This document provides training on running MRP processes in SAP. It explains how to prepare for an MRP run by closing open purchase orders, production orders, and schedule lines. It then outlines the steps to run MRP using transaction code MD02 for a single item, including parameters to set and how to view the results. The MRP run will create planned orders and purchase requisitions based on the production plan and dependent requirements.
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
Â
SAP PP MRP Guide for Beginners
1. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
1
SAP USER TRAINING DOCUMENT
MRP
By Kanti Kumar
2. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
2
Experts agree that you get the most from your ERP software
when users become accepting, comfortable, and proficient
performing the new business processes the software
supports. In other words, much of the success of a multi-
million dollar ERP implementation depends on the
people using the system for day-to-day work.
Our Aims and Ideals
To train you on higher level in SAP ERP, that
is our aim.
3. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
3
MRP Process in SAP System
We run MRP for generating Vendor Schedules. This document will show process in SAP for
Production plan to material receive from vendors through SAP system.
First we focus on Production Plan. We receive Schedules from our Customers as:
Schedule from Maruti for July 2nd For Night OE & Spare Schedule Both Plant (Manesar & Gurgaon)
4. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
4
Other Customers and spare parts Schedule will be provided by Mr. Bharat.
5. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
5
On the basis of these delivery schedules Production Plan will be prepared.
RTM and Paint Shop for Unit 1 and Unit 2 Production plan prepared by Mr. Uday. Mr. Uday will fill
Production plan in these sheets. Mr. R.K. Gupta should help for preparation Production Plan for
Unit 2 for RTM products.
Production Plan (RTM and Paint Shop) for Unit 1
Production Plan (RTM and Paint Shop) for Unit 2
6. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
6
TCM Production Plan for Unit 1 and Unit 2 will be prepared by Mr. Satybir. Mr. Satybir will fill
Production plan in these sheets. Mr. R.K. Gupta should help for preparation Production Plan for
Unit 2 for RTM products.
Production Plan (TCM) for Unit 1
Production Plan (TCM) for Unit 2
7. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
7
PIM Production Plan for Unit 1 will be prepared by Mr. Satybir. Mr. Satybir will fill Production plan
in this sheet:
Production Plan (PIM) for Unit 1
We are running our PIM machines only on Electricity so daily planning is not possible for PIM
department. We are taking monthly planning from PIM.
Preparation to run MRP in SAP System:
These are the main points for run smooth MRP.
1. Inventory: Now our Physical and SAP system Inventory is matching.
2. Open Purchase Requisition: When we will run MRP old PR will be deleted automatically.
3. Open Purchase Orders: We will close old Purchase Orders.
4. Open Schedule Lines in Scheduling Agreements.
5. Open Production Orders: We will close all old unused Production Orders (TECO).
6. Open Planned Orders: We will close old Planned Orders.
7. Reorganizing Independent Requirements
8. Independent Requirements reorganization
9. Recorg. Independent Requirements
10. Delete Planned Independent Requirements
11. Create (Planned Independent Requirements ) Production Plan in SAP System
Finally Run MRP with MD02
8. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
8
2. Open Purchase Requisition: When we will run MRP open Purchase Requisition will be closed
automatically. Manually created Open Purchase Requisition will be closed with this. We will close
Open Purchase requisition on both NTF Unit 1 and Unit 2.
Tcode: ZPR_DELETE
3. Open Purchase Orders: We should close open Purchase Orders.
For getting list of open Purchase Orders these TCODE will be used.
ME2M, ME2L, ME2N
1) Make delivered quantity equal to order qty.
2) Block PO line items
3) Delete line items if there is no open GRâs or invoices.
4) Open Purchase orders will be close for both NTF Unit 1 and NTF Unit 2.
9. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
9
4. Open Schedule Lines in Scheduling Agreements.
We will get the list of open Scheduling Lines in Schedule Agreements. Open Schedule Lines should
be close for both NTF Unit 1 and NTF Unit 2 plants.
TCODE: ZOPENSHL
This is the list of open Schedule Lines. We should close these Schedule Lines in SAP System. These
Schedule Lines should not appear. These Schedule Lines are the vendor Schedules and we should
receive these materials in last month but not received and schedule lines are pending.
