than
chloride process
HPA1 in mid-2013
• $70 million invested
• A partially built plant
• That did not function as required
• Very limited remaining funds
• Refundable investment tax credits contingent
upon completion of the plant
7
Orbite © TSX: ORT OTCQX: EORBF
TSX: ORT OTCQX: EORBF
Building a plant
• Capacity, longevity & design issues
required material redesign
• Redesign required removal of piping
and equipment from HPA1
• Reengineering a plant, like renovating
a house, generally more complex and
difficult than building from scratch
• Original budget was to finalize HPA1
as per original design + new
calcination system
8
Orbite © TSX: ORT OTCQX: EORBF
Video
9
Orbite © TSX: ORT OTCQX: EORBF
What is a refractory system
The Orbite calcination system converts
into
This step is effected at extremely high temperatures
Decomposer 800 o
C
Calciner 1300 o
C
Inside the system acidic environment
Refractory ensures the system
stands up to operating
conditions
10
Orbite © TSX: ORT OTCQX: EORBF
Calcination system
Decomposer Calciner
11
Refractory Brick
Insulating
Refractory brick
Castables
Ceramic fiber blanket
Ceramic tube
Orbite © TSX: ORT OTCQX: EORBF
Corrosion
• 18 tests of 72 hrs each
• 2 tests of 144 hrs each
Chemical
• Over 200 analytical tests:
X-ray diffraction (XRD),
Scanning Electron
Microscope (SEM), etc.
Thermo-mechanical
• CCS, MOR, MOE,
abrasion, TE, PLC, etc.
• Spalling: 7 tests, 72 hrs ,
each consisting of three 24-
hr thermal cycles
After
Substantial change
Old
New
Old New
New
New
Old
Comprehensive testing program
Scale-up
Cold face
Hot face
After
No change
12
Before
Before
Orbite © TSX: ORT OTCQX: EORBF
Complexity of refractory installation
Large-scale operation
• 200 tonnes of materials
• 60,000 bricks
• 4 layers
• Multi-step curing process
Equipment cannot impart
impurities on end product
• Precision required
• Longer curing of
replacement materials
Difficult working environment
13
TSX: ORT OTCQX: EORBF© Orbite – Confidential 14
TSX: ORT OTCQX: EORBF15
Orbite © TSX: ORT OTCQX: EORBF
Brick installation
16
Orbite © TSX: ORT OTCQX: EORBF
Castable installation
17
Orbite © TSX: ORT OTCQX: EORBF
The final touch
18
Orbite © TSX: ORT OTCQX: EORBF
On the home stretch
In progress
• Completion calcination system
• Piping
• Mechanical
• Electrical & instrumentation
• Structural, buildings & foundations
• Ventilation & insulation
Final touches
• Operational readiness
Commissioning starting Q3 2015
Commercial production Q4 2015
Project on budget
19
Orbite © TSX: ORT OTCQX: EORBF
Looking forward - HPA
© Orbite
Positioning
• a reliable supplier of consistent
quality HPA (4N5 – 5N)*
Market dynamics
• new applications point to market
expansion beyond current
projections
• Sapphire screens for smart
phones, smart watches, etc.
• Separators for battery packs
Pricing
• $20,000 - $30,000 USD/tonne
*4N5 stands for 99.995% purity, 5N for 99.999%
17 340
21 240
25 360
30 360
34 390
2012 2013 2014 2015 2016
Global HPA Demand (tpa)
20
Orbite © TSX: ORT OTCQX: EORBF
Beyond HPA - Waste monetization
SIGN UP
PARTNER
PLANT
CONVERSION
TECHNICAL
DEMONSTRATION
ENGINEERING
BLUE PRINT
COMMERCIAL
PROTOTYPE
LICENSING
21
Orbite © TSX: ORT OTCQX: EORBF
TSX: ORT OTCQX: EORBF
Why waste monetization?
• Huge quantities of feedstock available
• Representing valuable asset for Orbite
(REEs, RMOs, Alumina, etc.)
• No mines to develop
• Already in industrial zone
• Transportation and energy infrastructure
in place
• Resource with negative value to current
owners
• Customer is right next door
