4. The Disaster
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
5. The Disaster
8.8 Richter followed by
a tsunami
• 524 people killed
• 31 missing persons
• ± 12000 injured
• ± 800.000 displaced
High density population
zone
• ±12.800.000 people
• Six administrative regions
• Zone of 100 km x 630 km
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
7. Destruction and Sadness
370.000 houses
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
8. Destruction and Sadness
4538 schools
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
9. Destruction and Sadness
67 hospitals
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
10. Destruction and Sadness
30.000.000.000 US could
be the total cost of the
reconstruction
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
11. Destruction and Sadness
30.000.000.000 US could be the total cost of the
reconstruction
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
12. Destruction and Sadness
30.000.000.000 US could be the total cost of the
reconstruction
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
13. Destruction and Sadness
What to say…?
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
15. Needs and Solutions
Houses & Shelters
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
16. Needs and Solutions
Houses
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
17. Needs and Solutions
Houses
Source: http://www.minvu.cl
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
18. Needs and Solutions
Housing and Urban Development
• On February 27th, 2011, over 132,000 reconstruction
subsidies have been allocated (60% of the total
committed)
• Over 76,000 reconstruction and repair works are ongoing
or delivered to the families
• 80 thousand emergency houses installed, doubling the
initial goal of 40 thousand
• 4,350 families located in 106 emergency camps,
distributed over the affected area.
• 80% of the families in emergency camps with allocated
reconstruction housing subsidies
• 100% of demolition works initiated or finished for social
condominiums
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
19. Needs and Solutions
Schools
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
20. Needs and Solutions
Hospitals
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
21. Needs and Solutions
Infrastructure
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
23. Problems related to the Reconstruction
Overcrowding
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
24. Problems related to the Reconstruction
No water service nor sewage system
Permanent solutions take time to arrive
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
25. Problems related to the Reconstruction
Reconstruction « should » start with houses but…
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
27. Final remarks
Tragedies can not always be predicted but
prevention…
Coordinated actions/solutions could speed
up the reconstruction process.
Prefabrication in-situ or kits coming from
abroad can certainly reduce the housing
problems.
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
28. Final remarks
Loss of land triggers property problems.
Overcrowding appears as one the most
complicated items as it promotes
insalubrities.
Transitory solutions become unfortunately
permanent ones in some cases.
@ 2010 FPInnovations. All rights reserved. Copying and redistribution prohibited.
29. Final remarks
Thanks for
your
attention!