UCWL-PPT

52 views

Published on

  • Be the first to comment

  • Be the first to like this

UCWL-PPT

  1. 1. ALL CONTRACTOR’S MEETING AT FAB YARD. 24/10/15 UCWL DEBOK
  2. 2. ALL CONTRACTOR’S MEETING HELD AT UCWL-DEBOK AT 24/10/2015
  3. 3. UNSAFE PRACTICES HOOK WELDING-
  4. 4. VEHICLE INSPECTION –UCWL ON 02/11/15
  5. 5. MEETING WITH UCWL –SAFETY HEAD ON 02/11/15
  6. 6. C.PULLEY BLOCK FOUND IN SITE WITHOUT INSPECTION COVER ON 02/11/15
  7. 7. CHAIN PULLEY BLOCK BEING USED WITHOUT INSPECTION COVER IN PREHEATER- UCWL DEBOK
  8. 8. JOINT INSPECTION WITH UCWL SAFETY HEAD AT 02.11.15
  9. 9. DAMAGED SLING WITH LOAD- 02.11.15 AT UCWL
  10. 10. PLATE BENDING MACHINE WITHOUT MACHINE GUARD- HIGHLY HAZARDOUS – FAB/YARD UCWL-DEBOK ON 02.11.15
  11. 11. MACHINE GUARD MISSING- FAB/YARD 02.11.15
  12. 12. THE TRAILER DON’T HAVE REVERSE HORN AND LIGHT ISSUES
  13. 13. 07 NOS CHAIN PULLEY BLOCKS FOUND ACROSS THE SITE IN SUCH CONDITION?
  14. 14. POOR HOUSE KEEPING AT FABRICATION YARD –UCWL DEBOK 2.11.15
  15. 15. POOR HOUSE KEEPING –UCWL DEBOK ON 02.11.15

×