SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 1
FIDIC Forms of Contracts
Training Course:
Saudi Council of Engineers
2017
LECTURE FIVE
‫وبركاته‬ ‫هللا‬ ‫ورحمة‬ ‫عليكن‬ ‫السالم‬
2017
• Cl.3
o Delegation – except for sub- Cl.3.5
Determination.
o Instructions in writing
• Verbal instructions to be followed by
confirmation by contractor – written
o Employer instructions to the Engineer
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 2
Engineer’s Responsibilities “continue”
2017
o Determination
• Consult – agreement – fair determination
• Give notice
• Give influence or proceed to Cl.20
• Cl.4.1 Request Method of Statements
Discuss determination task? fairness
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 3
Engineer’s Responsibilities “continue”
2017
• Cl.8.1 Give Commencement Notice
• Cl.8.6 Rate of Progress
• Cl.12.1 Measurement
• Cl.13.1 Variations
• Cl.14.6 Interim Payment Certificates
• Cl.20.1 Records / Determination
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 4
Engineer’s Responsibilities “continued”
2017
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 5
Engineer’s Responsibilities “continue”
Cl.4
• Execute & Complete the Works
 Cl.8.1 due expedition & without delay
 Adequacy & safety
 Method Statement
 Fit for purpose
• Performance Bond
 Engineer’s Approval of Representative
 May delegate
 Fluent in language
 Sub Contractor approval
2017
• Setting Out to lines & levels
• Quality Assurance (Process oriented)
o Details in Specification
o Procedures
o Compliance documents
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 6
Contractor’s Responsibilities
2017
• Site records
o Costs comprised
o Risk
o Inspections
o All relevant data – obligation
o Caution in Tender – failure to provide
• Adequacy of Contract Amount
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 7
Contractor’s Responsibilities “continued”
2017
• Unforeseen site Physical Conditions
o Excludes climatic conditions
• S. Cl.8.4 & S.Cl. 17.3 Employer’s Risks
o Extension of time
o Payment of cost
• (see S. Cl.1.1.4.3 includes off site)
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 8
Contractor’s Responsibilities “continue”
2017
• Transport to site
• Protection of the Environment
• Emissions S.Cl. 4.18 Protection of the
• Environment
o Surface discharges
o Effluent
o Local/applicable Law
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 9
Contractor’s Responsibilities “continued”
2017
 Progress Report
 Monthly – 6 copies
 Cl.4.9 procedures and:
Cl. 6.7 Accident Records
Cl. 6.10 Personnel
Cl.14.3 Application for payment
Cl.20.1 Contemporary records
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 10
Contractor’s Responsibilities “continue”
2017
• Progress Report:
o Charts
o Photographs
o Manufacturing report
o Personnel
o Quality Assurance documents
o Claims Cl.2.5 Employer & 20.1 Contractor
o Safety statistics
o Progress
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 11
Contractor’s Responsibilities “continue”
2017
• Security
• Staff & Labour
o Facilities / Health & Safety
• Tests on Completion Cl. 9.1
• Value Engineering Cl. 13.3
• Application for Payment Cl. 14.3
• Contemporary records to support Cl. 20.1
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 12
Contractor’s Responsibilities “continue”
2017
Nominated Subcontractors
• Clause 5
• Definition:
 "nominated Subcontractor" means subcontractor:
(a) who is stated in the Contract as being a nominated
Subcontractor. or
(b) whom the Engineer. under Clause 13 [Variations
and Adjustments]. Instructs the Contractor to employ as
a Subcontractor.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 132017
• Applies to Subcontractors and suppliers
nominated by Employer or as instructed by the
Engineer under Cl.13 (Variations and
Adjustments)
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 142017
Nominated Subcontractors
• Clause 5.2
o Contractor practical Objection
o Supporting particulars/details
o Lack of competence, recourses, financial strength
o Lack of indemnity- indemnify contractor
o Lack of obligations and liability -sub-con shall
enable the Contractor to discharge his obligations
and liabilities
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 152017
Nominated Subcontractors
Payment Clause 5.3:
• The Contractor shall pay to the nominated
Subcontractor the amounts which the
Engineer certifies to be due in accordance
with the subcontract.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 162017
Nominated Subcontractors’continued’
• These amounts plus
• Other charges shall be included in the
Contract Price in accordance with
subparagraph (b) of Sub-Clause 13.5
[Provisional Sums]. except as stated in the
following Sub Clause 5.4.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 172017
Nominated Subcontractors ’continued’
Nominated Subcontractors “continued”
• 5.4 Evidence of Payments
1. Engineer requests reasonable evidence from
nominated S/C- for receipt amount requested in the
Contractor’s payment certificate previously paid
(OR)
2. The contractor justifies non payment and
notification issued to the nominated S/C for non
payment with reasons : if no justification :
3. The Employer may pay and get back from the
contractor ......deductions considered in any payment
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 182017
Q&A
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 19
Q1. Nominated Sun-Con is:
1-Defined in the contract 2- assigned by the Contractor
Q.2 Employer's Personnel S. Cl. 2.3 requirements:
The Employer shall be responsible for ensuring that the Employer's Personnel
and the Employer's other contractors on the Site co-operate with the
Contractor's efforts, take actions similar to those which the Contractor is
required to take for [Safety Procedures] and [Protection of the Environment].
1. TRUE 2-False
Q.3
Pursuant S. Cl . 4.2 Cl. 4.2 Issue of the Performance
Security should be within 28 days from Issuance of the
Letter of Acceptance.
1-TRUE 2-False Eng: …………………………
2017
Q&A
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 20
Q1. Nominated Sun-Con is:
1-Defined in the contract 2- assigned by the Contractor
Q.2 Employer's Personnel S. Cl. 2.3 requirements:
The Employer shall be responsible for ensuring that the Employer's Personnel
and the Employer's other contractors on the Site co-operate with the
Contractor's efforts, take actions similar to those which the Contractor is
required to take for [Safety Procedures] and [Protection of the Environment].
1. TRUE 2-False
Q.3
Pursuant S. Cl . 4.2 Cl. 4.2 Issue of the Performance
Security should be within 28 days from Issuance of the
Letter of Acceptance.
1-TRUE 2-False
2017
Project Engagement of Staff & Labour
Clause 6
• Contractor shall make arrangements for the engagement of all
staff and labor. local or otherwise, their payment. housing.
feeding and transport.
• Rates of Wages and Conditions // similar to the average in the
work location/country
• The Contractor shall not recruit// Employer's Personnel.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 212017
Staff and labour “continue”
• Labour Laws (including Expat/immigration)
• Working Hours
• Facilities (including Employer’s Personnel)
• Health & Safety
Medical staff & facilities
Accident prevention officer
Records
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 222017
 Cl.4.3 – Contractor’s Representative
 Cl.6.8 – Superintendence (Language)
 Personnel competent– qualified, skilled, experienced
 Cl.4.9 procedures monthly records