22
Orbite © TSX: ORT OTCQX: EORBF
Fly ash: what’s in it for us
23
Typical Content *
Typical
Pricing **
(US $/tonne)
Annual revenue
range
(US $ M)
Al2O3 15% - 30% 330 49.5 - 99.0
Fe2O3 15% - 25% 87 13.1 - 21.8
SiO2 30% - 60% 40 12.0 - 24.0
TiO2 2% - 5% 400 8.0 - 20.0
CaO 3% - 15% 170 5.1 - 25.5
NaOH 0% - 2% 400 0.0 - 8.0
Sc2O3 30 -100 ppm 1,500,000 45.0 - 150.0
Ga 30 - 75 ppm 225,000 6.8 - 16.9
REO's 400 - 800 ppm 30,000 12.0 - 24.0
Fly Ash represents
considerable value that only
Orbite can extract fully
Fly Ash Monetization - 1 Million tonne of Fly Ash/year plant
Average: 270.3
Indicative CapEx: $400 – 700M
* From internal analyses, ** See quarterly MD&A on Sedar for sources
Orbite © TSX: ORT OTCQX: EORBF
Red Mud: what’s in it for us
24
Typical Content*
Typical
Pricing **
(US $/tonne)
Annual revenue
range
(US $ M)
Al2O3 10% - 25% 330 33.0 - 82.5
Fe2O3 25% - 40% 87 21.8 - 34.8
SiO2 8% - 12% 40 3.2 - 4.8
TiO2 4% - 8% 400 16.0 - 32.0
CaO 1% - 3% 170 1.7 - 5.1
NaOH 4% - 8% 400 16.0 - 32.0
Sc2O3 20 -150 ppm 1,500,000 30.0 - 225.0
Ga 80 - 250 ppm 225,000 18.0 - 56.3
REO's 400 - 800 ppm 30,000 12.0 - 24.0
Selective extraction of all
valuable components turns
liabilities into significant assets
Red Mud Monetization - 1 Million tonne of Red Mud/year plant
Average: 324.1
Indicative CapEx: $500 – 800M
* From internal analyses, ** See quarterly MD&A on Sedar for sources
Orbite © TSX: ORT OTCQX: EORBF
A very significant opportunity
>$101.5 billion
Asset value based on current production levels only
>$455 billion
Value in current red mud stock piles
Fly Ash
550 Mt
*
produced annually
Red Mud
120 Mt**
produced annually
3 billion tonnes***
stored globally
25
* World Coal Association, ** International Aluminium Institute, *** idem
Orbite © TSX: ORT OTCQX: EORBF
0
2
4
6
8
10
12
Baseline Assumption Full Excavation All-Dry Systems
TSX: ORT OTCQX: EORBF
The current outlook for waste owners – a look at Duke Energy
© Orbite
The value of waste monetization
is not just in the asset but also
in the size of the potential liability
it turns into an asset.
Fined $110 Million
$2.0B - $2.5B
$6.0B - $8.0B
$7.0B - $10.0B
~$0.5B
~$0.5B
$1.0B - $1.5B
$4.0B - $5.5B
$1.0B - $2.0B
Movement to full excavation and all dry handling
26
Duke Energy estimates compliance
costs of $2-10 billion
Orbite © TSX: ORT OTCQX: EORBF
First things first
Complete Construction
Complete Financing
Commissioning
Commence Commercial Production
Commercial Contracts
Revenues
27
Orbite © TSX: ORT OTCQX: EORBF
Let’s talk funding
Public via prospectus $16M
CED $4M
IQ $10M
Series X $10M
IQ bridge loan $3M
Bought deal + over allotment $15M
IQ bridge loan $5M
Surplus ITCs (2012,2013) $0.9M
Total $63.9M
Proven ability to
raise substantial
funds considering
pre-revenue status.
Improving terms
28
Raised since December 2013
Orbite © TSX: ORT OTCQX: EORBF
Funding sources
Non-dilutive
Future
• ITC backed debt
• Asset backed debt
• ITCs 2016-2017
• Selected for $4.5M non-dilutive SDTC
grant towards conversion front end HPA
plant to HCl process
Very close to
completing
plant funding.
Multiple options
under review
29
Equity
• $15 million left on base-shelf prospectus
Orbite © TSX: ORT OTCQX: EORBF
Conclusion
Not an easy year but
progressed significantly
All challenges encountered
were met
Reputation of TDC well
established with potential
partners
Interest from and traction
with multiple industry and
government parties
In good shape financially
and operationally
Positive about the future,
both near and long term
30

