SlideShare a Scribd company logo
1 of 30
SERVICE REVAMP
Supply Chain overhaul
Lean Six Sigma Black Belt Sample Project
Sumit K Jha (MBA (Fin), LSSGB, PMP®)
Flow of the Presentation


Define



Measure



Analyze



Improve



Control
Define
Define Measure Analyze Improve Control

Business opportunity

Project cycle time schedule variance

x1- Purchase
schedule variance

x2-Warehouse
schedule variance

x3- Delivery
schedule variance

x4- Installation
schedule variance
Define Measure Analyze Improve Control

Team Charter
Project Title- Service Revamp
Business Case
XYZ executes multiple projects for its clients. Timely delivery of goods
according to the specification is paramount for the business success of
XYZ. Timely delivery is measured in terms of total project cycle time. The
project starts with getting an order from the client. The date of delivery is
decided. The project goes through four key stages- 1) Purchase, 2)
Delivery, 3) Warehouse and 4) Installation. The increase in the total
cycle time leads to liquidated damages, which can be severe in the
industry that XYZ operates in.
Goal statement
Metric
Current level
Goal / Target
Target date
Total project
-0.59
+ve
30th Jun 2013
schedule
variance mean
CPk
0.6
>1
30th Jun 2013

Phase
Define
Measure
Analyze
Improve
Control

Project plan
Start
End
st Feb 2012
1
29th Feb 22012
1st March
31st March
1st April
30th April
1st May
31st December
1st Jan
30th Jun

Opportunity Statement
Pain- Liquidated damages
Impact of pain in Rs. (or soft)- INR 5
crores per year

Sigma Level- 3.14
Project scope
Process under improvement: Project
execution

Starts with: Generation of purchase order
Ends with: Installation of equipments
Team Selection

Remarks
Done
Done
Done
Done
Done

Champion:: CEO
GB / BB: Mr. Sumit K Jha
Member: Plant Head
Member: Production manager
Define Measure Analyze Improve Control

Critical to Quality and Critical to Process Chart
Critical to Quality Critical customer
Customer
requirement
issues
Installation on
Timely installation Late delivery
time

Voice of
business
Project not
executed on
time

Business
issues
Liquidated
damages due
to late
installation

Voice of
customer
Goods not
delivered on
time
No customer
Installed
Installed
Customer
complaints
equipment should equipment not complaints
regarding
give pre-stated
working properly regarding
specification not performance
quality
met
increasing
Critical business
Critical for
requirement
processes
On-time installation Project cycle
time brought
within the
customer
specification

Remark
1. Voice of customer and voice of business to be prioritized to those which are related to project objective
2. Use VOB or VOC or both depending on the project objectives
Define Measure Analyze Improve Control

SIPOC DIAGRAM- Purchase
Starting point: Consignment inward
Supplier
SCM SPOC
SCM SPOC
SCM SPOC

SCM SPOC

End point: Delivery task assignment

Input
Process
Approval Data
After approval, SCM releases a Purchase order based on the
Entry in AX / XYZ
approval
MIS
Data Entry in AX / In case of other than back to back orders, get confirmation from
XYZ MIS
the distributor for releasing their internal PO to OEM
Data Entry in AX /
SCM determines date and address of delivery from the vendor
XYZ MIS
SCM updates date of delivery to all stakeholders through email
and on Google docs. Exact date of delivery is not in hands of
SCM and thereby SCM will update tentative date to all
Data Entry in AX /
stakeholders.
XYZ MIS
- Raw material required for production
- Peripherals (SCM to fix date of deliery with Vendor in such a
way that it is stayed for least amount of time at warehouse).
SCM also update delivery address.

Output

Customer

PO

Vendor

Actionable Data Entry
Vendor
in AX / XYZ MIS
Actionable Data Entry
Vendor
in AX / XYZ MIS

Actionable Data Entry
System
in AX / XYZ MIS

Data Entry in AX / At this stage, Zonal hubs are not in place and thereby cannot be Actionable Data Entry
System
XYZ MIS
made at hubs. Also, because of logistics concerns, delivery to in AX / XYZ MIS
customer's address directly is also difficult. Processes for above
two options can be made once SCM starts implementing it.
Based on tentative delivery date, Projects team to send an email
Data Entry in AX / to Commercial team for Performa Invoice preparation date.
Actionable Data Entry Commercial
Project SPOC
XYZ MIS
Performa Invoice should be available with Logisitics SPOC 7
in AX / XYZ MIS
team
days before DC date.
SCM SPOC
Define Measure Analyze Improve Control

SIPOC DIAGRAM- Warehousing
Starting point: Consignment inward
Supplier

Input

End point: Delivery task assignment

Process
Output
Customer
On receipt of material at Warehouse gate, Security checks for
Material /
Security
documents, condition of goods, and allow the goods to be taken Data Entry in AX / XYZ
Consignment
Transporter
personnel
inside after making entries in the Security material inward register MIS
inward
and stamping the documents.
In case of any damage or short receipt of goods, security SPOC
immediately informs warehouse supervisor / executive.
Security
Data Entry in
Data Entry in AX / XYZ Warehouse
Supervisor mentions the fact on acknowledgement and POD and
personnel AX / XYZ MIS
Supervisor
MIS
gives copies to transporter. However, security will inward all
material. SCM to do Purchase return on a later date.
Warehouse Data Entry in
Data Entry in AX / XYZ
SCM SPOC
Supervisor executive inturn informs SCM about the damage.
Supervisor AX / XYZ MIS
MIS
Data Entry in SCM SPOC initiates discussion with supplier and finance for
Actionable Data Entry Supplier /
SCM SPOC
Finance team
AX / XYZ MIS insurance claim depending upon price of the damaged item.
in AX / XYZ MIS
Warehouse SPOc completes barcode scanning activity and
Warehouse Data Entry in
Actionable Data Entry
NA
verifies the serial numbers mentioned on documents received with
SPOC
AX / XYZ MIS
in AX / XYZ MIS
material. Incase of any discrepancy, informs to SCM spoc.
Warehouse Data Entry in Warehouse executive generate goods receipt note after checking Actionable Data Entry
NA
Executive AX / XYZ MIS purchase order details.
in AX / XYZ MIS
Warehouse Data Entry in Warehouse executive sends all original documents to SCM at
Actionable Data Entry
SCM SPOC
Executive AX / XYZ MIS corporate office and keeps a copy of it for their record.
in AX / XYZ MIS
Warehouse Data Entry in Physical transfer of packed goods from Stores to Logistics
Actionable Data Entry Logistics
Executive AX / XYZ MIS Warehouse
SPOC
in AX / XYZ MIS
Data Entry in Status of SO will change to " Dispatched" and Delivery task is
Actionable Data Entry
System
System
AX / XYZ MIS automatically assigned to Logistics SPOC
in AX / XYZ MIS
Define Measure Analyze Improve Control

SIPOC DIAGRAM- Delivery
Starting point: Material Consignment
Delivery Challan (DC) courier
Supplier

