Test your general Project Engineer skills

Published in: Education

Project engineer test level 3

  1. 1. HERVE BARON ©2015–HervéBaron Welcome to this assessment It will test you general knowledge as a Project Engineer. Enjoy! Comments are most welcome (herve.baron@gmail.com), which I will incorporate for the benefit of all. Hervé Project Engineer knowledge test
  2. 2. HERVE BARON ©2015–HervéBaron What is the cost of the Spare Parts for 2 years operation for the following commodity:  0% of PO Price  10% of PO Price  20% of PO price? Pressure Vessels Pumps Control, ON/OFF valves, PSVs Unit Control Panel Project Engineer knowledge test
  3. 3. HERVE BARON ©2015–HervéBaron What is the cost of the Spare Parts for 2 years operation for the following commodity:  0% of PO Price  10% of PO Price  20% of PO price? Pressure Vessels – 0% Pumps – 10% Control, ON/OFF valves, PSVs – 20% Unit Control Panel – 10% Project Engineer knowledge test
  4. 4. HERVE BARON ©2015–HervéBaron What is missing from the table of contents of the Engineering Design Data shown below? Project Engineer knowledge test
  5. 5. HERVE BARON ©2015–HervéBaron What is missing from the table of contents of the Engineering Design Data shown below? Project Engineer knowledge test Source: ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, page 12
  6. 6. HERVE BARON ©2015–HervéBaron Which system is used to calculate the engineering progress by document weight and progress steps (revision status) 1) the Project scheduling software, such as Primavera, 2) the document control system and master document register 3) another system Project Engineer knowledge test
  7. 7. HERVE BARON ©2015–HervéBaron Which system is used to calculate the engineering progress by document weight and progress steps (revision status) 1) the Project scheduling software, such as Primavera, 2) the document control system and master document register 3) another system, as the progress measurement is done by group of documents, e.g., Unit 12 P&IDs, not by individual document which is the level system 2 goes to. The grouping is finer than that of the scheduling software. Project Engineer knowledge test
  8. 8. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test What is the graphic scale of the Civil Works Installation (also called Civil Area) drawings? 1) 1:50 2) 1:200 3) 1:500
  9. 9. HERVE BARON ©2015–HervéBaron What is the graphic scale of the Civil Works Installation (also called Civil Area) drawings? 1) 1:50 2) 1:200 3) 1:500 Project Engineer knowledge test
  10. 10. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test When does Engineering progress picks-up to reach cruising speed on an EPC? 1) after all disciplines have been mobilized 2) after the P&IDs have been finalized 3) after the Plot Plan has been finalized 4) after the purchase orders for equipment have been placed 5) after the completion of the 3D model
  11. 11. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test When does Engineering progress picks-up to reach cruising speed on an EPC? 1) after all disciplines have been mobilized 2) after the P&IDs have been finalized 3) after the Plot Plan has been finalized 4) after the purchase orders for equipment have been placed. Cruise speed is reached 2 months after 50% of equipment purchase orders have ben placed. 5) after the completion of the 3D model
  12. 12. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test What type of specification is issued (by Equipment/Mechanical discipline) for air-coolers? 1) a particular specification 2) a general specification
  13. 13. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test What type of specification is issued (by Equipment/Mechanical discipline) for air-coolers? 1) a particular specification 2) a general specification
  14. 14. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test The lengths of pipes used for the first purchase order of piping materials are obtained from? 1) The Piping General Arrangement drawings, 2) The Plot plan, 3) Piping layout drawings, 4) The 3D model, 5) The isometric drawings,
  15. 15. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test The lengths of pipes used for the first purchase order of piping materials are obtained from? 1) The Piping General Arrangement drawings, 2) The Plot plan, 3) Piping layout drawings, 4) The 3D model, 5) The isometric drawings,
  16. 16. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Which of the following documents are produced at BASIC engineering stage (prior to FEED stage) 1) Equipment Process data sheets 2) Equipment Mechanical data sheets 3) Material Take-Off's 4) Piping routing drawings
  17. 17. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Which of the following documents are produced at BASIC engineering stage (prior to FEED stage) 1) Equipment Process data sheets 2) Equipment Mechanical data sheets 3) Material Take-Off's 4) Piping routing drawings
  18. 18. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test What is a Material Take-Off? 1) an estimate of quantities to be supplied/erected, 2) the cumulated quantities of what is shown on a set of drawings
  19. 19. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test What is a Material Take-Off? 1) an estimate of quantities to be supplied/erected, 2) the cumulated quantities of what is shown on a set of drawings
  20. 20. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test What does IP level of electrical and instrumentation equipment mean and stand for?  Level of mechanical protection  Level of explosion protection IP means: ………….
