NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
1
SAP USER TRAINING DOCUMENT
MRP
By Kanti Kumar
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
2
Experts agree that you get the most from your ERP software
when users become accepting, comfortable, and proficient
performing the new business processes the software
supports. In other words, much of the success of a multi-
million dollar ERP implementation depends on the
people using the system for day-to-day work.
Our Aims and Ideals
To train you on higher level in SAP ERP, that
is our aim.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
3
MRP Process in SAP System
We run MRP for generating Vendor Schedules. This document will show process in SAP for
Production plan to material receive from vendors through SAP system.
First we focus on Production Plan. We receive Schedules from our Customers as:
Schedule from Maruti for July 2nd For Night OE & Spare Schedule Both Plant (Manesar & Gurgaon)
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
4
Other Customers and spare parts Schedule will be provided by Mr. Bharat.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
5
On the basis of these delivery schedules Production Plan will be prepared.
RTM and Paint Shop for Unit 1 and Unit 2 Production plan prepared by Mr. Uday. Mr. Uday will fill
Production plan in these sheets. Mr. R.K. Gupta should help for preparation Production Plan for
Unit 2 for RTM products.
Production Plan (RTM and Paint Shop) for Unit 1
Production Plan (RTM and Paint Shop) for Unit 2
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
6
TCM Production Plan for Unit 1 and Unit 2 will be prepared by Mr. Satybir. Mr. Satybir will fill
Production plan in these sheets. Mr. R.K. Gupta should help for preparation Production Plan for
Unit 2 for RTM products.
Production Plan (TCM) for Unit 1
Production Plan (TCM) for Unit 2
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
7
PIM Production Plan for Unit 1 will be prepared by Mr. Satybir. Mr. Satybir will fill Production plan
in this sheet:
Production Plan (PIM) for Unit 1
We are running our PIM machines only on Electricity so daily planning is not possible for PIM
department. We are taking monthly planning from PIM.
Preparation to run MRP in SAP System:
These are the main points for run smooth MRP.
1. Inventory: Now our Physical and SAP system Inventory is matching.
2. Open Purchase Requisition: When we will run MRP old PR will be deleted automatically.
3. Open Purchase Orders: We will close old Purchase Orders.
4. Open Schedule Lines in Scheduling Agreements.
5. Open Production Orders: We will close all old unused Production Orders (TECO).
6. Open Planned Orders: We will close old Planned Orders.
7. Reorganizing Independent Requirements
8. Independent Requirements reorganization
9. Recorg. Independent Requirements
10. Delete Planned Independent Requirements
11. Create (Planned Independent Requirements ) Production Plan in SAP System
Finally Run MRP with MD02
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
8
2. Open Purchase Requisition: When we will run MRP open Purchase Requisition will be closed
automatically. Manually created Open Purchase Requisition will be closed with this. We will close
Open Purchase requisition on both NTF Unit 1 and Unit 2.
Tcode: ZPR_DELETE
3. Open Purchase Orders: We should close open Purchase Orders.
For getting list of open Purchase Orders these TCODE will be used.
ME2M, ME2L, ME2N
1) Make delivered quantity equal to order qty.
2) Block PO line items
3) Delete line items if there is no open GR’s or invoices.
4) Open Purchase orders will be close for both NTF Unit 1 and NTF Unit 2.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
9
4. Open Schedule Lines in Scheduling Agreements.
We will get the list of open Scheduling Lines in Schedule Agreements. Open Schedule Lines should
be close for both NTF Unit 1 and NTF Unit 2 plants.
TCODE: ZOPENSHL
This is the list of open Schedule Lines. We should close these Schedule Lines in SAP System. These
Schedule Lines should not appear. These Schedule Lines are the vendor Schedules and we should
receive these materials in last month but not received and schedule lines are pending.
Now close schedule line in Scheduling Agreement.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
10
TCODE: ME38
Enter Scheduling Agreement Number and press enter key.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
11
5. Open Production Orders: We should close open production orders. For getting open
production orders
TCODE: COOIS
Delete
Qty.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
12
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
13
Take the list of Open production orders. Open production order for (TECO) closing.
TCODE: CO02
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
14
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
15
Save the production Order.
If Quantity of open Production Orders is high then we should close in mass.
TCODE: COHV
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
16
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
17
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
18
Other condition for getting open Production Orders
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
19
Select layout as Standard Layout and press Select All tab right side on order screen.
Select Mass Processing Tab.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
20
Select Technical Complete and press copy button then press execute button.
6. Open Planned Orders
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
21
For getting list of open Planned order and delete open planned order this tcode required.
TCODE: MD16
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
22
Press Select All as per below given screen.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
23
Press Delete All.
All Open Planned Orders from NTF Unit 1 and NTF Unit 2 should delete from the SAP System.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
24
7. Reorganizing Independent Requirements (Run for NTF Uint1 and NTF Unit2)
TCODE: MD74
Press to for run this utility. It will show this type of results.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
25
8. Independent Requirements reorganization (Run for NTF Uint1 and NTF Unit2)
TCODE: MD75
