Software Estimation

2,953 views

Published on

Describe what the estimation is, sources of error and how to make estimation

Published in: Technology, Business
  • Excellent stuff ! Thanks for sharing

    -Balaji OS
    http://osbalaji.blogspot.com
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here

Software Estimation

  1. 1. 1 ESTIMATION Author: Nguyen Phuc Hai Created date: 1/9/2008
  2. 2. Agenda 2 What is estimation? Reasons to make wrong estimations Fundamental estimation Techniques Estimation process of Agile Mobile Politics, Negotiation, and Problem Solving
  3. 3. What is estimation 3 Estimates, Target and Commitments Good estimation
  4. 4. Estimation 4 Estimation is a prediction of how long a project will take or how much it will cost
  5. 5. Target 5 A Target is a statement of a desirable business objective. Examples: quot;We need to have Version 2.1 ready to demonstrate at a trade show in May.quot; quot;We need to have this release stabilized in time for the holiday sales cycle.“ Businesses have important reasons to establish targets independent of software estimates. But the fact that a target is desirable or even mandatory does not necessarily mean that it is achievable.
  6. 6. Commitment 6 A commitment is a promise to deliver defined functionality at a specific level of quality by a certain date. A commitment can be the same as the estimate, or it can be more aggressive or more conservative than the estimate
  7. 7. Distinguish between estimates, targets, and commitments. 7
  8. 8. What is an estimation 8 Estimate, Target and Commitments Good estimation
  9. 9. Good estimation 9 A good estimation approach should provide estimates that are within 25% of the actual results 75% of the time. However, accurate estimation results cannot be accomplished through estimation practices alone. They must also be supported by effective project control.
  10. 10. Estimation and Project Control 10
  11. 11. Estimation Track Record 11
  12. 12. Project Outcomes by Project Size 12
  13. 13. Estimation and Project Control 13 The criteria for a quot;goodquot; estimate cannot be based on its predictive capability, which is impossible to assess, but on the estimate's ability to support project success
  14. 14. Reasons to make incorrect 14 estimation
  15. 15. Source of estimation Uncertainly 15
  16. 16. Cone of Uncertainly 16
  17. 17. The cone doesn’t narrow itself 17 Don't assume that the Cone of Uncertainty will narrow itself. You must force the Cone to narrow by removing sources of variability from your project.
  18. 18. The cone doesn’t narrow itself 18 Estimation Error by Software-Development Activity
  19. 19. The cone doesn’t narrow itself 19 Relationship Between the Cone of Uncertainty and Commitment Meaningful commitments are not possible in the early, wide part of the Cone. Effective organizations delay their commitments until they have done the work to force the Cone to narrow. Meaningful commitments in the early-middle part of the project (about 30% of the way in) are possible and appropriate.
  20. 20. Chaotic Development Process 20
  21. 21. Common examples of project chaotic 21 Requirements that weren't investigated very well in the first place Lack of end-user involvement in requirements validation Poor designs that lead to numerous errors in the code Poor coding practices that give rise to extensive bug fixing Inexperienced personnel Incomplete or unskilled project planning Abandoning planning under pressure Developer gold-plating
  22. 22. Unstable requirements 22
  23. 23. Unstable requirements 23 If requirements cannot be stabilized, the Cone of Uncertainty can't be narrowed, and estimation variability will remain high through the end of the project. To deal with unstable requirements, consider project control strategies instead of or in addition to estimation strategies.
  24. 24. Omitted activities 24
  25. 25. Software-Development Activities Commonly Missing 25 Ramp-up time for new team members Mentoring of new team members Management coordination/manager meetings Requirements clarifications Maintaining the revision control system Review of technical documentation Coordination with team members
  26. 26. Software-Development Activities Commonly Missing 26 Technical support of existing systems during the project Maintenance work on previous systems during the project Integration work Reviewing plans, estimates, architecture, detailed designs, stage plans, code, test cases, and so on Input to user documentation and review of user documentation
  27. 27. Non-Software-Development Activities Commonly Missing 27 Vacations and Holidays Sick days Company/Department meetings Hardware and Software problems Setting up new Workstations
  28. 28. Unfounded optimism 28
  29. 29. Common optimistic issues 29 We'll be more productive on this project than we were on the last project. A lot of things went wrong on the last project. Not so many things will go wrong on this project. We started the project slowly and were climbing a steep learning curve. We learned a lot of lessons the hard way, but all the lessons we learned will allow us to finish the project much faster than we started it.
  30. 30. Common optimistic issues 30 We will recruit/staff the talents or experience to team and timeline could be reduced We have experience with that kind of project before
  31. 31. Subjectivity and Bias 31
  32. 32. Off-The-Cuff Estimates 32
  33. 33. Avoid Off-The-Cuff Estimation 33 Average error of estimates in these 24 groups of estimators for off-the-cuff estimates versus estimates that go through a group review process.