More Related Content

Viewers also liked

enOrt corp-presentation_december-18-2014-eng-web
enOrt  corp-presentation_december-18-2014-eng-webenOrt  corp-presentation_december-18-2014-eng-web
enOrt corp-presentation_december-18-2014-eng-weborbitealuminae
 
U-Jew. Выпуск №6
U-Jew. Выпуск №6U-Jew. Выпуск №6
U-Jew. Выпуск №6Mila Lerner
 
27th ROTH Capital Partners Annual Conference
27th ROTH Capital Partners Annual Conference27th ROTH Capital Partners Annual Conference
27th ROTH Capital Partners Annual Conferenceorbitealuminae
 
Teaching manual of surumi. k (1)
Teaching manual of surumi. k (1)Teaching manual of surumi. k (1)
Teaching manual of surumi. k (1)Siyad Siyad E
 
Ort agm presentation_2016_web
Ort agm presentation_2016_webOrt agm presentation_2016_web
Ort agm presentation_2016_weborbitealuminae
 

Viewers also liked (7)

enOrt corp-presentation_december-18-2014-eng-web
enOrt  corp-presentation_december-18-2014-eng-webenOrt  corp-presentation_december-18-2014-eng-web
enOrt corp-presentation_december-18-2014-eng-web
 
U-Jew. Выпуск №6
U-Jew. Выпуск №6U-Jew. Выпуск №6
U-Jew. Выпуск №6
 
27th ROTH Capital Partners Annual Conference
27th ROTH Capital Partners Annual Conference27th ROTH Capital Partners Annual Conference
27th ROTH Capital Partners Annual Conference
 
Adjective
AdjectiveAdjective
Adjective
 
MECHANICAL BASED ENERGY PROCESS
MECHANICAL BASED ENERGY PROCESSMECHANICAL BASED ENERGY PROCESS
MECHANICAL BASED ENERGY PROCESS
 
Teaching manual of surumi. k (1)
Teaching manual of surumi. k (1)Teaching manual of surumi. k (1)
Teaching manual of surumi. k (1)
 
Ort agm presentation_2016_web
Ort agm presentation_2016_webOrt agm presentation_2016_web
Ort agm presentation_2016_web
 

Similar to AGM 2015 Presentation

Ort corp_presentation_2015-06
Ort  corp_presentation_2015-06Ort  corp_presentation_2015-06
Ort corp_presentation_2015-06orbitealuminae
 
27e conférence annuelle ROTH Capital Partners
27e conférence annuelle ROTH Capital Partners27e conférence annuelle ROTH Capital Partners
27e conférence annuelle ROTH Capital Partnersorbitealuminae
 
Corporate Presentation - July 2015
Corporate Presentation - July 2015Corporate Presentation - July 2015
Corporate Presentation - July 2015orbitealuminae
 
Ort corp-presentation_december-18-2014-eng-web
Ort  corp-presentation_december-18-2014-eng-webOrt  corp-presentation_december-18-2014-eng-web
Ort corp-presentation_december-18-2014-eng-weborbitealuminae
 
Ort corp-presentation_december-18-2014-eng-web.pdf
Ort  corp-presentation_december-18-2014-eng-web.pdfOrt  corp-presentation_december-18-2014-eng-web.pdf
Ort corp-presentation_december-18-2014-eng-web.pdforbitealuminae
 
December Corporate Presentation
December Corporate PresentationDecember Corporate Presentation
December Corporate Presentationorbitealuminae
 
Orbite AR2013 ENG FinalWeb
Orbite AR2013 ENG FinalWebOrbite AR2013 ENG FinalWeb
Orbite AR2013 ENG FinalWeborbitealuminae
 
Orbite_AR2013-ENG-FinalWeb
Orbite_AR2013-ENG-FinalWebOrbite_AR2013-ENG-FinalWeb
Orbite_AR2013-ENG-FinalWeborbitealuminae
 
