Successfully reported this slideshow.
We use your LinkedIn profile and activity data to personalize ads and to show you more relevant ads. You can change your ad preferences anytime.
Bangkok MEGA Bridge Trimester 2007/ 1
Group Members <ul><li>Nuttaya  R. 4949273 </li></ul><ul><li>Nalinrat  P. 4949278 </li></ul><ul><li>Nantana  K. 4949279 </l...
Agenda <ul><li>Bangkok Mega Bridge </li></ul><ul><ul><li>Project Background </li></ul></ul><ul><ul><li>Key Stakeholders </...
 
Project Background <ul><li>On 29 th  May 2000, the project was inaugurated by His Majesty The King. </li></ul><ul><li>The ...
Project Background <ul><li>The objective of the project is  to alleviate traffic congestion  resulting from freight transp...
Project Background (Overall) <ul><li>Value:  8.7 billion Baht </li></ul><ul><li>Specifications: </li></ul><ul><ul><li>Firs...
Expected Benefits <ul><li>To ease the congestion of commercial traffic in Bangkok </li></ul><ul><li>To encourage the gover...
Project  Manager Ministry of Transport Ministry of  Finance Local Marine  Department People  (Near Site) Workers Insurance...
Owner:  Kingdom  o f   T h a i l a n d, Ministry of Transport, Dept. of Rural Roads <ul><li>Main Contractors </li></ul><ul...
VSL Thailand <ul><li>VSL’s  Scope of Work   </li></ul><ul><li>Deck lifting </li></ul><ul><li>Stay cable installation </li>...
 
VSL’s Project Objective Statement (POS) <ul><li>“ To finish  lifting  60 concrete decks,  installing   stay cables, and  p...
Project Priority Matrix Time Requirement Cost Constrained Enhanced Accepted
Major Deliverables <ul><li>Drawings/ Blueprints </li></ul><ul><li>Main spans building </li></ul><ul><ul><li>Gantry assembl...
Major Deliverables <ul><li>Stay cable installation </li></ul><ul><ul><li>Erecting tendon </li></ul></ul><ul><ul><li>Wiring...
Specifications of Deliverables <ul><li>Unit Concrete Deck </li></ul><ul><ul><li>36 metres wide </li></ul></ul><ul><ul><li>...
Major Constraints <ul><li>Water Traffic </li></ul><ul><ul><li>To avoid interfering the water traffic, VSL is allowed only ...
 
Exclusion <ul><li>Not include pavement on road </li></ul><ul><li>Not include concrete curb and handrail </li></ul><ul><li>...
Major Work Areas <ul><li>Design drawings </li></ul><ul><li>Survey work </li></ul><ul><li>Assemble gantry </li></ul><ul><li...
Work Break-down Structure (WBS)
 
Resources <ul><li>Manpower </li></ul><ul><ul><li>Project manager </li></ul></ul><ul><ul><li>Civil engineer </li></ul></ul>...
Risks Assessment <ul><li>Methods </li></ul><ul><li>Technology </li></ul><ul><li>Suppliers </li></ul><ul><li>Security & Saf...
Risks <ul><li>A. Methods </li></ul><ul><ul><li>Cables falling down and hurting the workers </li></ul></ul><ul><ul><li>Unsu...
 
Risks <ul><li>B. Technology </li></ul><ul><ul><li>Hydraulic pump for lifting equipment is not working. </li></ul></ul><ul>...
Risks <ul><li>C. Suppliers </li></ul><ul><ul><li>Late delivery of parts and related materials </li></ul></ul><ul><ul><li>L...
Risks <ul><li>D. Security & Safety </li></ul><ul><ul><li>Machinery and equipment, e.g. scaffolding </li></ul></ul><ul><ul>...
 