Input
Material
Consignment DC

End point: End customer update

Process
Output
Customer
Warehouse SPOC will courier DC to the Zonal Data Entry in AX /
Project SPOC
Zonal head
Head of relevant region once DC is generated. XYZ MIS
Zonal head receives DC document. The Zonal
Head manually assigns the task to the
Actionable data entry
Zonal head
Engineer
in AX
Actionable data entry available Zonal engineer for Permit
Documentation
in AX
Engineer coordinates with consultant for
Actionable data entry
Engineer
Consultant
Actionable data entry Permit document preparation. Refer road
in AX
permit process for details.
in AX
Actionable data entry Zonal head / Engineer couriers the Permit to Actionable data entry
Zonal head
Courier
material delivery address
in AX
in AX
Material
Receipt of material at
Material delivered via Transporter
transporter location Transporter
Logistics SPOC Consignment
Material Receipt
Docket number of Delivery entered in AX &
Data Entry in AX /
Google docs
XYZ MIS
Logistics SPOC Note / POD / DC
System
Material
Transporter delivers Material to end customer Delivery of
Customer/Wareho
Consignment
location
Consignment
Transporter
use
Data Entry as per
Transporter updates the POD in website
MIS in Transporters'
POD
against LR no/Docket no
portal
Transporter
System
Tracking the booked On availability of POD date, SCM SPOC to
Data Entry in AX /
consignment no
update the AX.
XYZ MIS
SCM SPOC
AX
Define Measure Analyze Improve Control

SIPOC DIAGRAM- Installation
Starting point: Material Delivery alert
Supplier
Project SPOC

Input
Material Delivery
alert in AX
Actionable data
entry in AX

Project SPOC
Call center
Tele calling
SPOC
Zonal head /
Actionable data
Support Manager entry in AX
Service engineer Actionable data
entry in AX
Service engineer HIR Data Entry
Service engineer HIR Data Entry

End point: Delivery task assignment

Process
Output
Project Team SPOC to retrieve a dump of updated POD file from Actionable data entry in
AX
AX
Actionable data entry in
Project SPOC to forward the dump to Call centre SPOC
AX for Telecalling
Call centre SPOC telecall on POD sites to check for site
Appointment with
readiness
customer
The zonal Head assigns task to engineer

Engineer goes to Customer site for installation. If the material is
partially delivered, Zonal SPOC to take a call on whether engineer Customer visit
will visit the site for installation or will wait till full delivery is done.
Engineer installs
HIR Data Entry
Engineer carries an HIR form
HIR Data Entry
Customer Acceptance
Customer Signs on physical HIR form
of installed material

Customer

HIR Data Entry

Service engineer

Data Entry in AX / Engineer calls up Zonal head / SD (Service delivery SPOC) &
XYZ MIS
provides HIR number against SO number

Zonal head / SD
Data Entry in AX / Zonal head / SD (Service delivery SPOC) uploads the scan HIR
(Service delivery
XYZ MIS
on FTP
SPOC)
Call Centre
SPOC

Tele calling

Service SPOC

Telecall

Service SPOC

Feedback Rating

Service SPOC

Feedback Rating
AnalyXYZ

Customer visit

Call Centre SPOC pulls dump form the FTP and uploads in
system and flashes report

Customer
AX
Call center
SPOC
Customer
Service
engineer
Customer
Customer
HIR form
HIR form

Zonal head / SD
Data Entry in AX / XYZ
(Service
MIS
delivery SPOC)
Actionable data entry in FTP
AX for Telecalling
Data Entry in AX / XYZ
All stakeholders
MIS and feedback
/ AX
verification

Call center executive calls on the same / next day of HIR date /
Feedback
Issue resolved date
Call center SPOC to take CSAT on set of parameters (parameters
Feedback Verification
to be defined)
Call center SPOC to collate the score of every monthly and sends Decision Making /
it to all stakeholders.
Actions taken

Customer
Customer
Stakeholders
Define Measure Analyze Improve Control

Pugh Matrix
Sr.No
Criteria / Objectives
1 Total project cycle schedule variance

CTC
9

CTQ
9

CTK
3

CTG
9

Sum
30

2

Installation schedule variance

9

9

3

9

30

3

Delivery schedule variance

3

9

9

9

30

4

Warehouse schedule variance

9

3

9

9

30

5

Purchase schedule variance

9

9

9

9

36

6

Procurement schedule variance

9

1

9

9

28

7

Defect Density in production

9

3

9

3

24

8

No display defect %

9

9

9

3

30

9
10

Electro-static Density (ESD)
Torque

9
9

3
9

9
1

3
3

24
22

11

Procurement Quality

9

9

3

9

30

12

Skill Index (Manufacturing unit)

9

1

1

9

20

13

Collections cost planned vs. actual

9

1

3

3

16

14

Warehousing cost planned vs. actual

9

3

1

1

14

15

Delivery cost planned vs. actual

9

3

1

1

14

16

% units delivered vs. ordered

3

3

1

3

10

17

Installations cost planned vs. actual

9

1

3

3

16
Measure
Define

Measure Analyze Improve Control

Fishbone analysis (Cause and Effect Diagram)
Major Categories of causes of Problem Statement
Define

Measure Analyze Improve Control

Ishikawa Diagram (Cause and Effect Diagram)
Major Categories of causes of Problem Statement
Define

Measure Analyze Improve Control

Data Measurement Plan
Organizational Measure
process
s/UOM
Total Project
cycle time
schedule
variance

Ratio

X1

Purchase
schedule variance

Ratio

X2

Warehouse
schedule variance

Ratio

X3

Delivery schedule
variance

Ratio

Installation
schedule variance

Ratio

Y

X4

Operational definition

Planned number of days Actual number of days
/Planned number of days
Planned number of days Actual number of days
/Planned number of days
Planned number of days Actual number of days
/Planned number of days
Planned number of days Actual number of days
/Planned number of days
Planned number of days Actual number of days
/Planned number of days

Data source

Measurement Organizational / Controllable/
Frequency
Project Level Uncontrollable

As per Project Organization/
Plan
Project

Controllable

AX
AX

Monthly

Organization/Pro
Controllable
ject

AX

Monthly

Organization/Pro
Controllable
ject

AX

AX

As per Project Organization/Pro
Controllable
Plan
ject
As per Project Organization/Pro
Controllable
Plan
ject
Analyze
Define

Measure Analyze Improve Control

Validation of Xs
Regression analysis
Regression Analysis: TT versus Del, Warehouse, Installation, Purchase
The regression equation
is
TT = 0.0367 + 0.477 Del + 0.418 Warehouse + 0.0389
Installation
+ 0.0059 Purchase
Predictor
Coef SE Coef
T
P
Constant
0.036663 0.007122 5.15
0.000
Del
0.47732 0.02402 19.88 0.000
Warehouse
0.41843 0.02402 17.42
0.000
Installation -0.03893 0.01459 -2.67 0.008
Purchase
0.00587 0.01459 0.40 0.687
S = 0.0490296

R-Sq = 72.3%

R-Sq(adj) = 72.2%

Analysis of Variance
Source
DF
SS
MS
F
P
Regression
4 8.1775 2.0444 850.44 0.000
Residual Error 1302 3.1299 0.0024
Total
1306 11.3074
Source
DF Seq SS
Del
1 7.4316
Warehouse
1 0.7283
Installation 1 0.0172
Purchase
1 0.0004
Inference
Delivery ,Warehouse and Installation are most significant x's to the Y of Total project cycle time schedule variance
Define

Measure Analyze Improve Control

Hypothesis testing

Hypothesis testing / ANOVA
Purpose : To test the Hypothesis derived during the measure phase out of the data and CE diagrams

Null Hypothesis, H0 :

Alternate Hypothesis, H1 :

Q4 mean = Q8 mean

Q4 mean < Q8 mean
Improve
Define

Measure Analyze Improve Control

…1/2

List Possible Solutions
Sl
Area
No.