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 23
Staff and labour “continued”
2017
6.4 Labor Laws
• The Contractor complies- applicable labor Laws (employment.
health. Safety). Labor to obey applicable law.
6.5 Working Hours
No work on rest days- no work outside working hours-// unless stated
in the contract/ instructed. Or non avoidable.
6.6 Facilities for Staff and Labor
• Contractor provide necessary accommodation and welfare
facilities, for labors Contractor shall also provide facilities for
the Employer's Personnel as stated in the Specification.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 24
Staff and labour “continue”
2017
6.7 Health and Safety
• Contractor shall take reasonable precautions to maintain
the health/ safety of its Personnel.
'6.8 Contractor’s Superintendence
• the Contractor shall provide all necessary superintendence
to plan. arrange. direct. manage. inspect and test the work.
6.9 Contractor’s Personnel
• Contractor's Personnel shall be appropriately qualified. skilled
and experienced in their respective trades or occupations.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 25
Staff and labour “continue”
2017
6.10 Records of Contractor's Personnel and Equipment
• The Contractor shall submit. to the Engineer. details each class
of Personnel/Equipment on the Site.
'6.11 Disorderly Conduct
• Take all reasonable precautions to prevent any unlawful,
riotous or disorderly conduct by his Personnel. and to preserve
peace and protection of persons & property on & near the Site.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 26
Staff and labour “continued”
2017
7.1 Manner of Execution
• The manufacture of Plant, and all other execution of the Works
in the manner (if any) specified in the Contract, in a proper
workmanlike, with properly equipped facilities and non-
hazardous Materials.
7.2 Samples
• Submit the samples of Material & relevant information. to
Engineer for consent in advance, labeled as to origin and
intended use.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 27
Plant, Materials and Workmanship
2017
7.3 Inspection
The Employer's Personnel shall :
• (have access to all parts of Site & all places of natural
Materials, and during production, manufacture & construction
• be entitled to examine. inspect. measure and test the materials
and workmanship & check the progress of manufacture
• 7.4 Testing
• This Sub-Clause shall apply to all tests specified in the
Contract other than the Tests after Completion (if any).
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 28
Plant, Materials and Workmanship
2017
7.5 Rejection
• As a result of an examination. inspection, measurement or testing.
any defective work/not in accordance with the Contract. the
Engineer may reject it by giving notice to the Contractor. with
reasons.
7.6 Remedial Work
• Notwithstanding any previous test or certification. the Engineer may
instruct::
• remove/ replace any Plant or Materials not complying
• remove and re-execute work not complying.
• execute any work urgently required for the safety. The Contractor complies
in a reasonable time, as in the instruction. or immediately if urgency is
specified under sub-paragraph (c). employ and pay other persons to do
the remedial.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 29
Plant, Materials and Workmanship
2017
7.7 Ownership of Plant and Materials
• Each item becomes the property of the Employer the
earlier of the following times:
• when it is delivered to the Site; or when Suspension
S.Cl. 8.10.
7.8 Royalties.
The Contractor shall pay all royalties, rents and other
payments for:
• (a) natural Materials, the disposal of material from
demolitions and , excavations & of other surplus, material
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 30
Plant, Materials and Workmanship
2017
8.1 Commencement of Works
 Engineer shall give 7 d. notice of commencement date.
Unless otherwise stated in the P. Conditions. 42 d. (LOA).
• Contractor commence execution as soon as is practicable
(due expedition/ without delay).
8.2 Time for Completion
Contractor shall complete the Works. & each Section (if
any).
• within the Time for Completion including: ( passing of
the Tests on Completion, completing all work which is
stated in the Contract, mandatory for work required to fit
S. Cl.10.1 [Taking Over of the Works, Sections].
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 31
8.0 Commencement, Delays and Suspension
2017
8.3 Program
• Submit a detailed program within 28 d. After notice S.-
Cl. 8.1 [Commencement of Works].
• Revised program whenever the previous program is
inconsistent with progress or Contractor's obligations.
• Program shall include:
o order of how to carry out the Works.
o anticipated timing of each stage of design (if any).
Contractor's Documents. procurement. manufacture of
Plant. delivery to Site. construction. erection and testing.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 32
8.0 Commencement, Delays and Suspension
2017
8.3 Program- continued
• each of these stages for work by each N. Sub-Con.
• sequence and timing of inspections and tests, and
• supporting report which includes:
• (i) a general description of the methods intended to be adopted
• (ii) details showing reasonable estimate of Personnel and
Equipment. Histogram
• Unless, responded 21 d. (not comply) with the Contract. the
• Contractor shall proceed in accordance with the program.
subject to his other contractual obligations.
• Employer's Personnel shall be entitled to rely on the program
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 33
8.0 Commencement, Delays and Suspension
2017
8.3 Program- continued
• Contractor shall notify the Engineer of specific probable future
events which may adversely affect the work/ Time- Cost.
• The Engineer may require the Contractor to submit an estimate
of the anticipated effect of the future event or circumstances.
• and/or a proposal under Sub-Clause 13.3 [Variation
Procedure].
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 34
8.0 Commencement, Delays and Suspension
2017
8.4 Extension of Time for Completion
• Contractor shall be entitled subject to S. Cl. 20.1 [C. Claims]
to EOT for Completion if Sub-Clause 10.1 [Taking Over ] is or
will be delayed by any of:
Procedure of Extension of Time in LEC VI slide 11
o Variation
o In culpable delay
o Adverse weather
o Unforeseeable shortages in the availability of personnel or
Goods caused by epidemic or governmental actions. Or
o delay, impediment or prevention by the Employer
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 35
8.0 Commencement, Delays and Suspension
2017
8.4 Extension of Time for Completion- continued
• If Contractor considers himself entitled to EOT, the Contractor
shall give notice to the Engineer in accordance with Sub-
Clause 20.1 - the Engineer shall review previous
determinations and may increase, but shall not decrease, the
total extension of time
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 36
8.0 Commencement, Delays and Suspension
2017
8.5 Delays Caused by Authorities
 If specifically:
• Contractor has diligently followed the procedures laid down
by the relevant public authorities.
• These authorities delay or disrupt the Contractor's work. And
• the delay or disruption was Unforeseeable.
then this delay or disruption will be considered as a cause of delay
under subparagraph (b) of S. Cl. 8.4 [EOT for Completion] .
Inculpable delay
