Steve Wake
Earned Value Sets You
Freemaybe.
What do we all want
our projects to do?
SUCCEED!
How many projects
failin the uk?
What is a project
failure?
Who has the influence?
Politics is the art of the possible.
And so is project management.
Focus on what you can influence.
14
Stakeholders
Enablers
Disablers
Who is?
Sponsor
Competition
Customer
Project Manager
Champion
Health and Safety
Rival t...
What can we do?
Pay attention
This is the only slide with any
practical advice!
Project Management nearly always appears on the WBS.
It is...
Can I go home now?
What makes a successful
project?
Widespread agreement
that it is a success
What is the reality of
Consensus?
What is success for
us?Realisation of the benefits.
Financial and/or Social.
Commonly agreed.
Even if you are not
a benefi...
How do we do this with
projects?
We clearly define the
benefits.
primeiro
segundo
We Program the changes required
to achieve the benefits.
terceiro
We clearly define the projects
needed to achieve the changes.
What have I just
described?
The Problem with P3
• We just don’t do it!(properly).
• Projects are created without reference to
benefit.
• Portfolios do...
The Result is project failure
Lots of effort. No result.
Portfolios today are generally
houses built on sand,
and that is why projects continue
to fail.
We live in a world
where we accept this
as normal behaviour
We lie or cheat to win business
We have to decide who we are
or
We must become Professional
In English Professional can mean ,
Someone who acts with integrity.
Someone who is mercenary a...
Integrity 1
Integrity 2
Integrity 3
Interestingly for leaders
We have to become
trusted for the accuracy
and reliability of the data
under our control.
Then
Management can
manage.
But always remember…
there are some you can never trust!
What is Project
Management?
Cost Time Scope
Quality
To Budget
What is the best project
management can do?
Status
•It tells us where we are
•How much we’ve done
How do we work out where we
are?
What if we can’t?
•Build a plan
•Freeze the plan
•Measure progress
1. DEFINE THE WORK SCOPE
2. SCHEDULE THE WORK
3. ALLOCATE BUDGETS TO SCHEDULE
EVM: Performance Measurement Baseline
100
40...
0
500
1000
1500
2000
2500
3000
J F M A M J J A S O N D J F M A M J J A S O N D J F
Actual Costs
Budget (Plan) Reporting Cu...
•Build a plan and baseline it.
•Calculate physical progress
Physical progress
•How much do I want to spend?
•How much have I spent?
•What have I got to show for it?
0
500
1000
1500
2000
2500
3000
J F M A M J J A S O N D J F M A M J J A S O N D J F
Work Performed (Earned Value)
Actual Co...
• I planned to spend £1300
• I spent £1500
• I’ve achieved £1100
• I am completing 73p of work for every £1 planned.
• It ...
The Earned Value line
• Is an additional line
• Tracks physical completeness. What has been done.
• It should not be treat...
Earned Value is the best way to
determine the status of a
project.
And yet….
If you don’t know where you
are.
How do you manage?
If a portfolio manager does not
know the true status of the projects
which drive the portfolio.
Is this OK?
Earned Value sets you free
Because
• With poor status data your job is to fix and defend the
data.
• With good status data...
EV
Or not
EV?
Conclusion
• If project managers focus on becoming professionals
with integrity they will always be part of the solution.
...
May 2014
swprojects@blueyonder.co.uk
Steve Wake earned value sets you free
Steve Wake earned value sets you free
Steve Wake earned value sets you free
Steve Wake earned value sets you free
Steve Wake earned value sets you free
Steve Wake earned value sets you free
Steve Wake earned value sets you free
Steve Wake earned value sets you free
Steve Wake earned value sets you free
Steve Wake earned value sets you free
Steve Wake earned value sets you free
Upcoming SlideShare
Loading in …5
×

