SlideShare a Scribd company logo
1 of 31
Download to read offline
ni.com
Greg Crouch
Selection and Economics of Test Fixtures
and Test Interconnect
Circuit Check, Inc.
Director of Engineering Services Business Development
greg.crouch@circuitcheck.com
Scrap and failed good boards costs money.
Source: Teradyne
Visual
Inspection
In-Circuit
Test
Functional
Test
Rework Rework
A lot of variables that must align in a production process
Major variables to cost of test
– Programming Cost
– Equipment Cost
– Fixture Cost
– Maintenance Cost
– Test operators Cost
– Scrap Cost
– Re-test (false rejects) Cost
– Repair & Diagnostics Cost
– Field Return Cost
Source: Circuit Check; S. Scheiber ISBN:0-9656161-0-X
Simple case example: How to loose $54,000 fast.
Supplier build quantity of 1000 boards, and a first pass yield at 75%.
Visual
Inspection
In-Circuit
Test
Functional
Test
Rework Rework
Quoted at
beginning of
project plan
Actual
test
time
vs
Visual
Inspection
In-Circuit
Test
Functional
Test
Rework
10 min
4.2 loops actual
9.2 min actual
Ave of 3.2
extra
loops
Rework
Quoted at
beginning of
project plan
Actual
test
time
vs
7 min of re-testing
32 min of rework
7 min/brd x $250/hr (250/60=$4.16/min) = $ 29.12 / brd
32 min/brd x $75/hr (75/60=$1.25/min) = $40.00 / brd
Total: $69.12 / brd
250 brds x $49.12 / brd = $17,280.00
9.2 min – 2.2 min =
1000 boards, and a first pass yield of 75%
Line / Tester time
Technician Time
2.2 min quoted
Visual
Inspection
In-Circuit
Test
Functional
Test
Rework
82.2 min quoted
1.57 loops actual
129.1 min actual
Ave 0.57
extra loops
Rework
25.6 min
Quoted at
beginning of
project plan
Actual
test
time
vs
46.9 min of re-testing
~25.6 min of rework
46.9 min/brd x $150/hr (150/60=$2.50/min) = $ 117.25 / brd
25.6 min/brd x $75/hr (75/60=$1.25/min) = $ 32.00 / brd
Total: $ 149.25 / brd
250 brds x $149.25 / brd = $ 37,312.50
129.1 min – 82.2 min =
1000 boards, and a first pass yield of 75%
Line / Tester Time
Technician Time
Visual
Inspection
In-Circuit
Test
Functional
Test
Rework
10 min
12 min
quoted
1 Loop actual
12 min actual
2.2 min quoted
4.2 loops actual
9.2 min actual
82.2 min quoted
1.57 loops actual
129.1 min actual
3.2 extra
loops
0.57 extra
loops
Rework
25.6 min~ 70 min
Manual
labor
Quoted at
beginning of
project plan
Actual
test
time
vs
Line time quoted to run 1000 boards: 2.2 min/brd x 1000 brd = 36.6 hrs
7 min/brd x 250 brd = 29 hrs
29 hrs x $250 / hr = $ 7250.00
Additional time for 250 reworked boards
Key point: a lot more manual labor cost going into each board manufactured than you expect.
Lost Productivity
Missed opportunity from retesting boards (Un-utilized Line time)
Additional Impacts …
Testing DUTs more than once
 Re-testing products induces additional wear and tear on fixture
components (tooling pins, test probes, etc.) and the tester.
 Re-testing negatively impacts run and through-put rates.
Costs not calculated
 Damaged boards, un-repairable boards
 Late shipments, expedited shipping
 Field failures, RMA’s
What was the cause for the poor yield?
Things to think about that drive cost of test
 ATE architecture that can not last the life-cycle of the product and be updated and
maintained easily.
 Poor DUT to instrument interconnect from mass interconnect or wiring
 Poor fixturing causing test probe stress on the DUT during test.
 Not keeping up with the disruptions within the industry forcing new measurement
modalities.
Simplify as much as possible
 Test rack wiring
 Maintenance accessibility
Things to think about..
Test rack layout can reduce maintenance costs
Minimize hand made custom cabling.
Things to think about..
Test rack layout can reduce maintenance costs
Cables between PXI and
receiver modules
PCB or hard-wired interface between
PXI and receiver modules
Things to think about..
Test rack layout can reduce maintenance costs
Video
Things to think about..
Test rack layout can reduce maintenance costs
Fixture to DUT Registration
 Repeatable electrical and mechanical contact to
the DUT is essential for accurate measurements.
 .018 - .025 diameter test pads on boards make it is
easy to miss a target
 One missed contact and the product is destined to
false failure, false pass, and excess processing.
 PXI system does not get the correct measurement.
CL
CL