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 37
8.0 Commencement, Delays and Suspension
2017
8.6 Rate of Progress
If. at any time:
 Low progress
 progress has fallen (or will fall) behind the current program, THEN:
o then the Engineer may instruct a revised program, supporting
report for the corrective measures.
o the Contractor adopt revised methods, may require
increases in the working hours and/or in the numbers of
labor, and/or Goods. at the risk and cost of the Contractor.
And pays delay damages to the Employer.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 38
8.0 Commencement, Delays and Suspension
2017
8.7 Delay Damages
• If the Contractor fails to comply with S. Cl. 8.2 [Time for
Completion]. The Contractor shall subject to Sub-Clause 2.5
[Employer's Claims] pay delay damages to the Employer for
this default. These delay damages shall be the sum:
• stated in the Appendix to Tender. which shall be paid for
every day from Time for Completion & date stated in the T.
Over Certificate
However, the total amount due under this Sub-Clause (10-15%)
• shall not exceed the maximum as per Appendix to Tender.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 39
8.0 Commencement, Delays and Suspension
2017
8.7 Delay Damages - continued
• These delay damages shall be the only damages due from the
Contractor for such default. other than in the event of
termination under Sub-Clause 15.2 [Termination by
Employer] prior to completion of the Works.
• These damages shall not relieve the Contractor from his
obligation to complete the Works, or from any other
contractual obligations.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 40
8.0 Commencement, Delays and Suspension
2017
8.8 Suspension of Work
• The Engineer may instruct the Contractor to suspend progress
part/or all. During suspension , the Contractor protect. store
and secure such part or the Works against any deterioration.
loss or damage.
• If the cause is notified and is the responsibility of the
Contractor, the following S. Cl. 8.9. 8.10 and 8.11 shall not
apply.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 41
8.0 Commencement, Delays and Suspension
2017
8.9 Consequences of Suspension
• If the Contractor suffers delay/Cost from complying with
instructions Suspension. and/or from resuming the work. Then
give notice to the Engineer and shall be entitled S. Cl. 20.1to:
(a) an EOT for delay, and payment of any such Cost.
After this notice, the Engineer shall proceed [Determinations].
The Contractor shall not be entitled EOT/ cost incurred in,
making good Contractor's faulty design, workmanship or
materials, or failure to protect. store or secure in accordance
with Sub-Clause 8.8 [Suspension of Work].
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 42
8.0 Commencement, Delays and Suspension
2017
8.10 Payment for Plant and Materials in Event of Suspension
1.1 .5.5 "Plant" means the apparatus(Equipment). machinery and
vehicles intended to or forming part of the Permanent Works.
• Shall be entitled to payment of the value of plant/Materials
which have not delivered to Site. if:
(a) Suspended for more than 28 days, and
(b) Contractor marked Plant and/or Materials as the Employer’s
property in accordance with Engineer's instructions.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 43
8.0 Commencement, Delays and Suspension
2017
8.11 Prolonged Suspension
• If more than 84 days, the Contractor may request the
Engineer's permission to proceed.
• If no permission within 28 days after request, Contractor may,
notify, treat the suspension as an omission under Clause 13.
OR termination S. Cl. 16.2 Termination by Contractor if all
Work is affected.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 44
8.0 Commencement, Delays and Suspension
2017
8.12 Resumption of Work
• After the permission or instruction to proceed is given, the
Contractor and the Engineer shall jointly examine the Works
and the Plant and Materials affected by the suspension. The
Contractor shall make good any deterioration or defect in or
loss of the Works or Plant or Materials, which has occurred
during the suspension.
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 45
8.0 Commencement, Delays and Suspension
2017
You are the project Engineer for a private school construction project
which includes hundreds of activities, valued 4.50 M SAR and the contract
is FIDIC Red Book 1999, the value of the school buildings is 4.0 M SAR
while the fence and car shades are 0.50 M SAR, total duration 8 months
Discuss the following in case you are the project Engineer/Employer
1. If the Contractor’s caused delay was prolonged for 6 months for the
whole project- discuss clauses for LD and termination- value.
………………………………………………………………………………
………………………………………………………………………………
………………………………………………………………………………
……………………………………………………………………………....
Analyzed by Eng. …………
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 46
Event Analysis 2
2017
You are the project Engineer/ Contractor for a governmental school
construction project which includes hundreds of activities, valued 4.50 M SAR
and the contract is FIDIC Red Book 1999, the value of the school buildings is
4.0 M SAR while the fence and car shades are 0.50 M SAR, total duration 8
months Discuss the following in case you are the project Contractor:
1. If the Employers late decisions/drawings/ payment caused delay was
prolonged for 3 months for the whole project- discuss clauses for LD and
termination- value.
……………………………………………………………………………………………
……………………………………………………………………………………………
……………………………………………………………………………
Analyzed by Eng. …………
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 47
Event Analysis 3
2017
You are the project Engineer/ Contractor for a high demand/urgency school for the
public construction project which includes hundreds of activities, valued 4.50 M SAR
and the contract is FIDIC Red Book 1999, the value of the school buildings is 4.0 M
SAR while the fence and car shades are 0.50 M SAR, total duration 8 months Discuss
the following in case you are the project Contractor:
3. If the Employers late decisions/drawings/ payment caused delay was prolonged for 3
months for the whole project- discuss clauses for LD and termination- value.
……………………………………………………………………………………………
……………………………………………………………………………………………
……………………………………………………………………………………………
Analyzed by Eng. …………
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 48
Event Analysis 4
2017
You are the project Engineer/ Contractor for a private school construction project
which includes hundreds of activities, valued 4.50 M SAR and the contract is FIDIC
Red Book 1999, the value of the school buildings is 4.0 M SAR while the fence and car
shades are 0.50 M SAR, total duration 8 months Discuss the following in case you are
the project Eng/Employer:
3. If the Contractor’s (lack of funds/resources/Equipment/mismanagement) caused
delay was prolonged for 3 months for the fence and car shade only and the rest of the
project is completed - discuss clauses for LD and termination- value.
……………………………………………………………………………………………
……………………………………………………………………………………………
……………………………………………………………………………………………
Analyzed by Eng. …………
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 49
Event Analysis 4
2017
Contractor’s letters- exercise
• Notice of claim
2017SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 50
SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 51
End of
LECTURE Five
Thank You
‫وبركاته‬ ‫هللا‬ ‫ورحوة‬ ‫عليكن‬ ‫السالم‬
‫هللا‬ ‫أهاى‬ ‫فى‬
2017