Potential Area for
improvement

Root Cause

Suggested Action Points

1

Installation

Delay in Installation of
Material at customer site

Manpower
Shortage

Pre planning of deployment of engineers for
installation on the Dispatch date ( Estimated time of
travel and task completion documented)

2

Installation

Delay in Installation of
Material at customer site
Delay in Installation of
Installation
Material at customer site

Manpower
Shortage
Manpower
Shortage

Delay in Installation of
Material at customer site

Manpower
Shortage

Delay in Installation of
Material at customer site
Delay in Installation of
Material at customer site
Delay in Installation of
Material at customer site
The average Timeline for
delivery of material (receipt of
material at Parwanoo
Warehouse) is significantly
higher than the target.
Delay in delivery of Material
to XYZ warehouse from
Suppliers/OEM’s
Delay in delivery of Material
to XYZ warehouse from
Suppliers/OEM’s

Manpower
Shortage
Manpower
Shortage
Manpower
Shortage

3
4

Installation

5

Installation

6

Installation

7

Installation

8

Warehouse

9

Warehouse

10

Warehouse

11

Warehouse

12
13

Delay of Material at
Warehouse
Delay in Material delivery
Warehouse
timeline ( Supplier )
Delay in Material delivery
Warehouse timeline ( Supplier )

Low
Easy to
Visible
Manpower
Capital
implement short term RPN
Utilization
utilization
and cascade benefits
9

9

9

9

36

9

9

9

9

36

1

9

3

3

16

1

9

3

3

16

1

9

3

3

16

1

9

3

3

16

1

9

3

3

16

Delay in permit Strict adherence Online permit documentation started
documentation for some states.(Karnataka , Andhra, WB, Orrisa ,MP)

9

3

9

9

30

Delay in permit Circulation of pending DC status to Zonal SPOC for
documentation permit documentation.

9

9

9

9

36

Delay in permit Permit documentation activity to start with XYZ PO
documentation generation

1

9

3

3

16

1

9

3

3

16

1

9

3

3

16

1

9

3

3

16

Delay in permit
documentation
Delay in permit
documentation

Product trainings conducted for engineers
Auto assignment of tasks to Engineer task force via AX
HHHT terminals to be carried by Engineer for
generation of online HIR with intimation to XYZ for
installation
Auto Material issue and replacement on request by
engineers with triggers and escalation
GPS tracking of engineers by the Zonal head for
optimum utilization of resources
Contract based manpower planning model to be
worked out for remote locations

Automation of Permit documentation task assignment
via AX
Triggers and escalations to be incorporated based on
the Task assignment module

Delay in permit Development of registered office premises al all
documentation strategic location to avoid permit documentation
Define

Measure Analyze Improve Control

…2/2

List Possible Solutions
Sl
No.

Area

14

Delivery

15

Delivery

16

Delivery

17

Delivery

18

Delivery

19

Delivery

Delay by
transporter

20

Delivery

Delay by
transporter

21

Delivery

22

Delivery

23

Delivery

24

Delivery

25

Delivery

Root Cause
Delay by
transporter
Delay by
transporter
Delay by
transporter
Delay by
transporter
Delay by
transporter

Delay by
transporter
Delay by
transporter
Delay by
tranporter
Delay by
transporter
Delay by
transporter

Suggested Action Points

Easy to
Low Capital Manpower
Visible short
implement and
RPN
utilization Utilization
term benefits
cascade

Proper Monitoring and tracking by phone and mail

9

9

9

9

36

Daily tracking of material from Transporters website

9

9

9

9

36

Flashing of transporters tracker to transporter to
transporter in order to deliver

9

9

9

9

36

MIS report from transporters to track material

9

9

9

9

36

9

9

9

9

36

1

9

9

1

20

1

9

9

1

20

1

9

9

1

20

1

9

9

1

20

1

9

9

1

20

1

9

9

1

20

1

9

9

1

20

Timely up-dation of POD by monitoring of
transporters website
Synchronization of XYZ AX with transporters
website to flash delivery reminders to transporter
and online updating of the POD
HHHT terminals to be carried by Transporters
SPOC for generation of online POD with intimation
to XYZ for installation
SLA based payment deduction form transporters
Payout
SLA's to be incorporated in the agreement for every
transporter
Deduction form transporters payout in case of
Damaged delivery
Strict SLA adherence in case of DOA and Wrong
delivery
GPS tracking of every transporter truck to be
informed on the status of all deliveries
Define

Measure Analyze Improve Control

Technology led efficiency and effectiveness
improvement


XYZ decided to streamline the activities with the help of ERP
solution. The process maps have been created to restructure the
activities and bring more efficiency within them



Technologies such as handheld devices to capture the information
from the vouchers has been created. It has the capability to
transmit the data that can be easily fed into the ERP



This has allowed for the information flow to be quick and precise.
Most of the delays that were happening earlier was due to late and
imprecise information flow
Control
Define

Measure Analyze Improve Control

Normality tests and control charts
Process capability of total project schedule variance
(Jul 2012 to Sep 2012)
Define

Measure Analyze Improve Control

Box plot
Boxplot of total project schedule
variance (Apr 2013 to June 2013)

Value plot (Q4- Apr 2012 to Jun
2012, Q8- Apr 2013 to Jun 2013)
Define

Measure Analyze Improve Control

Normality tests and control charts
Test carried out : Hypothesis testing [ One sample / t test / Paired etc., ] / One way ANOVA /
Two way ANOVA

Probability plot of project schedule
variance (Mar 2013 to Jun 2013)

IMR for project schedule variance
(Mar 2013 to Jun 2013)
Define

Measure Analyze Improve Control

Process Capability - Total Project Cycle Time
Process capability of total project schedule
variance (Mar 2013 to Jun 2013)

•
•
•

The Process Capability has
increased from 0.8 to 1.11 .
The process control chart is stable
with no outliers in Individual Chart .
Therefore there has been a
considerable improvement in the
process
Define

Measure Analyze Improve Control

Project Benefit
Initial estimate / COPQ: INR 168 lacs
Project Name

Service Revamp

Black Belt (Candidate)

Sumit K Jha

Financial Benefits

(Numbers in INR lacs)

1st Quarter

2nd Quarter

3rd Quarter

4th Quarter

Direct savings (Liquidated
damages)

5

15

30

40

90

Increased revenues

-

15

20

23

58

Reduced costs

-

2

5

7

15

Working capital changes

-

1

1.7

2.4

5.1

Investment/ loan changes

-

-

-

-

Total

5

33

56.7

72.4

Non-Financial Benefits

Improved csat score
Signature

Approvals

MBB Name

XYZ

Date
Champion Name

CEO

Date
Finance Name

CFO

Total

168.1
Define

Measure Analyze Improve Control

Conditions Worksheet
Initial estimate / COPQ: INR 168 lacs
Project Name
Black Belt (Candidate)
Financial Benefits

Calculation formulas
Approvals

Service Revamp
Sumit K Jha
1)
Reduction in liquidated damages, which is levied if the goods are not
delivered in time. The liquidated damages have come out to be less than INR
2)
10 lacs in the control phase.
3)
4)
1)
Sum of (Project delivered late* % liquidated damages clause in the project)
2)
Signature
MBB Name
XYZ
Date
Champion Name
CEO
Finance Name
CFO
Thank You

More Related Content

What's hot

Six sigma case study-a good approach with example
Six sigma case study-a good approach with exampleSix sigma case study-a good approach with example
Six sigma case study-a good approach with examplebhanutomar
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSMSedhuSiddarth
 
six sigma DMAIC approach for reducing quality defects of camshaft binding pro...
six sigma DMAIC approach for reducing quality defects of camshaft binding pro...six sigma DMAIC approach for reducing quality defects of camshaft binding pro...
six sigma DMAIC approach for reducing quality defects of camshaft binding pro...Niranjana B
 