Now close schedule line in Scheduling Agreement.
10. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
10
TCODE: ME38
Enter Scheduling Agreement Number and press enter key.
11. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
11
5. Open Production Orders: We should close open production orders. For getting open
production orders
TCODE: COOIS
Delete
Qty.
12. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
12
13. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
13
Take the list of Open production orders. Open production order for (TECO) closing.
TCODE: CO02
14. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
14
15. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
15
Save the production Order.
If Quantity of open Production Orders is high then we should close in mass.
TCODE: COHV
16. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
16
17. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
17
18. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
18
Other condition for getting open Production Orders
19. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
19
Select layout as Standard Layout and press Select All tab right side on order screen.
Select Mass Processing Tab.
20. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
20
Select Technical Complete and press copy button then press execute button.
6. Open Planned Orders
21. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
21
For getting list of open Planned order and delete open planned order this tcode required.
TCODE: MD16
22. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
22
Press Select All as per below given screen.
23. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
23
Press Delete All.
All Open Planned Orders from NTF Unit 1 and NTF Unit 2 should delete from the SAP System.
24. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
24
7. Reorganizing Independent Requirements (Run for NTF Uint1 and NTF Unit2)
TCODE: MD74
Press to for run this utility. It will show this type of results.
25. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
25
8. Independent Requirements reorganization (Run for NTF Uint1 and NTF Unit2)
TCODE: MD75
Press to for run this utility. It will show this type of results
26. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
26
9. Recorg. Independent Requirements (Run for NTF Uint1 and NTF Unit2)
TCODE: MD76
Press to for run this utility. It will show this type of results
27. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
27
10.Delete Planned Independent Requirements
We enters production plan on daily basis for run MRP. For enter next month production plan we should
delete old Planned Independent requirement (production plan).
TCODE: MD62
We should delete all of these
entries.
28. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
28
Data Selection in the fields:
The select of data in these fields is very important.
(1) Product Group: We have created two main product groups.
TCODE: MC84
NTFUNIT1: For enter production planning for NTF Unit 1
29. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
29
NTFUNIT2: For enter production planning for NTF Unit 2
For display all Product Group we will use this Tcode.
TCODE: MC85
30. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
30
We want to see the Members of Product Group then user this:
TCODE: MC85
For NTFUNIT1 (Manesar Plant) product Group these are the members:
For NTFUNIT2 (Neemrana Plant) product Group these are the members:
31. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
31
For Add or change the Materials in product Group Members we will use this tcode.
TCODE: MC86
32. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
32
33. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
33
Add the Material and plant in the list and before save it press âDistribute
proportnsâ
Now Press save button for save material in product group member list.
Other Fields Data Selection for delete and enter production Plan:
Please check all marked fields according to document. Enter planning horizon date
according you production plan.
34. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
34
Create Planned Independent Requirements (Enter Production
Plan):
TCODE: MD61
Enter Daily Production Plan and save.
35. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
35
The below screen is the
production planning
cycle
36. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
36
Create Planned Independent Requirements MD61
Check In Stock Requirement List MD04
Online
Single Item Multi Level Multi Items
Order Confirmation & Scrap (FINAL) CO15
Excess Goods Issue for
production Orders
Release Order
1. Check Material Availability
2. Check Capacity Availability
Convert Planned Order into Production Order
Rework Confirmation
Partial Confirmation
Rework
Goods Receipt to FG Store (SPF1)
Sales Order
Background
Capacity Availability
Check
Finite Scheduling
Transfer into
Operative
Planning
LTP
MD4C
CO40 or MD04
> Enter Pld Order no
>OK
> Save
> Prod order no generated
Planning Run MD02
CO02
> Click Material Button
> Click Capacity Button
CO02
Click on Green FLAG button
and SAVE
MB1A (Store Department)
> movement type - 261
> Production Oder No.
MB31 Movement type
101,Sto. Loc. SPF1
37. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
37
PLANNING RUN (MRP RUN)
Def: The execution of materials planning for all materials or assemblies that have the nessary
entries in the planning file.
Planning File: A file that contains a list of all materials for which a change relevant to requirements
planning has occurred and that are automatically flagged for planning.
If such a change has taken place, the entry in the planning file is performed automatically. We
need not do anything as everything is done automatically but to check planning file the TCODE is
MZD21.