Press to for run this utility. It will show this type of results
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
26
9. Recorg. Independent Requirements (Run for NTF Uint1 and NTF Unit2)
TCODE: MD76
Press to for run this utility. It will show this type of results
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
27
10.Delete Planned Independent Requirements
We enters production plan on daily basis for run MRP. For enter next month production plan we should
delete old Planned Independent requirement (production plan).
TCODE: MD62
We should delete all of these
entries.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
28
Data Selection in the fields:
The select of data in these fields is very important.
(1) Product Group: We have created two main product groups.
TCODE: MC84
NTFUNIT1: For enter production planning for NTF Unit 1
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
29
NTFUNIT2: For enter production planning for NTF Unit 2
For display all Product Group we will use this Tcode.
TCODE: MC85
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
30
We want to see the Members of Product Group then user this:
TCODE: MC85
For NTFUNIT1 (Manesar Plant) product Group these are the members:
For NTFUNIT2 (Neemrana Plant) product Group these are the members:
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
31
For Add or change the Materials in product Group Members we will use this tcode.
TCODE: MC86
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
32
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
33
Add the Material and plant in the list and before save it press “Distribute
proportns”
Now Press save button for save material in product group member list.
Other Fields Data Selection for delete and enter production Plan:
Please check all marked fields according to document. Enter planning horizon date
according you production plan.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
34
Create Planned Independent Requirements (Enter Production
Plan):
TCODE: MD61
Enter Daily Production Plan and save.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
35
The below screen is the
production planning
cycle
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
36
Create Planned Independent Requirements MD61
Check In Stock Requirement List MD04
Online
Single Item Multi Level Multi Items
Order Confirmation & Scrap (FINAL) CO15
Excess Goods Issue for
production Orders
Release Order
1. Check Material Availability
2. Check Capacity Availability
Convert Planned Order into Production Order
Rework Confirmation
Partial Confirmation
Rework
Goods Receipt to FG Store (SPF1)
Sales Order
Background
Capacity Availability
Check
Finite Scheduling
Transfer into
Operative
Planning
LTP
MD4C
CO40 or MD04
> Enter Pld Order no
>OK
> Save
> Prod order no generated
Planning Run MD02
CO02
> Click Material Button
> Click Capacity Button
CO02
Click on Green FLAG button
and SAVE
MB1A (Store Department)
> movement type - 261
> Production Oder No.
MB31 Movement type
101,Sto. Loc. SPF1
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
37
PLANNING RUN (MRP RUN)
Def: The execution of materials planning for all materials or assemblies that have the nessary
entries in the planning file.
Planning File: A file that contains a list of all materials for which a change relevant to requirements
planning has occurred and that are automatically flagged for planning.
If such a change has taken place, the entry in the planning file is performed automatically. We
need not do anything as everything is done automatically but to check planning file the TCODE is
MZD21.
For this type of ne change planning, only materials that change relecant to MRP in the period are
planned in the planning run.
There are several types of planning run.
1. Total planning on-line TCODE = MD01
2. Single item-multi level TCODE = MD02
3. Single item – single level TCODE = MD03
4. Total planning back-ground TCODE = MD04
Here we run MRP back-ground every week once but we may require running MRP foreground
sometimes for single item.
TCODE: MD02
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
38
Enter the material to which planning is required.
MRP Control Parameters.
Processing Key: Enter NETCH
Create purchase req: Select 2 for purchase requisition in the opening period.
Delivery Schedules: Select 3 for schedule lines.
Create MRP list : Enter 1 for MRP List.
Planning Mode : Re-explode BOM and routing.
Scheduling : Lead time Scheduling and capacity planning.
Process Control Parameters
Tick Also plan Unchanged components.
Tick display results before they are saved.
Tick display material list.
After entering the above details press enter.
You get notification that “please check input parameters”. Again press enter.MRP run will takes
place and you can observe the following screen.
Press Save button.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
39
First Select “Proceed without stopping” radio button and then Press
Continue Tab
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
40
Press Material Tab on the screen for getting Material List.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
41
We get the information of all the dependent materials.
Planned orders are created for items that are not available on date. For in-house production
dependent requirements we get planned orders and for external procurements items we get
either planned order or purchase requisitions depending upon the time availability of converting
planned orders to purchase requisitions in opening period.
The MRP controller will check the planning result and make changes if required in dates and
quantities.
The system carries out the following processes in the planning run:
1) The system checks the planning file. During this process, the system checks whether a material
is to be planned due to a change relevant to MRP, and how to proceed if there are already existing
procurement proposals.
2) The system calculates net requirements for every material. For this calculation, the system
checks whether the requirements are covered by the warehouse stock and dispatched receipts
from Purchasing or Production. If the requirements cannot be covered, the system creates a
procurement proposal.
3) The system calculates procurement quantities. When doing this, the system takes into account
the selected lot-sizing procedure and, if necessary, scrap and rounding values.
