Waterfront Toronto Archetype Condo Project

650 views

Published on

The largest urban renewal project in North America, this project focuses on revitalization, not just redevelopment, to exceed code compliance

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
650
On SlideShare
0
From Embeds
0
Number of Embeds
33
Actions
Shares
0
Downloads
9
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Waterfront Toronto Archetype Condo Project

  1. 1. ARCHETYPE CONDO PROJECT
  2. 2. 800 hectares of mixed use development ARCHETYPE CONDO PROJECT 475 hectares parks and open spaces 40,000 new homes 40,000 new jobs West Don Lands East Bayfront Lower Don Lands Central WaterfrontThe largest urban renewal project in North America
  3. 3. ARCHETYPE CONDO PROJECTRevitalization not just redevelopment
  4. 4. ARCHETYPE CONDO PROJECT • South-East Corner of Mill Street and Cherry Street • Extension of Distillery District to the West • 579 Residential Units
  5. 5. ARCHETYPE CONDO PROJECT
  6. 6. ARCHETYPE CONDO PROJECTSetting the Baseline
  7. 7. ARCHETYPE CONDO PROJECT
  8. 8. ARCHETYPE CONDO PROJECTSeveral ‘Performance’ Options: 0% better, plus 5% Better SB-10
  9. 9. ARCHETYPE CONDO PROJECTIDP - Revit > Green Building Studio
  10. 10. ARCHETYPE CONDO PROJECTIDP - Green Building Studio > eQuest modeling software
  11. 11. ARCHETYPE CONDO PROJECTResults Breakdown Lights MiscEnd Use ekWh EquipmentLights 325,776 CoolingMisc Equipment 374,031Cooling 430,197 DomesticPumps 286,134 Hot Water PumpsFans 650,291Heating 3,043,492Domestic Hot Water 1,503,273 FansFuelElectricity (kWh) 1,963,108Natural Gas (ekWh) 4,319,427 Heating
  12. 12. ARCHETYPE CONDO PROJECT Envelope Requirements OBC / ASHRAE 90.1 Typical residential Baseline constructionRoof R-20.8 overall R-20.8 overall minimumGlazing 0.55 U value; 40% of 0.55 U value (0.30 wall area Centre of Glass); 70% of wall areaWalls R-15.6 overall R-11 overall (R-21 nominal)
  13. 13. ARCHETYPE CONDO PROJECTEnvelope Requirements  Spandrel back pan – 2 x 1 inch Roxul insulation:  Nominal R-8 (overall R-5)  Batt insulation in metal framing:  Nominal R-13 (overall R-7)  Total R-11 Overall
  14. 14. ARCHETYPE CONDO PROJECTWaterfront Toronto – Archetype Condominiums, Base Building Base Building Roof Assemblies and R value IEAD; 20.8 R Value Wall Assemblies and R Value Steel Framed; 15.6 R Value Window Type and U Value Metal Framed; 0.55 Total U Value; Window to Wall Ratio 40% Floor, Slab Assemblies and R Value - Balcony Isolation and Edge N/A Space Heating Type and Efficiency Central Atmospheric HW Boiler; 80% Efficient Pumps and Drives Constant Speed Space Cooling Type and Efficiency Centrifugal Chiller with Cooling Tower; COP of 6.1 Ventilation and Pressurization Combined 100 cfm/Suite Metering and Controls None Lighting Loads 6.6 W/sq.m. Low Flow Fixtures - Onsite Energy Production None Renewable Energy None Net Energy Reduction - Energy Fuel Cost Reduction - GHG Reduction -
  15. 15. ARCHETYPE CONDO PROJECTImprove Net Energy Performance by 5%
  16. 16. ARCHETYPE CONDO PROJECTArchetype Base Building vs. 5% Energy Performance Improvement Base Building Base Building Proposed Building Proposed Building Roof Assemblies and R value Roof Assemblies and R value IEAD; 20.8 R Value IEAD; 20.8 R Value IEAD; 20.8 R R Value IEAD; 20.8 value Wall Assemblies and R Value Steel Framed; 15.6 R Value Steel Framed; 11.0 R 11.0 R Value Steel Framed; value Wall Assemblies and R Value Window Type and U Value Steel Framed; 15.6 R Value Metal Framed; 0.55 Total U Value; Metal Framed; 0.35 total U value Metal Framed; 0.35 Total U Value Window Type and U Value Metal Framed; 