Green Belt Project Storyboard Template Example
Green Belt Project Storyboard Template Example Green Belt Project Storyboard Template Example
Green Belt Project Storyboard Template Example GoLeanSixSigma.com
 
Lean six sigma and process excellence ppt
Lean six sigma and process excellence pptLean six sigma and process excellence ppt
Lean six sigma and process excellence pptAnexas Consultancy
 
WEBINAR: Introduction to DMAIC
WEBINAR: Introduction to DMAICWEBINAR: Introduction to DMAIC
WEBINAR: Introduction to DMAICGoLeanSixSigma.com
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakharMohammad IFTAKHAR
 
iNTRODUCTION TO LEAN
iNTRODUCTION TO LEANiNTRODUCTION TO LEAN
iNTRODUCTION TO LEANKiril Nikolov
 
Six sigma awareness
Six sigma awarenessSix sigma awareness
Six sigma awarenesssawate
 
Lean Six Sigma 101
Lean Six Sigma 101Lean Six Sigma 101
Lean Six Sigma 101shailsood
 
Principles of Kanban - November 2016
Principles of Kanban - November 2016Principles of Kanban - November 2016
Principles of Kanban - November 2016W3 Group Canada Inc.
 
Kaizen Events Blitz & Lean Projects
Kaizen Events   Blitz  & Lean ProjectsKaizen Events   Blitz  & Lean Projects
Kaizen Events Blitz & Lean ProjectsAnand Subramaniam
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS Julian Kalac P.Eng
 

What's hot (20)

Six sigma case study-a good approach with example
Six sigma case study-a good approach with exampleSix sigma case study-a good approach with example
Six sigma case study-a good approach with example
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
 
six sigma DMAIC approach for reducing quality defects of camshaft binding pro...
six sigma DMAIC approach for reducing quality defects of camshaft binding pro...six sigma DMAIC approach for reducing quality defects of camshaft binding pro...
six sigma DMAIC approach for reducing quality defects of camshaft binding pro...
 
Dmaic
DmaicDmaic
Dmaic
 
Green Belt Project Storyboard Template Example
Green Belt Project Storyboard Template Example Green Belt Project Storyboard Template Example
Green Belt Project Storyboard Template Example
 
Lean six sigma and process excellence ppt
Lean six sigma and process excellence pptLean six sigma and process excellence ppt
Lean six sigma and process excellence ppt
 
Lean Six Sigma Green Belt roadmap poster
Lean Six Sigma Green Belt roadmap posterLean Six Sigma Green Belt roadmap poster
Lean Six Sigma Green Belt roadmap poster
 
Lean 6sigma and DMAIC
Lean 6sigma and DMAICLean 6sigma and DMAIC
Lean 6sigma and DMAIC
 
WEBINAR: Introduction to DMAIC
WEBINAR: Introduction to DMAICWEBINAR: Introduction to DMAIC
WEBINAR: Introduction to DMAIC
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
 
DMAIC Components
DMAIC ComponentsDMAIC Components
DMAIC Components
 
iNTRODUCTION TO LEAN
iNTRODUCTION TO LEANiNTRODUCTION TO LEAN
iNTRODUCTION TO LEAN
 
Six sigma awareness
Six sigma awarenessSix sigma awareness
Six sigma awareness
 
Lean Six Sigma 101
Lean Six Sigma 101Lean Six Sigma 101
Lean Six Sigma 101
 
Six Sigma Sample Project
Six Sigma Sample ProjectSix Sigma Sample Project
Six Sigma Sample Project
 
Principles of Kanban - November 2016
Principles of Kanban - November 2016Principles of Kanban - November 2016
Principles of Kanban - November 2016
 
Kaizen Events Blitz & Lean Projects
Kaizen Events   Blitz  & Lean ProjectsKaizen Events   Blitz  & Lean Projects
Kaizen Events Blitz & Lean Projects
 
Six sigma green belt project roadmap in 10 deliverables 2013 07
Six sigma green belt project roadmap in 10 deliverables 2013 07Six sigma green belt project roadmap in 10 deliverables 2013 07
Six sigma green belt project roadmap in 10 deliverables 2013 07
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
 
PDCA
PDCAPDCA
PDCA
 

Viewers also liked

Define phase lean six sigma tollgate template
Define phase   lean six sigma tollgate templateDefine phase   lean six sigma tollgate template
Define phase lean six sigma tollgate templateSteven Bonacorsi
 
Lean Manufacturing And Six Sigma
Lean Manufacturing And Six SigmaLean Manufacturing And Six Sigma
Lean Manufacturing And Six SigmakumarVerma
 
Financial analysis towards lean & six sigma
Financial analysis towards lean & six sigmaFinancial analysis towards lean & six sigma
Financial analysis towards lean & six sigmaMichael R. Büchler
 
Process excellence being efficient & effective
Process excellence being efficient & effectiveProcess excellence being efficient & effective
Process excellence being efficient & effectiveSumit K Jha
 
Flipkart company analysis and strategic & tactical recommendations
Flipkart  company analysis and strategic & tactical recommendationsFlipkart  company analysis and strategic & tactical recommendations
Flipkart company analysis and strategic & tactical recommendationsSumit K Jha
 
Smart grids business case
Smart grids  business caseSmart grids  business case
Smart grids business caseSumit K Jha
 
Resume bab 9
Resume bab 9Resume bab 9
Resume bab 9Arga1693
 
Creating Unforgettable Ppt Presentations By Ning De Guzman
Creating Unforgettable Ppt Presentations By Ning De GuzmanCreating Unforgettable Ppt Presentations By Ning De Guzman
Creating Unforgettable Ppt Presentations By Ning De GuzmanNing de Guzman
 
IC Management - Measuring the Immeasurable
IC Management - Measuring the ImmeasurableIC Management - Measuring the Immeasurable
IC Management - Measuring the ImmeasurableJoris Claeys
 
Change Management for Lean Six Sigma based Transformation
Change Management for Lean Six Sigma based TransformationChange Management for Lean Six Sigma based Transformation
Change Management for Lean Six Sigma based TransformationAjay Koul
 
Six sigma-and-supply-chain
Six sigma-and-supply-chainSix sigma-and-supply-chain
Six sigma-and-supply-chainStephen Depoe
 
Kiker.ronald
Kiker.ronaldKiker.ronald
Kiker.ronaldNASAPMC
 
Build a Lean Six Sigma Process for Inventory Management in Hospitals
Build a Lean Six Sigma Process for Inventory Management in HospitalsBuild a Lean Six Sigma Process for Inventory Management in Hospitals
Build a Lean Six Sigma Process for Inventory Management in HospitalsJump Technologies, Inc.
 