More Related Content

What's hot

Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC ContractKai Yun Pang
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1Moustafa Ismail Abu Dief
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFrancis Ho
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts finalFitBlar Mit
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesCNC
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 
fidic history and publications
fidic history and publicationsfidic history and publications
fidic history and publicationsmohamed Ismail
 

What's hot (20)

Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
An Overview of the FIDIC FORMS OF CONTRACT and Contracts Committee Activi...
 
Standard Forms of Construction Contracts
Standard Forms of Construction ContractsStandard Forms of Construction Contracts
Standard Forms of Construction Contracts
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Ss training fidic moustafa ismail 2017 _ lec. 1
Ss training fidic moustafa ismail  2017 _ lec. 1Ss training fidic moustafa ismail  2017 _ lec. 1
Ss training fidic moustafa ismail 2017 _ lec. 1
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Fidic
FidicFidic
Fidic
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
Fidic flow charts final
Fidic flow charts finalFidic flow charts final
Fidic flow charts final
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Fidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable ChangesFidic contracts 2017 - Notable Changes
Fidic contracts 2017 - Notable Changes
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
fidic history and publications
fidic history and publicationsfidic history and publications
fidic history and publications
 
Introduction to construction contracts fundamentals
Introduction to construction contracts fundamentalsIntroduction to construction contracts fundamentals
Introduction to construction contracts fundamentals
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 

Similar to Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5

Training fidic moustafa ismail 2018 _ lec 8
Training fidic moustafa ismail  2018 _ lec 8Training fidic moustafa ismail  2018 _ lec 8
Training fidic moustafa ismail 2018 _ lec 8Moustafa Ismail Abu Dief
 
Ss 07 training fidic moustafa ismail 2018__ lec 7B
Ss 07 training fidic moustafa ismail  2018__ lec 7BSs 07 training fidic moustafa ismail  2018__ lec 7B
Ss 07 training fidic moustafa ismail 2018__ lec 7BMoustafa Ismail Abu Dief
 
Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020Moustafa Ismail Abu Dief
 
م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...
م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...
م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...Egyptian Engineers Association
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_aMoustafa Ismail Abu Dief
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_aMoustafa Ismail Abu Dief
 
Julian Scott - Contract Law and CDM 2007 Regulations
Julian Scott -  Contract Law and CDM 2007 RegulationsJulian Scott -  Contract Law and CDM 2007 Regulations
Julian Scott - Contract Law and CDM 2007 RegulationsKhalida Suleymanova
 
Bim arabia-red-fidic
Bim arabia-red-fidicBim arabia-red-fidic
Bim arabia-red-fidicOmar Selim
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo
 
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT Irfan Quraishi
 
Refinery Overhauling Introduction
Refinery Overhauling IntroductionRefinery Overhauling Introduction
Refinery Overhauling IntroductionAshar Ahmed
 
Minimum Wages Policy
Minimum Wages PolicyMinimum Wages Policy
Minimum Wages PolicyYash Mahendra
 
Understanding the hazards at your mine and an enforceable undertaking - Clint...
Understanding the hazards at your mine and an enforceable undertaking - Clint...Understanding the hazards at your mine and an enforceable undertaking - Clint...
Understanding the hazards at your mine and an enforceable undertaking - Clint...NSW Environment and Planning
 
Health and Safety Construction - APEX.pdf
Health and Safety Construction - APEX.pdfHealth and Safety Construction - APEX.pdf
Health and Safety Construction - APEX.pdfXiMdhk
 
Irish Public Works Contract - Clause 10.6 - Practical Application
Irish Public Works Contract - Clause 10.6 - Practical ApplicationIrish Public Works Contract - Clause 10.6 - Practical Application
Irish Public Works Contract - Clause 10.6 - Practical ApplicationMark Wearen
 
UON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdfUON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdfHabtamuGaroma3
 

Similar to Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5 (20)

Training fidic moustafa ismail 2018 _ lec 8
Training fidic moustafa ismail  2018 _ lec 8Training fidic moustafa ismail  2018 _ lec 8
Training fidic moustafa ismail 2018 _ lec 8
 
Ss 07 training fidic moustafa ismail 2018__ lec 7B
Ss 07 training fidic moustafa ismail  2018__ lec 7BSs 07 training fidic moustafa ismail  2018__ lec 7B
Ss 07 training fidic moustafa ismail 2018__ lec 7B
 
Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020Presentation eci dr moustafa ismail 20 july 2020
Presentation eci dr moustafa ismail 20 july 2020
 
م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...
م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...
م.35- مبادرة#تواصل_تطوير- د.مصطفى إسماعيل - التخفيف من مطالبات مشروعات التشيد...
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
 
Julian Scott - Contract Law and CDM 2007 Regulations
Julian Scott -  Contract Law and CDM 2007 RegulationsJulian Scott -  Contract Law and CDM 2007 Regulations
Julian Scott - Contract Law and CDM 2007 Regulations
 
Bim arabia red fidic
Bim arabia red fidicBim arabia red fidic
Bim arabia red fidic
 
Bim arabia-red-fidic
Bim arabia-red-fidicBim arabia-red-fidic
Bim arabia-red-fidic
 
Cl report final
Cl report finalCl report final
Cl report final
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
SUMMER INTERNSHIP REPORT FOR 3RD YEAR STUDENT
 
Refinery Overhauling Introduction
Refinery Overhauling IntroductionRefinery Overhauling Introduction
Refinery Overhauling Introduction
 
CDM 2015 - A quick summary
CDM 2015 - A quick summaryCDM 2015 - A quick summary
CDM 2015 - A quick summary
 
Minimum Wages Policy
Minimum Wages PolicyMinimum Wages Policy
Minimum Wages Policy
 
Understanding the hazards at your mine and an enforceable undertaking - Clint...
Understanding the hazards at your mine and an enforceable undertaking - Clint...Understanding the hazards at your mine and an enforceable undertaking - Clint...
Understanding the hazards at your mine and an enforceable undertaking - Clint...
 
Health and Safety Construction - APEX.pdf
Health and Safety Construction - APEX.pdfHealth and Safety Construction - APEX.pdf
Health and Safety Construction - APEX.pdf
 
Irish Public Works Contract - Clause 10.6 - Practical Application
Irish Public Works Contract - Clause 10.6 - Practical ApplicationIrish Public Works Contract - Clause 10.6 - Practical Application
Irish Public Works Contract - Clause 10.6 - Practical Application
 
Module 1
Module 1Module 1
Module 1
 
UON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdfUON-Project-Handover-Guideline-v1.2-010920.pdf
UON-Project-Handover-Guideline-v1.2-010920.pdf
 

More from Moustafa Ismail Abu Dief

Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...Moustafa Ismail Abu Dief
 
Ss 09 cost engineering management training- nov 2017 moustafa sec 5 part ii...
Ss 09 cost engineering management  training- nov 2017  moustafa sec 5 part ii...Ss 09 cost engineering management  training- nov 2017  moustafa sec 5 part ii...
Ss 09 cost engineering management training- nov 2017 moustafa sec 5 part ii...Moustafa Ismail Abu Dief
 
07 b cost engineering management training- nov 2017 moustafa sec 5 part ii...
07 b  cost engineering management  training- nov 2017  moustafa sec 5 part ii...07 b  cost engineering management  training- nov 2017  moustafa sec 5 part ii...
07 b cost engineering management training- nov 2017 moustafa sec 5 part ii...Moustafa Ismail Abu Dief
 
07A cost engineering management training- nov 2017 moustafa sec 5 part iii...
07A  cost engineering management  training- nov 2017  moustafa sec 5 part iii...07A  cost engineering management  training- nov 2017  moustafa sec 5 part iii...
07A cost engineering management training- nov 2017 moustafa sec 5 part iii...Moustafa Ismail Abu Dief
 