  21. 21. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test What does IP level of electrical and instrumentation equipment mean and stand for?  Level of mechanical protection  Level of explosion protection IP means: Ingress Protection. It means mechanical protection and protection again ingress of water, dust etc. Reference code is IEC 60529 "Degree of Protection provided by enclosures". Typically a certain IP level is specified for outdoor equipment and another one for indoor equipment.
  22. 22. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test What do you call the Instrument & Control drawing showing all details of wiring, with termination and inter-connections from primary element to final, including tags of • Primary element, • Individual cables, • Junction boxes, • Multipair cables, • Cable cores • Terminals, • I/O cards, • Panels, • Locations (field, technical rooms)
  23. 23. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Source: ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, page 173
  24. 24. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Which of the following Equipment Vendor documents are critical for Engineering progress? 1) Cross section drawings and bills of materials 2) List of inputs/outputs to DCS 3) Foundation layout and loading plan 4) Filled-in data sheet 5) Operating Manual 6) General arrangement drawing 7) Strength calculation note 8) Utility consumption list 9) Performance curve
  25. 25. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Which of the following Equipment Vendor documents are critical for Engineering progress? 1) Cross section drawings and bills of materials 2) List of inputs/outputs to DCS 3) Foundation layout and loading plan 4) Filled-in data sheet 5) Operating Manual 6) General arrangement drawing 7) Strength calculation note 8) Utility consumption list 9) Performance curve
  26. 26. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Which sentences are correct: 1) The Piping General Arrangement Drawing contains all the information required to produce the piping isometric drawing, 2) The piping isometric drawing indicates the piping material class. The exact material designation is found in the piping material class specification. 3) The piping isometric drawing is used for piping pre-fabrciation, 4) The Piping General Arrangement drawing is used for piping erection, 5)The 3D model is often used nowdays in lieu of the Piping General Arrangement,
  27. 27. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Which sentences are correct: 1) The Piping General Arrangement Drawing contains all the information required to produce the piping isometric drawing, 2) The piping isometric drawing indicates the piping material class. The exact material designation is found in the piping material class specification. 3) The piping isometric drawing is used for piping pre-fabrciation, 4) The Piping General Arrangement drawing is used for piping erection, 5)The 3D model is often used nowdays in lieu of the Piping General Arrangement,
  28. 28. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test The Process Data Sheet of a heat exchanger indicates which of the following information? 1) the duty 2) the heat exchange area 3) the fouling factor 4) the type of each exchanger (U-tube etc.) 5) the allowable pressure drop 6) dimensions 7) overdesign
  29. 29. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test The Process Data Sheet of a heat exchanger indicates which of the following information? 1) the duty 2) the heat exchange area 3) the fouling factor 4) the type of each exchanger (U-tube etc.) 5) the allowable pressure drop 6) dimensions 7) overdesgin
  30. 30. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Which codes gives the corrosion rate (in mm/year) for the usual corrosion phenomena found in Oil & Gas facilities? 1) ASME VIII 2) NACE MR103 3) API RP 581 4) none of the above
  31. 31. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Which codes gives the corrosion rate (in mm/year) for the usual corrosion phenomena found in Oil & Gas facilities? 1) ASME VIII 2) NACE MR103 3) API RP 581 4) none of the above
  32. 32. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test FEED studies primarily focus on 1) Plant Layout 2) Piping routing 3) Process design
  33. 33. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test FEED studies primarily focus on 1) Plant Layout 2) Piping routing 3) Process design
  34. 34. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test "free draining" and "no pocket" indication on P&IDs mean the same thing. Right or Wrong?
  35. 35. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test "free draining" and "no pocket" indication on P&IDs mean the same thing. Right or Wrong?
  36. 36. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Which drawing corresponds to the following definition: "initial graphic piping plan. It is not a finished document, nor is it a deliverable to a Client. It shows all equipment in a given area to scale and includes major process and utility piping systems, significant valving and instruments. It indicates the exact equipment locations and elevations, nozzles, platform and ladder requirements and any pipe support that affects the design of equipment or structure other disciplines". 1) the Piping and Instrumentation Diagram 2) the Unit Plot Plan 3) the line diagram 4) the Piping layout drawing 5) the Piping General Arrangement drawing
  37. 37. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Which drawing corresponds to the following definition: "initial graphic piping plan. It is not a finished document, nor is it a deliverable to a Client. It shows all equipment in a given area to scale and includes major process and utility piping systems, significant valving and instruments. It indicates the exact equipment locations and elevations, nozzles, platform and ladder requirements and any pipe support that affects the design of equipment or structure other disciplines". 1) the Piping and Instrumentation Diagram 2) the Unit Plot Plan 3) the line diagram 4) the Piping layout drawing 5) the Piping General Arrangement drawing
  38. 38. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Which pumps are inter-changeable, i.e., have standard dimensions 1) the ones designed to API code 2) the ones designed to ANSI code
  39. 39. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test Which pumps are inter-changeable, i.e., have standard dimensions 1) the ones designed to API code 2) the ones designed to ANSI code
  40. 40. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test The process engineer enters the heat exchange area and transfer coefficient in the process simulator as input data. Right or Wrong?