 
Risks <ul><li>E. Political </li></ul><ul><ul><li>Residential Mob </li></ul></ul><ul><ul><li>Coup De E’tat </li></ul></ul><...
Risks <ul><li>F. Regulatory </li></ul><ul><ul><li>Unable to finish deck lifting within the 4 hours permitted by the Water ...
Risks <ul><li>G. Requirements </li></ul><ul><ul><li>Incorrect specifications of equipment and materials </li></ul></ul><ul...
Risks <ul><li>H. Clients </li></ul><ul><ul><li>Unacceptable outcomes </li></ul></ul><ul><ul><li>Outcomes do not meet their...
Risks <ul><li>I. Acts of God </li></ul><ul><ul><li>Typhoon </li></ul></ul><ul><ul><li>Earthquake </li></ul></ul><ul><ul><l...
Risks <ul><li>J. Dependencies on other projects </li></ul><ul><ul><li>Delay of completing approach ramps installation </li...
Risks <ul><li>K. Contracts </li></ul><ul><ul><li>Clauses in agreements allow more flexibilities to clients to change their...
Risks <ul><li>L. Human Resources </li></ul><ul><ul><li>Lack of labor during the harvesting season </li></ul></ul><ul><ul><...
Monitoring and Controlling Actual  Progress Project Plan VS Variance Corrective Action Requirement Resources/ Cost Schedul...
Major Changes <ul><li>Method of cable wiring </li></ul><ul><li>More budgets on incentives for workers during the harvestin...
Total Budgets Spent <ul><li>Real Budgets Spent* </li></ul><ul><ul><li>Deck Lifting  88.5m THB </li></ul></ul><ul><ul><li>S...
 
References & Credits <ul><li>2Bangkok.com :  http://angkor.com/2bangkok/2bangkok/Bridge/wongwein/wongwein.shtml </li></ul>...
T H A N K  Y O U !
Upcoming SlideShare
Loading in …5
×

Bangkok Mega Bridge Project Management 2007

15,373 views

Published on

Project presentation on Bangkok Mega Bridge project management

Published in: Business, Technology
  • Is it possible to get a copy of these presentation slides?
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here
  • harlo,ur slides is very good ...
    can sent to me ?
    my email address is snowwhite_88@hotmail.com
       Reply 
    Are you sure you want to  Yes  No
    Your message goes here