Viewers also liked (18)

Define phase lean six sigma tollgate template
Define phase   lean six sigma tollgate templateDefine phase   lean six sigma tollgate template
Define phase lean six sigma tollgate template
 
Lean Manufacturing And Six Sigma
Lean Manufacturing And Six SigmaLean Manufacturing And Six Sigma
Lean Manufacturing And Six Sigma
 
Financial analysis towards lean & six sigma
Financial analysis towards lean & six sigmaFinancial analysis towards lean & six sigma
Financial analysis towards lean & six sigma
 
Process excellence being efficient & effective
Process excellence being efficient & effectiveProcess excellence being efficient & effective
Process excellence being efficient & effective
 
Pharmex Six Sigma Project
Pharmex Six Sigma ProjectPharmex Six Sigma Project
Pharmex Six Sigma Project
 
Flipkart company analysis and strategic & tactical recommendations
Flipkart  company analysis and strategic & tactical recommendationsFlipkart  company analysis and strategic & tactical recommendations
Flipkart company analysis and strategic & tactical recommendations
 
Smart grids business case
Smart grids  business caseSmart grids  business case
Smart grids business case
 
Resume bab 9
Resume bab 9Resume bab 9
Resume bab 9
 
Creating Unforgettable Ppt Presentations By Ning De Guzman
Creating Unforgettable Ppt Presentations By Ning De GuzmanCreating Unforgettable Ppt Presentations By Ning De Guzman
Creating Unforgettable Ppt Presentations By Ning De Guzman
 
Lean Six Sigma
Lean Six SigmaLean Six Sigma
Lean Six Sigma
 
Lean vs six sigma -jk
Lean vs six sigma  -jkLean vs six sigma  -jk
Lean vs six sigma -jk
 
IC Management - Measuring the Immeasurable
IC Management - Measuring the ImmeasurableIC Management - Measuring the Immeasurable
IC Management - Measuring the Immeasurable
 
SCM PROJECT
SCM PROJECTSCM PROJECT
SCM PROJECT
 
Change Management for Lean Six Sigma based Transformation
Change Management for Lean Six Sigma based TransformationChange Management for Lean Six Sigma based Transformation
Change Management for Lean Six Sigma based Transformation
 
Six sigma-and-supply-chain
Six sigma-and-supply-chainSix sigma-and-supply-chain
Six sigma-and-supply-chain
 
Kiker.ronald
Kiker.ronaldKiker.ronald
Kiker.ronald
 
Build a Lean Six Sigma Process for Inventory Management in Hospitals
Build a Lean Six Sigma Process for Inventory Management in HospitalsBuild a Lean Six Sigma Process for Inventory Management in Hospitals
Build a Lean Six Sigma Process for Inventory Management in Hospitals
 
The Face of Supply Chain in 2025
The Face of Supply Chain in 2025The Face of Supply Chain in 2025
The Face of Supply Chain in 2025
 

Similar to Service revamp lean six sigma black belt project

Sean Solid RFID In Construction V1
Sean Solid   RFID In Construction V1Sean Solid   RFID In Construction V1
Sean Solid RFID In Construction V1TheHolloway
 
COLLABORATE 18 Presentation: Implementing WMS for 30+ Warehouses in 12 Months
COLLABORATE 18 Presentation: Implementing WMS for 30+ Warehouses in 12 MonthsCOLLABORATE 18 Presentation: Implementing WMS for 30+ Warehouses in 12 Months
COLLABORATE 18 Presentation: Implementing WMS for 30+ Warehouses in 12 MonthsJade Global
 
Base Hospitality Pres 08
Base Hospitality Pres   08Base Hospitality Pres   08
Base Hospitality Pres 08Petewebb
 
Initiative Based Technology Consulting Case Studies
Initiative Based Technology Consulting Case StudiesInitiative Based Technology Consulting Case Studies
Initiative Based Technology Consulting Case Studieschanderdw
 
O'Reilly SA: Complex event flows in distributed systems
O'Reilly SA: Complex event flows in distributed systemsO'Reilly SA: Complex event flows in distributed systems
O'Reilly SA: Complex event flows in distributed systemsBernd Ruecker
 
New Charts Architectures (2)
New Charts Architectures (2)New Charts Architectures (2)
New Charts Architectures (2)guestf73e68
 
SAP LES WM Multi Step Production Picking
SAP LES WM Multi Step Production PickingSAP LES WM Multi Step Production Picking
SAP LES WM Multi Step Production PickingVijay Pisipaty
 
Concur integration with PI solution pack
Concur integration with PI solution pack Concur integration with PI solution pack
Concur integration with PI solution pack SatyaSuman Lakkimsetty
 
Process Flow Tech
Process Flow TechProcess Flow Tech
Process Flow TechFloydBement
 
P2 p enabled through blockchain sanjay badhai and rahul pasrija-cwin18_india
P2 p enabled through blockchain sanjay badhai and rahul pasrija-cwin18_indiaP2 p enabled through blockchain sanjay badhai and rahul pasrija-cwin18_india
P2 p enabled through blockchain sanjay badhai and rahul pasrija-cwin18_indiaCapgemini
 
Npo end to end validation
Npo end to end validationNpo end to end validation
Npo end to end validationPeter Macdonald
 
Amanda Spence Resume_US Gulfcoast Analytics
Amanda Spence Resume_US Gulfcoast AnalyticsAmanda Spence Resume_US Gulfcoast Analytics
Amanda Spence Resume_US Gulfcoast AnalyticsAmanda Alexander Spence
 
Project procurement Management final report.docx
Project procurement Management final report.docxProject procurement Management final report.docx
Project procurement Management final report.docxZiyad Zaidi
 
Previous WorksLink systems
Previous WorksLink systemsPrevious WorksLink systems
Previous WorksLink systemsAndrew McGrath
 
BCMS - BPM Presentation
BCMS - BPM PresentationBCMS - BPM Presentation
BCMS - BPM PresentationAdrien LABORIE
 
Resume Alok kumar
Resume Alok kumarResume Alok kumar
Resume Alok kumarAlok kumar
 

Similar to Service revamp lean six sigma black belt project (20)

Sean Solid RFID In Construction V1
Sean Solid   RFID In Construction V1Sean Solid   RFID In Construction V1
Sean Solid RFID In Construction V1
 
COLLABORATE 18 Presentation: Implementing WMS for 30+ Warehouses in 12 Months
COLLABORATE 18 Presentation: Implementing WMS for 30+ Warehouses in 12 MonthsCOLLABORATE 18 Presentation: Implementing WMS for 30+ Warehouses in 12 Months
COLLABORATE 18 Presentation: Implementing WMS for 30+ Warehouses in 12 Months
 
Base Hospitality Pres 08
Base Hospitality Pres   08Base Hospitality Pres   08
Base Hospitality Pres 08
 
Sharon Kutzner Resume
Sharon Kutzner ResumeSharon Kutzner Resume
Sharon Kutzner Resume
 
Initiative Based Technology Consulting Case Studies
Initiative Based Technology Consulting Case StudiesInitiative Based Technology Consulting Case Studies
Initiative Based Technology Consulting Case Studies
 
O'Reilly SA: Complex event flows in distributed systems
O'Reilly SA: Complex event flows in distributed systemsO'Reilly SA: Complex event flows in distributed systems
O'Reilly SA: Complex event flows in distributed systems
 
Veerapradeep_Apps_profile
Veerapradeep_Apps_profileVeerapradeep_Apps_profile
Veerapradeep_Apps_profile
 
New Charts Architectures (2)
New Charts Architectures (2)New Charts Architectures (2)
New Charts Architectures (2)
 
SAP LES WM Multi Step Production Picking
SAP LES WM Multi Step Production PickingSAP LES WM Multi Step Production Picking
SAP LES WM Multi Step Production Picking
 
Concur integration with PI solution pack
Concur integration with PI solution pack Concur integration with PI solution pack
Concur integration with PI solution pack
 
Process Flow Tech
Process Flow TechProcess Flow Tech
Process Flow Tech
 
Falcon grocery model 2014
Falcon grocery model 2014Falcon grocery model 2014
Falcon grocery model 2014
 