Probe center line centered
on test point center
Probe center line skewed
off test point center
Things to think about..
Poor probe-based fixturing can increase test costs
 Increase use of "socket-less" style probes
 Top-side guided probe technology mandatory
Probe Plate
Spacer Plate
Termination Plate
Probe
Termination
.100 - .075
Spacing
.039
Spacing
.050
Spacing
X-Probe Technology
.031
Spacing
Video
Things to think about..
Poor probe-based fixturing can increase test costs
 Multiple voltage levels per IC
 Easier to expose pins to electrical over-stress
 Voltage glitches exceed max spec ratings
 Damage from ‘over-driving’
 I/O logic levels differentiated by milli-volts
 Voltage instability can trigger unwanted logic
transitions
Source of unstable
tests & high false
fails
Source of device
stress and potential
damage
Things to think about..
Poor probe-based fixturing can increase test costs
video
Elevated Strain around BGA
ranges from 975 to 1783 µs
Things to think about..
Stress can causing unknown damage to the DUT
• Pushdown finger location and probe count have a dramatic affect on quality.
• How many probes equal 450 me on a typical BGA for a 0.092” thick board?
• 134 8.0 oz. probes,
• 261 4.1 oz. probes,
• 510 2.1 oz. probes
FEA on Fixture Strain to DUT
Elevated Strain around BGA
ranges from 482 to 710 µs
FEA Output – Strain after fixture modification
Elevated strain reduced to
acceptable levels of 92 to 202µs.
Strains were reduced across the board by
doubling the number of pushdown fingers.
 Through connector test i.e. how to access and what can be accessed
 Interconnect and fixtures that allow access through multitude connector types.
 Federal or industry specific regulations
 Test repeatability
 Mechatronics
 Blend of mechanical engineering, electrical engineering, computer control and information
technology.
 Ergonomics / reducing repetitive motion
 Drawer style fixtures, pneumatic operation, rotary fixtures
 Fixturing within RF chambers
 Many challenges come up with regard to product size and chamber size as well as metal content in
the fixtures.
 High-mix products
 Drop-in fixtuing adapters to leverage existing mechanics or automation
Disruptions within the industry; forcing new measurement methods
Through Connector/Side Access Fixturing
Positive connector alignment via floating
block assemblies.
Video
Test Repeatability
Product nest is
adjustable within fixture
allowing for variations in
part assembly.
Product nest is
interchangeable for
product variations
Mechatronics
Medical Automotive
Video
Multi-Cavities designed for rapid
loading & unloading
Drawer Load/unload
Rotating cavity with
Light Curtain safety
interlock
Multiple DUT load
with gravity feed
and auto discharge
Ergonomics / reducing repetitive motion
Video
Modular Replaceable Fixture
Four DUT drawer style fixture.
Complete fixture removable from base
ATE using mass interconnect.
Integrated Fixture with Drop-in
Top-plate of base ATE designed
as an integrated fixture. Uses
product specific drop-in plates.
Ergonomics / reducing repetitive motion
video
Ergonomics / reducing repetitive motion
 The more a product is handled, the
more likely it is to be damaged.
Extra handling caused
capacitor
damage
Rotary based fixturing
 High-volume and high-mix products
 Mission critical operations that must be quality assured and checked automatically
 Production rate increased throughput through concurrency
 Automated handling between manufacturing process steps
video
Full automation of DUT
connectivity inside RF FixtureModular DUT connectivity inside RF Fixture
Fixturing within RF chambers
video
High-mix products
Modular “drop-in’
adapters in addition to
mass interconnect.
Interchangeable PCBA adapters within the fixture help
with system reuse in higher product mix applications.
600 video
1000 Video
High-mix products
Line automation with quick change adapters video
Copyright © Circuit Check, Inc.
Additional Resources:
International Electronics Manufacturing Initiative (iNEMI
http://community.inemi.org/
Search for:
Manufacturing Test Strategy Cost Model
Test Strategy Project
Contacts:
Speaker:
Greg Crouch, greg.crouch@circuitcheck.com
Local Field Engineer from Circuit Check:
https://www.circuitcheck.com/index.php/about-us/global-offices

