Successfully reported this slideshow.
We use your LinkedIn profile and activity data to personalize ads and to show you more relevant ads. You can change your ad preferences anytime.

Chichester Lane Sidewalk Improvements

24 views

Published on

Chichester Lane Walkway: Day Lily Court Trail to Cherry Drive improvement included approximately 270 linear feet of a five-foot wide concrete sidewalk, curb, gutter, stormwater infrastructure and restoration.

Published in: Environment
  • Be the first to comment

  • Be the first to like this

Chichester Lane Sidewalk Improvements

  1. 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Chichester Lane Sidewalk Improvements Day Lilly Court Trail to Cherry Drive Contract No. CN17304122 Task Order No. 42 Project No. ST-000036-007 Providence District Tax Map No. 49-3, 48-4 April 15, 2019
  2. 2. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Chichester Lane Sidewalk Improvements: Day Lilly Court Trail to Cherry Drive Providence District, Tax Map No. 49-3, 48-4 Project Site N
  3. 3. Project Details Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Description: Chichester Lane Walkway: Day Lily Court Trail to Cherry Drive Project was substantially completed on March 25, 2019. The project includes approximately 270 LF of a 5 foot wide concrete sidewalk, curb, gutter, storm water infrastructure and restoration. Project Overview: • Project Delivery: Annual Contract • Contract: Unit Price Project Construction Team: • Contractor • Ashburn Contracting Corporation • Fairfax County • Department of Transportation – Alexander Tsybin • Utilities Design and Construction Division – Lisa McCorkle • Project Inspector, UDCD – Yagya Bhandari, Jim Cooper • Land Survey Branch, UDCD – Chris Jensen • Right-of-Way Agent, Land Acquisition Division- Daniel Rusu Chichester Lane Sidewalk Improvements: Day Lilly Court Trail to Cherry Drive
  4. 4. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Chichester Lane Sidewalk Improvements: Day Lilly Court to Cherry Drive
  5. 5. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Chichester Lane Sidewalk Improvements: Day Lilly Court Trail to Cherry Drive Installation of Storm Sewer Structures for Outfall
  6. 6. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Chichester Lane Sidewalk Improvements: Day Lilly Court Trail to Cherry Drive Storm Sewer Outfall
  7. 7. Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Chichester Lane Sidewalk Improvements: Day Lilly Court Trail to Cherry Drive Installation of Concrete Sidewalk
  8. 8. Before After Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Chichester Lane Sidewalk Improvements: Day Lilly Court to Cherry Drive
  9. 9. Additional Information For additional Information, please call www.fairfaxcounty.gov/publicworks Chichester Lane Walkway: Day Lily Court Trail to Cherry Drive Capital Facilities/Utilities Design and Construction Division/Transportation Construction Branch Matthew Kaiser, Public Information Officer 703-324-8455, TTY 711 Matthew.kaiser@fairfaxcounty.gov

×