0.55 Total U Value; - Window to Wall Ratio 40% 65% Window to Wall Ratio 40% 65%%Floor, Slab Assemblies and ValueFloor, Slab Assemblies and R R Value -- - - Balcony Isolation and Edge N/A Central Atmospheric with Lead N/A Balcony Isolation and Edge N/A Condensing HW Boiler; 89% Efficient Central Atmospheric with Lead Central Atmospheric HW Boiler; 80% (Effective)Space Heating Type and Efficiency Condensing HW Boiler; 89% Efficient Efficient Centrifugal VSD Chiller with Cooling Central Atmospheric HW Boiler; 80% (Effective) Space Heating Type and Efficiency Tower; COP of 6.1; IPLV of 0.325 Pumps and Drives Efficient Constant Speed Constant Speed kW/Ton Centrifugal Chiller with Cooling Tower; Centrifugal Chiller with Cooling Tower;Space Cooling Type and Efficiency Pumps and Drives Constant Speed COP of 6.1 COP ofConstant Speed 6.1; IPLV of 0.325kW/ton Ventilation and Pressurization Combined 100 cfm/Suite Combined 100 cfm/Suite Centrifugal Chiller with Cooling Tower; Space Cooling Type and Efficiency Combined 100 cfm per suite Metering and Controls None COP of 6.1 None Ventilation and Loads Lighting Pressurization Combined 100 CFM/Suite 6.6 W/sq.m. None 6.6 W/sq.m. Metering and Controls None 6.6 W/sq.m. Low Flow Showerheads 1.5 gpm. Faucets Low flow showerheads 1.5 gpm, Low Flow Fixtures - Lighting Loads 6.6 W/sq.m. 1.0 gpm faucets 1.0 gpm Onsite Energy Production Onsite Energy Production None None None None Renewable Energy Renewable Energy None None None None Net Energy Reduction - 318,364 kWh (5.1%) Net Energy Reduction - 318,364 kWh (5.1%) Energy Fuel Cost Reduction - -$10,840 (-3.4%) EnergyGHG Reduction Fuel Cost Reduction -- -$10,840 (-3.4%) 67,771 kg CO2e (5.0%) GHG Reduction - 67,771 kg CO2e (5.0%)
  17. 17. ARCHETYPE CONDO PROJECTInternat Energy Solutions – 5% Energy Performance ImprovementEnergy Conservation Measures (ECMs) ECM 1 – Upgrade heating boilers to high efficiency atmospheric units with a lead condensing boiler ECM 2 – Upgrade chiller to a VSD centrifugal chiller ECM 3 – Upgrade domestic hot water boilers to high efficiency condensing boilers ECM 4 – Upgrade to low flow showerheads and faucets ECM 5 – Upgrade window-wall assembly to high performance glazing system ECM 6 – Reduce window-to-wall ratio to 65% Note: Each ECM is cumulative
  18. 18. ARCHETYPE CONDO PROJECTEnergy Use Table – 5% Energy Performance Improvement Consumption Electricity Gas Total Incremental Performance (kWh) (m3) (kWh) Change Relative to (%) Baseline (%)Reference 2,413,200 492,000 7,500,900 - -19.4ECM 1 2,413,200 456,000 7,128,700 5.0 -13.5ECM 2 2,163,300 456,000 6,878,800 3.5 -9.5ECM 3 2,163,300 432,800 6,638,500 3.5 -5.7ECM 4 2,163,300 417,600 6,481,800 2.4 -3.2ECM 5 2,226,800 369,500 6,047,000 6.7 3.7ECM 6 2,179,100 366,100 5,964,200 1.4 5.1 Note: Each ECM is cumulative
  19. 19. ARCHETYPE CONDO PROJECTEnergy Use Chart – 5% Energy Performance Improvement Lights Cooling 5% 6% Heating 45%Misc Equipment 6%Pumps & Aux. 6% Fans 13% DHW 19%
  20. 20. ARCHETYPE CONDO PROJECTImprove Net Energy Performance by 15%
  21. 21. ARCHETYPE CONDO PROJECTArchetype Base Building vs. 15% Energy Performance Improvement Base Building Proposed Building Roof Assemblies and R value IEAD; 20.8 R Value IEAD; 20.8 R Value Wall Assemblies and R Value Steel Framed; 15.6 R Value Steel Framed; 11 R Value Window Type and U Value Metal Framed; 0.55 Total U Value Metal Framed; 0.35 Total U Value Window to Wall Ratio 40% 70%Floor, Slab Assemblies and R Value - - Balcony Isolation and Edge N/A N/A Central Atmospheric HW Boiler; 80%Space Heating Type and Efficiency 88% Efficient Forced Draft Efficient Pumps and Drives Constant Speed Constant Speed Centrifugal Chiller with Cooling Tower; Centrifugal Chiller with Cooling Tower;Space Cooling Type and Efficiency COP of 6.1 COP of 6.1 Ventilation and Pressurization Combined 100 cfm/Suite In Suite ERV Metering and Controls None None Lighting Loads 6.6 W/sq.m. 6.6 W/sq.m. Low Flow Fixtures - Low flow Onsite Energy Production None None Renewable Energy None None Net Energy Reduction - 992,166ekWh (15.8%) Energy Fuel Cost Reduction - -$63,600 (-19.9%) GHG Reduction - 210,351 kg CO2e (15.6%)