More Related Content

What's hot

Counterfeit Detection Using X-Ray Image as a Fingerprint
Counterfeit Detection Using X-Ray Image as a FingerprintCounterfeit Detection Using X-Ray Image as a Fingerprint
Counterfeit Detection Using X-Ray Image as a FingerprintBill Cardoso
 
Virtual Pcb Fjelstad With Audio
Virtual Pcb   Fjelstad With AudioVirtual Pcb   Fjelstad With Audio
Virtual Pcb Fjelstad With Audiobendueker
 
Reducing Head in Pillow Defects
Reducing Head in Pillow DefectsReducing Head in Pillow Defects
Reducing Head in Pillow DefectsAlpha
 
Effective design and management of LEV systems
Effective design and management of LEV systemsEffective design and management of LEV systems
Effective design and management of LEV systemsMike Slater
 
Fisher-Barton Materials Lab Brochure
Fisher-Barton Materials Lab BrochureFisher-Barton Materials Lab Brochure
Fisher-Barton Materials Lab Brochurefisherbarton
 
411_en_LW_Autoline_400
411_en_LW_Autoline_400411_en_LW_Autoline_400
411_en_LW_Autoline_400Eric Andersson
 
IEEE Semiconductor Wafer Test Workshop SWTW 2014 - International Technology R...
IEEE Semiconductor Wafer Test Workshop SWTW 2014 - International Technology R...IEEE Semiconductor Wafer Test Workshop SWTW 2014 - International Technology R...
IEEE Semiconductor Wafer Test Workshop SWTW 2014 - International Technology R...Ira Feldman
 
How X-ray Technology is Improving the Electronics Assembly Process
How X-ray Technology is Improving the Electronics Assembly ProcessHow X-ray Technology is Improving the Electronics Assembly Process
How X-ray Technology is Improving the Electronics Assembly ProcessBill Cardoso
 
LEV - eExtracting best practice
LEV - eExtracting best practiceLEV - eExtracting best practice
LEV - eExtracting best practiceAdrian Sims
 
Laser Depanelization of PCBs
Laser Depanelization of PCBs Laser Depanelization of PCBs
Laser Depanelization of PCBs Bob Wettermann
 
Scaffold Testing BIC 09-11-01
Scaffold Testing BIC 09-11-01Scaffold Testing BIC 09-11-01
Scaffold Testing BIC 09-11-01ffrietsch
 
Why should you make tooling with 3D printing?
Why should you make tooling with 3D printing?Why should you make tooling with 3D printing?
Why should you make tooling with 3D printing?Design World
 
Stratasys Application Brief - Oreck
Stratasys Application Brief - OreckStratasys Application Brief - Oreck
Stratasys Application Brief - OreckSUE BROWN
 

What's hot (19)

Counterfeit Detection Using X-Ray Image as a Fingerprint
Counterfeit Detection Using X-Ray Image as a FingerprintCounterfeit Detection Using X-Ray Image as a Fingerprint
Counterfeit Detection Using X-Ray Image as a Fingerprint
 
Virtual Pcb Fjelstad With Audio
Virtual Pcb   Fjelstad With AudioVirtual Pcb   Fjelstad With Audio
Virtual Pcb Fjelstad With Audio
 
Reducing Head in Pillow Defects
Reducing Head in Pillow DefectsReducing Head in Pillow Defects
Reducing Head in Pillow Defects
 
Effective design and management of LEV systems
Effective design and management of LEV systemsEffective design and management of LEV systems
Effective design and management of LEV systems
 
5 tendon scan_ipc_flyer
5 tendon scan_ipc_flyer5 tendon scan_ipc_flyer
5 tendon scan_ipc_flyer
 
Fisher-Barton Materials Lab Brochure
Fisher-Barton Materials Lab BrochureFisher-Barton Materials Lab Brochure
Fisher-Barton Materials Lab Brochure
 
411_en_LW_Autoline_400
411_en_LW_Autoline_400411_en_LW_Autoline_400
411_en_LW_Autoline_400
 
TeamCapabilitiesBro
TeamCapabilitiesBroTeamCapabilitiesBro
TeamCapabilitiesBro
 
IEEE Semiconductor Wafer Test Workshop SWTW 2014 - International Technology R...
IEEE Semiconductor Wafer Test Workshop SWTW 2014 - International Technology R...IEEE Semiconductor Wafer Test Workshop SWTW 2014 - International Technology R...
IEEE Semiconductor Wafer Test Workshop SWTW 2014 - International Technology R...
 