For this type of ne change planning, only materials that change relecant to MRP in the period are
planned in the planning run.
There are several types of planning run.
1. Total planning on-line TCODE = MD01
2. Single item-multi level TCODE = MD02
3. Single item â single level TCODE = MD03
4. Total planning back-ground TCODE = MD04
Here we run MRP back-ground every week once but we may require running MRP foreground
sometimes for single item.
TCODE: MD02
38. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
38
Enter the material to which planning is required.
MRP Control Parameters.
Processing Key: Enter NETCH
Create purchase req: Select 2 for purchase requisition in the opening period.
Delivery Schedules: Select 3 for schedule lines.
Create MRP list : Enter 1 for MRP List.
Planning Mode : Re-explode BOM and routing.
Scheduling : Lead time Scheduling and capacity planning.
Process Control Parameters
Tick Also plan Unchanged components.
Tick display results before they are saved.
Tick display material list.
After entering the above details press enter.
You get notification that âplease check input parametersâ. Again press enter.MRP run will takes
place and you can observe the following screen.
Press Save button.
39. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
39
First Select âProceed without stoppingâ radio button and then Press
Continue Tab
40. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
40
Press Material Tab on the screen for getting Material List.
41. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
41
We get the information of all the dependent materials.
Planned orders are created for items that are not available on date. For in-house production
dependent requirements we get planned orders and for external procurements items we get
either planned order or purchase requisitions depending upon the time availability of converting
planned orders to purchase requisitions in opening period.
The MRP controller will check the planning result and make changes if required in dates and
quantities.
The system carries out the following processes in the planning run:
1) The system checks the planning file. During this process, the system checks whether a material
is to be planned due to a change relevant to MRP, and how to proceed if there are already existing
procurement proposals.
2) The system calculates net requirements for every material. For this calculation, the system
checks whether the requirements are covered by the warehouse stock and dispatched receipts
from Purchasing or Production. If the requirements cannot be covered, the system creates a
procurement proposal.
3) The system calculates procurement quantities. When doing this, the system takes into account
the selected lot-sizing procedure and, if necessary, scrap and rounding values.
4) The system carries out the scheduling in order to calculate the start and finish dates for the
procurement proposals.
5) The system determines the type of procurement proposal. Dependent upon the defined setting,
planned orders, purchase requisitions or delivery schedules are created by the system for a
material.
6) For every procurement proposal of an assembly, the system explodes the BOM and determines
the dependent requirements.
7) During the planning run, the system recognizes critical situations that have to be assessed
manually in the planning result by the work scheduler. The system creates exception messages
and, if necessary, checks rescheduling.
42. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
42
Stock Requirement List:
In this list we can see all planned orders, Ind. Requirement and Vendor Schedule
lines.
TCODE: MD04
43. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
43
Master Data: Material Master
We should enter correct Master data in SAP system. This is to inform you all who are
creating new Material Master Data, Routing or BOM (with similar components and
work centers), are not adapting standard procedures. After creating Material in
Material Master, problem occurs at the time of production order creation or
material consumption or report generation.
The easiest and simplest way to create a Material Master data is to copy from the
old material or routing or BOM and edit wherever necessary so that chances of
committing errors can be reduced. So I am requesting you all who are responsible
for master data creation, let us not invent the wheel again.
Use Simplest way to create a Material in Material Master Data is to copy from the
old materials.
Some views are very important for run MRP. Please check these views:
MRP1
MRP2
MRP3
MRP4
Accounting
Costing
Enter old Material
number for Copy the material.
44. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
44
MRP 1 View:
MRP 2 View
45. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
45
MRP 3 View
MRP 4 View
46. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
46
Account 1 View
S: Standard price
for Finished and
semi-finished
goods.
V: Moving price
for Raw Materials
Enter or Check Profit Center
47. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
47
Purchasing View
Please check
Unit of
measure/EANs
in Purchasing
View ->
Additional
Data Tab.
48. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
48
WORK SCHEDULING View
Issue Storage Location: In the case of a material produced in-house, this is the key of the storage
location that is copied to the planned order or production order.
Production Scheduler: Scheduler responsible for a material in production activity control.