Fission Uranium Corporate Presentation
Fission Uranium Corporate PresentationFission Uranium Corporate Presentation
Fission Uranium Corporate PresentationDev Randhawa
 
Orbite presentation april 2013 final 930
Orbite presentation april 2013 final   930Orbite presentation april 2013 final   930
Orbite presentation april 2013 final 930proedge2013
 
Oroco Resource Corp Oco.V March 1 09 PDAC
Oroco Resource Corp Oco.V March 1 09 PDACOroco Resource Corp Oco.V March 1 09 PDAC
Oroco Resource Corp Oco.V March 1 09 PDACChristopher R Anderson
 
Industrial gas appliances optec 2014 drsv2
Industrial gas appliances optec 2014 drsv2Industrial gas appliances optec 2014 drsv2
Industrial gas appliances optec 2014 drsv2Rovel Shackleford
 
Nemaska Lithium Corporate Presentation Jan 04 2016 FINAL
Nemaska Lithium Corporate Presentation Jan 04 2016 FINALNemaska Lithium Corporate Presentation Jan 04 2016 FINAL
Nemaska Lithium Corporate Presentation Jan 04 2016 FINALVictor Cantore
 
A New Separation Technology to Process Tantalite Bearing Minerals
A New Separation Technology to Process Tantalite Bearing MineralsA New Separation Technology to Process Tantalite Bearing Minerals
A New Separation Technology to Process Tantalite Bearing MineralsCurt Huber
 
3. DEFOAMERS CONCRETECH.pptx
3. DEFOAMERS CONCRETECH.pptx3. DEFOAMERS CONCRETECH.pptx
3. DEFOAMERS CONCRETECH.pptxmichaelsqs
 
Osx institutional ingls_june2011_v1
Osx institutional ingls_june2011_v1Osx institutional ingls_june2011_v1
Osx institutional ingls_june2011_v1osxri
 
Oroco Resource Corp Oco.V March 1 09 Pdac
Oroco Resource Corp Oco.V March 1 09 PdacOroco Resource Corp Oco.V March 1 09 Pdac
Oroco Resource Corp Oco.V March 1 09 PdacChristopher R Anderson
 
Erhc south africa conference october 2013 final
Erhc south africa conference october 2013 finalErhc south africa conference october 2013 final
Erhc south africa conference october 2013 finalDan Keeney
 

Similar to AGM 2015 Presentation (20)

Ort corp_presentation_2015-06
Ort  corp_presentation_2015-06Ort  corp_presentation_2015-06
Ort corp_presentation_2015-06
 
27e conférence annuelle ROTH Capital Partners
27e conférence annuelle ROTH Capital Partners27e conférence annuelle ROTH Capital Partners
27e conférence annuelle ROTH Capital Partners
 
Corporate Presentation - July 2015
Corporate Presentation - July 2015Corporate Presentation - July 2015
Corporate Presentation - July 2015
 
Ort corp-presentation_december-18-2014-eng-web
Ort  corp-presentation_december-18-2014-eng-webOrt  corp-presentation_december-18-2014-eng-web
Ort corp-presentation_december-18-2014-eng-web
 
Ort corp-presentation_december-18-2014-eng-web.pdf
Ort  corp-presentation_december-18-2014-eng-web.pdfOrt  corp-presentation_december-18-2014-eng-web.pdf
Ort corp-presentation_december-18-2014-eng-web.pdf
 
December Corporate Presentation
December Corporate PresentationDecember Corporate Presentation
December Corporate Presentation
 
Orbite AR2013 ENG FinalWeb
Orbite AR2013 ENG FinalWebOrbite AR2013 ENG FinalWeb
Orbite AR2013 ENG FinalWeb
 
Orbite_AR2013-ENG-FinalWeb
Orbite_AR2013-ENG-FinalWebOrbite_AR2013-ENG-FinalWeb
Orbite_AR2013-ENG-FinalWeb
 
Fission Uranium Corporate Presentation
Fission Uranium Corporate PresentationFission Uranium Corporate Presentation
Fission Uranium Corporate Presentation
 
Orbite presentation april 2013 final 930
Orbite presentation april 2013 final   930Orbite presentation april 2013 final   930
Orbite presentation april 2013 final 930
 