P2 p enabled through blockchain sanjay badhai and rahul pasrija-cwin18_india
P2 p enabled through blockchain sanjay badhai and rahul pasrija-cwin18_indiaP2 p enabled through blockchain sanjay badhai and rahul pasrija-cwin18_india
P2 p enabled through blockchain sanjay badhai and rahul pasrija-cwin18_india
 
Npo end to end validation
Npo end to end validationNpo end to end validation
Npo end to end validation
 
Amanda Spence Resume_US Gulfcoast Analytics
Amanda Spence Resume_US Gulfcoast AnalyticsAmanda Spence Resume_US Gulfcoast Analytics
Amanda Spence Resume_US Gulfcoast Analytics
 
Project procurement Management final report.docx
Project procurement Management final report.docxProject procurement Management final report.docx
Project procurement Management final report.docx
 
Previous WorksLink systems
Previous WorksLink systemsPrevious WorksLink systems
Previous WorksLink systems
 
Resume_Indrani Banerjee
Resume_Indrani BanerjeeResume_Indrani Banerjee
Resume_Indrani Banerjee
 
BCMS - BPM Presentation
BCMS - BPM PresentationBCMS - BPM Presentation
BCMS - BPM Presentation
 
Resume Alok kumar
Resume Alok kumarResume Alok kumar
Resume Alok kumar
 

Recently uploaded

Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfpanagenda
 
Connecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfConnecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfNeo4j
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxLoriGlavin3
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Alkin Tezuysal
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demoHarshalMandlekar2
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsRavi Sanghani
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersNicole Novielli
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...Wes McKinney
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...panagenda
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsNathaniel Shimoni
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
Assure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyesAssure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyesThousandEyes
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPathCommunity
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Strongerpanagenda
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 

Recently uploaded (20)

Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
 
Connecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfConnecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdf
 
The State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptxThe State of Passkeys with FIDO Alliance.pptx
The State of Passkeys with FIDO Alliance.pptx
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demo
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and Insights
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software Developers
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directions
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
Assure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyesAssure Ecommerce and Retail Operations Uptime with ThousandEyes
Assure Ecommerce and Retail Operations Uptime with ThousandEyes
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to Hero
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 

