PRESENTATION
ON
Progress of NPR in ODISHA
Dt. 24th Jan 2014
By
DCO, Odisha
ABOUT NPR

Generation of Aadhaar number of each individual above 5
years is an important component of NPR Project.
NPR P...
PRESENT ENROLMENT STATUS
BME Present Status
13,686,418

BME done

BME leftover

24,679,466

TARGET POP-3,83,65,884
PLAN OF COMPLETION
First Round BME Completed
SI NO

DISTRICT

Target
Population

2nd Round BME Status/ Expected
Date of Completion

% age
Com...
Enrolment Operation in Progress
SI NO

1
2
3
4
5
6
7
8
9
10
11

DISTRICT

Target
Population

1nd Round BME Status/
Expecte...
DBT/DBTL Odisha
 Four districts viz. Balangir, Puri, Khordha & Cuttack
were selected for DBTL where the scheme is to be o...
Operator Utilization as on 17-Jan-2014-At Balangir
Coverage Of NPR Left Out Population
 Left out population in First Round is covered during
Second round of BME operation a...
Coverage of “Out of NPR” Population
 To cover the persons who were not covered during NPR
survey or he/she is a new entra...
Coverage of DBT / DBTL Beneficiaries
 2nd round BME operation in DBT districts to cover all left-out
including DBT/DBTL b...
Coverage of Rejected Enrolments
It is reported that BME packets of some persons are rejected due
to various reasons causi...
Coverage of Rejected Enrolments….Contd
BME packets were successfully generated during enrolment
and same were accepted du...
Setting-up of Permanent Enrollment Centres
And RGI policy for coverage of under 5 age group
 The proposal for setting-up ...
Thank You
E-mail: dco-ori.rgi@censusindia.gov.in
bishnupada.sethi@gmail.com
eOdisha Summit 2014 - Integrating Service Delivery... - Prabhakar Barad, Deputy Director, Directorate...
Upcoming SlideShare
Loading in …5
×

eOdisha Summit 2014 - Integrating Service Delivery... - Prabhakar Barad, Deputy Director, Directorate...

601 views

Published on

Published in: Education, Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
601
On SlideShare
0
From Embeds
0
Number of Embeds
20
Actions
Shares
0
Downloads
4
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

eOdisha Summit 2014 - Integrating Service Delivery... - Prabhakar Barad, Deputy Director, Directorate...

