SlideShare a Scribd company logo
1 of 25
SPM-UNIT III
RISK MANAGEMENT
MONITORING & CONTROL
Prof. Kanchana Devi
Introduction
 After scheduling , project will start and then
attention must be focused on progress.
 Progress needs monitoring
 What is happening
 Comparison of actual achievement against the schedule
 Revision of plans and schedules (wherever necessary)
2
Prof. Kanchana Devi
Creating Framework
Prof. Kanchana Devi
3
 Exercising control over a project and ensuring
that targets are met is a matter of regular
monitoring.
 Finding out what is happening and comparing
it with targets
 Re-planning also sometimes required
Project control cycle
Prof. Kanchana Devi
4
Responsibility
Prof. Kanchana Devi
5
 The overall responsibility
 Ensuring satisfactory progress on a project
 It is the role of “Steering Committee”, project
management board or Project Board.
Project Reporting Structure
Prof. Kanchana Devi
6
Reporting
Prof. Kanchana Devi
7
 Reporting may be
 Oral/Written
 Formal/Informal
 Regular/Ad-hoc
Assessing Progress
Prof. Kanchana Devi
8
 Information should be collected routinely
 Information should be objective and tangible
 Whether or not a particular report has been delivered
 Sometimes the assessment depends on
estimates of proportion of current activity that
has been completed
Setting Checkpoints
Prof. Kanchana Devi
9
 Necessary to set a series of check points in
the initial activity plan.
 Checkpoints may be:
 Regular(Monthly)
 Tied to specific events (production of report)
Collecting the Data
Prof. Kanchana Devi
10
 Rule: Manager will breakdown the long
activities into more controllable tasks of one or
two weeks.
 It is necessary to gather information about
partially completed activities, forecasts of how
much work is left to be completed.
Example of partial completion reporting
Prof. Kanchana Devi
11
Risk Reporting
Prof. Kanchana Devi
12
 One way to overcome the objections of partial
completion report is to avoid asking for
completion dates. (instead ask for likelihood of meeting the
target)
 Called “Traffic Light Method”.
Consists of following steps
Prof. Kanchana Devi
13
 Identify the key elements for assessment in a piece of
work
 Break these key elements into constituent element
 Assess each of the second level element on the scale
 Green for target,
 Amber for ‘not on target but recoverable’
 Red for ‘not on target and recoverable only with
difficulty’
 Review second level assessment to arrive at first level
 Review first level assessment to produce an overall
assessment
Example
Prof. Kanchana Devi
14
Visualizing Progress
Prof. Kanchana Devi
15
 Gantt Chart
 Slip Chart
 Ball Chart
 Timeline Chart
Cost Monitoring
Prof. Kanchana Devi
16
 Expenditure monitoring is an important
component of project control
 A project might be on time but only because
more money has been spent on activities than
originally budgeted
Tracking cumulative expenditure
Prof. Kanchana Devi
17
Cumulative Expenditure Chart
Prof. Kanchana Devi
18
Earned Value
Prof. Kanchana Devi
19
 Analysis is based on assigning a ‘value’ to each
task or work package based on expenditure
forecasts.
 The assigned value is the original budgeted cost
for the item and is known as the ‘baseline budget’
or ‘budgeted cost of work scheduled’(BCWS)
 The total value credited to a project at any point is
known as the ‘earned value’ or ‘budgeted cost of
the work performed’(BCWP)
Actual Cost
Prof. Kanchana Devi
20
 By recording the “Earned Value”, the actual
cost of each task can be collected as “Actual
Cost” or ACWP-Actual Cost of Work
Performed.
 There are three types of Variance:
 Schedule Variance(SV)
 Time Variance(TV)
 Cost Variance(CV)
Schedule Variance(SV)
Prof. Kanchana Devi
21
 The Schedule Variance is measured in
cost terms as EV-PV
 It indicates the degree to which the value
of the completed work differs from the
planned work.
Example:
Prof. Kanchana Devi
22
 A work with a PV of $40,000 should have
been completed by now. In fact, some of that
work has not been done so that the EV is only
$35,000. Calculate SV.
 SV=EV-PV
 35000-40000= - 5000
 A negative SV means the project is behind
schedule
Time Variance (TV)
Prof. Kanchana Devi
23
 Difference between the time when the
achievement of the current earned value was
planned to occur and the time now.
 Eg:
 The current EV should have been achieved in the
early part of month 9 and as the time now is end
of month 11, the TV is about -1.75 months from
graph.
Cost Variance (CV)
Prof. Kanchana Devi
24
 This is calculated as EV-AC.
 It indicates the difference between the earned
value or budgeted cost and the actual cost of the
completed work.
 Let Actual Cost for previous example is $ 55,000
 CV=35000-55000
 = -20000
 A negative CV means that the project is over cost
Prioritizing Monitoring
Prof. Kanchana Devi
25
 List of priorities
 Critical Path Activities
 Activities with no free float
 Activities with less than a specified float
 High Risk Activities
 Activities using critical resources