  22. 22. ARCHETYPE CONDO PROJECTMCW Consultants– 15% Energy Performance ImprovementEnergy Conservation Measures (ECMs) ECM 1 – In-Suite Energy Recovery Ventilation ECM 2 – 88% Efficient Boiler ECM 3 – 95% Efficient DHW Heater ECM 4 – Low Flow DHW Fixtures ECM 5 – U0.35 Window Note: Each ECM is cumulative
  23. 23. ARCHETYPE CONDO PROJECTEnergy Use Table – 15% Energy Performance Improvement Consumption Electricity Gas Total Incremental Performance (kWh) (m3) (ekWh) Change Relative to (%) Baseline (%)Reference 2,413,244 491,578 7,501,072 - -19.4ECM 1 2,876,447 383,502 6,845,689 8.7 -9.0ECM 2 2,881,645 317,521 6,167,992 9.9 1.8ECM 3 2,881,645 294,588 5,930,632 3.8 5.6ECM 4 2,881,645 264,272 5,616,859 5.3 10.6ECM 5 2,983,188 222,935 5,290,563 5.8 15.8 Note: Each ECM is cumulative
  24. 24. ARCHETYPE CONDO PROJECT Energy Use Chart – 15% Energy Performance Improvement 15% Energy Performance Improvement Area Lights, 6% Space Cool, 14% Misc. Equip., 7% Pumps & Aux., 9% Space Heat, 26%Vent. Fans, 20% Hot Water, 18%
  25. 25. ARCHETYPE CONDO PROJECTImprove Net Energy Performance by 25%
  26. 26. ARCHETYPE CONDO PROJECT Archetype Base Building vs. 25% Energy Performance Improvement Base Building Proposed Building Roof Assemblies and R value IEAD; 20.8 R Value IEAD; 20.8 R Value Wall Assemblies and R Value Steel Framed; 15.6 R Value Steel Framed; 15.6 R Value Window Type and U Value Metal Framed; 0.55 Total U Value; Metal Framed; 0.55 Total U Value; Window to Wall Ratio 40% 70%Floor, Slab Assemblies and R Value - - Balcony Isolation and Edge N/A N/A Central Atmospheric HW Boiler; 80% Vertical Ground Loop HX; Heating COP :Space Heating Type and Efficiency Efficient 3.9 Pumps and Drives Constant Speed Variable Speed Centrifugal Chiller with Cooling Tower; Vertical Ground Loop HX; Cooling EER :Space Cooling Type and Efficiency COP of 6.1 18.1 Ventilation and Pressurization Combined 100 cfm/Suite Combined 100 cfm/Suite Metering and Controls None None Lighting Loads 6.6 W/sq.m. 6.6 W/sq.m. Onsite Energy Production None None Renewable Energy None None Net Energy Reduction - 37.2% Energy Fuel Cost Reduction - 11.1% GHG Reduction - 40.2%
  27. 27. ARCHETYPE CONDO PROJECTFootprint– 25% Energy Performance ImprovementEnergy Conservation Measures (ECMs) ECM 1 – Market Building with Geo-Exchange System ECM 2 – Variable Speed Drives
  28. 28. ARCHETYPE CONDO PROJECTEnergy Use Chart - 25% Energy Performance Improvement
  29. 29. ARCHETYPE CONDO PROJECT Sustainable Buildings Canada would like to thank our volunteer design team for their time and efforts in completing this project• Michelle Xuereb – Quadrangle Architects• Katy Mulla – Quadrangle Architects• John Janzen – Autodesk• Craig McIntyre – Provident energy management• Adam Barker – Provident energy management• Ian Stahlbrand – Internat Energy Solutions• Brian Tysoe – MCW Consultants Ltd.• Lyle Scott – S.A. Footprint• Shaheen Asif – S.A. Footprint
  30. 30. ARCHETYPE CONDO PROJECT Principle SponsorsThank you to our Principle Sponsors and Proponent who’s financial andresource support made this project possible.

×