The Vesper Street Shared Use project was substantially completed within budget on January 24, 2019. This project provided of a 10’ft wide asphalt shared use path approximately 2030’ft in length from the end of Vesper Street to the intersection of Leesburg Pike and the Spring Hill Metro Station. The project includes a 90’ft pedestrian bridge over Courthouse Spring Branch, storm water drainage, asphalt paving, light poles, handrails, guardrails bollards, pavement markings and related signage.

Published in: Government & Nonprofit
  • Be the first to comment

  • Be the first to like this

Vesper St. Shared Use Path

  1. 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Contract No. CN17102027 Project No. AA1400120-2013 HUNTER MILL District Tax Map No. 29-3 February 25, 2019 VESPER STREET SHARED USE PATH
  2. 2. Vesper Street Shared Use Path Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch
  3. 3. Project Details Vesper Street Shared Path Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch Description: The Vesper Street Shared Use project was substantially completed within budget on January 24, 2019. This project provided of a 10’ft wide asphalt shared use path approximately 2030’ft in length from the end of Vesper Street to the intersection of Leesburg Pike and the Spring Hill Metro Station. The project includes a 90’ft pedestrian bridge over Courthouse Spring Branch, storm water drainage, asphalt paving, light poles, handrails, guardrails bollards, pavement markings and related signage. Benefits: • Provides safe access to the Spring Hill Metro Station from the surrounding neighborhoods. Project Team: Fairfax County Department of Transportation (FCDOT) Project Manager: John Dresser Fairfax County DPWES- Utilities Design and Construction Division (UDCD) Project Engineer: Tom Cutler Fairfax County DPWES- Land Survey Branch (LSB): Chris Jenson, Greg Harper and Brian Wilson Fairfax County DPWES- Land Acquisition Division (LAD): Richard Finnell Consultant, Engineering & Inspection (CEI): Volkert, Inc.- Ben Lineberry, Will Selim Design Engineer(s): WRA – (Structural Eng.)- Tim Beavers, RDA – (Civil Eng.), Volkert Inc.– (Electrical Eng.)- Michael Glickman, Ken Powers, Hari Thacker Contractor: A & M Concrete Corporation – Brian Grover and Carlos Batista
  4. 4. Vesper Street Shared Use Path Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch Tax Map 29-3
  5. 5. Vesper Street Shared Use Path Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch Pre-Existing Conditions
  6. 6. Before After Vesper Street Shared Use Path Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch
  7. 7. Before After Vesper Street Shared Use Path Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch
  8. 8. Additional Information For additional Information, please call www.fairfaxcounty.gov/publicworks Vesper Street Shared Use Path Capital Facilities/Utilities Design and Construction Division, Stormwater Construction Branch Matthew Kaiser, Public Information Officer 703-324-8455, TTY 711 Matthew.Kaiser@fairfaxcounty.gov

×