Bangkok Mega Bridge Project Management 2007

  1. 1. Bangkok MEGA Bridge Trimester 2007/ 1
  2. 2. Group Members <ul><li>Nuttaya R. 4949273 </li></ul><ul><li>Nalinrat P. 4949278 </li></ul><ul><li>Nantana K. 4949279 </li></ul><ul><li>Sompol L. 4949282 </li></ul><ul><li>Supak C. 4949284 </li></ul>
  3. 3. Agenda <ul><li>Bangkok Mega Bridge </li></ul><ul><ul><li>Project Background </li></ul></ul><ul><ul><li>Key Stakeholders </li></ul></ul><ul><li>VSL Thailand </li></ul><ul><ul><li>Scope of Work </li></ul></ul><ul><ul><li>Project Objective Statement (POS) </li></ul></ul><ul><ul><li>Expected Benefits </li></ul></ul><ul><li>Project Priority Matrix </li></ul><ul><li>Major Deliverables and Specifications </li></ul><ul><li>Major Constraints and Exclusion </li></ul><ul><li>Major Work Areas, WBS, and Timing </li></ul><ul><li>Resources </li></ul><ul><li>Risk Management </li></ul><ul><li>Major Changes </li></ul><ul><li>Monitoring and Controlling </li></ul>
  4. 5. Project Background <ul><li>On 29 th May 2000, the project was inaugurated by His Majesty The King. </li></ul><ul><li>The construction started 18 th February 2003. </li></ul><ul><li>The official name of the project is ‘Bangkok Mega Bridge’ that is a part of the Industrial Ring Road Project. </li></ul>
  5. 6. Project Background <ul><li>The objective of the project is to alleviate traffic congestion resulting from freight transportation… </li></ul><ul><li>… . by providing a new road and bridge network to link Bangkok Port with.. </li></ul><ul><ul><li>the existing Pu Chao Saming Phrai Road to the South; </li></ul></ul><ul><ul><li>Suksawat Road to the west; and </li></ul></ul><ul><ul><li>Rama III to the north. </li></ul></ul>
  6. 7. Project Background (Overall) <ul><li>Value: 8.7 billion Baht </li></ul><ul><li>Specifications: </li></ul><ul><ul><li>First 2 cable-stayed bridges in Thailand </li></ul></ul><ul><ul><li>51 metres high </li></ul></ul><ul><ul><li>4.2 kilometres long </li></ul></ul><ul><ul><li>7 lanes </li></ul></ul><ul><ul><li>2.2 kiometres of elevated ramps </li></ul></ul>
  7. 8. Expected Benefits <ul><li>To ease the congestion of commercial traffic in Bangkok </li></ul><ul><li>To encourage the government sector to accelerate and accomplish public-sector construction and infrastructure developments </li></ul>
  8. 9. Project Manager Ministry of Transport Ministry of Finance Local Marine Department People (Near Site) Workers Insurance Company Bangkok Metropolitan Consultant Shipping& Cruise Line Bridge Architect Suppliers Key Stakeholders
  9. 10. Owner: Kingdom o f T h a i l a n d, Ministry of Transport, Dept. of Rural Roads <ul><li>Main Contractors </li></ul><ul><ul><li>TNNS Joint Venture </li></ul></ul><ul><li>Main Sub-Contractors </li></ul><ul><ul><li>VSL Thailand </li></ul></ul><ul><ul><li>Deck Bolting: STP&I </li></ul></ul><ul><li>Designers </li></ul><ul><ul><li>Norconsult </li></ul></ul><ul><ul><li>Mott McDonald </li></ul></ul><ul><ul><li>Epsilon </li></ul></ul><ul><li>Engineers </li></ul><ul><ul><li>Asian Engineering Consultants Ltd </li></ul></ul><ul><ul><li>Thai Engineering Consultants Jean Muller International </li></ul></ul>
  10. 11. VSL Thailand <ul><li>VSL’s Scope of Work </li></ul><ul><li>Deck lifting </li></ul><ul><li>Stay cable installation </li></ul><ul><li>Post tensioning </li></ul>
  11. 13. VSL’s Project Objective Statement (POS) <ul><li>“ To finish lifting 60 concrete decks, installing stay cables, and post-tensioning of Bangkok Mega Bridge within the budget of 445 million Baht </li></ul><ul><li>by 31 st of May 2006 .” </li></ul>
  12. 14. Project Priority Matrix Time Requirement Cost Constrained Enhanced Accepted