4) The system carries out the scheduling in order to calculate the start and finish dates for the
procurement proposals.
5) The system determines the type of procurement proposal. Dependent upon the defined setting,
planned orders, purchase requisitions or delivery schedules are created by the system for a
material.
6) For every procurement proposal of an assembly, the system explodes the BOM and determines
the dependent requirements.
7) During the planning run, the system recognizes critical situations that have to be assessed
manually in the planning result by the work scheduler. The system creates exception messages
and, if necessary, checks rescheduling.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
42
Stock Requirement List:
In this list we can see all planned orders, Ind. Requirement and Vendor Schedule
lines.
TCODE: MD04
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
43
Master Data: Material Master
We should enter correct Master data in SAP system. This is to inform you all who are
creating new Material Master Data, Routing or BOM (with similar components and
work centers), are not adapting standard procedures. After creating Material in
Material Master, problem occurs at the time of production order creation or
material consumption or report generation.
The easiest and simplest way to create a Material Master data is to copy from the
old material or routing or BOM and edit wherever necessary so that chances of
committing errors can be reduced. So I am requesting you all who are responsible
for master data creation, let us not invent the wheel again.
Use Simplest way to create a Material in Material Master Data is to copy from the
old materials.
Some views are very important for run MRP. Please check these views:
MRP1
MRP2
MRP3
MRP4
Accounting
Costing
Enter old Material
number for Copy the material.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
44
MRP 1 View:
MRP 2 View
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
45
MRP 3 View
MRP 4 View
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
46
Account 1 View
S: Standard price
for Finished and
semi-finished
goods.
V: Moving price
for Raw Materials
Enter or Check Profit Center
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
47
Purchasing View
Please check
Unit of
measure/EANs
in Purchasing
View ->
Additional
Data Tab.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
48
WORK SCHEDULING View
Issue Storage Location: In the case of a material produced in-house, this is the key of the storage
location that is copied to the planned order or production order.
Production Scheduler: Scheduler responsible for a material in production activity control.
The production scheduler determines how capacity requirements are calculated for a material
during a scheduling run.
Production Scheduling Profile: Profile that you can use to
Specify that certain business transactions are carried out in parallel in a production order /
process order (you can, for example, create and release an order at the same time, or release
an order and print the shop papers)
Trigger an automatic goods receipt
Specify an overall profile for capacity leveling
Serial No Profile: The data grouped under a four-digit identification code that defines the
conditions and operations for assigning serial numbers for serialized materials.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
49
The serial number profile must be entered in the master record of the material for which the
items are assigned serial numbers.
Batch entry: Defines when batches have to be determined.
We have the following options
The batches can be determined when the goods issue is posted.
The batches must be entered in the order before it is released.
The batches must be entered in the order before the goods issue is posted, but not necessarily
before the order is released
The batches are determined automatically when the order is released
Batch management: Specifies whether the material is managed in batches.
In house production time in days(Lot size dependant):
Set up and tear down time: Specifies the number of workdays needed to set up and tear down the
various work centers where the material is processed. This value is the total of the setup and
teardown times.
The setup and teardown time is independent of the order quantity.
Processing time: Specifies the time needed to process the material in the operations at the
different work centers.
The processing time depends on the order quantity.
Base quantity: Quantity to which the in house production time and the processing time of the
material relate.
We can also upload this data from routings.
When we maintain values for lot size dependent in-house production time in days we have to
carefully enter the values because it should be always equal or greater than the timings from
routings, otherwise the system will reduce the operation timings even though our intension is not
that.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
50
Maintain MRP 2 View storage location in MMSC.
TCODE: MMSC
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
51
PRODUCTION VERSION MAINTENANCE IN MATERIAL MASTER
Production version is the combination of BOM’s and Routings and should be maintained in the
material master under the following conditions. Mainly this PV is used in the finished goods
material master.
Consider GYPSY HARD TOP for example. There are two versions of hard top we make for GYPSY,
they are Milky white and Olive Green with the same item code for ex.93610m83F00-26U.
When we create production order without creating PV, system will select Alternate BOM 1 and
Routing Group 1 for this item. Since we have two different BOM’s for this item (two colors) we
should have an option to choose one that we manufacture and here it is not possible. Also while
planning material procurement it is difficult to plan for Alternate BOM 2 materials. So PV is must
in such case.
When there is a difference of operation times for two different items of same item code, it is
difficult to select which process we adopt to manufacture the item or if there more than one
process available to make an item ( such as alternate routing) it is only possible with PV.
Here is a demo to create the PV in material master for item 93610M83F00-26U
