Dialogue Session With Datuk Bandar KL
On Road Dispersal System in Bangsar & Brickfields
Dialogue Session with Datuk Bandar KL
CURRENT TRAFFIC SITUATION IN AND AROUND BANGSAR & BRICKFIELDS
Dialogue Session with Datuk Bandar KL
CURRENT TRAFFIC SITUATION IN AND AROUND BANGSAR & BRICKFIELDS


1) Traffic is heavy ...
Dialogue Session with Datuk Bandar KL
CURRENT TRAFFIC SITUATION IN AND AROUND BANGSAR & BRICKFIELDS
Dialogue Session with Datuk Bandar KL
TRAFFIC SITUATION IN AND AROUND BANGSAR & BRICKFIELDS AFTER
IMPROVEMENT
Dialogue Session with Datuk Bandar KL
 PROPOSED TRAFFIC SOLUTION FOR BANGSAR/BRICKFIELDS

                                ...
Dialogue Session with Datuk Bandar KL

PROPOSED TRAFFIC SOLUTION UNDER RM110 MILLION STIMULUS
PACKAGES


Package 1: Constr...
Dialogue Session with Datuk Bandar KL

STIMULUS PACKAGE 1:
CONSTRUCTION OF FLYOVER AT JALAN TRAVERS/JALAN BANGSAR INTERSEC...
Dialogue Session with Datuk Bandar KL

STIMULUS PACKAGE 1:
CONSTRUCTION OF FLYOVER AT JALAN TRAVERS/JALAN BANGSAR INTERSEC...
Dialogue Session with Datuk Bandar KL

STIMULUS PACKAGE 1:
CONSTRUCTION OF FLYOVER AT JALAN TRAVERS/JALAN BANGSAR INTERSEC...
Dialogue Session with Datuk Bandar KL

STIMULUS PACKAGE 1:
CONSTRUCTION OF FLYOVER AT JALAN TRAVERS/JALAN BANGSAR INTERSEC...
Dialogue Session with Datuk Bandar KL
STIMULUS PACKAGE 2:
CONSTRUCTION OF FLYOVER FROM KL SENTRAL TO JALAN DAMANSARA &
LEB...
Dialogue Session with Datuk Bandar KL
STIMULUS PACKAGE 2:
CONSTRUCTION OF FLYOVER FROM
KL SENTRAL TO JALAN DAMANSARA
& LEB...
Dialogue Session with Datuk Bandar KL
STIMULUS PACKAGE 3:
UPGRADING OF JALAN TUN SAMBANTHAN




The upgrading works includ...
Dialogue Session with Datuk Bandar KL
STIMULUS PACKAGE 3
PROPOSED BEAUTIFICATION OF JALAN TUN SAMBANTHAN WITH THE UPGRADIN...
Dialogue Session with Datuk Bandar KL
STIMULUS PACKAGE 3
PROPOSED BEAUTIFICATION OF
JALAN TUN SAMBANTHAN




 More artist ...
Dialogue Session with Datuk Bandar KL
STIMULUS PACKAGE 3
PROPOSED BEAUTIFICATION OF JALAN TUN SAMBANTHAN




Artist impres...
Dialogue Session with Datuk Bandar KL
STIMULUS PACKAGE 4:
CONSTRUCTION OF PEDESTRIAN BRIDGES & LINKAGES
Dialogue Session with Datuk Bandar KL
STIMULUS PACKAGE 4:
                 4
CONSTRUCTION OF PEDESTRIAN BRIDGES & LINKAGES...
Dialogue Session with Datuk Bandar KL
STIMULUS PACKAGE 4:
                 4
CONSTRUCTION OF PEDESTRIAN BRIDGES & LINKAGES...
Dialogue Session with Datuk Bandar KL

STIMULUS PACKAGE 4:
CONSTRUCTION OF PEDESTRIAN BRIDGES & LINKAGES



Artist impress...
Dialogue Session with Datuk Bandar KL

STIMULUS PACKAGE 5: UPGRADE AND REPAIR ROADS AT KL SENTRAL
Dialogue Session with Datuk Bandar KL

STIMULUS PACKAGE 5: UPGRADE AND REPAIR ROADS AT KL SENTRAL




 Jalan Stesen Sentra...
Dialogue Session with Datuk Bandar KL

STIMULUS PACKAGE 6:
CONSTRUCTION OF ELEVATED ROAD FROM JALAN BANGSAR TO JALAN MAARO...
Dialogue Session with Datuk Bandar KL