  13. 15. Major Deliverables <ul><li>Drawings/ Blueprints </li></ul><ul><li>Main spans building </li></ul><ul><ul><li>Gantry assembling </li></ul></ul><ul><ul><li>Deck </li></ul></ul><ul><ul><ul><li>Concrete pre-casting </li></ul></ul></ul><ul><ul><ul><li>Delivery on barge </li></ul></ul></ul><ul><ul><ul><li>Deck lifting </li></ul></ul></ul>
  14. 16. Major Deliverables <ul><li>Stay cable installation </li></ul><ul><ul><li>Erecting tendon </li></ul></ul><ul><ul><li>Wiring single strand cable </li></ul></ul><ul><li>Post-tensioning </li></ul>
  15. 17. Specifications of Deliverables <ul><li>Unit Concrete Deck </li></ul><ul><ul><li>36 metres wide </li></ul></ul><ul><ul><li>2.8 metres deep </li></ul></ul><ul><ul><li>12 metres long </li></ul></ul><ul><ul><li>weighing up to 500 tons </li></ul></ul><ul><ul><li>60 concrete decks for 2 bridges </li></ul></ul><ul><li>Single strand installation </li></ul><ul><ul><li>2,300 tons of stay cables (6-43 to 6-91 mono-strands) </li></ul></ul>
  16. 18. Major Constraints <ul><li>Water Traffic </li></ul><ul><ul><li>To avoid interfering the water traffic, VSL is allowed only 4 hours for lifting a deck from the barge to the bridge. </li></ul></ul>
  17. 20. Exclusion <ul><li>Not include pavement on road </li></ul><ul><li>Not include concrete curb and handrail </li></ul><ul><li>Not include Mechanical & Electrical work </li></ul>
  18. 21. Major Work Areas <ul><li>Design drawings </li></ul><ul><li>Survey work </li></ul><ul><li>Assemble gantry </li></ul><ul><li>Cast unit concrete decks </li></ul><ul><li>Rent Barge </li></ul><ul><li>Hoist segment </li></ul><ul><li>Install stay cable </li></ul>
  19. 22. Work Break-down Structure (WBS)
  20. 24. Resources <ul><li>Manpower </li></ul><ul><ul><li>Project manager </li></ul></ul><ul><ul><li>Civil engineer </li></ul></ul><ul><ul><li>Heavy lifting engineer </li></ul></ul><ul><ul><li>Heavy lifting superintendent </li></ul></ul><ul><ul><li>Stay cable superintendent </li></ul></ul><ul><ul><li>Post-tensioning superintendent </li></ul></ul><ul><ul><li>Workers </li></ul></ul><ul><li>Materials </li></ul><ul><ul><li>Cables </li></ul></ul><ul><ul><li>Concrete </li></ul></ul><ul><ul><li>Steel bars </li></ul></ul><ul><ul><li>Tendons </li></ul></ul><ul><ul><li>Metal buffers </li></ul></ul><ul><li>Equipment </li></ul><ul><ul><li>Gantry </li></ul></ul><ul><ul><li>Barge </li></ul></ul><ul><ul><li>Communication equipment </li></ul></ul><ul><ul><li>Energy generator </li></ul></ul><ul><ul><li>Forklift </li></ul></ul>
  21. 25. Risks Assessment <ul><li>Methods </li></ul><ul><li>Technology </li></ul><ul><li>Suppliers </li></ul><ul><li>Security & Safety </li></ul><ul><li>Political </li></ul><ul><li>Regulatory </li></ul><ul><li>Requirements </li></ul><ul><li>Clients </li></ul><ul><li>Acts of God </li></ul><ul><li>Dependencies on other projects </li></ul><ul><li>Contracts </li></ul><ul><li>Human Resources </li></ul>Impact Severity Chance Low High High A B C D E F G H I J K L
  22. 26. Risks <ul><li>A. Methods </li></ul><ul><ul><li>Cables falling down and hurting the workers </li></ul></ul><ul><ul><li>Unsuccessful method of moving gantry on the bridge surface </li></ul></ul><ul><ul><li>Wiring snap (Real case) </li></ul></ul><ul><ul><li>Unable to move a concrete deck from a trolley onto a barge </li></ul></ul><ul><ul><li>PREVENTIVE </li></ul></ul><ul><ul><li>PLANS </li></ul></ul><ul><ul><li>Pre-test. </li></ul></ul><ul><ul><li>Study previous projects. </li></ul></ul><ul><ul><li>Deal with the supplier. </li></ul></ul><ul><ul><li>Check the outcomes . </li></ul></ul><ul><ul><li>Training. </li></ul></ul><ul><ul><li>Check the neatness of the pathway. </li></ul></ul><ul><li>CONTINGENCY </li></ul><ul><li>PLANS </li></ul><ul><li>Swap back to the old-fashioned cabling method. </li></ul><ul><li>(in the case) Metal sheets are used to cover the pathway and make the smooth surface. </li></ul>