Create different BOM’s for 93610M83F00-26U, such as alt BOM1 and alt BOM2.
Create different routings for 93610M83F00-26U (if required).
Now in the material master MRP 4 View click on PV
Here we need to create version as 0001, 0002 and so on along with validity
Here I am creating version 0003 as test 1 and click on details and the following screen appears. Fill
the details such as lot size, valid from and to date, task list type and alternate BOM as under
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
52
Click on check and you should get the following screen.
If both task list and BOM exists check status will become green as under
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
53
Continue and create as many versions as needed and save.
One another configuration setting required in material master is in MRP 4 tab page
Select 2 0r 3 in BOM selection method. This is how we have to maintain PV for different items with
same item code. As there is a need to maintain PV I am providing this document to all the users
who create the material master.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
54
BOM:
Bill of Material Creation and updating is the responsibility of Engineering Department. For
getting change document (changes in the BOM) follow this process:
Go To Environment Tab and press Change Document:
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
55
Press Document Overview
All change documents:
Click on the doc. No. for getting details.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
56
Where-Used List: Materials
This Tcode shows the materials used in BOM component.
TCODE: CS15
List of all components where this material is using.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
57
Multi-Level BOM Report:
Menu
Transaction Code ZPP_BOM
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
58
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
59
For Searching Raw Material used in BOM
Enter Raw Material in (For material List BOM Component)
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
60
Creation of Routing
T-code: CA01
Pic. Shows the initial screen of creation of routings and the T-code is CA01.
We have to enter the material code for which we are going to create routing in the Material field.
We have to enter plant (7777).
Go to Header of the routing.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
61
Enter the task list description.
Enter the task list usage as production.
Enter the status as 4 which indicate this routing or task list is released (general).
Enter the lot size if anything is applicable.
Come back the initial screen.
Position the cursor on the operations field and enter.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
62
The operations screen appears.
The operational increment is 10 by default. Enter the work center assigned to the operation, in
work center field. Enter the control key in the field CO. The control key determines which business
transactions should be executed for the object that belongs to the task list or order. The business
transactions are whether the operations are included in scheduling. Costing automatic goods
receipt, mile stone conformation etc.
Enter the description of each operation.
Enter the base quantity, by default system takes 1.
Enter the Standard values (for ex. setup, labor etc).The standard values are planned values for
executing an operation. Standard values are used in costing, scheduling, and capacity planning to
calculate costs, execution times, and capacity requirements.
The setup operation is not depended upon the quantity but all other operations are depended
upon the operation quantity.
Ex.
Set up time =45min (die change).There we don’t enter any machine or labor time.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
63
The Next operation if it is done in machine work center we have to enter machine time and if
labor works then enters labor time.
In the Assembly work center where there is only labor involves enter labor time.
These timings are called standard values and used in calculation of capacities, scheduling and
costing functions.
Component allocations:
We have to assign materials to operations. The procedure is..
1) Click on component allocations and select materials and click on new assignment. In the
operation details all the operations are displayed. Select and assign materials to operations and
save.
The routing is saved with group and group counter.
If we have similar routings for several materials we can copy the routings .The procedure is
described below.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
64
Enter the material to which the routing is to be created and click on copy from and selct routing
from the pop up screen. We get the below screen.
Fill up the material name from which we want to copy the routings and click on copy and we get
the operations copied. We can edit for changes.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
65
Creation of Work Centers
An organizational unit that defines where and when an operation must be performed
The work center has an available capacity. Work centers can be:
Machines
People
Production lines
The initial screen of the work center is given below.
The T-Code to create work center is CR01.change CR02,DisplayCR03.
We have to enter the plant and name of the work center and work center category.
Ex: Plant =7777
Name of the Work center: LRTM
Work Center Category: 0001=machine,0003=Labor
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
66
We can copy work center from Different plants or in the same plant if they have got identical
characteristics.
Work Center is having 5 views.
1) basic data2) default values3) capacities4) scheduling and 5) costing
The basic data screen as follows
We need to enter the description of work centered: RTM work center.
Person responsible: the person who is responsible for that work center.
Usage: Key to control in which type of Routings we use work centers. Here it is 009=all task list
types.
Standard value key: Key defining and giving a dimension (for example, time or area) to one of up
to six standard values.
We use the parameter ID to determine the key word for a standard value, such as setup, machine
or labor. We assign values to the standard values in the task list.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
67
Default Values Screen
