1. LAPORAN KEMAJUAN PROJEK NO.13 ‘OGOS 2008’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B
3. BANGUNAN PENTADBIRAN BENGKEL TEK. MAKLUMAT & JAMIN KUALITI DEWAN BESAR PUSAT SUMBER DEWAN KULIAH LOBI UTAMA KAFETERIA MIKRO ELEKTRONIK KOMPOSIT PLASTIK M&E PLANT ROOM 1 TNB SUB STATION SERAMIK M&E PLANT ROOM 2 GARAJ KENDERAAN ASRAMA LELAKI ASRAMA PEREMPUAN DEWAN MAKAN SURAU KELAS F KELAS G KUARTERS B, C, C&D PELAN TAPAK ADTEC TAIPING
4. KEMAJUAN KERJA FIZIKAL JADUAL : 33.81% SEBENAR : 41.47% KESELURUHAN : 7.66% ( 56 HARI ) TARIKH LAPORAN : 22 OGOS 2008
5. KEMAJUAN KERJA KEWANGAN JADUAL : 39.26% SEBENAR : 43.62% KESELURUHAN : 4.36% ( 32 HARI ) TARIKH LAPORAN : 22 OGOS 2008
6.
7. KEMAJUAN KERJA FIZIKAL DEWAN BESAR BANGUNAN - 19.88% 35.41% 55.30% JULAI 08’ - 25.63% 44.19% 69.82% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
11. KEMAJUAN KERJA FIZIKAL DEWAN KULIAH UTAMA BANGUNAN - 6.52% 38.72% 45.24% JULAI 08’ - 8.44% 41.97% 50.41% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
13. KEMAJUAN KERJA FIZIKAL PUSAT SUMBER / PERPUSTAKAAN BANGUNAN - 4.16% 59.46% 63.62% JULAI 08’ 2.58% 68.80% 66.22% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
15. KEMAJUAN KERJA FIZIKAL PENTADBIRAN & PENGURUSAN SUMBER BANGUNAN - 4.16% 50.97% 55.13% JULAI 08’ - 1.19% 57.98% 59.17% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
19. KEMAJUAN KERJA FIZIKAL BENGKEL TEKNOLOGI MAKLUMAT (PENGATURCARAAN & MEKATRONIK) BANGUNAN 4.09% 59.54% 55.45% JULAI 08’ 4.82% 66.38% 61.56% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
21. KEMAJUAN KERJA FIZIKAL BENGKEL KEJURUTERAAN BAHAN TERMAJU (PLASTIK) BANGUNAN 14.92% 54.79% 39.87% JULAI 08’ 15.13% 63.31% 48.17% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
23. KEMAJUAN KERJA FIZIKAL BENGKEL KEJURUTERAAN BAHAN TERMAJU (KOMPOSIT) BANGUNAN 16.84% 53.93% 37.09% JULAI 08’ 15.12% 58.85% 43.73% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
25. KEMAJUAN KERJA FIZIKAL BENGKEL KEJURUTERAAN BAHAN TERMAJU (SERAMIK) BANGUNAN 10.81% 51.32% 40.50% JULAI 08’ 6.62% 56.74% 50.11% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
27. KEMAJUAN KERJA FIZIKAL BENGKEL KEJURUTERAAN JAMINAN KUALITI BANGUNAN 2.33% 53.49% 51.17% JULAI 08’ 3.50% 62.31% 58.81% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
29. KEMAJUAN KERJA FIZIKAL BENGKEL MIKRO ELEKTRONIK BANGUNAN 3.26% 48.19% 44.93% JULAI 08’ 0.03% 54.53% 54.49% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
35. KEMAJUAN KERJA FIZIKAL KUARTERS KELAS ‘C & D’ BANGUNAN 18.48% 60.34% 41.86% JULAI 08’ 20.56% 65.91% 45.34% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
37. KEMAJUAN KERJA FIZIKAL KUARTERS KELAS ‘F’ (1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT) BANGUNAN 16.55% 57.82% 41.27% JULAI 08’ 22.74% 68.24% 45.50% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
40. KEMAJUAN KERJA FIZIKAL KUARTERS KELAS ‘G’ (1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT) BANGUNAN 25.92% 66.26% 40.34% JULAI 08’ 33.28% 77.71% 44.42% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
45. KEMAJUAN KERJA FIZIKAL ASRAMA LELAKI ‘A & B’ BANGUNAN 10.83% 58.78% 47.96% JULAI 08’ 9.68% 62.37% 53.04% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
47. KEMAJUAN KERJA FIZIKAL ASRAMA PEREMPUAN ‘C & D’ BANGUNAN 23.25% 60.89% 37.65% JULAI 08’ 24.48% 69.77% 45.29% OGOS 08’ AHEAD / DELAY ACTUAL PLANNED MONTH
58. MECHANICAL SYSTEM 10.39% 10.39% 0.00% Compressed Air 0.00% 0.00% 0.00% Process Cooling System -18.53% 3.32% 21.85% Plumbing & Sanitary 2.59% 12.01% 9.43% Fire Proc. Services 36.68% 37.25% 0.57% Air Conditioning System AHEAD / DELAY ACTUAL PLANNED DES
59. ELECTRICAL & ICT INSTALLATION -1.30% 32.38% 33.68% Lightning Protec System 6.30% 6.69% 0.39% Public Address System 25.48% 25.90% 0.42% SMATV System 16.90% 16.90% 0.00% Security, Int Alarm & CCTV 59.09% 59.09% 0.00% External Lighting 0.12% 0.12% 0.00% Audio Visual System 80.00% 80.00% 0.00% External Telephone 7.78% 7.96% 0.18% Submain Cabling 48.11% 49.69% 1.57% Small Power & Lighting AHEAD / DELAY ACTUAL PLANNED DES