Oroco Resource Corp Oco.V March 1 09 PDAC
Oroco Resource Corp Oco.V March 1 09 PDACOroco Resource Corp Oco.V March 1 09 PDAC
Oroco Resource Corp Oco.V March 1 09 PDAC
 
Industrial gas appliances optec 2014 drsv2
Industrial gas appliances optec 2014 drsv2Industrial gas appliances optec 2014 drsv2
Industrial gas appliances optec 2014 drsv2
 
Nemaska Lithium Corporate Presentation Jan 04 2016 FINAL
Nemaska Lithium Corporate Presentation Jan 04 2016 FINALNemaska Lithium Corporate Presentation Jan 04 2016 FINAL
Nemaska Lithium Corporate Presentation Jan 04 2016 FINAL
 
A New Separation Technology to Process Tantalite Bearing Minerals
A New Separation Technology to Process Tantalite Bearing MineralsA New Separation Technology to Process Tantalite Bearing Minerals
A New Separation Technology to Process Tantalite Bearing Minerals
 
Cui 6262013
Cui 6262013Cui 6262013
Cui 6262013
 
3. DEFOAMERS CONCRETECH.pptx
3. DEFOAMERS CONCRETECH.pptx3. DEFOAMERS CONCRETECH.pptx
3. DEFOAMERS CONCRETECH.pptx
 
Osx institutional ingls_june2011_v1
Osx institutional ingls_june2011_v1Osx institutional ingls_june2011_v1
Osx institutional ingls_june2011_v1
 
Oroco Resource Corp Oco.V March 1 09 Pdac
Oroco Resource Corp Oco.V March 1 09 PdacOroco Resource Corp Oco.V March 1 09 Pdac
Oroco Resource Corp Oco.V March 1 09 Pdac
 
Meec introductory presentation jan 2015 copy
Meec introductory presentation jan 2015 copyMeec introductory presentation jan 2015 copy
Meec introductory presentation jan 2015 copy
 
Erhc south africa conference october 2013 final
Erhc south africa conference october 2013 finalErhc south africa conference october 2013 final
Erhc south africa conference october 2013 final
 

More from orbitealuminae

Ort presentation aga_2016_francais-web
Ort presentation aga_2016_francais-webOrt presentation aga_2016_francais-web
Ort presentation aga_2016_francais-weborbitealuminae
 
Ort presentation_corpo_juillet_2015-fra
Ort  presentation_corpo_juillet_2015-fraOrt  presentation_corpo_juillet_2015-fra
Ort presentation_corpo_juillet_2015-fraorbitealuminae
 
Ort presentation_corpo_juin_2015-fra
Ort  presentation_corpo_juin_2015-fraOrt  presentation_corpo_juin_2015-fra
Ort presentation_corpo_juin_2015-fraorbitealuminae
 
Présentation AGA 2015
Présentation AGA 2015Présentation AGA 2015
Présentation AGA 2015orbitealuminae
 
Presentation corporative Decembre
Presentation corporative DecembrePresentation corporative Decembre
Presentation corporative Decembreorbitealuminae
 
Ort agm mgment-june_2014_fra
Ort agm mgment-june_2014_fraOrt agm mgment-june_2014_fra
Ort agm mgment-june_2014_fraorbitealuminae
 

More from orbitealuminae (6)

Ort presentation aga_2016_francais-web
Ort presentation aga_2016_francais-webOrt presentation aga_2016_francais-web
Ort presentation aga_2016_francais-web
 
Ort presentation_corpo_juillet_2015-fra
Ort  presentation_corpo_juillet_2015-fraOrt  presentation_corpo_juillet_2015-fra
Ort presentation_corpo_juillet_2015-fra
 
Ort presentation_corpo_juin_2015-fra
Ort  presentation_corpo_juin_2015-fraOrt  presentation_corpo_juin_2015-fra
Ort presentation_corpo_juin_2015-fra
 
Présentation AGA 2015
Présentation AGA 2015Présentation AGA 2015
Présentation AGA 2015
 
Presentation corporative Decembre
Presentation corporative DecembrePresentation corporative Decembre
Presentation corporative Decembre
 