Control key: Determines which business transactions should be executed for the object that
belongs to the routing or order.
We have discussed about control key in routing, but if we tick in Ref.ID this is copied for an
operation otherwise what is given in routing or task list is considered.
No. of time tickets: Number of time tickets to be printed for an operation. This entry is only taken
into account if time tickets are to be printed according to the operation control key. The value
from the work center is the default in the routing.
No. of Conformation slips: Number of confirmation slips to be printed for an operation or an
activity. The system prints confirmations if the control key for the operation or activity has been
set. The value from the work center is the default in the routing.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
68
Capacities
In capacities screen we have to enter the formulas for setup requirements, processing
requirements and other requirements if necessary. The formulas you can find by using drop down
menu .The capacity category we have to enter if it is the machine category or labor category. A
machine can have labor capacity, (crew working on that machine)can be entered as additional
capacity in the same view. We need to enter data in another screen for capacities.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
69
Capacity planner grp: Key referring to the capacity planner group, which is responsible for
planning this capacity.
Factory calendar ID: IN
Active version: The active version of available capacity is used as a basis for scheduling. The
different versions allow you to maintain several available capacities at the same time.
Base Unit of measure: Unit in which available capacity is maintained
Standard available capacity: We have to define the available capacity(start time, finish time ,length
of breaks and no. of individual capacities).By entering these values we get standard available
capacity.
Planning details: We define whether the work center capacities are relevant to finite scheduling,
can be used by several operations and for long term planning.
Scheduling
In the capacity category we enter the main category of the work center.
Set up formula, processing formula: Here we assign formula in view of scheduling
Location group: Define where this work center is located.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
70
Work dimension, Work Unit: Define work dimension and units of work as TIME and HR.
Capacities in scheduling:
Capacities relevant to scheduling point of view
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
71
COSTING
We have to assign the activity types and the relevant formulas for costing purpose.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
72
Reference operation set
A type of routing that comprises of a series of operations that recur frequently. It is used to create
a routing.
A reference operation set cannot be used directly in production.
A reference operation set has the same structure as a routing. We cannot assign a material to be
produced to a reference operation set.
The T-Code to create reference operation set is CA11.
This is the default screen of the reference operation set.
Group: Here we can assign numeric key if it is required to combine several task lists. Otherwise
system will assign internal number automatically.
Click on header icon. System will display header for reference operation set.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
73
Group counter: This key and the task list group uniquely identify a routing. By default it is 1.
We need to fill the task list description.
Usage: Enter 1 for production.
Status: Enter 4 for released (general).
Enter the lot size if it is required and enter the unit of measure.
After entering data in above fields click operations. The operations screen is similar as routing
operations screen.
After entering values in operations screen save the reference operation set. The message will be
displayed as below.
Reference operation set was saved with group (ex.) 50000014.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
74
Trigger Points
A trigger point is an object that can be assigned to an operation in order to trigger a function. The
T-code for creation of trigger points is CO31.
Trigger points can trigger functions,
If the status of an operation changes
When an operation is confirmed, in this case the user decides whether the function is
triggered.
The default screen for creation of trigger points
We have to enter the name of the trigger point.
The following screen appears.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
75
We have to enter
Trigger point usage: Grouping (standard) trigger points by their usage can have the following
advantages: It becomes easier to locate similar trigger points
When you enter a usage, the system lists all standard trigger points that have the same usage. It
can display the type of function behind the trigger point.
Trigger point Group: A combination of standard trigger points.
We have click on the usage whether it is for triggering functions or used as release stop indicator
and also the function which is to be activated. In the pic. Trig point functions checkbox is ticked. It
means when the trigger point is activated and creates order with reference.
Enter the system status and click on the status change triggering function.
Activate once indicator: Use this indicator to specify that the milestone function can only be
triggered once.
Put the cursor on create order with reference and click on parameters. You can find the below
screen
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
76
We need to enter the system status, and status change as ‘+’,execute once indicator, group as well
as group counter and order type as ‘Zp01’.(or any other rework order type).
So when any order is partially confirmed the trigger point automatically triggers rework order or
reference operation set depends on the setting what we have entered.
If it triggers rework order the internal number assignment is done (the immediate no. of main
production order is created with order type ZP01).We have to manually confirm the rework
production order and goods movements and settlement is done for this to main production order.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
77
Production Resource Tools