The production scheduler determines how capacity requirements are calculated for a material
during a scheduling run.
Production Scheduling Profile: Profile that you can use to
Specify that certain business transactions are carried out in parallel in a production order /
process order (you can, for example, create and release an order at the same time, or release
an order and print the shop papers)
Trigger an automatic goods receipt
Specify an overall profile for capacity leveling
Serial No Profile: The data grouped under a four-digit identification code that defines the
conditions and operations for assigning serial numbers for serialized materials.
49. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
49
The serial number profile must be entered in the master record of the material for which the
items are assigned serial numbers.
Batch entry: Defines when batches have to be determined.
We have the following options
The batches can be determined when the goods issue is posted.
The batches must be entered in the order before it is released.
The batches must be entered in the order before the goods issue is posted, but not necessarily
before the order is released
The batches are determined automatically when the order is released
Batch management: Specifies whether the material is managed in batches.
In house production time in days(Lot size dependant):
Set up and tear down time: Specifies the number of workdays needed to set up and tear down the
various work centers where the material is processed. This value is the total of the setup and
teardown times.
The setup and teardown time is independent of the order quantity.
Processing time: Specifies the time needed to process the material in the operations at the
different work centers.
The processing time depends on the order quantity.
Base quantity: Quantity to which the in house production time and the processing time of the
material relate.
We can also upload this data from routings.
When we maintain values for lot size dependent in-house production time in days we have to
carefully enter the values because it should be always equal or greater than the timings from
routings, otherwise the system will reduce the operation timings even though our intension is not
that.
50. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
50
Maintain MRP 2 View storage location in MMSC.
TCODE: MMSC
51. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
51
PRODUCTION VERSION MAINTENANCE IN MATERIAL MASTER
Production version is the combination of BOMâs and Routings and should be maintained in the
material master under the following conditions. Mainly this PV is used in the finished goods
material master.
Consider GYPSY HARD TOP for example. There are two versions of hard top we make for GYPSY,
they are Milky white and Olive Green with the same item code for ex.93610m83F00-26U.
When we create production order without creating PV, system will select Alternate BOM 1 and
Routing Group 1 for this item. Since we have two different BOMâs for this item (two colors) we
should have an option to choose one that we manufacture and here it is not possible. Also while
planning material procurement it is difficult to plan for Alternate BOM 2 materials. So PV is must
in such case.
When there is a difference of operation times for two different items of same item code, it is
difficult to select which process we adopt to manufacture the item or if there more than one
process available to make an item ( such as alternate routing) it is only possible with PV.
Here is a demo to create the PV in material master for item 93610M83F00-26U
Create different BOMâs for 93610M83F00-26U, such as alt BOM1 and alt BOM2.
Create different routings for 93610M83F00-26U (if required).
Now in the material master MRP 4 View click on PV
Here we need to create version as 0001, 0002 and so on along with validity
Here I am creating version 0003 as test 1 and click on details and the following screen appears. Fill
the details such as lot size, valid from and to date, task list type and alternate BOM as under
52. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
52
Click on check and you should get the following screen.
If both task list and BOM exists check status will become green as under
53. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
53
Continue and create as many versions as needed and save.
One another configuration setting required in material master is in MRP 4 tab page
Select 2 0r 3 in BOM selection method. This is how we have to maintain PV for different items with
same item code. As there is a need to maintain PV I am providing this document to all the users
who create the material master.
54. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
54
BOM:
Bill of Material Creation and updating is the responsibility of Engineering Department. For
getting change document (changes in the BOM) follow this process:
Go To Environment Tab and press Change Document:
55. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
55
Press Document Overview
All change documents:
Click on the doc. No. for getting details.
56. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
56
Where-Used List: Materials
This Tcode shows the materials used in BOM component.
TCODE: CS15
List of all components where this material is using.
57. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
57
Multi-Level BOM Report:
Menu
Transaction Code ZPP_BOM
58. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
58
59. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
59
For Searching Raw Material used in BOM
Enter Raw Material in (For material List BOM Component)
60. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
60
Creation of Routing
T-code: CA01
Pic. Shows the initial screen of creation of routings and the T-code is CA01.
We have to enter the material code for which we are going to create routing in the Material field.
We have to enter plant (7777).