How X-ray Technology is Improving the Electronics Assembly Process
How X-ray Technology is Improving the Electronics Assembly ProcessHow X-ray Technology is Improving the Electronics Assembly Process
How X-ray Technology is Improving the Electronics Assembly Process
 
CS001
CS001CS001
CS001
 
BE Final - PPT
BE Final - PPTBE Final - PPT
BE Final - PPT
 
LEV - eExtracting best practice
LEV - eExtracting best practiceLEV - eExtracting best practice
LEV - eExtracting best practice
 
Cacade Microtech Investors Presentation
Cacade Microtech Investors PresentationCacade Microtech Investors Presentation
Cacade Microtech Investors Presentation
 
Laser Depanelization of PCBs
Laser Depanelization of PCBs Laser Depanelization of PCBs
Laser Depanelization of PCBs
 
IBC brochure 2015
IBC brochure 2015IBC brochure 2015
IBC brochure 2015
 
Scaffold Testing BIC 09-11-01
Scaffold Testing BIC 09-11-01Scaffold Testing BIC 09-11-01
Scaffold Testing BIC 09-11-01
 
Why should you make tooling with 3D printing?
Why should you make tooling with 3D printing?Why should you make tooling with 3D printing?
Why should you make tooling with 3D printing?
 
Stratasys Application Brief - Oreck
Stratasys Application Brief - OreckStratasys Application Brief - Oreck
Stratasys Application Brief - Oreck
 

Similar to Selection and Economics for Test Fixtures and Test Interconnect

EME 185 Poster
EME 185 PosterEME 185 Poster
EME 185 Postertonygom
 
Physics of Failure Electronics Reliability Assurance Software
Physics of Failure Electronics Reliability Assurance SoftwarePhysics of Failure Electronics Reliability Assurance Software
Physics of Failure Electronics Reliability Assurance SoftwareCheryl Tulkoff
 
Maintenance and Test Equipment Cyber Security
Maintenance and Test Equipment Cyber Security Maintenance and Test Equipment Cyber Security
Maintenance and Test Equipment Cyber Security Michael Toecker
 
Wuderlich Malec Engineering - Modular Construction
Wuderlich Malec Engineering - Modular ConstructionWuderlich Malec Engineering - Modular Construction
Wuderlich Malec Engineering - Modular ConstructionJoel Gil
 
Extending the Life of Existing Switchgear
Extending the Life of Existing SwitchgearExtending the Life of Existing Switchgear
Extending the Life of Existing SwitchgearSchneider Electric
 
cellular automata as a test pattern generator and output response compactor f...
cellular automata as a test pattern generator and output response compactor f...cellular automata as a test pattern generator and output response compactor f...
cellular automata as a test pattern generator and output response compactor f...Shiva Narayan Reddy
 
IPC 7711/7721 Revision B Rework, Modification & Repair of Electronic Assemblies
IPC 7711/7721 Revision B Rework, Modification & Repair of Electronic AssembliesIPC 7711/7721 Revision B Rework, Modification & Repair of Electronic Assemblies
IPC 7711/7721 Revision B Rework, Modification & Repair of Electronic Assembliesimagination
 
2013 Q A Presentation (2) (2)
2013 Q A Presentation (2) (2)2013 Q A Presentation (2) (2)
2013 Q A Presentation (2) (2)MICHAEL MORGAN
 
CV Arif Nusyirwan - 20150510
CV Arif Nusyirwan - 20150510CV Arif Nusyirwan - 20150510
CV Arif Nusyirwan - 20150510Arif Nusyirwan
 
3 test economic_test_equipments_yield
3 test economic_test_equipments_yield3 test economic_test_equipments_yield
3 test economic_test_equipments_yieldUsha Mehta
 
Enhancing & Predicting Auto Reliability Using Physics of Failure Software Mod...
Enhancing & Predicting Auto Reliability Using Physics of Failure Software Mod...Enhancing & Predicting Auto Reliability Using Physics of Failure Software Mod...
Enhancing & Predicting Auto Reliability Using Physics of Failure Software Mod...Cheryl Tulkoff
 
Amts Presentation
Amts PresentationAmts Presentation
Amts Presentationguest03d3e3
 
PCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdf
PCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdfPCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdf
PCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdfCynthia HitechPCB
 
Scalable sampling solutions for in-process particle size monitoring
Scalable sampling solutions for in-process particle size monitoringScalable sampling solutions for in-process particle size monitoring
Scalable sampling solutions for in-process particle size monitoringXoptix
 
Controlling interests editors
Controlling interests editorsControlling interests editors
Controlling interests editorseldhoev
 

Similar to Selection and Economics for Test Fixtures and Test Interconnect (20)

EME 185 Poster
EME 185 PosterEME 185 Poster
EME 185 Poster
 
Thermal Techniques Brochure
Thermal Techniques BrochureThermal Techniques Brochure
Thermal Techniques Brochure
 
Physics of Failure Electronics Reliability Assurance Software
Physics of Failure Electronics Reliability Assurance SoftwarePhysics of Failure Electronics Reliability Assurance Software
Physics of Failure Electronics Reliability Assurance Software
 
Maintenance and Test Equipment Cyber Security
Maintenance and Test Equipment Cyber Security Maintenance and Test Equipment Cyber Security
Maintenance and Test Equipment Cyber Security
 
Wuderlich Malec Engineering - Modular Construction
Wuderlich Malec Engineering - Modular ConstructionWuderlich Malec Engineering - Modular Construction
Wuderlich Malec Engineering - Modular Construction
 
Vlsi testing
Vlsi testingVlsi testing
Vlsi testing
 
Extending the Life of Existing Switchgear
Extending the Life of Existing SwitchgearExtending the Life of Existing Switchgear
Extending the Life of Existing Switchgear
 
cellular automata as a test pattern generator and output response compactor f...
cellular automata as a test pattern generator and output response compactor f...cellular automata as a test pattern generator and output response compactor f...
cellular automata as a test pattern generator and output response compactor f...
 
VLSI testing and analysis
VLSI testing and analysisVLSI testing and analysis
VLSI testing and analysis
 
GE Inspection: Industrial Process Control with Computed Tomography (CT)
GE Inspection: Industrial Process Control with Computed Tomography (CT)GE Inspection: Industrial Process Control with Computed Tomography (CT)
GE Inspection: Industrial Process Control with Computed Tomography (CT)
 
IPC 7711/7721 Revision B Rework, Modification & Repair of Electronic Assemblies
IPC 7711/7721 Revision B Rework, Modification & Repair of Electronic AssembliesIPC 7711/7721 Revision B Rework, Modification & Repair of Electronic Assemblies
IPC 7711/7721 Revision B Rework, Modification & Repair of Electronic Assemblies
 
2013 Q A Presentation (2) (2)
2013 Q A Presentation (2) (2)2013 Q A Presentation (2) (2)
2013 Q A Presentation (2) (2)
 
resumelrs_jan_2017
resumelrs_jan_2017resumelrs_jan_2017
resumelrs_jan_2017
 
CV Arif Nusyirwan - 20150510
CV Arif Nusyirwan - 20150510CV Arif Nusyirwan - 20150510
CV Arif Nusyirwan - 20150510
 
3 test economic_test_equipments_yield
3 test economic_test_equipments_yield3 test economic_test_equipments_yield
3 test economic_test_equipments_yield
 
Enhancing & Predicting Auto Reliability Using Physics of Failure Software Mod...
Enhancing & Predicting Auto Reliability Using Physics of Failure Software Mod...Enhancing & Predicting Auto Reliability Using Physics of Failure Software Mod...
Enhancing & Predicting Auto Reliability Using Physics of Failure Software Mod...
 
Amts Presentation
Amts PresentationAmts Presentation
Amts Presentation
 
PCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdf
PCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdfPCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdf
PCB Assembly Testing and Inspection, from Hitech Circuits Co., Limited.pdf
 
Scalable sampling solutions for in-process particle size monitoring
Scalable sampling solutions for in-process particle size monitoringScalable sampling solutions for in-process particle size monitoring
Scalable sampling solutions for in-process particle size monitoring
 
Controlling interests editors
Controlling interests editorsControlling interests editors
Controlling interests editors
 

Recently uploaded

Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectssuserb6619e
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
Crushers to screens in aggregate production
Crushers to screens in aggregate productionCrushers to screens in aggregate production
Crushers to screens in aggregate productionChinnuNinan
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectErbil Polytechnic University
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 