Production Resource/Tool (PRT) is a moveable operating resource used in production or plant
maintenance. We can assign production resources and tools to the task lists and production
orders for which they are required.
Creation of PRT: T-code CF01
Enter the PRT name.
Press enter.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
78
The screen follows
Enter the status as 03 =released for production
Task list usage =009
Base unit of measure = EA
Plant =7777
Location=0001
Grouping key =2000 for fixtures.
And press defaults
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
79
You will see the following screen:
Enter control key =1
Quantity formula =SAPF01
Usage value formula =SAPF02
Ref.date for start = 01
Ref. date for finish =04
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
80
Go to extras and formula constants and you will find below screen.
Enter the prt quantity and units as 2 nos and EA.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
81
Now we Closed these Movement Type:
These (202,309,521) movement type is effecting our financial data and a lot of problems
occurred in Balance sheet.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
82
Check Vendor Schedules:
We should check vendor schedules with this Tcode.
TCODE: ZOPENSHL
These materials should receive on 23.07.2012 from respected vendors.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
83
Manually Created Schedule Lines:
TCODE: YSLC
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
84
In Scheduling Agreements Schedule Lines will be created by MRP. We
closed manually creation of schedule lines in Vendor Scheduling
Agreements.
We closed Manually Creation of Production Orders. TCODE - CO01 Closed.
On the basis of Production plan MRP will create planned orders and users will
convert these planned orders in Production Orders. If there is any change in
production plan we will change production plan in SAP system and run MRP again
for getting planned orders and Procurement schedule lines.
TCODE: MD04
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
85
Select PldOrd and convert it in Production Order.
User can convert total order qty.
Or
User can convert PartConvProdOrder
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
86
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
87
Scrap and rework doc
TCODE: CO01
Order is created for 200 qty for 88912M68K00
Order conformation
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
88
TCODE: CO15
Order is confirmed with 145 Nos , rework of 33 nos and rejection or scrap of 22 nos as shown in
below screen and reason for variance in order quantity is also entered. Save confirmation.
TCODE: MB31
GR is done for confirmed quantity only, that is 145 nos
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
89
System show the screen below as deficit of order quantity 55 nos, ignore this message.
After rework you can GR ( no conformation again) the quantity as shown below.
Suzzest zero lines indicator as shown. Enter the rework order qty as 33 in the units of entry and
save the order.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
90
Now the order quantity received is 178.
do GR in MB31 screen for 22 nos in scrap storage location.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
91
The material in the Scrap store is scrapped by using 551 goods movement later in mb1a as below.
TCODE: MB1A (Movement Type is 551)
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
92
If you have created a Production orders and some change in BOM required.
Engineering Department change in BOM and that change material are not
effective in old production orders. This process will update BOM material in
production orders after change in BOM.
TCODE-CO02
Open production order in change mode.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
93
Go to Functions menu and Select Read PP master data.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
94
Click on check box “New BOM” and enter today’s date for explosion new/change
BOM in production order.
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
95
SAP TCODES FOR PRODUCTION USERS
TCODE Description
MM03 Display Material
MMBE Stock Overview
MM60 Material List
CS03 Display Material BOM
CS11 Explode BOM: Level by Level
CS12 Explode BOM: Multi Level BOM
CS13 Explode BOM: Summarized BOM
CR01 Create Work Center
CR02 Change Work Center
CR03 Display Work Center
CR11 Create Capacity
CR12 Change Capacity
CR13 Display Capacity
CR05 Work Center List
CA80 Work Center Where-Used
CR15 Capacity Where-Used
CR10 Work Center Change Document
CA01 Create Routing
CA02 Change Routing
CA03 Display Routing
CA12 Change Reference Operation Set
CA13 Display Reference Operation Set
MD61 Create Planned Independent Requirements
MD62 Change Planned Independent Requirements
MD63 Display Planned Independent Requirements
MD4C Multilevel Order Report
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
96
Evaluations
MD04 Stock / Requirements List
MD07 Collective access of stock / requirements list
MD05 MRP List
MD06 Collective access of MRP lists
CO46 Order Progress
Planned Order
MD11 Create planned order
MD12 Change planned order
MD13 Display planned order
MD16 Collective access of planned orders
MD14 Individual conversion of planned order into
MD15 Collective conversion of planned orders int
MDVP Collective availability check
CO01 Production order create (With Material)
CO07 Production order create (Without Material)
CO40 Production order create (From Planned Order)
CO41 Collective convention of planned order
CO08 Production order create (For Sales Order)
COHV Mass Processing Production Orders
COMAC Collective Availability check
CO05N Release Production Orders
CO04N Print Production Orders
CO09 Availability Overwiew
MB1A Enter Goods Issue
MB31 Goods Receipt for order
NTF (INDIA) PVT. LTD. User Training Document
NTF Technik India Pvt. Ltd.
97
Reports
COOIS Order Information System
MCP7 Work Center Analysis
MCP1 Operation Analysis
MCP5 Material Analysis
MCP3 Production Order Analysis
MCRE Material Uses Analysis
MCYJ Shop Floor Information System
CO20 Orders Acc. to Order Number
CO21 Orders for material
CO22 Orders for MRP Controller
CO23 Orders for Production Scheduler
CO24 Missing Parts Info System
CO27 Picking List
CO28 Selection of Indiv. Objects List
CO26 Order Information System