Go to Header of the routing.
61. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
61
Enter the task list description.
Enter the task list usage as production.
Enter the status as 4 which indicate this routing or task list is released (general).
Enter the lot size if anything is applicable.
Come back the initial screen.
Position the cursor on the operations field and enter.
62. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
62
The operations screen appears.
The operational increment is 10 by default. Enter the work center assigned to the operation, in
work center field. Enter the control key in the field CO. The control key determines which business
transactions should be executed for the object that belongs to the task list or order. The business
transactions are whether the operations are included in scheduling. Costing automatic goods
receipt, mile stone conformation etc.
Enter the description of each operation.
Enter the base quantity, by default system takes 1.
Enter the Standard values (for ex. setup, labor etc).The standard values are planned values for
executing an operation. Standard values are used in costing, scheduling, and capacity planning to
calculate costs, execution times, and capacity requirements.
The setup operation is not depended upon the quantity but all other operations are depended
upon the operation quantity.
Ex.
Set up time =45min (die change).There we donât enter any machine or labor time.
63. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
63
The Next operation if it is done in machine work center we have to enter machine time and if
labor works then enters labor time.
In the Assembly work center where there is only labor involves enter labor time.
These timings are called standard values and used in calculation of capacities, scheduling and
costing functions.
Component allocations:
We have to assign materials to operations. The procedure is..
1) Click on component allocations and select materials and click on new assignment. In the
operation details all the operations are displayed. Select and assign materials to operations and
save.
The routing is saved with group and group counter.
If we have similar routings for several materials we can copy the routings .The procedure is
described below.
64. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
64
Enter the material to which the routing is to be created and click on copy from and selct routing
from the pop up screen. We get the below screen.
Fill up the material name from which we want to copy the routings and click on copy and we get
the operations copied. We can edit for changes.
65. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
65
Creation of Work Centers
An organizational unit that defines where and when an operation must be performed
The work center has an available capacity. Work centers can be:
Machines
People
Production lines
The initial screen of the work center is given below.
The T-Code to create work center is CR01.change CR02,DisplayCR03.
We have to enter the plant and name of the work center and work center category.
Ex: Plant =7777
Name of the Work center: LRTM
Work Center Category: 0001=machine,0003=Labor
66. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
66
We can copy work center from Different plants or in the same plant if they have got identical
characteristics.
Work Center is having 5 views.
1) basic data2) default values3) capacities4) scheduling and 5) costing
The basic data screen as follows
We need to enter the description of work centered: RTM work center.
Person responsible: the person who is responsible for that work center.
Usage: Key to control in which type of Routings we use work centers. Here it is 009=all task list
types.
Standard value key: Key defining and giving a dimension (for example, time or area) to one of up
to six standard values.
We use the parameter ID to determine the key word for a standard value, such as setup, machine
or labor. We assign values to the standard values in the task list.
67. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
67
Default Values Screen
Control key: Determines which business transactions should be executed for the object that
belongs to the routing or order.
We have discussed about control key in routing, but if we tick in Ref.ID this is copied for an
operation otherwise what is given in routing or task list is considered.
No. of time tickets: Number of time tickets to be printed for an operation. This entry is only taken
into account if time tickets are to be printed according to the operation control key. The value
from the work center is the default in the routing.
No. of Conformation slips: Number of confirmation slips to be printed for an operation or an
activity. The system prints confirmations if the control key for the operation or activity has been
set. The value from the work center is the default in the routing.
68. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
68
Capacities
In capacities screen we have to enter the formulas for setup requirements, processing
requirements and other requirements if necessary. The formulas you can find by using drop down
menu .The capacity category we have to enter if it is the machine category or labor category. A
machine can have labor capacity, (crew working on that machine)can be entered as additional
capacity in the same view. We need to enter data in another screen for capacities.
69. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
69
Capacity planner grp: Key referring to the capacity planner group, which is responsible for
planning this capacity.
Factory calendar ID: IN
Active version: The active version of available capacity is used as a basis for scheduling. The
different versions allow you to maintain several available capacities at the same time.
Base Unit of measure: Unit in which available capacity is maintained
Standard available capacity: We have to define the available capacity(start time, finish time ,length
of breaks and no. of individual capacities).By entering these values we get standard available
capacity.