Steve Wake earned value sets you free

561 views

Published on

This is one of many excellent presentations given over the last three years of the eVa in the UK series. They can also be found in the archive at: http://evaintheuk.org/archive along with back-copy video footage in http://evaintheuk/pmchannel
EVA19, the long established Earned Value conference, has this year described its theme as looking at a project management ‘ABC’ – Agile, Benefits and Complex.
The four day event, which returns to the Armourers Hall, runs from the 19th to 22nd of May with the flagship conference being held on 20th and 21st May and workshops before and after.
The conference will look at how this ‘ABC’ can be made to work within a portfolio and how agile fits into major and minor projects. It will investigate how to manage the relationship between portfolio benefits and project budgets, and whether complex projects even exist.
Conference organiser and APM chairman, Steve Wake says:
“Currently there is little evidence that this ‘ABC’ is being effectively deployed and managed. This conference aims to address that concern through EVA’s trademark blend of learning and professional development. Case studies and unusual presentations, delivered by top-notch speakers and experienced practitioners, will again engage and entertain the audience.
We’ve used string quartets to illustrate points in the past and this year we will be using a Blues band for the first time.”
Speakers across the two days include many familiar faces from the APM events programme including; Adrian Pyne of the APM ProgM SIG ‘Changing the project wasteland with a portfolio culture that works,’ APM Honorary Fellow Tim Banfield Director at the Major Projects Authority and Stephen Jones, Sellafield and Planning Monitoring and Control Specific Interest Group (PMC SIG) and Carolyn Limbert of the APM PMC SIG to talk about agile, benefits and complex.
Peter Taylor, the Lazy Project Manager will be presenting on “The project manager who smiled” and the ever popular Stephen Carver will present the leadership lessons that can be learnt from Alfred the Great.
In addition, there will be speakers from AIRBUS, TfL, Bloodhound, Heathrow T2 and London Tideway Tunnels.
The conference will be supplemented by a number of workshops being held at the Chartered Institute of Arbitrators, Bloomsbury Square on Monday 19th and Thursday 22nd May 2014.
'eVa in the UK' http://evaintheuk.org is building a reputation, brand and a learning legacy for the Project Management Profession. The event series is now in its nineteenth year. It is almost as if it all kicked-off when Steve Wake was in short trousers and knights roamed the land on their chargers!
#eva19 is an excellent example of Listening, Learning and Leading #apmLLL in action, and great opportunity for professional development.

I would encourage anyone who is interested in 'Building a better Project Manager,' to take a look at the web site, and book your place and get involved.

Published in: Business, Technology
0 Comments
2 Likes
Statistics
Notes
  • Be the first to comment

No Downloads
Views
Total views
561
On SlideShare
0
From Embeds
0
Number of Embeds
3
Actions
Shares
0
Downloads
12
Comments
0
Likes
2
Embeds 0
No embeds