Ss 07 cost engineering management training- nov 2017 moustafa part ii ch 14...
Ss 07 cost engineering management  training- nov 2017  moustafa part ii ch 14...Ss 07 cost engineering management  training- nov 2017  moustafa part ii ch 14...
Ss 07 cost engineering management training- nov 2017 moustafa part ii ch 14...Moustafa Ismail Abu Dief
 
Ss 06 cost engineering management training- nov 2017 - moustafa part ii ch 1...
Ss 06 cost engineering management  training- nov 2017 - moustafa part ii ch 1...Ss 06 cost engineering management  training- nov 2017 - moustafa part ii ch 1...
Ss 06 cost engineering management training- nov 2017 - moustafa part ii ch 1...Moustafa Ismail Abu Dief
 
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...Moustafa Ismail Abu Dief
 
Ss 05 Cost engineering management training- nov 2017 - moustafa part ii ch 10
 Ss 05 Cost engineering management  training- nov 2017 - moustafa part ii ch 10 Ss 05 Cost engineering management  training- nov 2017 - moustafa part ii ch 10
Ss 05 Cost engineering management training- nov 2017 - moustafa part ii ch 10Moustafa Ismail Abu Dief
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9Moustafa Ismail Abu Dief
 
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...Moustafa Ismail Abu Dief
 
Ss 2 cost engineering management training- 2017 -dr moustafa ismail ch 5-6
Ss 2 cost engineering management  training- 2017 -dr  moustafa ismail  ch  5-6Ss 2 cost engineering management  training- 2017 -dr  moustafa ismail  ch  5-6
Ss 2 cost engineering management training- 2017 -dr moustafa ismail ch 5-6Moustafa Ismail Abu Dief
 
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
Cfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismailCfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismail
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismailMoustafa Ismail Abu Dief
 
Ss ccp course cost engineering management training- 2017 - moustafa ch 1-4
Ss ccp course cost engineering management  training- 2017 - moustafa  ch  1-4Ss ccp course cost engineering management  training- 2017 - moustafa  ch  1-4
Ss ccp course cost engineering management training- 2017 - moustafa ch 1-4Moustafa Ismail Abu Dief
 

More from Moustafa Ismail Abu Dief (18)

Fidic 2017 engineering
Fidic 2017 engineeringFidic 2017 engineering
Fidic 2017 engineering
 
Yellow book session bimarabia
Yellow book session bimarabiaYellow book session bimarabia
Yellow book session bimarabia
 
CMC certification
CMC certificationCMC certification
CMC certification
 
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...Ss 10   cost engineering management  training-   moustafa sec 5 part iii ch 2...
Ss 10 cost engineering management training- moustafa sec 5 part iii ch 2...
 
Construction Claims Training Course 2019
Construction Claims Training Course 2019Construction Claims Training Course 2019
Construction Claims Training Course 2019
 
Construction Claims Training Course 2019
Construction Claims Training Course 2019Construction Claims Training Course 2019
Construction Claims Training Course 2019
 
Ss 09 cost engineering management training- nov 2017 moustafa sec 5 part ii...
Ss 09 cost engineering management  training- nov 2017  moustafa sec 5 part ii...Ss 09 cost engineering management  training- nov 2017  moustafa sec 5 part ii...
Ss 09 cost engineering management training- nov 2017 moustafa sec 5 part ii...
 
07 b cost engineering management training- nov 2017 moustafa sec 5 part ii...
07 b  cost engineering management  training- nov 2017  moustafa sec 5 part ii...07 b  cost engineering management  training- nov 2017  moustafa sec 5 part ii...
07 b cost engineering management training- nov 2017 moustafa sec 5 part ii...
 
07A cost engineering management training- nov 2017 moustafa sec 5 part iii...
07A  cost engineering management  training- nov 2017  moustafa sec 5 part iii...07A  cost engineering management  training- nov 2017  moustafa sec 5 part iii...
07A cost engineering management training- nov 2017 moustafa sec 5 part iii...
 
Ss 07 cost engineering management training- nov 2017 moustafa part ii ch 14...
Ss 07 cost engineering management  training- nov 2017  moustafa part ii ch 14...Ss 07 cost engineering management  training- nov 2017  moustafa part ii ch 14...
Ss 07 cost engineering management training- nov 2017 moustafa part ii ch 14...
 
Ss 06 cost engineering management training- nov 2017 - moustafa part ii ch 1...
Ss 06 cost engineering management  training- nov 2017 - moustafa part ii ch 1...Ss 06 cost engineering management  training- nov 2017 - moustafa part ii ch 1...
Ss 06 cost engineering management training- nov 2017 - moustafa part ii ch 1...
 
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...SCE 1 2018 claims management-in-construction-projects-seminar-.-2017  dr mous...
SCE 1 2018 claims management-in-construction-projects-seminar-.-2017 dr mous...
 
Ss 05 Cost engineering management training- nov 2017 - moustafa part ii ch 10
 Ss 05 Cost engineering management  training- nov 2017 - moustafa part ii ch 10 Ss 05 Cost engineering management  training- nov 2017 - moustafa part ii ch 10
Ss 05 Cost engineering management training- nov 2017 - moustafa part ii ch 10
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
 
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...Ss 03 CCP- AACE.org  cost engineering management  training- 2017 - dr. mousta...
Ss 03 CCP- AACE.org cost engineering management training- 2017 - dr. mousta...
 
Ss 2 cost engineering management training- 2017 -dr moustafa ismail ch 5-6
Ss 2 cost engineering management  training- 2017 -dr  moustafa ismail  ch  5-6Ss 2 cost engineering management  training- 2017 -dr  moustafa ismail  ch  5-6
Ss 2 cost engineering management training- 2017 -dr moustafa ismail ch 5-6
 
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
Cfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismailCfcc certified forensic claims consultant  lecture one  2017- dr moustafa ismail
Cfcc certified forensic claims consultant lecture one 2017- dr moustafa ismail
 
Ss ccp course cost engineering management training- 2017 - moustafa ch 1-4
Ss ccp course cost engineering management  training- 2017 - moustafa  ch  1-4Ss ccp course cost engineering management  training- 2017 - moustafa  ch  1-4
Ss ccp course cost engineering management training- 2017 - moustafa ch 1-4
 

Recently uploaded

Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmDeepika Walanjkar
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdfAkritiPradhan2
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHSneha Padhiar
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfalene1
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Sumanth A
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxStephen Sitton
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfDrew Moseley
 
CS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfCS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfBalamuruganV28
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming languageSmritiSharma901052
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsapna80328
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfManish Kumar
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfisabel213075
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodManicka Mamallan Andavar
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptxmohitesoham12
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Communityprachaibot
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSneha Padhiar
 

Recently uploaded (20)

Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdfDEVICE DRIVERS AND INTERRUPTS  SERVICE MECHANISM.pdf
DEVICE DRIVERS AND INTERRUPTS SERVICE MECHANISM.pdf
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptx
 
Immutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdfImmutable Image-Based Operating Systems - EW2024.pdf
Immutable Image-Based Operating Systems - EW2024.pdf
 
CS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdfCS 3251 Programming in c all unit notes pdf
CS 3251 Programming in c all unit notes pdf
 
OOP concepts -in-Python programming language
OOP concepts -in-Python programming languageOOP concepts -in-Python programming language
OOP concepts -in-Python programming language
 
signals in triangulation .. ...Surveying
signals in triangulation .. ...Surveyingsignals in triangulation .. ...Surveying
signals in triangulation .. ...Surveying
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdf
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument method
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptx
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Community
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
 

Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5

  • 1. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 1 FIDIC Forms of Contracts Training Course: Saudi Council of Engineers 2017 LECTURE FIVE ‫وبركاته‬ ‫هللا‬ ‫ورحمة‬ ‫عليكن‬ ‫السالم‬ 2017
  • 2. • Cl.3 o Delegation – except for sub- Cl.3.5 Determination. o Instructions in writing • Verbal instructions to be followed by confirmation by contractor – written o Employer instructions to the Engineer SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 2 Engineer’s Responsibilities “continue” 2017
  • 3. o Determination • Consult – agreement – fair determination • Give notice • Give influence or proceed to Cl.20 • Cl.4.1 Request Method of Statements Discuss determination task? fairness SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 3 Engineer’s Responsibilities “continue” 2017
  • 4. • Cl.8.1 Give Commencement Notice • Cl.8.6 Rate of Progress • Cl.12.1 Measurement • Cl.13.1 Variations • Cl.14.6 Interim Payment Certificates • Cl.20.1 Records / Determination SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 4 Engineer’s Responsibilities “continued” 2017
  • 5. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 5 Engineer’s Responsibilities “continue” Cl.4 • Execute & Complete the Works  Cl.8.1 due expedition & without delay  Adequacy & safety  Method Statement  Fit for purpose • Performance Bond  Engineer’s Approval of Representative  May delegate  Fluent in language  Sub Contractor approval 2017
  • 6. • Setting Out to lines & levels • Quality Assurance (Process oriented) o Details in Specification o Procedures o Compliance documents SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 6 Contractor’s Responsibilities 2017
  • 7. • Site records o Costs comprised o Risk o Inspections o All relevant data – obligation o Caution in Tender – failure to provide • Adequacy of Contract Amount SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 7 Contractor’s Responsibilities “continued” 2017
  • 8. • Unforeseen site Physical Conditions o Excludes climatic conditions • S. Cl.8.4 & S.Cl. 17.3 Employer’s Risks o Extension of time o Payment of cost • (see S. Cl.1.1.4.3 includes off site) SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 8 Contractor’s Responsibilities “continue” 2017
  • 9. • Transport to site • Protection of the Environment • Emissions S.Cl. 4.18 Protection of the • Environment o Surface discharges o Effluent o Local/applicable Law SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 9 Contractor’s Responsibilities “continued” 2017
  • 10.  Progress Report  Monthly – 6 copies  Cl.4.9 procedures and: Cl. 6.7 Accident Records Cl. 6.10 Personnel Cl.14.3 Application for payment Cl.20.1 Contemporary records SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 10 Contractor’s Responsibilities “continue” 2017
  • 11. • Progress Report: o Charts o Photographs o Manufacturing report o Personnel o Quality Assurance documents o Claims Cl.2.5 Employer & 20.1 Contractor o Safety statistics o Progress SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 11 Contractor’s Responsibilities “continue” 2017
  • 12. • Security • Staff & Labour o Facilities / Health & Safety • Tests on Completion Cl. 9.1 • Value Engineering Cl. 13.3 • Application for Payment Cl. 14.3 • Contemporary records to support Cl. 20.1 SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 12 Contractor’s Responsibilities “continue” 2017
  • 13. Nominated Subcontractors • Clause 5 • Definition:  "nominated Subcontractor" means subcontractor: (a) who is stated in the Contract as being a nominated Subcontractor. or (b) whom the Engineer. under Clause 13 [Variations and Adjustments]. Instructs the Contractor to employ as a Subcontractor. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 132017
  • 14. • Applies to Subcontractors and suppliers nominated by Employer or as instructed by the Engineer under Cl.13 (Variations and Adjustments) SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 142017 Nominated Subcontractors
  • 15. • Clause 5.2 o Contractor practical Objection o Supporting particulars/details o Lack of competence, recourses, financial strength o Lack of indemnity- indemnify contractor o Lack of obligations and liability -sub-con shall enable the Contractor to discharge his obligations and liabilities SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 152017 Nominated Subcontractors
  • 16. Payment Clause 5.3: • The Contractor shall pay to the nominated Subcontractor the amounts which the Engineer certifies to be due in accordance with the subcontract. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 162017 Nominated Subcontractors’continued’
  • 17. • These amounts plus • Other charges shall be included in the Contract Price in accordance with subparagraph (b) of Sub-Clause 13.5 [Provisional Sums]. except as stated in the following Sub Clause 5.4. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 172017 Nominated Subcontractors ’continued’
  • 18. Nominated Subcontractors “continued” • 5.4 Evidence of Payments 1. Engineer requests reasonable evidence from nominated S/C- for receipt amount requested in the Contractor’s payment certificate previously paid (OR) 2. The contractor justifies non payment and notification issued to the nominated S/C for non payment with reasons : if no justification : 3. The Employer may pay and get back from the contractor ......deductions considered in any payment SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 182017
  • 19. Q&A SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 19 Q1. Nominated Sun-Con is: 1-Defined in the contract 2- assigned by the Contractor Q.2 Employer's Personnel S. Cl. 2.3 requirements: The Employer shall be responsible for ensuring that the Employer's Personnel and the Employer's other contractors on the Site co-operate with the Contractor's efforts, take actions similar to those which the Contractor is required to take for [Safety Procedures] and [Protection of the Environment]. 1. TRUE 2-False Q.3 Pursuant S. Cl . 4.2 Cl. 4.2 Issue of the Performance Security should be within 28 days from Issuance of the Letter of Acceptance. 1-TRUE 2-False Eng: ………………………… 2017
  • 20. Q&A SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 20 Q1. Nominated Sun-Con is: 1-Defined in the contract 2- assigned by the Contractor Q.2 Employer's Personnel S. Cl. 2.3 requirements: The Employer shall be responsible for ensuring that the Employer's Personnel and the Employer's other contractors on the Site co-operate with the Contractor's efforts, take actions similar to those which the Contractor is required to take for [Safety Procedures] and [Protection of the Environment]. 1. TRUE 2-False Q.3 Pursuant S. Cl . 4.2 Cl. 4.2 Issue of the Performance Security should be within 28 days from Issuance of the Letter of Acceptance. 1-TRUE 2-False 2017
