  1. 1. Water and Sewer Category Change Requests March 2011 County Council and 2011-1 Administrative Cases Montgomery County Planning Board : June 9, 2011 M-NCPPC
  2. 2. Orchard Run 09A-CKB-01 Recommendation: Defer Action pending zoning application
  3. 3. Ross Boddy Community Center 10G-CLO-01 Approve S-3 Approve W-3 Service to this Public Facility should be provided such that public health problems in the immediate area may be alleviated. Consistent with the 1998 Sandy Spring/Ashton Master Plan
  4. 4. Burtonsville Category Change Requests
  5. 5. Eglise De Dieu Silver Spring 09A-PAX-01 Deny S-3 Decision taken by the Planning Board on 11/5/09 (see attachment #3)
  6. 6. Eglise De Dieu Silver Spring 09A-PAX-01 Deny S-3 Decision taken by the Planning Board on 11/5/09 (see attachment #3)
  7. 7. Sunny Varkey 09A-PAX-04 Deny S-1 Approve W-1 1997 Cloverly Master Plan: Extension of sewer service not recommended for residential, institutional, and special exception uses or in the Patuxent River watershed.
  8. 8. Burtonsville Crossing and Burtonsville Associates 09A-PAX-05 & 06 Deny S-1 Deny W-1 Fairland Master Plan Site #26 – Do not extend sewer service to RC zoned properties; water service on a case by case basis. Site #34 – Water and sewer service to approved special exception uses to be considered on a case by case basis. 34 26
  9. 9. Ted and Roxanne Smart - 09A-TRV-02&03 Christopher and Christina Marshall - 11A-TRV-01 Deny S-3 Inconsistent with the Glen Hills policy within the Potomac Subregion Master Plan
  10. 10. Water and Sewer Category Change Requests

Editor's Notes

  • Location of Four Cases against existing and proposed sewer envelope.
  • Within Clarksburg Master Plan But adjacent to Germantown and Agriculture and Open Space Within the Clarksburg SPA Circle 10 – Request to defer action pending the rezoning application.
  • Extension will have to be from the gravity sewer line, not the pressure sewer line, which is much farther away. There will be one stream crossing. Also historically, homes abutting the pressure sewer are allowed to tap in, particularly in cases of failing septics.
  • At the direction of the County Council, staff met with the applicant on November 5, 2010 to review a concept for the church. We were asked how the concept could conform to the master plan. Comments from staff are on circle 35.
  • Within the Glen Hills Neighborhood and the Piney Branch Special Protection Area

×