Service revamp lean six sigma black belt project

  • 1. SERVICE REVAMP Supply Chain overhaul Lean Six Sigma Black Belt Sample Project Sumit K Jha (MBA (Fin), LSSGB, PMP®)
  • 2. Flow of the Presentation  Define  Measure  Analyze  Improve  Control
  • 4. Define Measure Analyze Improve Control Business opportunity Project cycle time schedule variance x1- Purchase schedule variance x2-Warehouse schedule variance x3- Delivery schedule variance x4- Installation schedule variance
  • 5. Define Measure Analyze Improve Control Team Charter Project Title- Service Revamp Business Case XYZ executes multiple projects for its clients. Timely delivery of goods according to the specification is paramount for the business success of XYZ. Timely delivery is measured in terms of total project cycle time. The project starts with getting an order from the client. The date of delivery is decided. The project goes through four key stages- 1) Purchase, 2) Delivery, 3) Warehouse and 4) Installation. The increase in the total cycle time leads to liquidated damages, which can be severe in the industry that XYZ operates in. Goal statement Metric Current level Goal / Target Target date Total project -0.59 +ve 30th Jun 2013 schedule variance mean CPk 0.6 >1 30th Jun 2013 Phase Define Measure Analyze Improve Control Project plan Start End st Feb 2012 1 29th Feb 22012 1st March 31st March 1st April 30th April 1st May 31st December 1st Jan 30th Jun Opportunity Statement Pain- Liquidated damages Impact of pain in Rs. (or soft)- INR 5 crores per year Sigma Level- 3.14 Project scope Process under improvement: Project execution Starts with: Generation of purchase order Ends with: Installation of equipments Team Selection Remarks Done Done Done Done Done Champion:: CEO GB / BB: Mr. Sumit K Jha Member: Plant Head Member: Production manager
  • 6. Define Measure Analyze Improve Control Critical to Quality and Critical to Process Chart Critical to Quality Critical customer Customer requirement issues Installation on Timely installation Late delivery time Voice of business Project not executed on time Business issues Liquidated damages due to late installation Voice of customer Goods not delivered on time No customer Installed Installed Customer complaints equipment should equipment not complaints regarding give pre-stated working properly regarding specification not performance quality met increasing Critical business Critical for requirement processes On-time installation Project cycle time brought within the customer specification Remark 1. Voice of customer and voice of business to be prioritized to those which are related to project objective 2. Use VOB or VOC or both depending on the project objectives
  • 7. Define Measure Analyze Improve Control SIPOC DIAGRAM- Purchase Starting point: Consignment inward Supplier SCM SPOC SCM SPOC SCM SPOC SCM SPOC End point: Delivery task assignment Input Process Approval Data After approval, SCM releases a Purchase order based on the Entry in AX / XYZ approval MIS Data Entry in AX / In case of other than back to back orders, get confirmation from XYZ MIS the distributor for releasing their internal PO to OEM Data Entry in AX / SCM determines date and address of delivery from the vendor XYZ MIS SCM updates date of delivery to all stakeholders through email and on Google docs. Exact date of delivery is not in hands of SCM and thereby SCM will update tentative date to all Data Entry in AX / stakeholders. XYZ MIS - Raw material required for production - Peripherals (SCM to fix date of deliery with Vendor in such a way that it is stayed for least amount of time at warehouse). SCM also update delivery address. Output Customer PO Vendor Actionable Data Entry Vendor in AX / XYZ MIS Actionable Data Entry Vendor in AX / XYZ MIS Actionable Data Entry System in AX / XYZ MIS Data Entry in AX / At this stage, Zonal hubs are not in place and thereby cannot be Actionable Data Entry System XYZ MIS made at hubs. Also, because of logistics concerns, delivery to in AX / XYZ MIS customer's address directly is also difficult. Processes for above two options can be made once SCM starts implementing it. Based on tentative delivery date, Projects team to send an email Data Entry in AX / to Commercial team for Performa Invoice preparation date. Actionable Data Entry Commercial Project SPOC XYZ MIS Performa Invoice should be available with Logisitics SPOC 7 in AX / XYZ MIS team days before DC date. SCM SPOC
  • 8. Define Measure Analyze Improve Control SIPOC DIAGRAM- Warehousing Starting point: Consignment inward Supplier Input End point: Delivery task assignment Process Output Customer On receipt of material at Warehouse gate, Security checks for Material / Security documents, condition of goods, and allow the goods to be taken Data Entry in AX / XYZ Consignment Transporter personnel inside after making entries in the Security material inward register MIS inward and stamping the documents. In case of any damage or short receipt of goods, security SPOC immediately informs warehouse supervisor / executive. Security Data Entry in Data Entry in AX / XYZ Warehouse Supervisor mentions the fact on acknowledgement and POD and personnel AX / XYZ MIS Supervisor MIS gives copies to transporter. However, security will inward all material. SCM to do Purchase return on a later date. Warehouse Data Entry in Data Entry in AX / XYZ SCM SPOC Supervisor executive inturn informs SCM about the damage. Supervisor AX / XYZ MIS MIS Data Entry in SCM SPOC initiates discussion with supplier and finance for Actionable Data Entry Supplier / SCM SPOC Finance team AX / XYZ MIS insurance claim depending upon price of the damaged item. in AX / XYZ MIS Warehouse SPOc completes barcode scanning activity and Warehouse Data Entry in Actionable Data Entry NA verifies the serial numbers mentioned on documents received with SPOC AX / XYZ MIS in AX / XYZ MIS material. Incase of any discrepancy, informs to SCM spoc. Warehouse Data Entry in Warehouse executive generate goods receipt note after checking Actionable Data Entry NA Executive AX / XYZ MIS purchase order details. in AX / XYZ MIS Warehouse Data Entry in Warehouse executive sends all original documents to SCM at Actionable Data Entry SCM SPOC Executive AX / XYZ MIS corporate office and keeps a copy of it for their record. in AX / XYZ MIS Warehouse Data Entry in Physical transfer of packed goods from Stores to Logistics Actionable Data Entry Logistics Executive AX / XYZ MIS Warehouse SPOC in AX / XYZ MIS Data Entry in Status of SO will change to " Dispatched" and Delivery task is Actionable Data Entry System System AX / XYZ MIS automatically assigned to Logistics SPOC in AX / XYZ MIS
  • 9. Define Measure Analyze Improve Control SIPOC DIAGRAM- Delivery Starting point: Material Consignment Delivery Challan (DC) courier Supplier Input Material Consignment DC End point: End customer update Process Output Customer Warehouse SPOC will courier DC to the Zonal Data Entry in AX / Project SPOC Zonal head Head of relevant region once DC is generated. XYZ MIS Zonal head receives DC document. The Zonal Head manually assigns the task to the Actionable data entry Zonal head Engineer in AX Actionable data entry available Zonal engineer for Permit Documentation in AX Engineer coordinates with consultant for Actionable data entry Engineer Consultant Actionable data entry Permit document preparation. Refer road in AX permit process for details. in AX Actionable data entry Zonal head / Engineer couriers the Permit to Actionable data entry Zonal head Courier material delivery address in AX in AX Material Receipt of material at Material delivered via Transporter transporter location Transporter Logistics SPOC Consignment Material Receipt Docket number of Delivery entered in AX & Data Entry in AX / Google docs XYZ MIS Logistics SPOC Note / POD / DC System Material Transporter delivers Material to end customer Delivery of Customer/Wareho Consignment location Consignment Transporter use Data Entry as per Transporter updates the POD in website MIS in Transporters' POD against LR no/Docket no portal Transporter System Tracking the booked On availability of POD date, SCM SPOC to Data Entry in AX / consignment no update the AX. XYZ MIS SCM SPOC AX
  • 10. Define Measure Analyze Improve Control SIPOC DIAGRAM- Installation Starting point: Material Delivery alert Supplier Project SPOC Input Material Delivery alert in AX Actionable data entry in AX Project SPOC Call center Tele calling SPOC Zonal head / Actionable data Support Manager entry in AX Service engineer Actionable data entry in AX Service engineer HIR Data Entry Service engineer HIR Data Entry End point: Delivery task assignment Process Output Project Team SPOC to retrieve a dump of updated POD file from Actionable data entry in AX AX Actionable data entry in Project SPOC to forward the dump to Call centre SPOC AX for Telecalling Call centre SPOC telecall on POD sites to check for site Appointment with readiness customer The zonal Head assigns task to engineer Engineer goes to Customer site for installation. If the material is partially delivered, Zonal SPOC to take a call on whether engineer Customer visit will visit the site for installation or will wait till full delivery is done. Engineer installs HIR Data Entry Engineer carries an HIR form HIR Data Entry Customer Acceptance Customer Signs on physical HIR form of installed material Customer HIR Data Entry Service engineer Data Entry in AX / Engineer calls up Zonal head / SD (Service delivery SPOC) & XYZ MIS provides HIR number against SO number Zonal head / SD Data Entry in AX / Zonal head / SD (Service delivery SPOC) uploads the scan HIR (Service delivery XYZ MIS on FTP SPOC) Call Centre SPOC Tele calling Service SPOC Telecall Service SPOC Feedback Rating Service SPOC Feedback Rating AnalyXYZ Customer visit Call Centre SPOC pulls dump form the FTP and uploads in system and flashes report Customer AX Call center SPOC Customer Service engineer Customer Customer HIR form HIR form Zonal head / SD Data Entry in AX / XYZ (Service MIS delivery SPOC) Actionable data entry in FTP AX for Telecalling Data Entry in AX / XYZ All stakeholders MIS and feedback / AX verification Call center executive calls on the same / next day of HIR date / Feedback Issue resolved date Call center SPOC to take CSAT on set of parameters (parameters Feedback Verification to be defined) Call center SPOC to collate the score of every monthly and sends Decision Making / it to all stakeholders. Actions taken Customer Customer Stakeholders
