Oahu – Underway – NTP July 1, 2015
Maui- working on RFP and use of consultants
Big Island +/- FY 18-21 (l...
Lidar
• Oahu, Maui, Big Island and Kauai – FY 25
Geoid Model
• Oahu, Maui, Big Island and Kauai – FY 26+
Depend on when al...
Oahu Leveling
2 Consultants
DOT
Honolulu
Tide Gauge
H-3
DELETED
UNIT 2
UNIT 1
H-3 DELETED
VERTICAL ACCURACY STANDARDS
Relative Accuracy Between
Directly Connected Points or Benchmarks
Classification (Standard Err...
Scope of Work developed with the
help of NGS
• Phase 1 – Training time two (2) eight hour days
– Office – NGS Software Win...
• Phase 4 – Digital Leveling
– Requires a minimum of a two mark tie at the beginning
and two mark tie at the end of the le...
Oahu Consultants 2012 to present
• DOT RFP 12/2012- 01/2013
– http://spo3.hawaii.gov/notices/notices/none-91
– http://spo3...
Typical Level Unit
• One observer (instrument person)*
• Two rod people*
• One or two vehicles
– One capable of transporti...
Maui County
4 Consultants
Total
Kahului
Tide Gauge
Not Included
KAHULUI
Tide Gauge
Kaunakakai
Tide Gauge
Kaumalapau
Tide Gauge
2 separate consultants for
Molokai And Lanai
Consultant
Consultant
4 Consultants
Hilo Bay
Tide Gauge
Not
included
Hilo Bay
Tide Gauge
Nawiliwili Tide Gauge
VRS / CORS from a county wide system
Oahu 7 New 1 Update
• Dot is looking to keep each CORS/VRS in State
(Airports, Schools, DOT maintenance yards, etc.),
county property (Parks, ...
Example of CORS stations
Maui 8-9 New 1 Update
Big Island 9 New 2 Update
Kauai 6 New 1 Update
to a State Wide Network
LIDAR and Airborne Gravity
• High accuracy and or resolution from
Shoreline to toe of mountain.
• Standard accuracy and or...
Proposed LIDAR Scope
– Planning route
– Plane & Fuel
– Personal office and field
– Processing and quality control check
– ...
Research and Development
• Calculating of a new Geoid Model for the State of
Hawaii
• Using the Digital Leveling, LIDAR Da...
Who will Benefit MOST from this
Height Mondernization?
• Private Sector (Engineers, Surveyors, Planners,
Contractors, and ...
Question
• Thank you for allowing me to present our
plans for The Height Modernization for the
State of Hawaii
Contact Information
• Christopher Guerin
601 Kamokila Blvd. Room 600
Kapolei, Hawaii. 96707
808-692-7602 Phone
808-692-760...
State of Hawaii Digital Leveling Project
State of Hawaii Digital Leveling Project
Upcoming SlideShare
Loading in …5
×

