Kanban team simulation

Download to read offline

A simulation of a Kanban team for an article about TOC in Software Startups: https://medium.com/@flpvsk/systems-thinking-in-management-c3ed049e8d91

Related Books

Free with a 30 day trial from Scribd

See all

Related Audiobooks

Free with a 30 day trial from Scribd

See all
  • Be the first to like this

Kanban team simulation

  1. 1. Kanban team simulation. Stages: 1. PO in progress 2. DEV waiting 3. DEV in progress 4. QA waiting 5. QA in progress 6. QA waiting RC 7. QA RC 8. DONE
  2. 2. WIP: 0 Done: 0 Lead times: (no data) Now: Limit: 0 7 Now: Limit: 0 10 Day: 0
  3. 3. WIP: 3 Done: 0 Lead times: (no data) Now: Limit: 3 7 Now: Limit: 0 10 Day: 1
  4. 4. WIP: 6 Done: 0 Lead times: (no data) Now: Limit: 6 7 Now: Limit: 3 10 Day: 2
  5. 5. WIP: 7 Done: 0 Lead times: (no data) Now: Limit: 7 7 Now: Limit: 4 10 Day: 3
  6. 6. WIP: 10 Done: 0 Lead times: (no data) Now: Limit: 7 7 Now: Limit: 6 10 Day: 4
  7. 7. WIP: 11 Done: 0 Lead times: (no data) Now: Limit: 7 7 Now: Limit: 7 10 Day: 5
  8. 8. WIP: 13 Done: 0 Lead times: (no data) Now: Limit: 7 7 Now: Limit: 10 10 Day: 6
  9. 9. WIP: 14 Done: 0 Lead times: (no data) Now: Limit: 7 7 Now: Limit: 10 10 Day: 7
  10. 10. ! WIP: 11 Done: 6 Lead times: 3x6d, 3x7d Now: Limit: 7 7 Now: Limit: 8 10 Day: 8
  11. 11. WIP: 11 Done: 6 Lead times: 3x6d, 3x7d Now: Limit: 7 7 Now: Limit: 8 10 Day: 9
  12. 12. WIP: 14 Done: 6 Lead times: 3x6d, 3x7d Now: Limit: 6 7 Now: Limit: 10 10 Day: 10
  13. 13. WIP: 15 Done: 6 Lead times: 3x6d, 3x7d Now: Limit: 7 7 Now: Limit: 10 10 Day: 11
  14. 14. ! WIP: 11 Done: 12 Lead times: 4x6d, 4x7d, 3x8d, 1x9d Now: Limit: 7 7 Now: Limit: 8 10 Day: 12
  15. 15. WIP: 11 Done: 12 Lead times: 4x6d, 4x7d, 3x8d, 1x9d Now: Limit: 7 7 Now: Limit: 8 10 Day: 13
  16. 16. WIP: 14 Done: 12 Lead times: 4x6d, 4x7d, 3x8d, 1x9d Now: Limit: 6 7 Now: Limit: 10 10 Day: 14
  17. 17. WIP: 15 Done: 12 Lead times: 4x6d, 4x7d, 3x8d, 1x9d Now: Limit: 7 7 Now: Limit: 10 10 Day: 15
  18. 18. WIP: 11 Done: 18 Lead times: 5x6d, 4x7d, 6x8d, 1x9d, 1x10d Now: Limit: 7 7 Now: Limit: 8 10 Day: 16 !
  19. 19. WIP: 11 Done: 18 Lead times: 5x6d, 4x7d, 6x8d, 1x9d, 1x10d Now: Limit: 7 7 Now: Limit: 8 10 Day: 17
  20. 20. WIP: 14 Done: 18 Lead times: 5x6d, 4x7d, 6x8d, 1x9d, 1x10d Now: Limit: 7 7 Now: Limit: 10 10 Day: 18
  21. 21. WIP: 15 Done: 18 Lead times: 5x6d, 4x7d, 6x8d, 1x9d, 1x10d Now: Limit: 7 7 Now: Limit: 10 10 Day: 19
  22. 22. Now: Limit: 7 7 Now: Limit: 8 10 Day: 20 WIP: 11Done: 24 Done: 24 Lead times: 6x6d, 4x7d, 8x8d, 2x9d, 3x10d !
  23. 23. Kanban team simulation. Results after 20 days. Work in Progress: 11 tasks Done: 24 tasks Work was released on: Day 8, Day 12, Day 16, Day 20 Lead times: 1st release: 3 x 6 days, 3 x 7 days 2nd release: 1 x 6 days, 1 x 7 days, 3 x 8 days, 1 x 9 days 3rd release: 1 x 6 days, 3 x 8 days, 1 x 9 days, 1 x 10 days 4th release: 1 x 7 days, 1 x 8 days, 2 x 9 days, 2 x 10 days

A simulation of a Kanban team for an article about TOC in Software Startups: https://medium.com/@flpvsk/systems-thinking-in-management-c3ed049e8d91