  • 11. Define Measure Analyze Improve Control Pugh Matrix Sr.No Criteria / Objectives 1 Total project cycle schedule variance CTC 9 CTQ 9 CTK 3 CTG 9 Sum 30 2 Installation schedule variance 9 9 3 9 30 3 Delivery schedule variance 3 9 9 9 30 4 Warehouse schedule variance 9 3 9 9 30 5 Purchase schedule variance 9 9 9 9 36 6 Procurement schedule variance 9 1 9 9 28 7 Defect Density in production 9 3 9 3 24 8 No display defect % 9 9 9 3 30 9 10 Electro-static Density (ESD) Torque 9 9 3 9 9 1 3 3 24 22 11 Procurement Quality 9 9 3 9 30 12 Skill Index (Manufacturing unit) 9 1 1 9 20 13 Collections cost planned vs. actual 9 1 3 3 16 14 Warehousing cost planned vs. actual 9 3 1 1 14 15 Delivery cost planned vs. actual 9 3 1 1 14 16 % units delivered vs. ordered 3 3 1 3 10 17 Installations cost planned vs. actual 9 1 3 3 16
  • 13. Define Measure Analyze Improve Control Fishbone analysis (Cause and Effect Diagram) Major Categories of causes of Problem Statement
  • 14. Define Measure Analyze Improve Control Ishikawa Diagram (Cause and Effect Diagram) Major Categories of causes of Problem Statement
  • 15. Define Measure Analyze Improve Control Data Measurement Plan Organizational Measure process s/UOM Total Project cycle time schedule variance Ratio X1 Purchase schedule variance Ratio X2 Warehouse schedule variance Ratio X3 Delivery schedule variance Ratio Installation schedule variance Ratio Y X4 Operational definition Planned number of days Actual number of days /Planned number of days Planned number of days Actual number of days /Planned number of days Planned number of days Actual number of days /Planned number of days Planned number of days Actual number of days /Planned number of days Planned number of days Actual number of days /Planned number of days Data source Measurement Organizational / Controllable/ Frequency Project Level Uncontrollable As per Project Organization/ Plan Project Controllable AX AX Monthly Organization/Pro Controllable ject AX Monthly Organization/Pro Controllable ject AX AX As per Project Organization/Pro Controllable Plan ject As per Project Organization/Pro Controllable Plan ject
  • 17. Define Measure Analyze Improve Control Validation of Xs Regression analysis Regression Analysis: TT versus Del, Warehouse, Installation, Purchase The regression equation is TT = 0.0367 + 0.477 Del + 0.418 Warehouse + 0.0389 Installation + 0.0059 Purchase Predictor Coef SE Coef T P Constant 0.036663 0.007122 5.15 0.000 Del 0.47732 0.02402 19.88 0.000 Warehouse 0.41843 0.02402 17.42 0.000 Installation -0.03893 0.01459 -2.67 0.008 Purchase 0.00587 0.01459 0.40 0.687 S = 0.0490296 R-Sq = 72.3% R-Sq(adj) = 72.2% Analysis of Variance Source DF SS MS F P Regression 4 8.1775 2.0444 850.44 0.000 Residual Error 1302 3.1299 0.0024 Total 1306 11.3074 Source DF Seq SS Del 1 7.4316 Warehouse 1 0.7283 Installation 1 0.0172 Purchase 1 0.0004 Inference Delivery ,Warehouse and Installation are most significant x's to the Y of Total project cycle time schedule variance
  • 18. Define Measure Analyze Improve Control Hypothesis testing Hypothesis testing / ANOVA Purpose : To test the Hypothesis derived during the measure phase out of the data and CE diagrams Null Hypothesis, H0 : Alternate Hypothesis, H1 : Q4 mean = Q8 mean Q4 mean < Q8 mean
  • 20. Define Measure Analyze Improve Control …1/2 List Possible Solutions Sl Area No. Potential Area for improvement Root Cause Suggested Action Points 1 Installation Delay in Installation of Material at customer site Manpower Shortage Pre planning of deployment of engineers for installation on the Dispatch date ( Estimated time of travel and task completion documented) 2 Installation Delay in Installation of Material at customer site Delay in Installation of Installation Material at customer site Manpower Shortage Manpower Shortage Delay in Installation of Material at customer site Manpower Shortage Delay in Installation of Material at customer site Delay in Installation of Material at customer site Delay in Installation of Material at customer site The average Timeline for delivery of material (receipt of material at Parwanoo Warehouse) is significantly higher than the target. Delay in delivery of Material to XYZ warehouse from Suppliers/OEM’s Delay in delivery of Material to XYZ warehouse from Suppliers/OEM’s Manpower Shortage Manpower Shortage Manpower Shortage 3 4 Installation 5 Installation 6 Installation 7 Installation 8 Warehouse 9 Warehouse 10 Warehouse 11 Warehouse 12 13 Delay of Material at Warehouse Delay in Material delivery Warehouse timeline ( Supplier ) Delay in Material delivery Warehouse timeline ( Supplier ) Low Easy to Visible Manpower Capital implement short term RPN Utilization utilization and cascade benefits 9 9 9 9 36 9 9 9 9 36 1 9 3 3 16 1 9 3 3 16 1 9 3 3 16 1 9 3 3 16 1 9 3 3 16 Delay in permit Strict adherence Online permit documentation started documentation for some states.(Karnataka , Andhra, WB, Orrisa ,MP) 9 3 9 9 30 Delay in permit Circulation of pending DC status to Zonal SPOC for documentation permit documentation. 9 9 9 9 36 Delay in permit Permit documentation activity to start with XYZ PO documentation generation 1 9 3 3 16 1 9 3 3 16 1 9 3 3 16 1 9 3 3 16 Delay in permit documentation Delay in permit documentation Product trainings conducted for engineers Auto assignment of tasks to Engineer task force via AX HHHT terminals to be carried by Engineer for generation of online HIR with intimation to XYZ for installation Auto Material issue and replacement on request by engineers with triggers and escalation GPS tracking of engineers by the Zonal head for optimum utilization of resources Contract based manpower planning model to be worked out for remote locations Automation of Permit documentation task assignment via AX Triggers and escalations to be incorporated based on the Task assignment module Delay in permit Development of registered office premises al all documentation strategic location to avoid permit documentation
  • 21. Define Measure Analyze Improve Control …2/2 List Possible Solutions Sl No. Area 14 Delivery 15 Delivery 16 Delivery 17 Delivery 18 Delivery 19 Delivery Delay by transporter 20 Delivery Delay by transporter 21 Delivery 22 Delivery 23 Delivery 24 Delivery 25 Delivery Root Cause Delay by transporter Delay by transporter Delay by transporter Delay by transporter Delay by transporter Delay by transporter Delay by transporter Delay by tranporter Delay by transporter Delay by transporter Suggested Action Points Easy to Low Capital Manpower Visible short implement and RPN utilization Utilization term benefits cascade Proper Monitoring and tracking by phone and mail 9 9 9 9 36 Daily tracking of material from Transporters website 9 9 9 9 36 Flashing of transporters tracker to transporter to transporter in order to deliver 9 9 9 9 36 MIS report from transporters to track material 9 9 9 9 36 9 9 9 9 36 1 9 9 1 20 1 9 9 1 20 1 9 9 1 20 1 9 9 1 20 1 9 9 1 20 1 9 9 1 20 1 9 9 1 20 Timely up-dation of POD by monitoring of transporters website Synchronization of XYZ AX with transporters website to flash delivery reminders to transporter and online updating of the POD HHHT terminals to be carried by Transporters SPOC for generation of online POD with intimation to XYZ for installation SLA based payment deduction form transporters Payout SLA's to be incorporated in the agreement for every transporter Deduction form transporters payout in case of Damaged delivery Strict SLA adherence in case of DOA and Wrong delivery GPS tracking of every transporter truck to be informed on the status of all deliveries
  • 22. Define Measure Analyze Improve Control Technology led efficiency and effectiveness improvement  XYZ decided to streamline the activities with the help of ERP solution. The process maps have been created to restructure the activities and bring more efficiency within them  Technologies such as handheld devices to capture the information from the vouchers has been created. It has the capability to transmit the data that can be easily fed into the ERP  This has allowed for the information flow to be quick and precise. Most of the delays that were happening earlier was due to late and imprecise information flow
  • 24. Define Measure Analyze Improve Control Normality tests and control charts Process capability of total project schedule variance (Jul 2012 to Sep 2012)
  • 25. Define Measure Analyze Improve Control Box plot Boxplot of total project schedule variance (Apr 2013 to June 2013) Value plot (Q4- Apr 2012 to Jun 2012, Q8- Apr 2013 to Jun 2013)
  • 26. Define Measure Analyze Improve Control Normality tests and control charts Test carried out : Hypothesis testing [ One sample / t test / Paired etc., ] / One way ANOVA / Two way ANOVA Probability plot of project schedule variance (Mar 2013 to Jun 2013) IMR for project schedule variance (Mar 2013 to Jun 2013)
  • 27. Define Measure Analyze Improve Control Process Capability - Total Project Cycle Time Process capability of total project schedule variance (Mar 2013 to Jun 2013) • • • The Process Capability has increased from 0.8 to 1.11 . The process control chart is stable with no outliers in Individual Chart . Therefore there has been a considerable improvement in the process
  • 28. Define Measure Analyze Improve Control Project Benefit Initial estimate / COPQ: INR 168 lacs Project Name Service Revamp Black Belt (Candidate) Sumit K Jha Financial Benefits (Numbers in INR lacs) 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Direct savings (Liquidated damages) 5 15 30 40 90 Increased revenues - 15 20 23 58 Reduced costs - 2 5 7 15 Working capital changes - 1 1.7 2.4 5.1 Investment/ loan changes - - - - Total 5 33 56.7 72.4 Non-Financial Benefits Improved csat score Signature Approvals MBB Name XYZ Date Champion Name CEO Date Finance Name CFO Total 168.1
  • 29. Define Measure Analyze Improve Control Conditions Worksheet Initial estimate / COPQ: INR 168 lacs Project Name Black Belt (Candidate) Financial Benefits Calculation formulas Approvals Service Revamp Sumit K Jha 1) Reduction in liquidated damages, which is levied if the goods are not delivered in time. The liquidated damages have come out to be less than INR 2) 10 lacs in the control phase. 3) 4) 1) Sum of (Project delivered late* % liquidated damages clause in the project) 2) Signature MBB Name XYZ Date Champion Name CEO Finance Name CFO