State of Hawaii Digital Leveling Project

318 views

Published on

HIGICC Conference 2015
October 14-16, 2015
Chris Guerin

Published in: Government & Nonprofit
  • Be the first to comment

  • Be the first to like this

State of Hawaii Digital Leveling Project

  1. 1. HCPO-HIGICC 10/16/2015 Hawaii Convention Center
  2. 2. Digital Leveling Oahu – Underway – NTP July 1, 2015 Maui- working on RFP and use of consultants Big Island +/- FY 18-21 (lots of mile to run) Kauai +/- FY 22 Oahu, Maui, Big Island and Kauai – FY 16 -24 County by County VRS/CORS construction will start once the digital leveling is complete DOT Height Modernization Current Timeline
  3. 3. Lidar • Oahu, Maui, Big Island and Kauai – FY 25 Geoid Model • Oahu, Maui, Big Island and Kauai – FY 26+ Depend on when all other activity has been completed
  4. 4. Oahu Leveling 2 Consultants DOT Honolulu Tide Gauge H-3 DELETED UNIT 2 UNIT 1
  5. 5. H-3 DELETED
  6. 6. VERTICAL ACCURACY STANDARDS Relative Accuracy Between Directly Connected Points or Benchmarks Classification (Standard Error) First, Class I 0.5 mm K First, Class II 0.7 mm K Second, Class I 1.0 mm K Second, Class II 1.3 mm K Third, Class I 2.0 mm K K = distance in Kilometers between points
  7. 7. Scope of Work developed with the help of NGS • Phase 1 – Training time two (2) eight hour days – Office – NGS Software WinDesc • Phase 2 – Record research – Database search – Website and other government agencies – Mark Recovery - Prepared by the consultant – Planning - Prepared by the consultant – Preparation of Survey Plan – Prepared by the consultant – Preparation of Quality Control Plan - Prepared by the consultant – Preparation of Safety Plan - Prepared by the consultant • Phase 3 – Mark Setting - bridge abutments, Storm Drain Inlets – NGS Class to teach Field Procedures and proper use of equipment. – NGS Software Translev
  8. 8. • Phase 4 – Digital Leveling – Requires a minimum of a two mark tie at the beginning and two mark tie at the end of the level line – Equipment Check – Collimation (Peg Test or C-check) Kukkamaki, Förstner every day or when the level is jarred or long travel – Double-run leveling – Run up and run down – All data to stored on instrument and download daily and on Backup Recording Sheet – Record collimation (arc-seconds) an all important information on Backup Recording Sheet – Run the NGS Translev Software DAILY – Combine Daily Translev Processing for Completed Project • Phase 5 – Final Report – Consultant to prepare • Phase 6 - Submit Data to Hawaii DOT • DOT to submit work to NGS to be incorporated into the existing database.
  9. 9. Oahu Consultants 2012 to present • DOT RFP 12/2012- 01/2013 – http://spo3.hawaii.gov/notices/notices/none-91 – http://spo3.hawaii.gov/notices/notices/none-92 • Consultant selection took longer than normal. Not a normal DOT project. Lot of department employees overseeing to make sure the project is not going to have to many problems. 04/2013 • Negotiations – Only a few changes were made from the original proposal to fit a tight budget. • Fee acceptance 12/2014 • NTP July 1, 2015 • Workshop (NGS and State of Hawaii) – WinDesc – Completed in 7/2015 • Recovery and planning of survey marks – Survey disk have been ordered by the consultants and delivered to the consultants 09/2015 • Currently, both consultants are working on their Survey Plans, Quality Control Plans and Safety Plans. They should be finished by end this month, 10/2015 • Planning has taken a bit longer, should be faster in future projects. • Mark Settings (about 3-4 weeks depending on weather delays) and a leveling workshop by NGS (2-3days) • Leveling (about 3 to 5 months depending on weather delays) • Final Report. The final report will also include recommendations for future height modernization projects – 04 to 05/2016
  10. 10. Typical Level Unit • One observer (instrument person)* • Two rod people* • One or two vehicles – One capable of transporting equipment – rods* • Rods are 3 meter in length – Drop one vehicle at end of day’s work • Safety people if necessary – Warning person to drive behind crew • One pacer to help with setups ** • Computer to download and process data* * Required ** Optional
  11. 11. Maui County 4 Consultants Total Kahului Tide Gauge Not Included
  12. 12. KAHULUI Tide Gauge
  13. 13. Kaunakakai Tide Gauge Kaumalapau Tide Gauge 2 separate consultants for Molokai And Lanai Consultant Consultant
  14. 14. 4 Consultants Hilo Bay Tide Gauge Not included
  15. 15. Hilo Bay Tide Gauge
  16. 16. Nawiliwili Tide Gauge
  17. 17. VRS / CORS from a county wide system Oahu 7 New 1 Update
  18. 18. • Dot is looking to keep each CORS/VRS in State (Airports, Schools, DOT maintenance yards, etc.), county property (Parks, Police stations etc.). This will help to reduce overall cost. • Consultant will look at each site to make sure the sight is acceptable (low GPS multipath, internet connection, power 24/7, etc. or has the option to recommend a new site. • Consultant will determine what type of CORS station will be used, what types of permit(s) (building, etc.,)will be required and make a construction budget for each site and determine annual cost (servers, Internet, software etc.)
  19. 19. Example of CORS stations
  20. 20. Maui 8-9 New 1 Update
  21. 21. Big Island 9 New 2 Update
  22. 22. Kauai 6 New 1 Update
  23. 23. to a State Wide Network
  24. 24. LIDAR and Airborne Gravity • High accuracy and or resolution from Shoreline to toe of mountain. • Standard accuracy and or resolution from toe of mountain to mountain tops • Bare earth and First to last return (First return for vegetation • DEM • Aerial Photos if there is enough money left.
  25. 25. Proposed LIDAR Scope – Planning route – Plane & Fuel – Personal office and field – Processing and quality control check – Delivering data
  26. 26. Research and Development • Calculating of a new Geoid Model for the State of Hawaii • Using the Digital Leveling, LIDAR Data and Airborne Gravity for the new Geoid Model. • A major University to make calculation • NGS to advise when needed. • New Geoid Model to be published and used for Hawaii
  27. 27. Who will Benefit MOST from this Height Mondernization? • Private Sector (Engineers, Surveyors, Planners, Contractors, and Construction Company’s, etc.) • Government Sector (Military, Federal, State, County) • Public Utilities - Precision As-builts • GIS Community • And the tax payers in general (lower cost for surveying, engineering, etc.)
  28. 28. Question • Thank you for allowing me to present our plans for The Height Modernization for the State of Hawaii
  29. 29. Contact Information • Christopher Guerin 601 Kamokila Blvd. Room 600 Kapolei, Hawaii. 96707 808-692-7602 Phone 808-692-7608 Fax christopher.guerin@hawaii.gov

×