  23. 28. Risks <ul><li>B. Technology </li></ul><ul><ul><li>Hydraulic pump for lifting equipment is not working. </li></ul></ul><ul><ul><li>Communication equipment, i.e. walkie-talkies, does not work. </li></ul></ul><ul><ul><li>Workers do not know how to use the equipment. </li></ul></ul><ul><ul><li>PREVENTIVE </li></ul></ul><ul><ul><li>PLANS </li></ul></ul><ul><ul><li>Pre-check and re-check the system. </li></ul></ul><ul><ul><li>Technician </li></ul></ul><ul><ul><li>Deal with another supplier for a spare pump or spare walkie-talkies. </li></ul></ul><ul><ul><li>Training. </li></ul></ul><ul><ul><li>Spare batteries/ walkie-talkies </li></ul></ul><ul><li>CONTINGENCY </li></ul><ul><li>PLANS </li></ul><ul><li>Get the technician to check. </li></ul><ul><li>Contact the supplier for the spare dealt. </li></ul><ul><li>Change batteries. </li></ul><ul><li>Spare walkie-talkies </li></ul><ul><li>Buy new walkie-talkies. </li></ul>
  24. 29. Risks <ul><li>C. Suppliers </li></ul><ul><ul><li>Late delivery of parts and related materials </li></ul></ul><ul><ul><li>Lower quality of supplies than required </li></ul></ul><ul><ul><li>Short supply of materials </li></ul></ul><ul><ul><li>PREVENTIVE </li></ul></ul><ul><ul><li>PLANS </li></ul></ul><ul><ul><li>Pre-confirm and pre-check schedules of parts required. </li></ul></ul><ul><ul><li>Confirm order early. </li></ul></ul><ul><ul><li>Sign off a contract with the supplier in case of late delivery. </li></ul></ul><ul><ul><li>Deal with a spare supplier. </li></ul></ul><ul><li>CONTINGENCY </li></ul><ul><li>PLANS </li></ul><ul><li>Contact the spare supplier. </li></ul><ul><li>Fine the supplier for the delay caused to the project. </li></ul><ul><li>Re-schedule work plan if possible. </li></ul><ul><li>Claim for a replacement from the supplier. </li></ul>
  25. 30. Risks <ul><li>D. Security & Safety </li></ul><ul><ul><li>Machinery and equipment, e.g. scaffolding </li></ul></ul><ul><ul><li>Processes </li></ul></ul><ul><ul><li>Human, e.g. theft, carelessness </li></ul></ul><ul><ul><li>Short electricity circuit </li></ul></ul><ul><ul><li>Fire </li></ul></ul><ul><ul><li>PREVENTIVE PLANS </li></ul></ul><ul><ul><li>Check specifications. </li></ul></ul><ul><ul><li>Hold safety meeting. </li></ul></ul><ul><ul><li>Sign contract with conditions. </li></ul></ul><ul><ul><li>Safety equipment for workers. </li></ul></ul><ul><ul><li>Set rules and regulations. </li></ul></ul><ul><ul><li>Conduct safety training. </li></ul></ul><ul><ul><li>Extinguisher </li></ul></ul><ul><ul><li>All-risk Insurance </li></ul></ul><ul><ul><li>Dealer for a spare generator </li></ul></ul><ul><li>CONTINGENCY PLANS </li></ul><ul><li>Claim with suppliers. </li></ul><ul><li>Call hospitals. </li></ul><ul><li>First aid materials </li></ul><ul><li>Claim with insurance company </li></ul><ul><li>Contact police. </li></ul><ul><li>Use extinguisher. </li></ul><ul><li>Call police/ fire fighters. </li></ul><ul><li>Warning/ Punishment </li></ul><ul><li>Spare generator </li></ul>
  26. 33. Risks <ul><li>E. Political </li></ul><ul><ul><li>Residential Mob </li></ul></ul><ul><ul><li>Coup De E’tat </li></ul></ul><ul><ul><li>PREVENTIVE </li></ul></ul><ul><ul><li>PLANS </li></ul></ul><ul><ul><li>This is beyond control, so we just keep an eye on the situation if any action is needed, e.g. day-off, to avoid any hazardous situation. </li></ul></ul><ul><ul><li>Check if it is possible to double employ workers during a short period of time. </li></ul></ul><ul><li>CONTINGENCY PLANS </li></ul><ul><li>Inform the impacts caused by the situation to the stakeholders. </li></ul><ul><li>Re-schedule the work plan. </li></ul><ul><li>Assign more resources to the work during a period of time in order to finish the work in time. </li></ul><ul><li>Ask for the postponement of the deadline referring to the situation. </li></ul>