Ort agm mgment-june_2014_fra
Ort agm mgment-june_2014_fraOrt agm mgment-june_2014_fra
Ort agm mgment-june_2014_fra
 

Recently uploaded

Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfProbe Gold
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024CollectiveMining1
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...USDAReapgrants.com
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfFrancenel
 
Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Probe Gold
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfsansanir
 
Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024CollectiveMining1
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
Mandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalayResources
 

Recently uploaded (12)

Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdf
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024
 
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
Osisko Gold Royalties Ltd - Corporate Presentation, April 10, 2024
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdf
 
Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024Q1 Probe Gold Quarterly Update- April 2024
Q1 Probe Gold Quarterly Update- April 2024
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdf
 
Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024Collective Mining | Corporate Presentation | April 2024
Collective Mining | Corporate Presentation | April 2024
 
Korea District Heating Corporation 071320 Algorithm Investment Report
Korea District Heating Corporation 071320 Algorithm Investment ReportKorea District Heating Corporation 071320 Algorithm Investment Report
Korea District Heating Corporation 071320 Algorithm Investment Report
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
Mandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR PresentationMandalay Resources 2024 April IR Presentation
Mandalay Resources 2024 April IR Presentation
 

AGM 2015 Presentation

  • 2. Orbite © TSX: ORT OTCQX: EORBF Certain information contained in this document may include "forward-looking information". Without limiting the foregoing, the information and any forward-looking information may include statements regarding projects, costs, objectives and future returns of the Company or hypotheses underlying these items. In this document, words such as "may", "would", "could", "will", "likely", "believe", "expect", "anticipate", "intend", "plan", "estimate" and similar words and the negative form thereof are used to identify forward-looking statements. Forward-looking statements should not be read as guarantees of future performance or results, and will not necessarily be accurate indications of whether, or the times at or by which, such future performance will be achieved. Forward-looking statements and information are based on information available at the time and/or the Company management's good-faith beliefs with respect to future events and are subject to known or unknown risks, uncertainties, assumptions and other unpredictable factors, many of which are beyond the Company's control. These risks uncertainties and assumptions include, but are not limited to, those described in the section of the Management's Discussion and Analysis (MD&A) entitled "Risk and Uncertainties" as filed on March 31, 2015 on SEDAR. The Company does not intend, nor does it undertake, any obligation to update or revise any forward-looking information or statements contained in this document to reflect subsequent information, events or circumstances or otherwise, except as required by applicable laws. Annual and Special Meeting of Shareholders 2
  • 3. Orbite © TSX: ORT OTCQX: EORBF TSX: ORT OTCQX: EORBF This time last year... We anticipated: • Construction to start July 2014, plant commercial Q1 2015 • Formalization commercial relationship with waste monetization partner in H1 of 2015 • Commencement of engineering and conversion HPA plant to 5tpd and chloride process • Name change effective end of September 2014 3
  • 4. Orbite © TSX: ORT OTCQX: EORBF TSX: ORT OTCQX: EORBF What happened Replace picture with decomposer being dropped in or schematic cross section Started construction in July, calcinator installation in September Identified defects with supplied refractory materials Supplier-based delay in shipping replacement refractory materials Identified design, capacity and longevity issues with legacy plant 4