More Related Content

What's hot

MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTKathirvel Ayyaswamy
 
Software project management introduction
Software project management introductionSoftware project management introduction
Software project management introductionKanchana Devi
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTKathirvel Ayyaswamy
 
Globalization issues in project management
Globalization issues in project managementGlobalization issues in project management
Globalization issues in project managementMenakapriyaM
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project ManagementReetesh Gupta
 
Capability maturity model cmm lecture 8
Capability maturity model cmm lecture 8Capability maturity model cmm lecture 8
Capability maturity model cmm lecture 8Abdul Basit
 
Spm unit iii-risk-intro
Spm unit iii-risk-introSpm unit iii-risk-intro
Spm unit iii-risk-introKanchana Devi
 
Agile development, software engineering
Agile development, software engineeringAgile development, software engineering
Agile development, software engineeringRupesh Vaishnav
 
Project Evaluation and Estimation in Software Development
Project Evaluation and Estimation in Software DevelopmentProject Evaluation and Estimation in Software Development
Project Evaluation and Estimation in Software DevelopmentProf Ansari
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project ManagementSaadi Jadoon
 
Software Configuration Management (SCM)
Software Configuration Management (SCM)Software Configuration Management (SCM)
Software Configuration Management (SCM)Er. Shiva K. Shrestha
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTKathirvel Ayyaswamy
 
Capability Maturity Model
Capability Maturity ModelCapability Maturity Model
Capability Maturity ModelUzair Akram
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project ManagementkarthikeyanC40
 

What's hot (20)

Spm unit 3
Spm unit 3Spm unit 3
Spm unit 3
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENT
 
Software project management introduction
Software project management introductionSoftware project management introduction
Software project management introduction
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENT
 
Globalization issues in project management
Globalization issues in project managementGlobalization issues in project management
Globalization issues in project management
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
 
Spm unit 4
Spm unit 4Spm unit 4
Spm unit 4
 
SPM PPT
SPM PPTSPM PPT
SPM PPT
 
Capability maturity model cmm lecture 8
Capability maturity model cmm lecture 8Capability maturity model cmm lecture 8
Capability maturity model cmm lecture 8
 
Spm unit iii-risk-intro
Spm unit iii-risk-introSpm unit iii-risk-intro
Spm unit iii-risk-intro
 
Agile development, software engineering
Agile development, software engineeringAgile development, software engineering
Agile development, software engineering
 
Project Evaluation and Estimation in Software Development
Project Evaluation and Estimation in Software DevelopmentProject Evaluation and Estimation in Software Development
Project Evaluation and Estimation in Software Development
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
 
Software design
Software designSoftware design
Software design
 
Software Configuration Management (SCM)
Software Configuration Management (SCM)Software Configuration Management (SCM)
Software Configuration Management (SCM)
 
MG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENTMG6088 SOFTWARE PROJECT MANAGEMENT
MG6088 SOFTWARE PROJECT MANAGEMENT
 
Spm unit2
Spm unit2Spm unit2
Spm unit2
 
Capability Maturity Model
Capability Maturity ModelCapability Maturity Model
Capability Maturity Model
 
Software Project Management
Software Project ManagementSoftware Project Management
Software Project Management
 
Software Cost Factor
Software Cost FactorSoftware Cost Factor
Software Cost Factor
 

Viewers also liked

Spm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationSpm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationKanchana Devi
 
Risk Management
Risk ManagementRisk Management
Risk Managementcgeorgeo
 
Spm unit iii-risk-pert
Spm unit iii-risk-pertSpm unit iii-risk-pert
Spm unit iii-risk-pertKanchana Devi
 
Spm unit iii-risk-working in teams
Spm unit iii-risk-working in teamsSpm unit iii-risk-working in teams
Spm unit iii-risk-working in teamsKanchana Devi
 
List of 10 Sales Performance Management (SPM) Vendors
List of 10 Sales Performance Management (SPM) VendorsList of 10 Sales Performance Management (SPM) Vendors
List of 10 Sales Performance Management (SPM) VendorsTriCorps Technologies
 
Spm project planning
Spm project planning Spm project planning
Spm project planning Kanchana Devi
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updatedFarhana Rehman
 
How to monitor your project progress
How to monitor your project progressHow to monitor your project progress
How to monitor your project progressAsif A. Kabani
 
Bank risk management
Bank risk managementBank risk management
Bank risk managementAshima Thakur
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Controlguy_davis
 
Risk management in banks
Risk management in banksRisk management in banks
Risk management in bankseduCBA
 
Leadership In Project Management
Leadership In Project ManagementLeadership In Project Management
Leadership In Project Managementguest484a666
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoringharoldtaylor1113
 