More Related Content

What's hot

Sap pp shop floor control configuration
Sap pp   shop floor control configurationSap pp   shop floor control configuration
Sap pp shop floor control configurationVikranth Ikkalaki
 
Sales and Operation Planning in SAP
Sales and Operation Planning in SAPSales and Operation Planning in SAP
Sales and Operation Planning in SAPAnkit Sharma
 
SAP Production Planning
SAP Production PlanningSAP Production Planning
SAP Production PlanningRupesh Brahmankar
 
SAP ATP check for Sales Order
SAP ATP check for Sales OrderSAP ATP check for Sales Order
SAP ATP check for Sales OrderLee Scott
 
SAP Production Planning and Execution presentation
SAP Production Planning and Execution presentationSAP Production Planning and Execution presentation
SAP Production Planning and Execution presentationAnkur Aggarwal
 
SAP Flexible Planning
SAP Flexible PlanningSAP Flexible Planning
SAP Flexible Planningmohamed_elkady
 
SAP Long Term PLANNING
SAP Long Term PLANNINGSAP Long Term PLANNING
SAP Long Term PLANNINGAnkit Sharma
 
Sap pp rough cut capacity planning on sop
Sap pp rough cut capacity planning on sopSap pp rough cut capacity planning on sop
Sap pp rough cut capacity planning on sopKanapon Gunprom
 
Sap mrp-configuration-pp
Sap mrp-configuration-ppSap mrp-configuration-pp
Sap mrp-configuration-ppLokesh Modem
 
SAP Variant configuration
SAP Variant configurationSAP Variant configuration
SAP Variant configurationKumbum Ramesh
 
SAP Draft Solution for GST India
SAP Draft Solution for GST IndiaSAP Draft Solution for GST India
SAP Draft Solution for GST IndiaSandeep Mahindra
 
Stock requirements list md04
Stock requirements list   md04Stock requirements list   md04
Stock requirements list md04m2k2010
 
Sap pp tutorial
Sap pp tutorialSap pp tutorial
Sap pp tutorialRaja180
 
SCM-APO-PP/DS-Production Planning and Detailed Scheduling
SCM-APO-PP/DS-Production Planning and Detailed SchedulingSCM-APO-PP/DS-Production Planning and Detailed Scheduling
SCM-APO-PP/DS-Production Planning and Detailed SchedulingAJAY
 
SAP SOP process flow for production process
SAP SOP process flow for production processSAP SOP process flow for production process
SAP SOP process flow for production processAasif001234
 
Multiple Work Center/Resource Selection and Classification in Master Recipe f...
Multiple Work Center/Resource Selection and Classification in Master Recipe f...Multiple Work Center/Resource Selection and Classification in Master Recipe f...
Multiple Work Center/Resource Selection and Classification in Master Recipe f...Ankit Sharma
 

What's hot (20)

Pp interview questions
Pp interview questionsPp interview questions
Pp interview questions
 
Sap pp shop floor control configuration
Sap pp   shop floor control configurationSap pp   shop floor control configuration
Sap pp shop floor control configuration
 
Sales and Operation Planning in SAP
Sales and Operation Planning in SAPSales and Operation Planning in SAP
Sales and Operation Planning in SAP
 
SAP Production Planning
SAP Production PlanningSAP Production Planning
SAP Production Planning
 
SAP ATP check for Sales Order
SAP ATP check for Sales OrderSAP ATP check for Sales Order
SAP ATP check for Sales Order
 
SAP Production Planning and Execution presentation
SAP Production Planning and Execution presentationSAP Production Planning and Execution presentation
SAP Production Planning and Execution presentation
 
Transfer of requirements in SAP SD
Transfer of requirements in SAP SDTransfer of requirements in SAP SD
Transfer of requirements in SAP SD
 
SAP Flexible Planning
SAP Flexible PlanningSAP Flexible Planning
SAP Flexible Planning
 
SAP PP Certification Overview (mindmap edition)
SAP PP Certification Overview (mindmap edition)SAP PP Certification Overview (mindmap edition)
SAP PP Certification Overview (mindmap edition)
 
SAP Long Term PLANNING
SAP Long Term PLANNINGSAP Long Term PLANNING
SAP Long Term PLANNING
 
Sap pp rough cut capacity planning on sop
Sap pp rough cut capacity planning on sopSap pp rough cut capacity planning on sop
Sap pp rough cut capacity planning on sop
 
Sap mrp-configuration-pp
Sap mrp-configuration-ppSap mrp-configuration-pp
Sap mrp-configuration-pp
 
SAP Variant configuration
SAP Variant configurationSAP Variant configuration
SAP Variant configuration
 
SAP Draft Solution for GST India
SAP Draft Solution for GST IndiaSAP Draft Solution for GST India
SAP Draft Solution for GST India
 
Stock requirements list md04
Stock requirements list   md04Stock requirements list   md04
Stock requirements list md04
 
Sap pp tutorial
Sap pp tutorialSap pp tutorial
Sap pp tutorial
 
SCM-APO-PP/DS-Production Planning and Detailed Scheduling
SCM-APO-PP/DS-Production Planning and Detailed SchedulingSCM-APO-PP/DS-Production Planning and Detailed Scheduling
SCM-APO-PP/DS-Production Planning and Detailed Scheduling
 
Sap SD Standard Reports
Sap SD Standard ReportsSap SD Standard Reports
Sap SD Standard Reports
 
SAP SOP process flow for production process
SAP SOP process flow for production processSAP SOP process flow for production process
SAP SOP process flow for production process
 
Multiple Work Center/Resource Selection and Classification in Master Recipe f...
Multiple Work Center/Resource Selection and Classification in Master Recipe f...Multiple Work Center/Resource Selection and Classification in Master Recipe f...
Multiple Work Center/Resource Selection and Classification in Master Recipe f...
 

