First and foremost, allow us to take this opportunityto express our thanks and appreciation for having usbecome part of yo...
Our goal is to have the SAF Sulphur Factoryready and operational come June 2010.We have applied additional resources to sp...
Civil and Structural Works are now approximately70% complete for the…      * storage building,      * administration offic...
CONSTRUCTION PROGRESS REPORT                   % complete       Projected completion    Work Items                    as o...
Part of this initial stage is to have dry runsand testing.And with this activities, we need to haveSULPHUR SAMPLES to test...
Whenever available and ready, we shall submitimmediately all required documents andsamples to the Ministry of Agriculture ...
Setting up is only a start of many challengesand we commit ourselves to continueworking hard to make this business succeed...
This is only the beginning ofour dream becoming realityAnd you grant us the chanceto make this thing happens…
First aramco pp presentation
First aramco pp presentation
Upcoming SlideShare
Loading in …5
×

First aramco pp presentation

689 views

Published on

Published in: Travel, Business, Technology
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
689
On SlideShare
0
From Embeds
0
Number of Embeds
5
Actions
Shares
0
Downloads
0
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

First aramco pp presentation

  1. 1. First and foremost, allow us to take this opportunityto express our thanks and appreciation for having usbecome part of your prestigious company.Becoming part of your business is an honor and areality to a vision to move ahead in our expansionplans and programs, and join the many promisingand growing businesses within the kingdom.We assure to give value to this trust by providingfull attention through intelligent planning andcareful execution and make this venture a successfulone.
  2. 2. Our goal is to have the SAF Sulphur Factoryready and operational come June 2010.We have applied additional resources to speed upconstruction while we try our best to meet thisgoal as we work double time to catch the timeframe given.
  3. 3. Civil and Structural Works are now approximately70% complete for the… * storage building, * administration office and, * laboratory areas. We project to complete these works by the end of April 2010.Factory Machineries and Equipments are now 66%complete with target completion by middle of May2010.Dry run will be performed to test all systems fromreceiving, production and storing to check qualityresults.
  4. 4. CONSTRUCTION PROGRESS REPORT % complete Projected completion Work Items as of Jan Feb Mar Apr MayMobililizationSite PreparationWarehouseLaboratoryAdministrationHot SystemCool SystemConveyor SystemCrushing/ChippingSystemMixing SystemPacking SystemPipings
  5. 5. Part of this initial stage is to have dry runsand testing.And with this activities, we need to haveSULPHUR SAMPLES to test the systems as well assamples to be submitted to the Ministry ofAgriculture for their evaluation and approval.
  6. 6. Whenever available and ready, we shall submitimmediately all required documents andsamples to the Ministry of Agriculture forapproval.
  7. 7. Setting up is only a start of many challengesand we commit ourselves to continueworking hard to make this business succeed.With your guidance, we shall continue tostrive hard and explore opportunities ofimprovements and developments inProduction, Marketing, R&D, Logistics andManpower resources to attain excellentproduct quality and services.
  8. 8. This is only the beginning ofour dream becoming realityAnd you grant us the chanceto make this thing happens…

×