STIMULUS PACKAGE 6:
CONSTRUCTION OF ELEVATED ROAD FROM JALAN BANGSAR TO JALAN MAARO...
Dialogue Session with Datuk Bandar KL
ONGOING IMPLEMENTATION OF A PROPOSED TRAFFIC SOLUTION
(currently in progress) 
Dialogue Session with Datuk Bandar KL

PROPOSED TRAFFIC SOLUTION FOR BANGSAR/BRICKFIELDS




         RM110 MILLION TRAFFI...
Dialogue Session with Datuk Bandar KL

PROPOSED TRAFFIC SOLUTION FOR BANGSAR/BRICKFIELDS

Based on the outcome of the dial...
Dialogue Session with Datuk Bandar KL




         TERIMA KASIH
Upcoming SlideShare
Loading in …5
×

DBKL Brickfield Road Disbursement

2,931 views

Published on

DBKL Brickfield Road Disbursement proposal. Send in your views now.

Published in: Real Estate, Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
2,931
On SlideShare
0
From Embeds
0
Number of Embeds
93
Actions
Shares
0
Downloads
94
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

DBKL Brickfield Road Disbursement

  1. 1. Dialogue Session With Datuk Bandar KL On Road Dispersal System in Bangsar & Brickfields
  2. 2. Dialogue Session with Datuk Bandar KL CURRENT TRAFFIC SITUATION IN AND AROUND BANGSAR & BRICKFIELDS
  3. 3. Dialogue Session with Datuk Bandar KL CURRENT TRAFFIC SITUATION IN AND AROUND BANGSAR & BRICKFIELDS 1) Traffic is heavy on the main roads in and around Bangsar & Brickfields i.e.  intersection of Jalan Travers/ Jalan Bangsar;  Jalan Tun Sambanthan/ Jalan  i i f l / l l S b h / l Travers; Jalan Tun Sambanthan/ Jalan Tun Sambanthan 4 and  Jalan Tun  Sambanthan/ Jalan Robson. Side roads in and around residential areas are also heavy. CAUSES OF HEAVY TRAFFIC IN THE AREA CAUSES OF HEAVY TRAFFIC IN THE AREA i. Current roads are unable to cope with the surge in traffic volume due to the  fast‐paced development in and around Brickfields notably KL Sentral ii. Illegal parking of vehicles (especially on the main roads in Brickfields)  g p g ( p y ) compound the situation due to insufficient parking areas iii. Signalised junctions have already reached their optimum capacity
  4. 4. Dialogue Session with Datuk Bandar KL CURRENT TRAFFIC SITUATION IN AND AROUND BANGSAR & BRICKFIELDS
  5. 5. Dialogue Session with Datuk Bandar KL TRAFFIC SITUATION IN AND AROUND BANGSAR & BRICKFIELDS AFTER IMPROVEMENT
  6. 6. Dialogue Session with Datuk Bandar KL PROPOSED TRAFFIC SOLUTION FOR BANGSAR/BRICKFIELDS from KL Sentral to Jalan  Intersection of Jalan  Damansara and Lebuhraya  Travers/Jalan Bangsar / g Mahameru Slip road from Jalan  Bangsar to Jalan  B t J l Maarof
  7. 7. Dialogue Session with Datuk Bandar KL PROPOSED TRAFFIC SOLUTION UNDER RM110 MILLION STIMULUS PACKAGES Package 1: Construction of Flyover at Jalan Travers/Jalan Bangsar Intersection Package 2: Construction of Flyover from KL Sentral to Jalan Damansara &  g y Lebuhraya Mahameru Package 3: Upgrading of Jalan Tun Sambanthan and its vicinity Package 4: Construction of Pedestrian Bridges & Linkages Package 5: Upgrade and Repair Roads in KL Sentral k d d i d i S l Package 6: Construction of Elevated Road from Jalan Bangsar to Jalan Maarof
  8. 8. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 1: CONSTRUCTION OF FLYOVER AT JALAN TRAVERS/JALAN BANGSAR INTERSECTION Flyover at intersection of Jalan Travers/Jalan Bangsar
  9. 9. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 1: CONSTRUCTION OF FLYOVER AT JALAN TRAVERS/JALAN BANGSAR INTERSECTION View of Flyover from Jalan Bangsar
  10. 10. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 1: CONSTRUCTION OF FLYOVER AT JALAN TRAVERS/JALAN BANGSAR INTERSECTION View of Flyover from Jalan T Vi f Fl f J l Travers
  11. 11. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 1: CONSTRUCTION OF FLYOVER AT JALAN TRAVERS/JALAN BANGSAR INTERSECTION View of flyover from 1 Sentral Building on Jalan Travers y g