  34. 34. Unwarranted Precision 34 VS Accuracy Precision Accuracy refers to how close to the real value a number is. Precision refers merely to how exact a number is. In software estimation, this amounts to how many significant digits an estimate has. A measurement can be precise without being accurate, and it can be accurate without being precise.
  35. 35. Unwarranted Precision 35 VS High accuracy but low precision High precision but low accuracy Example Comments This project will take 395.7 days, ± 2 months Highly precise, but not accurate to the precision stated This project will take 1 year Not very precise, but could be accurate This project will require 7,214 staff hours Highly precise, but probably not accurate to the precision stated This project will require 4 staff years Not very precise, but could be accurate
  36. 36. Other sources of error 36 Unfamiliar business area Unfamiliar technology area Incorrect conversion from estimated time to project time (for example, assuming the project team will focus on the project eight hours per day, five days per week) Misunderstanding of statistical concepts (especially adding together a set of quot;best casequot; estimates or a set of quot;worst casequot; estimates) Budgeting processes that undermine effective estimation (especially those that require final budget approval in the wide part of the Cone of Uncertainty)
  37. 37. Other sources of error (cont.) 37 Having an accurate size estimate, but introducing errors when converting the size estimate to an effort estimate Having accurate size and effort estimates, but introducing errors when converting those to a schedule estimate Overstated savings from new development tools or methods Simplification of the estimate as it's reported up layers of management, fed into the budgeting process, and so on
  38. 38. Estimate Influences 38
  39. 39. Determinate factors to estimate 39 Project size Don't assume that effort scales up linearly as project size does. Effort scales up exponentially. The kind of software Personnel factors The programming language
  40. 40. Fundamental Estimation Techniques 40
  41. 41. Choosing Estimation Techniques 41 Project size Software Development Style Development Stage Accuracy Possible
  42. 42. Fundamental Estimation Techniques 42 Count, Compute, Judge • Calibration and Historical Data •
  43. 43. Applicability 43 Count Compute What's estimated Size, Features Size, Effort, Schedule, Features Size of project SML SML Development Stage Early-Late Early-Middle Iterative or sequential Both Both Accuracy possible High High
  44. 44. Count First 44 If you can count the answer directly, you should do that first. That approach produced the most accurate answer in the story. If you can't count the answer directly, you should count something else and then compute the answer by using some sort of calibration data Count if at all possible. Compute when you can't count. Use judgment alone only as a last resort.
  45. 45. What to count 45 Find something to count that's highly correlated with the size of the software you're estimating Find something to count that's available sooner rather than later in the development cycle Understand what you're counting Find something you can count with minimal effort
  46. 46. Convert Counts to Estimates Quantity to Count Historical Data Needed to Convert the Count to an Estimate Marketing requirements • Average effort hours per requirement for development • Average effort hours per requirement for independent testing • Average effort hours per requirement for documentation • Average effort hours per requirement to create engineering requirements from marketing requirements Features • Average effort hours per feature for development and/or testing Use cases • Average total effort hours per use case • Average number of use cases that can be delivered in a particular amount of calendar time Stories • Average total effort hours per story • Average number of stories that can be delivered in a particular amount of calendar time Change requests • Average development/test/documentation effort per change request (depending on variability of the change requests, the data might be decomposed into average effort per small, medium, and large change request) Function Points • Average development/test/documentation effort per Function Point • Average lines of code in the target language per Function Point Defects found • Average effort hours per defect to fix 46 • Average effort hours per defect to regression test • Average number of defects that can be corrected in a particular amount of calendar time Test cases already • Average amount of release-stage effort per test case written
  47. 47. Use Judgment Only as a Last Resort 47 Expert judgment is the least accurate means of estimation. Estimates seem to be the most accurate if they can be tied to something concrete
  48. 48. Fundamental Estimation Techniques 48 Count, Compute, Judge • Calibration and Historical Data •
  49. 49. Applicability 49 Calibration with Calibration with Calibration with Project-Specific Industry-Average Data Organizational Data Data What's Size, Effort, Schedule, Size, Effort, Schedule, Features Size, Effort, Schedule, Features estimated Features Size of project SML SML SML Development Early-Middle Early-Middle Middle-Late Stage Iterative or Both Both Both sequential Accuracy Low-Medium Medium-High High possible