  • 21. Project Engagement of Staff & Labour Clause 6 • Contractor shall make arrangements for the engagement of all staff and labor. local or otherwise, their payment. housing. feeding and transport. • Rates of Wages and Conditions // similar to the average in the work location/country • The Contractor shall not recruit// Employer's Personnel. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 212017
  • 22. Staff and labour “continue” • Labour Laws (including Expat/immigration) • Working Hours • Facilities (including Employer’s Personnel) • Health & Safety Medical staff & facilities Accident prevention officer Records SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 222017
  • 23.  Cl.4.3 – Contractor’s Representative  Cl.6.8 – Superintendence (Language)  Personnel competent– qualified, skilled, experienced  Cl.4.9 procedures monthly records SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 23 Staff and labour “continued” 2017
  • 24. 6.4 Labor Laws • The Contractor complies- applicable labor Laws (employment. health. Safety). Labor to obey applicable law. 6.5 Working Hours No work on rest days- no work outside working hours-// unless stated in the contract/ instructed. Or non avoidable. 6.6 Facilities for Staff and Labor • Contractor provide necessary accommodation and welfare facilities, for labors Contractor shall also provide facilities for the Employer's Personnel as stated in the Specification. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 24 Staff and labour “continue” 2017
  • 25. 6.7 Health and Safety • Contractor shall take reasonable precautions to maintain the health/ safety of its Personnel. '6.8 Contractor’s Superintendence • the Contractor shall provide all necessary superintendence to plan. arrange. direct. manage. inspect and test the work. 6.9 Contractor’s Personnel • Contractor's Personnel shall be appropriately qualified. skilled and experienced in their respective trades or occupations. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 25 Staff and labour “continue” 2017
  • 26. 6.10 Records of Contractor's Personnel and Equipment • The Contractor shall submit. to the Engineer. details each class of Personnel/Equipment on the Site. '6.11 Disorderly Conduct • Take all reasonable precautions to prevent any unlawful, riotous or disorderly conduct by his Personnel. and to preserve peace and protection of persons & property on & near the Site. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 26 Staff and labour “continued” 2017
  • 27. 7.1 Manner of Execution • The manufacture of Plant, and all other execution of the Works in the manner (if any) specified in the Contract, in a proper workmanlike, with properly equipped facilities and non- hazardous Materials. 7.2 Samples • Submit the samples of Material & relevant information. to Engineer for consent in advance, labeled as to origin and intended use. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 27 Plant, Materials and Workmanship 2017
  • 28. 7.3 Inspection The Employer's Personnel shall : • (have access to all parts of Site & all places of natural Materials, and during production, manufacture & construction • be entitled to examine. inspect. measure and test the materials and workmanship & check the progress of manufacture • 7.4 Testing • This Sub-Clause shall apply to all tests specified in the Contract other than the Tests after Completion (if any). SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 28 Plant, Materials and Workmanship 2017
  • 29. 7.5 Rejection • As a result of an examination. inspection, measurement or testing. any defective work/not in accordance with the Contract. the Engineer may reject it by giving notice to the Contractor. with reasons. 7.6 Remedial Work • Notwithstanding any previous test or certification. the Engineer may instruct:: • remove/ replace any Plant or Materials not complying • remove and re-execute work not complying. • execute any work urgently required for the safety. The Contractor complies in a reasonable time, as in the instruction. or immediately if urgency is specified under sub-paragraph (c). employ and pay other persons to do the remedial. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 29 Plant, Materials and Workmanship 2017
  • 30. 7.7 Ownership of Plant and Materials • Each item becomes the property of the Employer the earlier of the following times: • when it is delivered to the Site; or when Suspension S.Cl. 8.10. 7.8 Royalties. The Contractor shall pay all royalties, rents and other payments for: • (a) natural Materials, the disposal of material from demolitions and , excavations & of other surplus, material SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 30 Plant, Materials and Workmanship 2017
  • 31. 8.1 Commencement of Works  Engineer shall give 7 d. notice of commencement date. Unless otherwise stated in the P. Conditions. 42 d. (LOA). • Contractor commence execution as soon as is practicable (due expedition/ without delay). 8.2 Time for Completion Contractor shall complete the Works. & each Section (if any). • within the Time for Completion including: ( passing of the Tests on Completion, completing all work which is stated in the Contract, mandatory for work required to fit S. Cl.10.1 [Taking Over of the Works, Sections]. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 31 8.0 Commencement, Delays and Suspension 2017
  • 32. 8.3 Program • Submit a detailed program within 28 d. After notice S.- Cl. 8.1 [Commencement of Works]. • Revised program whenever the previous program is inconsistent with progress or Contractor's obligations. • Program shall include: o order of how to carry out the Works. o anticipated timing of each stage of design (if any). Contractor's Documents. procurement. manufacture of Plant. delivery to Site. construction. erection and testing. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 32 8.0 Commencement, Delays and Suspension 2017
  • 33. 8.3 Program- continued • each of these stages for work by each N. Sub-Con. • sequence and timing of inspections and tests, and • supporting report which includes: • (i) a general description of the methods intended to be adopted • (ii) details showing reasonable estimate of Personnel and Equipment. Histogram • Unless, responded 21 d. (not comply) with the Contract. the • Contractor shall proceed in accordance with the program. subject to his other contractual obligations. • Employer's Personnel shall be entitled to rely on the program SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 33 8.0 Commencement, Delays and Suspension 2017
  • 34. 8.3 Program- continued • Contractor shall notify the Engineer of specific probable future events which may adversely affect the work/ Time- Cost. • The Engineer may require the Contractor to submit an estimate of the anticipated effect of the future event or circumstances. • and/or a proposal under Sub-Clause 13.3 [Variation Procedure]. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 34 8.0 Commencement, Delays and Suspension 2017
  • 35. 8.4 Extension of Time for Completion • Contractor shall be entitled subject to S. Cl. 20.1 [C. Claims] to EOT for Completion if Sub-Clause 10.1 [Taking Over ] is or will be delayed by any of: Procedure of Extension of Time in LEC VI slide 11 o Variation o In culpable delay o Adverse weather o Unforeseeable shortages in the availability of personnel or Goods caused by epidemic or governmental actions. Or o delay, impediment or prevention by the Employer SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 35 8.0 Commencement, Delays and Suspension 2017
  • 36. 8.4 Extension of Time for Completion- continued • If Contractor considers himself entitled to EOT, the Contractor shall give notice to the Engineer in accordance with Sub- Clause 20.1 - the Engineer shall review previous determinations and may increase, but shall not decrease, the total extension of time SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 36 8.0 Commencement, Delays and Suspension 2017