  12. 12. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 2: CONSTRUCTION OF FLYOVER FROM KL SENTRAL TO JALAN DAMANSARA & LEBUHRAYA MAHAMERU Flyover from KL Sentral to Jalan Damansara/Lebuhraya Mahameru
  13. 13. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 2: CONSTRUCTION OF FLYOVER FROM KL SENTRAL TO JALAN DAMANSARA & LEBUHRAYA MAHAMERU View of Flyover from KL Sentral to Jalan Mahameru and Jalan Damansara
  14. 14. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 3: UPGRADING OF JALAN TUN SAMBANTHAN The upgrading works include widening and beautification of roads in Brickfields as well as  The upgrading works include widening and beautification of roads in Brickfields as well as conversion of roads to one‐way system
  15. 15. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 3 PROPOSED BEAUTIFICATION OF JALAN TUN SAMBANTHAN WITH THE UPGRADING & CONVERSION TO ONE-WAY STREET
  16. 16. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 3 PROPOSED BEAUTIFICATION OF JALAN TUN SAMBANTHAN More artist impression of the new one‐way  p y street system
  17. 17. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 3 PROPOSED BEAUTIFICATION OF JALAN TUN SAMBANTHAN Artist impression of the new one‐way street system alongside Nu Sentral Mall by 2012
  18. 18. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 4: CONSTRUCTION OF PEDESTRIAN BRIDGES & LINKAGES
  19. 19. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 4: 4 CONSTRUCTION OF PEDESTRIAN BRIDGES & LINKAGES Artist impression of a pedestrian bridge linking KL Monorail to Nu Sentral Mall
  20. 20. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 4: 4 CONSTRUCTION OF PEDESTRIAN BRIDGES & LINKAGES Artist impression of a pedestrian bridge near 348 Sentral
  21. 21. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 4: CONSTRUCTION OF PEDESTRIAN BRIDGES & LINKAGES Artist impression of a pedestrian bridge near 348 Sentral
  22. 22. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 5: UPGRADE AND REPAIR ROADS AT KL SENTRAL
  23. 23. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 5: UPGRADE AND REPAIR ROADS AT KL SENTRAL Jalan Stesen Sentral, one of the roads in the KL Sentral would undergo upgrade and repair
  24. 24. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 6: CONSTRUCTION OF ELEVATED ROAD FROM JALAN BANGSAR TO JALAN MAAROF Elevated road from Jalan Bangsar to Jalan Maarof
  25. 25. Dialogue Session with Datuk Bandar KL STIMULUS PACKAGE 6: CONSTRUCTION OF ELEVATED ROAD FROM JALAN BANGSAR TO JALAN MAAROF View of elevated road from Jalan Bangsar
  26. 26. Dialogue Session with Datuk Bandar KL ONGOING IMPLEMENTATION OF A PROPOSED TRAFFIC SOLUTION (currently in progress) 
  27. 27. Dialogue Session with Datuk Bandar KL PROPOSED TRAFFIC SOLUTION FOR BANGSAR/BRICKFIELDS RM110 MILLION TRAFFIC DISPERSAL SCHEME HAS BEEN  LAUNCHED PACKAGE 1 HAS COMMENCED WORK ON 1 OCTOBER 2009  SUBSEQUENT PACKAGES WILL BE IMPLEMENTED  ACCORDING TO SCHEDULE  THE WHOLE PROJECT IS EXPECTED TO BE COMPLETED BY  EARLY 2011
  28. 28. Dialogue Session with Datuk Bandar KL PROPOSED TRAFFIC SOLUTION FOR BANGSAR/BRICKFIELDS Based on the outcome of the dialogue on 9 October 2009, a one month period has been given to the Bangsar/Brickfields/Federal Hills community to comment & provide feedback on the matter. The agreed deadline was for a month ending by 5pm on 8 November 2009. Mohd Khi M hd Khir, Engineer, Public Works Department Dewan Bandaraya Kuala Lumpur y p 19th, Menara DBKL 1, Jalan Raja Laut 50350 Kuala Lumpur Tel: 03-2617 9000 / 2617 9402 03 2617 Fax: 03-2691 9149 Email: mohdkhir@dbkl.gov.my cc. corp.comm-assistline@mrcb.com.my
  29. 29. Dialogue Session with Datuk Bandar KL TERIMA KASIH

×