Successfully reported this slideshow.
Your SlideShare is downloading. ×

A project under consideration has a net present value of $10-000 for a.docx

Ad
Ad
Ad
Ad
Ad
Ad
Ad
Ad
Ad
Ad
Ad
Loading in …3
×

Check these out next

1 of 1 Ad

A project under consideration has a net present value of $10-000 for a.docx

Download to read offline

A project under consideration has a net present value of $10,000 for a required investment of $60,000. There are no other investment options at this time. However, the assumed discount rate used to calculate the net present value is 20%.
On the basis of this information alone, this project should:
Definitely be rejected because $10,000 is only 17% of $60,000
Be rejected on the basis that the project loses $50,000
Probably be approved since the net present value is greater than zero
Be accepted if the cost of capital is greater than or equal to 20 percent
Solution
Answer:
Probably be approved since the net present value is greater than zero
.

A project under consideration has a net present value of $10,000 for a required investment of $60,000. There are no other investment options at this time. However, the assumed discount rate used to calculate the net present value is 20%.
On the basis of this information alone, this project should:
Definitely be rejected because $10,000 is only 17% of $60,000
Be rejected on the basis that the project loses $50,000
Probably be approved since the net present value is greater than zero
Be accepted if the cost of capital is greater than or equal to 20 percent
Solution
Answer:
Probably be approved since the net present value is greater than zero
.

Advertisement
Advertisement

More Related Content

More from mrichard5 (20)

Recently uploaded (20)

Advertisement

A project under consideration has a net present value of $10-000 for a.docx

  1. 1. A project under consideration has a net present value of $10,000 for a required investment of $60,000. There are no other investment options at this time. However, the assumed discount rate used to calculate the net present value is 20%. On the basis of this information alone, this project should: Definitely be rejected because $10,000 is only 17% of $60,000 Be rejected on the basis that the project loses $50,000 Probably be approved since the net present value is greater than zero Be accepted if the cost of capital is greater than or equal to 20 percent Definitely be rejected because $10,000 is only 17% of $60,000 Be rejected on the basis that the project loses $50,000 Probably be approved since the net present value is greater than zero Be accepted if the cost of capital is greater than or equal to 20 percent Solution Answer: Probably be approved since the net present value is greater than zero

×