  • 37. 8.5 Delays Caused by Authorities  If specifically: • Contractor has diligently followed the procedures laid down by the relevant public authorities. • These authorities delay or disrupt the Contractor's work. And • the delay or disruption was Unforeseeable. then this delay or disruption will be considered as a cause of delay under subparagraph (b) of S. Cl. 8.4 [EOT for Completion] . Inculpable delay SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 37 8.0 Commencement, Delays and Suspension 2017
  • 38. 8.6 Rate of Progress If. at any time:  Low progress  progress has fallen (or will fall) behind the current program, THEN: o then the Engineer may instruct a revised program, supporting report for the corrective measures. o the Contractor adopt revised methods, may require increases in the working hours and/or in the numbers of labor, and/or Goods. at the risk and cost of the Contractor. And pays delay damages to the Employer. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 38 8.0 Commencement, Delays and Suspension 2017
  • 39. 8.7 Delay Damages • If the Contractor fails to comply with S. Cl. 8.2 [Time for Completion]. The Contractor shall subject to Sub-Clause 2.5 [Employer's Claims] pay delay damages to the Employer for this default. These delay damages shall be the sum: • stated in the Appendix to Tender. which shall be paid for every day from Time for Completion & date stated in the T. Over Certificate However, the total amount due under this Sub-Clause (10-15%) • shall not exceed the maximum as per Appendix to Tender. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 39 8.0 Commencement, Delays and Suspension 2017
  • 40. 8.7 Delay Damages - continued • These delay damages shall be the only damages due from the Contractor for such default. other than in the event of termination under Sub-Clause 15.2 [Termination by Employer] prior to completion of the Works. • These damages shall not relieve the Contractor from his obligation to complete the Works, or from any other contractual obligations. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 40 8.0 Commencement, Delays and Suspension 2017
  • 41. 8.8 Suspension of Work • The Engineer may instruct the Contractor to suspend progress part/or all. During suspension , the Contractor protect. store and secure such part or the Works against any deterioration. loss or damage. • If the cause is notified and is the responsibility of the Contractor, the following S. Cl. 8.9. 8.10 and 8.11 shall not apply. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 41 8.0 Commencement, Delays and Suspension 2017
  • 42. 8.9 Consequences of Suspension • If the Contractor suffers delay/Cost from complying with instructions Suspension. and/or from resuming the work. Then give notice to the Engineer and shall be entitled S. Cl. 20.1to: (a) an EOT for delay, and payment of any such Cost. After this notice, the Engineer shall proceed [Determinations]. The Contractor shall not be entitled EOT/ cost incurred in, making good Contractor's faulty design, workmanship or materials, or failure to protect. store or secure in accordance with Sub-Clause 8.8 [Suspension of Work]. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 42 8.0 Commencement, Delays and Suspension 2017
  • 43. 8.10 Payment for Plant and Materials in Event of Suspension 1.1 .5.5 "Plant" means the apparatus(Equipment). machinery and vehicles intended to or forming part of the Permanent Works. • Shall be entitled to payment of the value of plant/Materials which have not delivered to Site. if: (a) Suspended for more than 28 days, and (b) Contractor marked Plant and/or Materials as the Employer’s property in accordance with Engineer's instructions. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 43 8.0 Commencement, Delays and Suspension 2017
  • 44. 8.11 Prolonged Suspension • If more than 84 days, the Contractor may request the Engineer's permission to proceed. • If no permission within 28 days after request, Contractor may, notify, treat the suspension as an omission under Clause 13. OR termination S. Cl. 16.2 Termination by Contractor if all Work is affected. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 44 8.0 Commencement, Delays and Suspension 2017
  • 45. 8.12 Resumption of Work • After the permission or instruction to proceed is given, the Contractor and the Engineer shall jointly examine the Works and the Plant and Materials affected by the suspension. The Contractor shall make good any deterioration or defect in or loss of the Works or Plant or Materials, which has occurred during the suspension. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 45 8.0 Commencement, Delays and Suspension 2017
  • 46. You are the project Engineer for a private school construction project which includes hundreds of activities, valued 4.50 M SAR and the contract is FIDIC Red Book 1999, the value of the school buildings is 4.0 M SAR while the fence and car shades are 0.50 M SAR, total duration 8 months Discuss the following in case you are the project Engineer/Employer 1. If the Contractor’s caused delay was prolonged for 6 months for the whole project- discuss clauses for LD and termination- value. ……………………………………………………………………………… ……………………………………………………………………………… ……………………………………………………………………………… …………………………………………………………………………….... Analyzed by Eng. ………… SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 46 Event Analysis 2 2017
  • 47. You are the project Engineer/ Contractor for a governmental school construction project which includes hundreds of activities, valued 4.50 M SAR and the contract is FIDIC Red Book 1999, the value of the school buildings is 4.0 M SAR while the fence and car shades are 0.50 M SAR, total duration 8 months Discuss the following in case you are the project Contractor: 1. If the Employers late decisions/drawings/ payment caused delay was prolonged for 3 months for the whole project- discuss clauses for LD and termination- value. …………………………………………………………………………………………… …………………………………………………………………………………………… …………………………………………………………………………… Analyzed by Eng. ………… SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 47 Event Analysis 3 2017
  • 48. You are the project Engineer/ Contractor for a high demand/urgency school for the public construction project which includes hundreds of activities, valued 4.50 M SAR and the contract is FIDIC Red Book 1999, the value of the school buildings is 4.0 M SAR while the fence and car shades are 0.50 M SAR, total duration 8 months Discuss the following in case you are the project Contractor: 3. If the Employers late decisions/drawings/ payment caused delay was prolonged for 3 months for the whole project- discuss clauses for LD and termination- value. …………………………………………………………………………………………… …………………………………………………………………………………………… …………………………………………………………………………………………… Analyzed by Eng. ………… SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 48 Event Analysis 4 2017
  • 49. You are the project Engineer/ Contractor for a private school construction project which includes hundreds of activities, valued 4.50 M SAR and the contract is FIDIC Red Book 1999, the value of the school buildings is 4.0 M SAR while the fence and car shades are 0.50 M SAR, total duration 8 months Discuss the following in case you are the project Eng/Employer: 3. If the Contractor’s (lack of funds/resources/Equipment/mismanagement) caused delay was prolonged for 3 months for the fence and car shade only and the rest of the project is completed - discuss clauses for LD and termination- value. …………………………………………………………………………………………… …………………………………………………………………………………………… …………………………………………………………………………………………… Analyzed by Eng. ………… SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 49 Event Analysis 4 2017
  • 50. Contractor’s letters- exercise • Notice of claim 2017SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 50
  • 51. SCE FIDIC Training 1011 BTA - Dr. Moustafa Ismail 2017 LEC- V 51 End of LECTURE Five Thank You ‫وبركاته‬ ‫هللا‬ ‫ورحوة‬ ‫عليكن‬ ‫السالم‬ ‫هللا‬ ‫أهاى‬ ‫فى‬ 2017