  50. 50. Data to collect 50 Size (lines of code or something else you can count after the software has been released) Effort (staff months) Time (calendar months) Defects (classified by severity)
  51. 51. Improved Accuracy and Other Benefits of Historical Data 51 Accounts for Organizational Influences How complex is the software, how much documentation is required, how precedented is the application Is the project manager free to remove a problem team member from the project, or do the organization's Human Resources policies make it difficult or impossible to remove a problem employee? Is the team free to concentrate on the current project, or are team members frequently interrupted with calls to support production releases of previous projects?
  52. 52. Improved Accuracy and Other Benefits of Historical Data (Cont.) 52 Can the organization add team members to the new project as planned, or does it refuse to pull people off other projects before those projects have been completed? Does the organization support the use of effective design, construction, quality assurance, and testing practices? Can the project manager depend on team members staying until the project is complete, or does the organization have high turnover?
  53. 53. Improved Accuracy and Other Benefits of Historical Data (Cont.) 53 Avoids Subjectivity and Unfounded Optimism Use historical data as the basis for your productivity assumptions. Unlike mutual fund disclosures, your organization's past performance really is your best indicator of future performance. Reduces Estimation Politics Use historical data to help avoid politically charged estimation discussions arising from assumptions like quot;My team is below average.quot;
  54. 54. How to calibrate 54 The ultimate goal of collecting data is to convert the data to a model that you can use for estimation. Example: Our developers average X lines of code per staff month. Our team is averaging X staff hours per use case to create the use case, and Y hours per use case to construct and deliver the use case. Our testers create test cases at a rate of X hours per test case. In our environment, we average X lines of code per function point in C# and Y lines of code per function point in Python. On this project so far, defect correction work has averaged X hours per defect.
  55. 55. Using Project Data to Refine Your Estimates 55 Even if you don't have historical data from past projects, you can collect data from your current project and use that as a basis for estimating the remainder of your project. Your goal should be to switch from using organizational data or industry-average data to project data as soon as you can. The more iterative your project is, the sooner you'll be able to do this.
  56. 56. Estimation process of Agile Mobile 56
  57. 57. What is story point? 57 Story point is a random measure used by Scrum teams. This is used to measure the effort required to implement a story. Story points do give some indication of how much time was spent in a sprint. Example: At the end of a 10 day sprint a team of 4 covers 40 story points. 10 days = 10 * 8 working hours = 80 hours. = 320 total hours as there are 4 developers. That equated to 160 pairing hours. 160 divided by 40 = 4 hours pair hours per story point.
  58. 58. Agile Mobile estimation method 58 We use the story point as the unit to measure the size of features Maintain the project/product historical data (size/effort/schedule/defects) to improve the estimate precision
  59. 59. Politics, Negotiation, and Problem Solving 59
  60. 60. Attributes of Executives 60 1 Executives will always ask for what they want. 2 Executives will always probe to get what they want if they don't get it initially. 3 Executives will tend to probe until they discover your point of discomfort. 4 Executives won't always know what's possible, but they will know what would be good for the business if it were possible. 5 Executives will be assertive. That's how they got to be executives in the first place. 6 Executives will respect you when you are being assertive. In fact, they assume you will be assertive if you need to be. 7 Executives want you to operate with the organization's best interests at heart. 8 Executives will want to explore lots of variations to maximize business value. 9 Executives know things about the business, the market, and the company that you don't know, and they may prioritize your project's goals differently than you would. 10 Executives will always want visibility and commitment early (which would indeed have great business value, if it were possible).
  61. 61. Political Influences on Estimates 61 External Constraints Be aware of external influences on the target. Communicate that you understand the business requirements and their importance. Negotiating an Estimate vs. Negotiating a Commitment You can negotiate the commitment, but don't negotiate the estimate.
  62. 62. Political Influences on Estimates 62 What to Do if Your Estimate Doesn't Get Accepted Let it be Responsibility of Technical Staff to Educate Nontechnical Stakeholders Educate nontechnical stakeholders about effective software estimation practices.
  63. 63. Problem Solving and Principled Negotiation 63 Treat estimation discussions as problem solving, not negotiation. Recognize that all project stakeholders are on the same side of the table. Everyone wins, or everyone loses.
  64. 64. References 64
  65. 65. References 65 Steve McConnell, Software Estimation: Demystifying the Black Art – Microsoft Press Mike Cohn, Agile Estimating and Planning – Prentice Hall

×