  • 5. Orbite © TSX: ORT OTCQX: EORBF TSX: ORT OTCQX: EORBF However, substantial progress was made • Materially reengineered HPA1, led to increased budget • Identified and ordered new refractory solution • Progressed with non-calcination system related elements of plant • First commercial samples produced and shipped (4N8) • Raised funds at terms better than Series Y through CREDE 5
  • 6. Orbite © TSX: ORT OTCQX: EORBF TSX: ORT OTCQX: EORBF Where we are today Significant progress towards commercialization Positioned well to pursue waste monetization initiative • Near fully capitalized for plant completion • Commercial in Q4 2015 • Engineering for 5tpd upgrade and conversion to HCl process ongoing • Obtained red mud related patents in Canada and U.S. • Waste monetization partnership discussions ongoing with various parties • TSX approved technology/industrial listing 6
  • 7. Orbite © TSX: ORT OTCQX: EORBF TSX: ORT OTCQX: EORBF A look back before looking ahead Why HPA1 • Opportunity: HPA selling at up to $100,000 per tonne • Technology: hydroxide process more mature at that time than chloride process HPA1 in mid-2013 • $70 million invested • A partially built plant • That did not function as required • Very limited remaining funds • Refundable investment tax credits contingent upon completion of the plant 7
  • 8. Orbite © TSX: ORT OTCQX: EORBF TSX: ORT OTCQX: EORBF Building a plant • Capacity, longevity & design issues required material redesign • Redesign required removal of piping and equipment from HPA1 • Reengineering a plant, like renovating a house, generally more complex and difficult than building from scratch • Original budget was to finalize HPA1 as per original design + new calcination system 8
  • 9. Orbite © TSX: ORT OTCQX: EORBF Video 9
  • 10. Orbite © TSX: ORT OTCQX: EORBF What is a refractory system The Orbite calcination system converts into This step is effected at extremely high temperatures Decomposer 800 o C Calciner 1300 o C Inside the system acidic environment Refractory ensures the system stands up to operating conditions 10
  • 11. Orbite © TSX: ORT OTCQX: EORBF Calcination system Decomposer Calciner 11 Refractory Brick Insulating Refractory brick Castables Ceramic fiber blanket Ceramic tube
  • 12. Orbite © TSX: ORT OTCQX: EORBF Corrosion • 18 tests of 72 hrs each • 2 tests of 144 hrs each Chemical • Over 200 analytical tests: X-ray diffraction (XRD), Scanning Electron Microscope (SEM), etc. Thermo-mechanical • CCS, MOR, MOE, abrasion, TE, PLC, etc. • Spalling: 7 tests, 72 hrs , each consisting of three 24- hr thermal cycles After Substantial change Old New Old New New New Old Comprehensive testing program Scale-up Cold face Hot face After No change 12 Before Before
  • 13. Orbite © TSX: ORT OTCQX: EORBF Complexity of refractory installation Large-scale operation • 200 tonnes of materials • 60,000 bricks • 4 layers • Multi-step curing process Equipment cannot impart impurities on end product • Precision required • Longer curing of replacement materials Difficult working environment 13
  • 14. TSX: ORT OTCQX: EORBF© Orbite – Confidential 14
  • 15. TSX: ORT OTCQX: EORBF15
  • 16. Orbite © TSX: ORT OTCQX: EORBF Brick installation 16
  • 17. Orbite © TSX: ORT OTCQX: EORBF Castable installation 17
  • 18. Orbite © TSX: ORT OTCQX: EORBF The final touch 18
  • 19. Orbite © TSX: ORT OTCQX: EORBF On the home stretch In progress • Completion calcination system • Piping • Mechanical • Electrical & instrumentation • Structural, buildings & foundations • Ventilation & insulation Final touches • Operational readiness Commissioning starting Q3 2015 Commercial production Q4 2015 Project on budget 19
  • 20. Orbite © TSX: ORT OTCQX: EORBF Looking forward - HPA © Orbite Positioning • a reliable supplier of consistent quality HPA (4N5 – 5N)* Market dynamics • new applications point to market expansion beyond current projections • Sapphire screens for smart phones, smart watches, etc. • Separators for battery packs Pricing • $20,000 - $30,000 USD/tonne *4N5 stands for 99.995% purity, 5N for 99.999% 17 340 21 240 25 360 30 360 34 390 2012 2013 2014 2015 2016 Global HPA Demand (tpa) 20