  27. 34. Risks <ul><li>F. Regulatory </li></ul><ul><ul><li>Unable to finish deck lifting within the 4 hours permitted by the Water Transportation Office </li></ul></ul><ul><ul><li>PREVENTIVE </li></ul></ul><ul><ul><li>PLANS </li></ul></ul><ul><ul><li>Check and ensure that all related machinery and equipment, e.g. gantry, barge, and trolley, including the process are going smoothly. </li></ul></ul><ul><ul><li>Skillful boat (for moving barge) driver </li></ul></ul><ul><li>CONTINGENCY </li></ul><ul><li>PLANS </li></ul><ul><li>Provide a report of the cause of the delay to the stakeholders. </li></ul><ul><li>Contact the Water Transportation Office for an additional numbers of 4-hour day(s) may required. </li></ul>
  28. 35. Risks <ul><li>G. Requirements </li></ul><ul><ul><li>Incorrect specifications of equipment and materials </li></ul></ul><ul><ul><li>Wrong designs </li></ul></ul><ul><ul><li>Change of requirements </li></ul></ul><ul><ul><li>Outcomes do not match the designs. </li></ul></ul><ul><ul><li>PREVENTIVE </li></ul></ul><ul><ul><li>PLANS </li></ul></ul><ul><ul><li>Study previous projects, reports, and re-check all designs and specifications. </li></ul></ul><ul><ul><li>Get the third party to check the design. </li></ul></ul><ul><ul><li>Contract conditions </li></ul></ul><ul><ul><li>Keep in touch with stakeholders on requirements overtime. </li></ul></ul><ul><ul><li>Project inspection by the third party. </li></ul></ul><ul><li>CONTINGENCY PLANS </li></ul><ul><li>Get a replacement. </li></ul><ul><li>Stakeholder meeting </li></ul><ul><li>Re-schedule the work and resource plans. </li></ul>
  29. 36. Risks <ul><li>H. Clients </li></ul><ul><ul><li>Unacceptable outcomes </li></ul></ul><ul><ul><li>Outcomes do not meet their standard. </li></ul></ul><ul><ul><li>PREVENTIVE </li></ul></ul><ul><ul><li>PLANS </li></ul></ul><ul><ul><li>Regularly check with customers regarding their requirements. </li></ul></ul><ul><ul><li>Go through all requirements and standard needed by customers since the start of the project. </li></ul></ul><ul><ul><li>Discussion about the requirements and standards </li></ul></ul><ul><li>CONTINGENCY </li></ul><ul><li>PLANS </li></ul><ul><li>Meeting with stakeholders and customers. </li></ul><ul><li>Enhancement of other requirements instead. </li></ul><ul><li>Worst case, re-do. </li></ul>
  30. 37. Risks <ul><li>I. Acts of God </li></ul><ul><ul><li>Typhoon </li></ul></ul><ul><ul><li>Earthquake </li></ul></ul><ul><ul><li>Lightning </li></ul></ul><ul><ul><li>Rains </li></ul></ul><ul><ul><li>Flooding </li></ul></ul><ul><ul><li>PREVENTIVE </li></ul></ul><ul><ul><li>PLANS </li></ul></ul><ul><ul><li>Weather forecast </li></ul></ul><ul><ul><li>Discuss with workers in advance regarding this risk. </li></ul></ul><ul><ul><li>Check if anyone can work overtime if this risk occurs to accelerate the work. </li></ul></ul><ul><ul><li>Install lightning rods. </li></ul></ul><ul><ul><li>Wider space for concrete deck casting area </li></ul></ul><ul><ul><li>List of emergency numbers, e.g. hospital, police, fire fighters, etc. </li></ul></ul><ul><li>CONTINGENCY PLANS </li></ul><ul><li>Re-schedule resource and work plan. </li></ul><ul><li>Report stakeholders about the situation and cause of delay. </li></ul><ul><li>Evacuate workers to a safer place. </li></ul><ul><li>Emergency calls </li></ul>
  31. 38. Risks <ul><li>J. Dependencies on other projects </li></ul><ul><ul><li>Delay of completing approach ramps installation </li></ul></ul><ul><ul><li>Delay of completing pylons installation </li></ul></ul><ul><ul><li>PREVENTIVE </li></ul></ul><ul><ul><li>PLANS </li></ul></ul><ul><ul><li>Follow up and co-ordinate with the other projects that we are dependent with. </li></ul></ul><ul><ul><li>Check if our work can be done simultaneously with the other project. </li></ul></ul><ul><ul><li>Check available resources from time to time in case the work has been postponed. </li></ul></ul><ul><li>CONTINGENCY </li></ul><ul><li>PLANS </li></ul><ul><li>Inform stakeholders about the cause of delay. </li></ul><ul><li>Claim with the main contractor for the costs of the delay. </li></ul><ul><li>Re-schedule the work and resource plans. </li></ul>