Risk management in banking
Risk management in bankingRisk management in banking
Risk management in banking7939790a
 

Viewers also liked (20)

Spm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocationSpm unit iii-risk-resource allocation
Spm unit iii-risk-resource allocation
 
Risk management
Risk managementRisk management
Risk management
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Spm unit iii-risk-pert
Spm unit iii-risk-pertSpm unit iii-risk-pert
Spm unit iii-risk-pert
 
Spm chapter 8
Spm chapter 8Spm chapter 8
Spm chapter 8
 
Spm unit iii-risk-working in teams
Spm unit iii-risk-working in teamsSpm unit iii-risk-working in teams
Spm unit iii-risk-working in teams
 
List of 10 Sales Performance Management (SPM) Vendors
List of 10 Sales Performance Management (SPM) VendorsList of 10 Sales Performance Management (SPM) Vendors
List of 10 Sales Performance Management (SPM) Vendors
 
Spm project planning
Spm project planning Spm project planning
Spm project planning
 
Monitoring the control
Monitoring the control Monitoring the control
Monitoring the control
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Ch 9 project monitoring & control updated
Ch 9 project monitoring & control updatedCh 9 project monitoring & control updated
Ch 9 project monitoring & control updated
 
How to monitor your project progress
How to monitor your project progressHow to monitor your project progress
How to monitor your project progress
 
Bank risk management
Bank risk managementBank risk management
Bank risk management
 
Effective Risk Mgmt Kylucas (C) 2009 All Rights Reserved
Effective Risk Mgmt Kylucas (C) 2009 All Rights ReservedEffective Risk Mgmt Kylucas (C) 2009 All Rights Reserved
Effective Risk Mgmt Kylucas (C) 2009 All Rights Reserved
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 
Risk management in banks
Risk management in banksRisk management in banks
Risk management in banks
 
Leadership In Project Management
Leadership In Project ManagementLeadership In Project Management
Leadership In Project Management
 
Project Controlling and Project Monitoring
Project Controlling and Project MonitoringProject Controlling and Project Monitoring
Project Controlling and Project Monitoring
 
Risk management in banking
Risk management in bankingRisk management in banking
Risk management in banking
 

Similar to Spm unit iii-risk-monitoring & control1

Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptadabotor7
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..EngrMuhammadJavidNaw
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Mohammad Lemar ZALMAİ
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedWaqar Ahmed
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Earned value management
Earned value managementEarned value management
Earned value managementGautam Kumar
 

Similar to Spm unit iii-risk-monitoring & control1 (20)

Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Project monitoring lecture 1
Project monitoring lecture 1Project monitoring lecture 1
Project monitoring lecture 1
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.ppt
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..Primavera Calender and Earned Value.pdf..
Primavera Calender and Earned Value.pdf..
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
Performance Evaluation of Construction Projects by EVM Method, Using Primaver...
 
Project managment 6 (a)
Project managment 6 (a)Project managment 6 (a)
Project managment 6 (a)
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Summer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javedSummer Internship Report by waqar ahmed javed
Summer Internship Report by waqar ahmed javed
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Earned value management
Earned value managementEarned value management
Earned value management
 

More from Kanchana Devi

Spm unit v-software reliability-
Spm unit v-software reliability-Spm unit v-software reliability-
Spm unit v-software reliability-Kanchana Devi
 
Spm unit v-software maintenance-intro
Spm unit v-software maintenance-introSpm unit v-software maintenance-intro
Spm unit v-software maintenance-introKanchana Devi
 
Spm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilitiesSpm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilitiesKanchana Devi
 
Spm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-introSpm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-introKanchana Devi
 
Open source spm tools
Open source spm toolsOpen source spm tools
Open source spm toolsKanchana Devi
 

More from Kanchana Devi (6)

Spm unit v-software reliability-
Spm unit v-software reliability-Spm unit v-software reliability-
Spm unit v-software reliability-
 
Spm unit v-software maintenance-intro
Spm unit v-software maintenance-introSpm unit v-software maintenance-intro
Spm unit v-software maintenance-intro
 
Spm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilitiesSpm unit iii-configuration mgmt-responsibilities
Spm unit iii-configuration mgmt-responsibilities
 
Spm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-introSpm unit iii-configuration mgmt-intro
Spm unit iii-configuration mgmt-intro
 
SPM Evaluation
SPM EvaluationSPM Evaluation
SPM Evaluation
 
Open source spm tools
Open source spm toolsOpen source spm tools
Open source spm tools
 

Recently uploaded

Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsDILIPKUMARMONDAL6
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...Amil Baba Dawood bangali
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfRajuKanojiya4
 

Recently uploaded (20)

Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
The SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teamsThe SRE Report 2024 - Great Findings for the teams
The SRE Report 2024 - Great Findings for the teams
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
National Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdfNational Level Hackathon Participation Certificate.pdf
National Level Hackathon Participation Certificate.pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 

Spm unit iii-risk-monitoring & control1

  • 1. SPM-UNIT III RISK MANAGEMENT MONITORING & CONTROL Prof. Kanchana Devi
  • 2. Introduction  After scheduling , project will start and then attention must be focused on progress.  Progress needs monitoring  What is happening  Comparison of actual achievement against the schedule  Revision of plans and schedules (wherever necessary) 2 Prof. Kanchana Devi
  • 3. Creating Framework Prof. Kanchana Devi 3  Exercising control over a project and ensuring that targets are met is a matter of regular monitoring.  Finding out what is happening and comparing it with targets  Re-planning also sometimes required
  • 4. Project control cycle Prof. Kanchana Devi 4
  • 5. Responsibility Prof. Kanchana Devi 5  The overall responsibility  Ensuring satisfactory progress on a project  It is the role of “Steering Committee”, project management board or Project Board.
  • 7. Reporting Prof. Kanchana Devi 7  Reporting may be  Oral/Written  Formal/Informal  Regular/Ad-hoc
  • 8. Assessing Progress Prof. Kanchana Devi 8  Information should be collected routinely  Information should be objective and tangible  Whether or not a particular report has been delivered  Sometimes the assessment depends on estimates of proportion of current activity that has been completed
  • 9. Setting Checkpoints Prof. Kanchana Devi 9  Necessary to set a series of check points in the initial activity plan.  Checkpoints may be:  Regular(Monthly)  Tied to specific events (production of report)
  • 10. Collecting the Data Prof. Kanchana Devi 10  Rule: Manager will breakdown the long activities into more controllable tasks of one or two weeks.  It is necessary to gather information about partially completed activities, forecasts of how much work is left to be completed.
  • 11. Example of partial completion reporting Prof. Kanchana Devi 11
  • 12. Risk Reporting Prof. Kanchana Devi 12  One way to overcome the objections of partial completion report is to avoid asking for completion dates. (instead ask for likelihood of meeting the target)  Called “Traffic Light Method”.
  • 13. Consists of following steps Prof. Kanchana Devi 13  Identify the key elements for assessment in a piece of work  Break these key elements into constituent element  Assess each of the second level element on the scale  Green for target,  Amber for ‘not on target but recoverable’  Red for ‘not on target and recoverable only with difficulty’  Review second level assessment to arrive at first level  Review first level assessment to produce an overall assessment
  • 15. Visualizing Progress Prof. Kanchana Devi 15  Gantt Chart  Slip Chart  Ball Chart  Timeline Chart
  • 16. Cost Monitoring Prof. Kanchana Devi 16  Expenditure monitoring is an important component of project control  A project might be on time but only because more money has been spent on activities than originally budgeted
  • 19. Earned Value Prof. Kanchana Devi 19  Analysis is based on assigning a ‘value’ to each task or work package based on expenditure forecasts.  The assigned value is the original budgeted cost for the item and is known as the ‘baseline budget’ or ‘budgeted cost of work scheduled’(BCWS)  The total value credited to a project at any point is known as the ‘earned value’ or ‘budgeted cost of the work performed’(BCWP)
  • 20. Actual Cost Prof. Kanchana Devi 20  By recording the “Earned Value”, the actual cost of each task can be collected as “Actual Cost” or ACWP-Actual Cost of Work Performed.  There are three types of Variance:  Schedule Variance(SV)  Time Variance(TV)  Cost Variance(CV)
  • 21. Schedule Variance(SV) Prof. Kanchana Devi 21  The Schedule Variance is measured in cost terms as EV-PV  It indicates the degree to which the value of the completed work differs from the planned work.
  • 22. Example: Prof. Kanchana Devi 22  A work with a PV of $40,000 should have been completed by now. In fact, some of that work has not been done so that the EV is only $35,000. Calculate SV.  SV=EV-PV  35000-40000= - 5000  A negative SV means the project is behind schedule
  • 23. Time Variance (TV) Prof. Kanchana Devi 23  Difference between the time when the achievement of the current earned value was planned to occur and the time now.  Eg:  The current EV should have been achieved in the early part of month 9 and as the time now is end of month 11, the TV is about -1.75 months from graph.
  • 24. Cost Variance (CV) Prof. Kanchana Devi 24  This is calculated as EV-AC.  It indicates the difference between the earned value or budgeted cost and the actual cost of the completed work.  Let Actual Cost for previous example is $ 55,000  CV=35000-55000  = -20000  A negative CV means that the project is over cost
  • 25. Prioritizing Monitoring Prof. Kanchana Devi 25  List of priorities  Critical Path Activities  Activities with no free float  Activities with less than a specified float  High Risk Activities  Activities using critical resources