No notes for slide

Steve Wake earned value sets you free

  1. 1. Steve Wake Earned Value Sets You Freemaybe.
  2. 2. What do we all want our projects to do?
  3. 3. SUCCEED!
  4. 4. How many projects failin the uk?
  5. 5. What is a project failure?
  6. 6. Who has the influence?
  7. 7. Politics is the art of the possible. And so is project management. Focus on what you can influence.
  8. 8. 14 Stakeholders Enablers Disablers Who is? Sponsor Competition Customer Project Manager Champion Health and Safety Rival team Remember this from PMI Portugal 2003?
  9. 9. What can we do?
  10. 10. Pay attention This is the only slide with any practical advice! Project Management nearly always appears on the WBS. It is normally shown as level of effort (NVA) RENAME that WBS box “COMMUNICATIONS”. Define them as with any other deliverable. Place these communications on the schedule. And Project Manage them. The reason we communicate poorly is because it’s not in the plan!
  11. 11. Can I go home now?
  12. 12. What makes a successful project?
  13. 13. Widespread agreement that it is a success
  14. 14. What is the reality of Consensus?
  15. 15. What is success for us?Realisation of the benefits. Financial and/or Social. Commonly agreed. Even if you are not a beneficiary.
  16. 16. How do we do this with projects?
  17. 17. We clearly define the benefits. primeiro
  18. 18. segundo We Program the changes required to achieve the benefits.
  19. 19. terceiro We clearly define the projects needed to achieve the changes.
  20. 20. What have I just described?
  21. 21. The Problem with P3 • We just don’t do it!(properly). • Projects are created without reference to benefit. • Portfolios do not retain their dynamic links with the projects they created. • The Board and senior management just look at the Portfolio and assume the links with the project are there.
  22. 22. The Result is project failure Lots of effort. No result.
  23. 23. Portfolios today are generally houses built on sand, and that is why projects continue to fail.
  24. 24. We live in a world where we accept this as normal behaviour
  25. 25. We lie or cheat to win business
  26. 26. We have to decide who we are or
  27. 27. We must become Professional In English Professional can mean , Someone who acts with integrity. Someone who is mercenary and cynical.
  28. 28. Integrity 1
  29. 29. Integrity 2
  30. 30. Integrity 3
  31. 31. Interestingly for leaders
  32. 32. We have to become trusted for the accuracy and reliability of the data under our control. Then Management can manage.
  33. 33. But always remember… there are some you can never trust!
  34. 34. What is Project Management?
  35. 35. Cost Time Scope Quality To Budget
  36. 36. What is the best project management can do?
  37. 37. Status •It tells us where we are •How much we’ve done
  38. 38. How do we work out where we are? What if we can’t?
  39. 39. •Build a plan •Freeze the plan •Measure progress
  40. 40. 1. DEFINE THE WORK SCOPE 2. SCHEDULE THE WORK 3. ALLOCATE BUDGETS TO SCHEDULE EVM: Performance Measurement Baseline 100 40 60 80 PMB PMB TIME £ CONTRACT BUDGET BASE MR
  41. 41. 0 500 1000 1500 2000 2500 3000 J F M A M J J A S O N D J F M A M J J A S O N D J F Actual Costs Budget (Plan) Reporting Cut-off Date Where are we? ? Total Project Budget
  42. 42. •Build a plan and baseline it. •Calculate physical progress
  43. 43. Physical progress •How much do I want to spend? •How much have I spent? •What have I got to show for it?
  44. 44. 0 500 1000 1500 2000 2500 3000 J F M A M J J A S O N D J F M A M J J A S O N D J F Work Performed (Earned Value) Actual Costs Budget (Plan) Reporting Cut-off Date Cost Variance Schedule Variance (Currency) What does this tell us? Total Project Budget
  45. 45. • I planned to spend £1300 • I spent £1500 • I’ve achieved £1100 • I am completing 73p of work for every £1 planned. • It is costing me £1.36 to earn £1of work.
  46. 46. The Earned Value line • Is an additional line • Tracks physical completeness. What has been done. • It should not be treated as a discretionary add-on. • It is not possible to manage a project well without it. • And yet some project managers say they don’t need earned value.
  47. 47. Earned Value is the best way to determine the status of a project. And yet….
  48. 48. If you don’t know where you are. How do you manage?
  49. 49. If a portfolio manager does not know the true status of the projects which drive the portfolio. Is this OK?
  50. 50. Earned Value sets you free Because • With poor status data your job is to fix and defend the data. • With good status data you and your stakeholders can make good solid management decisions. • Earned value is not a miracle but it does make good managers better.
  51. 51. EV Or not EV?
  52. 52. Conclusion • If project managers focus on becoming professionals with integrity they will always be part of the solution. • Earned Value status provides the firm foundations portfolios need for effective delivery of benefits. • If project managers remain ‘pragmatic’ then projects will continue to fail at 73%. And project managers along with their stakeholders will continue to perpetuate the mess this planet and its macro economy is in now and for the foreseeable future.
  53. 53. May 2014
  54. 54. swprojects@blueyonder.co.uk

×