Recently uploaded (20)

Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
Crushers to screens in aggregate production
Crushers to screens in aggregate productionCrushers to screens in aggregate production
Crushers to screens in aggregate production
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction Project
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 

Selection and Economics for Test Fixtures and Test Interconnect

  • 1.
  • 2. ni.com Greg Crouch Selection and Economics of Test Fixtures and Test Interconnect Circuit Check, Inc. Director of Engineering Services Business Development greg.crouch@circuitcheck.com
  • 3. Scrap and failed good boards costs money. Source: Teradyne
  • 4. Visual Inspection In-Circuit Test Functional Test Rework Rework A lot of variables that must align in a production process Major variables to cost of test – Programming Cost – Equipment Cost – Fixture Cost – Maintenance Cost – Test operators Cost – Scrap Cost – Re-test (false rejects) Cost – Repair & Diagnostics Cost – Field Return Cost Source: Circuit Check; S. Scheiber ISBN:0-9656161-0-X
  • 5. Simple case example: How to loose $54,000 fast. Supplier build quantity of 1000 boards, and a first pass yield at 75%. Visual Inspection In-Circuit Test Functional Test Rework Rework Quoted at beginning of project plan Actual test time vs
  • 6. Visual Inspection In-Circuit Test Functional Test Rework 10 min 4.2 loops actual 9.2 min actual Ave of 3.2 extra loops Rework Quoted at beginning of project plan Actual test time vs 7 min of re-testing 32 min of rework 7 min/brd x $250/hr (250/60=$4.16/min) = $ 29.12 / brd 32 min/brd x $75/hr (75/60=$1.25/min) = $40.00 / brd Total: $69.12 / brd 250 brds x $49.12 / brd = $17,280.00 9.2 min – 2.2 min = 1000 boards, and a first pass yield of 75% Line / Tester time Technician Time 2.2 min quoted
  • 7. Visual Inspection In-Circuit Test Functional Test Rework 82.2 min quoted 1.57 loops actual 129.1 min actual Ave 0.57 extra loops Rework 25.6 min Quoted at beginning of project plan Actual test time vs 46.9 min of re-testing ~25.6 min of rework 46.9 min/brd x $150/hr (150/60=$2.50/min) = $ 117.25 / brd 25.6 min/brd x $75/hr (75/60=$1.25/min) = $ 32.00 / brd Total: $ 149.25 / brd 250 brds x $149.25 / brd = $ 37,312.50 129.1 min – 82.2 min = 1000 boards, and a first pass yield of 75% Line / Tester Time Technician Time
  • 8. Visual Inspection In-Circuit Test Functional Test Rework 10 min 12 min quoted 1 Loop actual 12 min actual 2.2 min quoted 4.2 loops actual 9.2 min actual 82.2 min quoted 1.57 loops actual 129.1 min actual 3.2 extra loops 0.57 extra loops Rework 25.6 min~ 70 min Manual labor Quoted at beginning of project plan Actual test time vs Line time quoted to run 1000 boards: 2.2 min/brd x 1000 brd = 36.6 hrs 7 min/brd x 250 brd = 29 hrs 29 hrs x $250 / hr = $ 7250.00 Additional time for 250 reworked boards Key point: a lot more manual labor cost going into each board manufactured than you expect. Lost Productivity Missed opportunity from retesting boards (Un-utilized Line time)
  • 9. Additional Impacts … Testing DUTs more than once  Re-testing products induces additional wear and tear on fixture components (tooling pins, test probes, etc.) and the tester.  Re-testing negatively impacts run and through-put rates. Costs not calculated  Damaged boards, un-repairable boards  Late shipments, expedited shipping  Field failures, RMA’s
  • 10. What was the cause for the poor yield? Things to think about that drive cost of test  ATE architecture that can not last the life-cycle of the product and be updated and maintained easily.  Poor DUT to instrument interconnect from mass interconnect or wiring  Poor fixturing causing test probe stress on the DUT during test.  Not keeping up with the disruptions within the industry forcing new measurement modalities.
  • 11. Simplify as much as possible  Test rack wiring  Maintenance accessibility Things to think about.. Test rack layout can reduce maintenance costs
  • 12. Minimize hand made custom cabling. Things to think about.. Test rack layout can reduce maintenance costs
  • 13. Cables between PXI and receiver modules PCB or hard-wired interface between PXI and receiver modules Things to think about.. Test rack layout can reduce maintenance costs Video
  • 14. Things to think about.. Test rack layout can reduce maintenance costs