  41. 41. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test The process engineer enters the heat exchange area and transfer coefficient in the process simulator as input data. Right or Wrong. The Process engineer enters the outlet temperature only.
  42. 42. HERVE BARON ©2015–HervéBaron Project Engineer knowledge test That’s all for now folks, but I won’t be long with new tests…
  43. 43. HERVE BARON ©2015–HervéBaron The Oil & Gas Engineering Guide - 2nd edition A unique synthesis for the busy Project professional  270 pages  300 illustrations Interested and wanting to know more on Engineering?
  44. 44. HERVE BARON ©2015–HervéBaron The Oil & Gas Engineering Guide - 2nd edition Table of Contents
  45. 45. HERVE BARON ©2015–HervéBaron The Oil & Gas Engineering Guide - 2nd edition Discipline presentation: activities and deliverables Table of Contents The overall process Methods & tools
  46. 46. HERVE BARON ©2015–HervéBaron The Oil & Gas Engineering Guide - 2nd edition Table of Contents Discipline presentation: activities and deliverables
  47. 47. HERVE BARON ©2015–HervéBaron The work of each Engineering discipline is described
  48. 48. HERVE BARON ©2015–HervéBaron Design activities are explained, e.g., Plant Equipment layout
  49. 49. HERVE BARON ©2015–HervéBaron Complex activities, such as QRA, are explained through a practical example.
  50. 50. HERVE BARON ©2015–HervéBaron How are materials of construction selected ?
  51. 51. HERVE BARON ©2015–HervéBaron How and when are Piping Materials ordered?
  52. 52. HERVE BARON ©2015–HervéBaron A sample of all common Engineering documents is included
  53. 53. HERVE BARON ©2015–HervéBaron A sample of all common Engineering documents is included Use this to specify what you want to your Engineering supplier !
  54. 54. HERVE BARON ©2015–HervéBaron Verify the contents of engineering documents with check lists.
  55. 55. HERVE BARON ©2015–HervéBaron Difference between Engineering and Shop drawings
  56. 56. HERVE BARON ©2015–HervéBaron Understand the main technical aspects, e.g., DCS vs ESD
  57. 57. HERVE BARON ©2015–HervéBaron The common 2 types of package control
  58. 58. HERVE BARON ©2015–HervéBaron The different Plant drainage systems
  59. 59. HERVE BARON ©2015–HervéBaron The dynamic forces to which an Off-Shore Plant is subject
  60. 60. HERVE BARON ©2015–HervéBaron The Oil & Gas Engineering Guide - 2nd edition Table of Contents The overall process
  61. 61. HERVE BARON ©2015–HervéBaron Use this as standard, question deviations.
  62. 62. HERVE BARON ©2015–HervéBaron Understand the new 3D-model centered engineering process
  63. 63. HERVE BARON ©2015–HervéBaron Know the interfaces between disciplines... and with Vendors
  64. 64. HERVE BARON ©2015–HervéBaron Understand what drives the Project schedule
  65. 65. HERVE BARON ©2015–HervéBaron The Oil & Gas Engineering Guide - 2nd edition Table of Contents Methods & tools
  66. 66. HERVE BARON ©2015–HervéBaron Use these methods as standard, question deviations.
  67. 67. HERVE BARON ©2015–HervéBaron Implement powerful procedures
  68. 68. HERVE BARON ©2015–HervéBaron Request meaningful progress reports
  69. 69. HERVE BARON ©2015–HervéBaron Implement effective Project Control
  70. 70. HERVE BARON ©2015–HervéBaron The Oil & Gas Engineering Guide - 2nd edition This book is destined to both:  Oil & Gas companies Project execution personnel  Oil & Gas contractors Project execution personnel Date of publication: March, 2015.
  71. 71. HERVE BARON ©2015–HervéBaron The Oil & Gas Engineering Guide 2nd edition If your are on the Client side, i.e., contracting Engineering services, this book will help you to:  Specify to an Engineering supplier what you want: what deliverables and with what contents,  Set a standard in Engineering execution that you and your supplier can adhere to: design stages/gates, methods to be used, etc.  Specify the progress report you want, with the meaningful indicators,  Ask the right questions to assess the true progress,
  72. 72. HERVE BARON ©2015–HervéBaron The Oil & Gas Engineering Guide 2nd edition If your are on the Contractor side, i.e., performing Engineering activities, this book will help you to:  Understand the work of each discipline and the overall picture,  Challenge what one discipline tells you,  Understand the critical areas,  Put in place the right methods to be successful,
  73. 73. HERVE BARON ©2015–HervéBaron The Oil & Gas Engineering Guide 2nd edition Order direct from the publisher: http://www.editionstechnip.com/en/catalogu e-detail/1111/oil-gas-engineering-guide- the.html

×