  32. 39. Risks <ul><li>K. Contracts </li></ul><ul><ul><li>Clauses in agreements allow more flexibilities to clients to change their requirements too much, which leads to higher costs. </li></ul></ul><ul><ul><li>PREVENTIVE PLANS </li></ul></ul><ul><ul><li>Set up a law team. </li></ul></ul><ul><ul><li>Assign a team to check and evaluate the terms and conditions in the agreements, preferably law team. </li></ul></ul><ul><ul><li>Compare the price quoted and our estimated costs that include exceeding requirements. </li></ul></ul><ul><li>CONTINGENCY PLANS </li></ul><ul><li>Stakeholders/ customer meeting, explaining about pros and cons of too exceeding requirements, for example, time consuming and higher budgets. </li></ul><ul><li>Consult a law firm/ department </li></ul>
  33. 40. Risks <ul><li>L. Human Resources </li></ul><ul><ul><li>Lack of labor during the harvesting season </li></ul></ul><ul><ul><li>Health problems </li></ul></ul><ul><ul><li>Worker mob </li></ul></ul><ul><ul><li>PREVENTIVE </li></ul></ul><ul><ul><li>PLANS </li></ul></ul><ul><ul><li>Source some spare workers who are willing to work during the time. </li></ul></ul><ul><ul><li>Health check-up </li></ul></ul><ul><ul><li>Communicate with workers and listen to them. </li></ul></ul><ul><ul><li>Rewarding </li></ul></ul><ul><ul><li>24/ 7 work and resource plan </li></ul></ul><ul><li>CONTINGENCY </li></ul><ul><li>PLANS </li></ul><ul><li>Incentives </li></ul><ul><li>Get spare workers from other sources. </li></ul><ul><li>Consider what the workers ask for, bring the issues to the stakeholder meeting, and discuss. </li></ul><ul><li>Compromising </li></ul>
  34. 41. Monitoring and Controlling Actual Progress Project Plan VS Variance Corrective Action Requirement Resources/ Cost Schedule Issues Risks
  35. 42. Major Changes <ul><li>Method of cable wiring </li></ul><ul><li>More budgets on incentives for workers during the harvesting season </li></ul>
  36. 43. Total Budgets Spent <ul><li>Real Budgets Spent* </li></ul><ul><ul><li>Deck Lifting 88.5m THB </li></ul></ul><ul><ul><li>Stay Cable Wiring 198m THB </li></ul></ul><ul><ul><li>Post-tensioning 155.73m THB </li></ul></ul><ul><li>Total of 442.23 million Baht </li></ul>* Source : K. Yutapol Siewthaisong, the Project Manager of the project, from VSL Thailand.
  37. 45. References & Credits <ul><li>2Bangkok.com : http://angkor.com/2bangkok/2bangkok/Bridge/wongwein/wongwein.shtml </li></ul><ul><li>Bureau of Bridges Construction Department of Rural Roads : http://www.bbc.go.th/page_bx.php?cno=466&cid=18 </li></ul><ul><li>Discovery Channel : http://www.discoverychannel.co.uk/machines_and_engineering/megabuilders/bangkokmegabridge/index.shtml </li></ul><ul><li>Engineering and Training Center : Steps of Industrial Ring Road Bridge Construction. http://www.tumcivil.com/engfanatic/article_gen.php?&article_id=7&p_content=10 </li></ul><ul><li>Industrial Ring Road Bridge : http://pongdej.multiply.com/photos/album/2 </li></ul><ul><li>Structurae : http :// en . structurae . de / structures / data / index . cfm?ID = s0016774 </li></ul><ul><li>Thailand Engineering Journal : Cover Story: Industrial Ring Road Project . Year 59, Vol., 6, November-December 2006. </li></ul><ul><li>The VSL News Magazine : Issue One 2006. http://www.vsl.com/index.php?option=com_content&task=view&id=138&Itemid=257. </li></ul><ul><li>VSL Thailand : http://www.vsl.com/ and K. Yutapol Siewthaisong, the Project Manager of the project, from VSL Thailand. </li></ul>
  38. 46. T H A N K Y O U !

×