  • 15. Fixture to DUT Registration  Repeatable electrical and mechanical contact to the DUT is essential for accurate measurements.  .018 - .025 diameter test pads on boards make it is easy to miss a target  One missed contact and the product is destined to false failure, false pass, and excess processing.  PXI system does not get the correct measurement. CL CL Probe center line centered on test point center Probe center line skewed off test point center Things to think about.. Poor probe-based fixturing can increase test costs
  • 16.  Increase use of "socket-less" style probes  Top-side guided probe technology mandatory Probe Plate Spacer Plate Termination Plate Probe Termination .100 - .075 Spacing .039 Spacing .050 Spacing X-Probe Technology .031 Spacing Video Things to think about.. Poor probe-based fixturing can increase test costs
  • 17.  Multiple voltage levels per IC  Easier to expose pins to electrical over-stress  Voltage glitches exceed max spec ratings  Damage from ‘over-driving’  I/O logic levels differentiated by milli-volts  Voltage instability can trigger unwanted logic transitions Source of unstable tests & high false fails Source of device stress and potential damage Things to think about.. Poor probe-based fixturing can increase test costs video
  • 18. Elevated Strain around BGA ranges from 975 to 1783 µs Things to think about.. Stress can causing unknown damage to the DUT • Pushdown finger location and probe count have a dramatic affect on quality. • How many probes equal 450 me on a typical BGA for a 0.092” thick board? • 134 8.0 oz. probes, • 261 4.1 oz. probes, • 510 2.1 oz. probes
  • 19. FEA on Fixture Strain to DUT Elevated Strain around BGA ranges from 482 to 710 µs
  • 20. FEA Output – Strain after fixture modification Elevated strain reduced to acceptable levels of 92 to 202µs. Strains were reduced across the board by doubling the number of pushdown fingers.
  • 21.  Through connector test i.e. how to access and what can be accessed  Interconnect and fixtures that allow access through multitude connector types.  Federal or industry specific regulations  Test repeatability  Mechatronics  Blend of mechanical engineering, electrical engineering, computer control and information technology.  Ergonomics / reducing repetitive motion  Drawer style fixtures, pneumatic operation, rotary fixtures  Fixturing within RF chambers  Many challenges come up with regard to product size and chamber size as well as metal content in the fixtures.  High-mix products  Drop-in fixtuing adapters to leverage existing mechanics or automation Disruptions within the industry; forcing new measurement methods
  • 22. Through Connector/Side Access Fixturing Positive connector alignment via floating block assemblies. Video
  • 23. Test Repeatability Product nest is adjustable within fixture allowing for variations in part assembly. Product nest is interchangeable for product variations
  • 25. Multi-Cavities designed for rapid loading & unloading Drawer Load/unload Rotating cavity with Light Curtain safety interlock Multiple DUT load with gravity feed and auto discharge Ergonomics / reducing repetitive motion Video
  • 26. Modular Replaceable Fixture Four DUT drawer style fixture. Complete fixture removable from base ATE using mass interconnect. Integrated Fixture with Drop-in Top-plate of base ATE designed as an integrated fixture. Uses product specific drop-in plates. Ergonomics / reducing repetitive motion video
  • 27. Ergonomics / reducing repetitive motion  The more a product is handled, the more likely it is to be damaged. Extra handling caused capacitor damage Rotary based fixturing  High-volume and high-mix products  Mission critical operations that must be quality assured and checked automatically  Production rate increased throughput through concurrency  Automated handling between manufacturing process steps video
  • 28. Full automation of DUT connectivity inside RF FixtureModular DUT connectivity inside RF Fixture Fixturing within RF chambers video
  • 29. High-mix products Modular “drop-in’ adapters in addition to mass interconnect. Interchangeable PCBA adapters within the fixture help with system reuse in higher product mix applications. 600 video 1000 Video
  • 30. High-mix products Line automation with quick change adapters video
  • 31. Copyright © Circuit Check, Inc. Additional Resources: International Electronics Manufacturing Initiative (iNEMI http://community.inemi.org/ Search for: Manufacturing Test Strategy Cost Model Test Strategy Project Contacts: Speaker: Greg Crouch, greg.crouch@circuitcheck.com Local Field Engineer from Circuit Check: https://www.circuitcheck.com/index.php/about-us/global-offices