  1. 1. Construction of Latvian National Library March 18, 2010.
  2. 2. <ul><li>The building’s concept is expressive. In its form are metaphors and references relating to the most significant fables and poetry found in Latvian literature, such as ‘Glass mountain’ or the symbolic ‘Castle of Light’ which, as the fable said, sank during the bloody days of enslavement. the castle will rise from the d e pths and free the people when its name is invoked by courageous men and women. </li></ul><ul><li>Gunnar Birkerts, architect of the National Library of Latvia </li></ul>National Library of Latvia Costs: 135 mi o LVL Government funding Construction: 2008 - 2012
  3. 3. Project development . <ul><li>1928. Idea to construct a building that would be designated especially for library functions arises for the first time </li></ul><ul><li>1988. Council of Ministers of LPSR passes decision on construction of the National Library of Latvia building </li></ul><ul><li>1993. Architect G.Birkerts develops the first sketch of the NLL building </li></ul><ul><li>1999. General Council of UNESCO passes resolution on supporting the NLL project </li></ul><ul><li>2003. Law on the NLL project is ratified </li></ul><ul><li>2004. Expropriation of the real estate located on the future NLL building site begins and architectural planning task is received </li></ul><ul><li>2006. One section of the NLL project is finished – the NLL book storage in Silakrog s is renovated and put into operation </li></ul><ul><li>2007. The construction design of the NLL building is developed </li></ul><ul><li>2008. Construction works of the NLL building commence </li></ul><ul><li>2009. Building ’s zero cycle is finished. The infrastructure project of the NLL building is developed </li></ul>
  4. 4. <ul><li>Total area of the building -40 455 m2 </li></ul><ul><li>Number of floors -13 (including basement) </li></ul><ul><li>Height of the building -68 m </li></ul><ul><li>Resources of global information: </li></ul><ul><li>- storage of 6,5 million copies of printed materials </li></ul><ul><li>- in excess of 1000 spaces in the reading area </li></ul><ul><li>- capacity of serving more than 3000 readers a day </li></ul><ul><li>- conference rooms and rooms for classes </li></ul><ul><li>- Exposition of Latvian Books museum, exhibition halls </li></ul><ul><li>- friendly environment for disabled people </li></ul>Highlights
  5. 5. Division of rooms <ul><li>Public zone – 9 298 m² or 23 % (lobby, Latvian Books museum, libraries’ development institute, ISBN, ISMN, ISSN, exhibition halls, souvenirs/book store, conference centre, restaurant/canteen, panorama plaza etc.) </li></ul><ul><li>Reading area – 12 773 m 2 or 31% (reading rooms with free access s resources (350 000 books), readers’ spaces equipped/not equipped with stationary PCs, information centre) </li></ul><ul><li>Storage zone – 5 016 m² or 12% (specifically equipped storage spaces for each type of storage, stock rooms, mobile shelving) </li></ul><ul><li>Rooms for the NLL operations, including research work – 8 945 m² or 21% (department of renovation un resources maintenance, digitalization, customer service department, institute of bibliography, administration etc.) </li></ul><ul><li>Technical rooms - 4980,2 m² or 12 % (rooms for maintenance staff, servers, ventilation cameras, heating, water preparation equipment, transform ers, diesel generator etc.) </li></ul>
  6. 6. <ul><li>1. NLL building </li></ul><ul><li>Multifunctional technical building </li></ul><ul><ul><li>(chillers, 110 kV substation, </li></ul></ul><ul><ul><li>Paper quality improvement room, </li></ul></ul><ul><ul><li>parking) </li></ul></ul><ul><li>3. Underground parking </li></ul>NLL territory
  7. 8. Expenditure by main elements (mio LVL) till 2004 2004 2005 2006 2007 2008 2009 Total Works prior to the project 1,340 0,037 0,298 - - - 1,675 Book storage in Silakrogs 0,016 0,412 0,408 0,023 - 0,859 Real estate 0,046 2,396 2,750 1,000 - 6,192 Site preparation - 0,012 0,304 0,606 0,515 1,437 Designing of NLL building - - 2,801 3,404 - - 6,205 Designing of infrastructure 1,689 0,338 1,403 3,430 NLL construction works - - - - 8,360 25,666 34,026 Other 0,09 0,079 0,102 0,33 0,090 0,072 0,672 Total 1,340 0,189 3,197 6,365 7,007 9,303 27,095 54,496
  8. 9. Expenditure by year
  9. 10. <ul><li>Construction of the NLL building </li></ul><ul><li>Construction of the infrastructure of the NLL building </li></ul><ul><li>E quipment of the library and moving </li></ul>With a maximum effort of rational expenditure of the assigned financing t o ensure that the new NLL building can be put into operation <ul><li>2 scenarios for completion of the NLL building: </li></ul><ul><ul><li>November, 2012 </li></ul></ul><ul><ul><li>1st quarter of 2014 </li></ul></ul>Future strategy of the NLL project
  10. 11. <ul><li>NLL building’s equipment </li></ul><ul><ul><li>Book storage shelving 2,8 </li></ul></ul><ul><ul><li>Specific furniture and equipment 6,4 </li></ul></ul><ul><ul><li>Final equipment of the final IKT systems 3,0 </li></ul></ul><ul><ul><li>Transferring the books and moving 0,8 </li></ul></ul><ul><ul><li> 12,2 </li></ul></ul><ul><li>NLL building </li></ul><ul><ul><li>Construction works 138,3 </li></ul></ul><ul><ul><li>Works supervision 5,7 </li></ul></ul><ul><li> 144,0 </li></ul><ul><li>NLL infrastructure </li></ul><ul><ul><li>External networks connections 1,0 </li></ul></ul><ul><ul><li>Technical support building 6,1 </li></ul></ul><ul><ul><li>Microclimate equipment 1,8 </li></ul></ul><ul><li> 8,9 </li></ul>Project costs (millions of Ls) TOTAL 166,1
  11. 12. Cost division by year
  12. 13. Time schedule of NLL project
  13. 14. Management structure of the NLL project National Library of Latvia State agency ‘Information Systems of Culture’ NLL project Public Supervisory board NLL project The NLL Foundation Ministry of Culture Republic of Latvia Implementation unit of NLL project
  14. 15. <ul><li>The Latvian National Library foundation </li></ul><ul><ul><li>a public non-profit organization created in 1998 in order to promote the Library Project and raise funds </li></ul></ul><ul><li>Transparency International Latvia – Delna </li></ul><ul><ul><li>cooperation agreement (integrity pact), supervision over the implementation of NLL project, making this process more transparent </li></ul></ul><ul><li>NLL Construction project Public Supervisory board </li></ul><ul><ul><li>Independent, advisory institution, in which professional and non-governmental organizations of construction industry are represented. The Board evaluates the construction works progress; provides recommendations on ethical practice for constructions works ; will submit proposals on improvement of legislation and regulations </li></ul></ul>Participation of Non-Government Bodies in the NLL project
  15. 16. Thank You!

×