Planning details: We define whether the work center capacities are relevant to finite scheduling,
can be used by several operations and for long term planning.
Scheduling
In the capacity category we enter the main category of the work center.
Set up formula, processing formula: Here we assign formula in view of scheduling
Location group: Define where this work center is located.
70. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
70
Work dimension, Work Unit: Define work dimension and units of work as TIME and HR.
Capacities in scheduling:
Capacities relevant to scheduling point of view
71. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
71
COSTING
We have to assign the activity types and the relevant formulas for costing purpose.
72. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
72
Reference operation set
A type of routing that comprises of a series of operations that recur frequently. It is used to create
a routing.
A reference operation set cannot be used directly in production.
A reference operation set has the same structure as a routing. We cannot assign a material to be
produced to a reference operation set.
The T-Code to create reference operation set is CA11.
This is the default screen of the reference operation set.
Group: Here we can assign numeric key if it is required to combine several task lists. Otherwise
system will assign internal number automatically.
Click on header icon. System will display header for reference operation set.
73. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
73
Group counter: This key and the task list group uniquely identify a routing. By default it is 1.
We need to fill the task list description.
Usage: Enter 1 for production.
Status: Enter 4 for released (general).
Enter the lot size if it is required and enter the unit of measure.
After entering data in above fields click operations. The operations screen is similar as routing
operations screen.
After entering values in operations screen save the reference operation set. The message will be
displayed as below.
Reference operation set was saved with group (ex.) 50000014.
74. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
74
Trigger Points
A trigger point is an object that can be assigned to an operation in order to trigger a function. The
T-code for creation of trigger points is CO31.
Trigger points can trigger functions,
If the status of an operation changes
When an operation is confirmed, in this case the user decides whether the function is
triggered.
The default screen for creation of trigger points
We have to enter the name of the trigger point.
The following screen appears.
75. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
75
We have to enter
Trigger point usage: Grouping (standard) trigger points by their usage can have the following
advantages: It becomes easier to locate similar trigger points
When you enter a usage, the system lists all standard trigger points that have the same usage. It
can display the type of function behind the trigger point.
Trigger point Group: A combination of standard trigger points.
We have click on the usage whether it is for triggering functions or used as release stop indicator
and also the function which is to be activated. In the pic. Trig point functions checkbox is ticked. It
means when the trigger point is activated and creates order with reference.
Enter the system status and click on the status change triggering function.
Activate once indicator: Use this indicator to specify that the milestone function can only be
triggered once.
Put the cursor on create order with reference and click on parameters. You can find the below
screen
76. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
76
We need to enter the system status, and status change as â+â,execute once indicator, group as well
as group counter and order type as âZp01â.(or any other rework order type).
So when any order is partially confirmed the trigger point automatically triggers rework order or
reference operation set depends on the setting what we have entered.
If it triggers rework order the internal number assignment is done (the immediate no. of main
production order is created with order type ZP01).We have to manually confirm the rework
production order and goods movements and settlement is done for this to main production order.
77. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
77
Production Resource Tools
Production Resource/Tool (PRT) is a moveable operating resource used in production or plant
maintenance. We can assign production resources and tools to the task lists and production
orders for which they are required.
Creation of PRT: T-code CF01
Enter the PRT name.
Press enter.
78. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
78
The screen follows
Enter the status as 03 =released for production
Task list usage =009
Base unit of measure = EA
Plant =7777
Location=0001
Grouping key =2000 for fixtures.
And press defaults
79. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
79
You will see the following screen:
Enter control key =1
Quantity formula =SAPF01
Usage value formula =SAPF02
Ref.date for start = 01
Ref. date for finish =04
80. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
80
Go to extras and formula constants and you will find below screen.
Enter the prt quantity and units as 2 nos and EA.
81. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
81
Now we Closed these Movement Type:
These (202,309,521) movement type is effecting our financial data and a lot of problems
occurred in Balance sheet.
82. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
82
Check Vendor Schedules:
We should check vendor schedules with this Tcode.
TCODE: ZOPENSHL
These materials should receive on 23.07.2012 from respected vendors.
83. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
83
Manually Created Schedule Lines:
TCODE: YSLC
84. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
84
In Scheduling Agreements Schedule Lines will be created by MRP. We
closed manually creation of schedule lines in Vendor Scheduling
Agreements.
We closed Manually Creation of Production Orders. TCODE - CO01 Closed.
On the basis of Production plan MRP will create planned orders and users will
convert these planned orders in Production Orders. If there is any change in
production plan we will change production plan in SAP system and run MRP again
for getting planned orders and Procurement schedule lines.
TCODE: MD04
85. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
85
Select PldOrd and convert it in Production Order.
User can convert total order qty.
Or
User can convert PartConvProdOrder
86. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
86
87. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
87
Scrap and rework doc
TCODE: CO01
Order is created for 200 qty for 88912M68K00
Order conformation
88. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
88
TCODE: CO15
Order is confirmed with 145 Nos , rework of 33 nos and rejection or scrap of 22 nos as shown in
below screen and reason for variance in order quantity is also entered. Save confirmation.
TCODE: MB31
GR is done for confirmed quantity only, that is 145 nos
89. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
89
System show the screen below as deficit of order quantity 55 nos, ignore this message.
After rework you can GR ( no conformation again) the quantity as shown below.
Suzzest zero lines indicator as shown. Enter the rework order qty as 33 in the units of entry and
save the order.
90. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
90
Now the order quantity received is 178.
do GR in MB31 screen for 22 nos in scrap storage location.
91. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
91
The material in the Scrap store is scrapped by using 551 goods movement later in mb1a as below.
TCODE: MB1A (Movement Type is 551)
92. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
92
If you have created a Production orders and some change in BOM required.
Engineering Department change in BOM and that change material are not
effective in old production orders. This process will update BOM material in
production orders after change in BOM.
TCODE-CO02
Open production order in change mode.
93. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
93
Go to Functions menu and Select Read PP master data.
94. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
94
Click on check box âNew BOMâ and enter todayâs date for explosion new/change
BOM in production order.
95. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
95
SAP TCODES FOR PRODUCTION USERS
TCODE Description
MM03 Display Material
MMBE Stock Overview
MM60 Material List
CS03 Display Material BOM
CS11 Explode BOM: Level by Level
CS12 Explode BOM: Multi Level BOM
CS13 Explode BOM: Summarized BOM
CR01 Create Work Center
CR02 Change Work Center
CR03 Display Work Center
CR11 Create Capacity
CR12 Change Capacity
CR13 Display Capacity
CR05 Work Center List
CA80 Work Center Where-Used
CR15 Capacity Where-Used
CR10 Work Center Change Document
CA01 Create Routing
CA02 Change Routing
CA03 Display Routing
CA12 Change Reference Operation Set
CA13 Display Reference Operation Set
MD61 Create Planned Independent Requirements
MD62 Change Planned Independent Requirements
MD63 Display Planned Independent Requirements
MD4C Multilevel Order Report
96. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
96
Evaluations
MD04 Stock / Requirements List
MD07 Collective access of stock / requirements list
MD05 MRP List
MD06 Collective access of MRP lists
CO46 Order Progress
Planned Order
MD11 Create planned order
MD12 Change planned order
MD13 Display planned order
MD16 Collective access of planned orders
MD14 Individual conversion of planned order into
MD15 Collective conversion of planned orders int
MDVP Collective availability check
CO01 Production order create (With Material)
CO07 Production order create (Without Material)
CO40 Production order create (From Planned Order)
CO41 Collective convention of planned order
CO08 Production order create (For Sales Order)
COHV Mass Processing Production Orders
COMAC Collective Availability check
CO05N Release Production Orders
CO04N Print Production Orders
CO09 Availability Overwiew
MB1A Enter Goods Issue
MB31 Goods Receipt for order
97. NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
97
Reports
COOIS Order Information System
MCP7 Work Center Analysis
MCP1 Operation Analysis
MCP5 Material Analysis
MCP3 Production Order Analysis
MCRE Material Uses Analysis
MCYJ Shop Floor Information System
CO20 Orders Acc. to Order Number
CO21 Orders for material
CO22 Orders for MRP Controller
CO23 Orders for Production Scheduler
CO24 Missing Parts Info System
CO27 Picking List
CO28 Selection of Indiv. Objects List
CO26 Order Information System