  1. 1. PRESENTATION ON Progress of NPR in ODISHA Dt. 24th Jan 2014 By DCO, Odisha
  2. 2. ABOUT NPR Generation of Aadhaar number of each individual above 5 years is an important component of NPR Project. NPR Project in the state is conducted as per the provision of Citizenship Act 1955 and issue of Identity Cards Rule 2003. Biographic data of each individual was collected during 7th April -22nd May, 2010 in the State. After data entry the collection of Photo-Biometric Data is now in progress. So far out of the target population of 3.84 Crore, Biometric enrollment is completed for population of 2.47 Crore (64.33%). 1st round collection of Photo-Biometric is completed for 19 districts. The Biographic data along with Biometric-data are being uploaded to UIDAI portal. UIDAI is processing the data generating the Aadhaar number of each individual and dispatching it directly to the person concerned through post
  3. 3. PRESENT ENROLMENT STATUS
  4. 4. BME Present Status 13,686,418 BME done BME leftover 24,679,466 TARGET POP-3,83,65,884
  5. 5. PLAN OF COMPLETION
  6. 6. First Round BME Completed SI NO DISTRICT Target Population 2nd Round BME Status/ Expected Date of Completion % age Complete 1 Balangir 1,567,292 In-progress/Jan-2014 88 2 Cuttack 2,352,690 In-progress/Feb-2014 80 3 Khurda 2,059,185 In-progress/Feb-2014 65 4 PURI 1,555,409 In-progress/Feb-2014 83 5 Balasore 2,122,738 In-progress/Feb-2014 75 6 Bhadrak 1,415,040 To be started/Feb-2014 75 7 Jagatsinghpur 1,081,072 To be started/Feb-2014 82 8 Kendrapara 1,380,532 To be started/Feb-2014 79 9 Dhenkanal 1,071,144 To be started/Feb-2014 94 10 Angul 1,146,482 To be started/Feb-2014 78 11 Nayagarh 889,652 To be started/Feb-2014 79 12 Debagarh 282,473 To be started/Feb-2014 88 13 Nuapada 587,759 To be started/Feb-2014 69 14 Boudh 282,972 To be started/Feb-2014 73 15 Kendujhar 1,635,106 To be started/Mar-2014 64 16 Mayurbhanj 2,278,567 To be started/Feb-2014 83 17 Jajpur 1,706,337 To be started/Feb-2014 78 18 Subarnapur 572,826 In-progress/Feb-2014 76 19 Kandhamal 668,751 To be started/Mar-2014 63
  7. 7. Enrolment Operation in Progress SI NO 1 2 3 4 5 6 7 8 9 10 11 DISTRICT Target Population 1nd Round BME Status/ Expected Date of Completion 2nd Round BME Status/ Expected % age Date of Completion Complete Sundargarh 1,872,493 In-progress/ Feb-2014 To be started/ Mar-2014 61 Bargarh 1,340,163 In-progress/Jan-2014 To be started/ Mar-2014 65 937,739 In-progress/ Feb-2014 To be started/ Mar-2014 50 Koraput 1,231,755 In-progress/ Feb-2014 To be started/ Mar-2014 34 Ganjam 3,238,903 In-progress/ Feb-2014 To be started/ Mar-2014 43 536,608 In-progress/Jan-2014 To be started/ Mar-2014 64 1,088,672 In-progress/Jan-2014 To be started/ Mar-2014 62 Rayagada 866,259 In-progress/ Feb-2014 To be started/ Mar-2014 8 Kalahandi 1,424,083 In-progress/ Feb-2014 To be started/ Mar-2014 4 Jharsuguda 518,616 In-progress/ Feb-2014 To be started/ Mar-2014 Malkangiri 540,011 In-progress/ Feb-2014 To be started/ Mar-2014 Sambalpur Gajapati Nabarangpur
  8. 8. DBT/DBTL Odisha  Four districts viz. Balangir, Puri, Khordha & Cuttack were selected for DBTL where the scheme is to be operated from 1st Feb 2014.  Subarnapur district has been selected for DBT .  Further three more districts viz. Baleswar, Bhadrak & Sundargarh have been selected for DBTL where the scheme is to be operated from 1st April 2014.  As per Directive from ORGI, Special Camps were setup at all distributer premises of Balangir district on pilot basis from 14-Dec-2013 to 22-Dec-2014 with extension upto 31-Dec-2013 and further extension upto 31-Jan-2014. (Total 47 days)
  9. 9. Operator Utilization as on 17-Jan-2014-At Balangir
  10. 10. Coverage Of NPR Left Out Population  Left out population in First Round is covered during Second round of BME operation along with the new entrants in the concerned Enumeration Block (EB).  Enumerators are inviting Enrollees by visiting door to door in their EBs to ensure their presence at BME camps.  If Capture percentage is still low, there will be establishment of special centres for BME under close supervision of Tahasil/Town/District Administration.
  11. 11. Coverage of “Out of NPR” Population  To cover the persons who were not covered during NPR survey or he/she is a new entrant after NPR, fresh NPR schedules were filled up during First Round of BME operation by the Enumerator under his/her jurisdiction.  For these persons Demographic Data entry were done at Bulk Data Center.  Afterwards these population are being covered during Second round of BME operation.
  12. 12. Coverage of DBT / DBTL Beneficiaries  2nd round BME operation in DBT districts to cover all left-out including DBT/DBTL beneficiaries has been prioritized.  Deployment of Kit had been made as per the requirement of of concerned DBT departments at Charge level camps. Steps taken for collection of Photo-Biometric Data : 1. List of left-out whose BME is required is being prepared. 2. Arrangement has been made for filling-up NPR data in the prescribed form. 3. Program for collection of Photo-Biometric data is now taken up. 4. Left-out beneficiaries are being called to the respective camps as per program. 5. State Government has sanctioned a sum of Rs 53.64 lacs for establishment Of Permanent Centres for four months to collect all the left out persons in eight DBT districts.
  13. 13. Coverage of Rejected Enrolments It is reported that BME packets of some persons are rejected due to various reasons causing disappointment to the people who have already gone through BME operation.  A sense of doubt is created among the people when they got the message of rejection.  A huge number around 30 lakhs of BME have been reported rejected due to data/process error.
  14. 14. Coverage of Rejected Enrolments….Contd BME packets were successfully generated during enrolment and same were accepted during uploading at CIDR server.  Total technology for generation of BME packets were provided by highly technical team of UIDAI authority considering all technical aspects and protocols.  UIDAI authority is requested to reconsider the rejected packets for Generation of Aadhaar Number as these were not rejected during enrolment. Steps are being taken for installation of helpline by UIDAI to sort out the rejected enrollments.
  15. 15. Setting-up of Permanent Enrollment Centres And RGI policy for coverage of under 5 age group  The proposal for setting-up of permanent Enrolment centres at districts/ sub-districts is now under active consideration. ECIL is starting BME enrollment at Tahsil/ Block offices on 25th Jan at Cuttack, Khurdha, Puri, Balangir, Balasore, Bhadrak .  There is no proposal for biometric coverage of under 5 age group, however those who attain age group of 5 will be covered in the permanent centres.
  16. 16. Thank You E-mail: dco-ori.rgi@censusindia.gov.in bishnupada.sethi@gmail.com

×