  • 21. Orbite © TSX: ORT OTCQX: EORBF Beyond HPA - Waste monetization SIGN UP PARTNER PLANT CONVERSION TECHNICAL DEMONSTRATION ENGINEERING BLUE PRINT COMMERCIAL PROTOTYPE LICENSING 21
  • 22. Orbite © TSX: ORT OTCQX: EORBF TSX: ORT OTCQX: EORBF Why waste monetization? • Huge quantities of feedstock available • Representing valuable asset for Orbite (REEs, RMOs, Alumina, etc.) • No mines to develop • Already in industrial zone • Transportation and energy infrastructure in place • Resource with negative value to current owners • Customer is right next door 22
  • 23. Orbite © TSX: ORT OTCQX: EORBF Fly ash: what’s in it for us 23 Typical Content * Typical Pricing ** (US $/tonne) Annual revenue range (US $ M) Al2O3 15% - 30% 330 49.5 - 99.0 Fe2O3 15% - 25% 87 13.1 - 21.8 SiO2 30% - 60% 40 12.0 - 24.0 TiO2 2% - 5% 400 8.0 - 20.0 CaO 3% - 15% 170 5.1 - 25.5 NaOH 0% - 2% 400 0.0 - 8.0 Sc2O3 30 -100 ppm 1,500,000 45.0 - 150.0 Ga 30 - 75 ppm 225,000 6.8 - 16.9 REO's 400 - 800 ppm 30,000 12.0 - 24.0 Fly Ash represents considerable value that only Orbite can extract fully Fly Ash Monetization - 1 Million tonne of Fly Ash/year plant Average: 270.3 Indicative CapEx: $400 – 700M * From internal analyses, ** See quarterly MD&A on Sedar for sources
  • 24. Orbite © TSX: ORT OTCQX: EORBF Red Mud: what’s in it for us 24 Typical Content* Typical Pricing ** (US $/tonne) Annual revenue range (US $ M) Al2O3 10% - 25% 330 33.0 - 82.5 Fe2O3 25% - 40% 87 21.8 - 34.8 SiO2 8% - 12% 40 3.2 - 4.8 TiO2 4% - 8% 400 16.0 - 32.0 CaO 1% - 3% 170 1.7 - 5.1 NaOH 4% - 8% 400 16.0 - 32.0 Sc2O3 20 -150 ppm 1,500,000 30.0 - 225.0 Ga 80 - 250 ppm 225,000 18.0 - 56.3 REO's 400 - 800 ppm 30,000 12.0 - 24.0 Selective extraction of all valuable components turns liabilities into significant assets Red Mud Monetization - 1 Million tonne of Red Mud/year plant Average: 324.1 Indicative CapEx: $500 – 800M * From internal analyses, ** See quarterly MD&A on Sedar for sources
  • 25. Orbite © TSX: ORT OTCQX: EORBF A very significant opportunity >$101.5 billion Asset value based on current production levels only >$455 billion Value in current red mud stock piles Fly Ash 550 Mt * produced annually Red Mud 120 Mt** produced annually 3 billion tonnes*** stored globally 25 * World Coal Association, ** International Aluminium Institute, *** idem
  • 26. Orbite © TSX: ORT OTCQX: EORBF 0 2 4 6 8 10 12 Baseline Assumption Full Excavation All-Dry Systems TSX: ORT OTCQX: EORBF The current outlook for waste owners – a look at Duke Energy © Orbite The value of waste monetization is not just in the asset but also in the size of the potential liability it turns into an asset. Fined $110 Million $2.0B - $2.5B $6.0B - $8.0B $7.0B - $10.0B ~$0.5B ~$0.5B $1.0B - $1.5B $4.0B - $5.5B $1.0B - $2.0B Movement to full excavation and all dry handling 26 Duke Energy estimates compliance costs of $2-10 billion
  • 27. Orbite © TSX: ORT OTCQX: EORBF First things first Complete Construction Complete Financing Commissioning Commence Commercial Production Commercial Contracts Revenues 27
  • 28. Orbite © TSX: ORT OTCQX: EORBF Let’s talk funding Public via prospectus $16M CED $4M IQ $10M Series X $10M IQ bridge loan $3M Bought deal + over allotment $15M IQ bridge loan $5M Surplus ITCs (2012,2013) $0.9M Total $63.9M Proven ability to raise substantial funds considering pre-revenue status. Improving terms 28 Raised since December 2013
  • 29. Orbite © TSX: ORT OTCQX: EORBF Funding sources Non-dilutive Future • ITC backed debt • Asset backed debt • ITCs 2016-2017 • Selected for $4.5M non-dilutive SDTC grant towards conversion front end HPA plant to HCl process Very close to completing plant funding. Multiple options under review 29 Equity • $15 million left on base-shelf prospectus
  • 30. Orbite © TSX: ORT OTCQX: EORBF Conclusion Not an easy year but progressed significantly All challenges encountered were met Reputation of TDC well established with potential partners Interest from and traction with multiple industry and government parties In good shape financially and operationally Positive about the future, both near and long term 30