Viewers also liked

SAP FI AP: Configuration & End User Guide
SAP FI AP: Configuration & End User GuideSAP FI AP: Configuration & End User Guide
SAP FI AP: Configuration & End User Guidesapdocs. info
 
SAP Configuration Guide for Functional Modules (Based on IDES)
SAP Configuration Guide for Functional Modules (Based on IDES)SAP Configuration Guide for Functional Modules (Based on IDES)
SAP Configuration Guide for Functional Modules (Based on IDES)sapdocs. info
 
SAP MM Configuration - Real Project Documentation
SAP MM Configuration - Real Project DocumentationSAP MM Configuration - Real Project Documentation
SAP MM Configuration - Real Project Documentationsapdocs. info
 
SAP FI AP: End User Guide for Beginners
SAP FI AP: End User Guide for BeginnersSAP FI AP: End User Guide for Beginners
SAP FI AP: End User Guide for Beginnerssapdocs. info
 
SAP FICO BBP Sample Document PDF NEW!
SAP FICO BBP Sample Document PDF NEW!SAP FICO BBP Sample Document PDF NEW!
SAP FICO BBP Sample Document PDF NEW!sapdocs. info
 
SAP FI Asset Accounting: End User Guide for Beginners
SAP FI Asset Accounting: End User Guide for BeginnersSAP FI Asset Accounting: End User Guide for Beginners
SAP FI Asset Accounting: End User Guide for Beginnerssapdocs. info
 
LSMW Tutorial (Spanish Espanol)
LSMW Tutorial (Spanish Espanol)LSMW Tutorial (Spanish Espanol)
LSMW Tutorial (Spanish Espanol)sapdocs. info
 
SAP PM Master Data Training Guide
SAP PM Master Data Training GuideSAP PM Master Data Training Guide
SAP PM Master Data Training Guidesapdocs. info
 
SAP FI-AR TCODES & MENU PATHS
SAP FI-AR TCODES & MENU PATHSSAP FI-AR TCODES & MENU PATHS
SAP FI-AR TCODES & MENU PATHSsapdocs. info
 
SAP PM Training Manual - www.sapdocs.info
SAP PM Training Manual - www.sapdocs.infoSAP PM Training Manual - www.sapdocs.info
SAP PM Training Manual - www.sapdocs.infosapdocs. info
 
SAP Basis Training Material | www.sapdocs.info
SAP Basis Training Material | www.sapdocs.infoSAP Basis Training Material | www.sapdocs.info
SAP Basis Training Material | www.sapdocs.infosapdocs. info
 
SAP SD Certification (C_TSCM62_66) Preparation Training Notes
SAP SD Certification (C_TSCM62_66) Preparation Training NotesSAP SD Certification (C_TSCM62_66) Preparation Training Notes
SAP SD Certification (C_TSCM62_66) Preparation Training Notessapdocs. info
 
Variant Configuration in SAP PP: Beginner's Guide
Variant Configuration in SAP PP: Beginner's GuideVariant Configuration in SAP PP: Beginner's Guide
Variant Configuration in SAP PP: Beginner's Guidesapdocs. info
 
SAP FI AR: End User Guide for Beginners
SAP FI AR: End User Guide for BeginnersSAP FI AR: End User Guide for Beginners
SAP FI AR: End User Guide for Beginnerssapdocs. info
 
Authorisation Concept In SAP | http://sapdocs.info
Authorisation Concept In SAP | http://sapdocs.infoAuthorisation Concept In SAP | http://sapdocs.info
Authorisation Concept In SAP | http://sapdocs.infosapdocs. info
 
SAP FI-AP TCODES & MENU PATHS
SAP FI-AP TCODES & MENU PATHSSAP FI-AP TCODES & MENU PATHS
SAP FI-AP TCODES & MENU PATHSsapdocs. info
 
ABAP Basico para Consultores Funcionales
ABAP Basico para Consultores FuncionalesABAP Basico para Consultores Funcionales
ABAP Basico para Consultores Funcionalessapdocs. info
 
SAP HR Time Management User Guide | www.sapdocs.info
SAP HR Time Management User Guide | www.sapdocs.infoSAP HR Time Management User Guide | www.sapdocs.info
SAP HR Time Management User Guide | www.sapdocs.infosapdocs. info
 
SAP PP End User Document - www.sapdocs.info
SAP PP End User Document - www.sapdocs.infoSAP PP End User Document - www.sapdocs.info
SAP PP End User Document - www.sapdocs.infosapdocs. info
 
Variant Configurition in SAP: Beginners Guide | www.sapdocs.info
Variant Configurition in SAP: Beginners Guide | www.sapdocs.infoVariant Configurition in SAP: Beginners Guide | www.sapdocs.info
Variant Configurition in SAP: Beginners Guide | www.sapdocs.infosapdocs. info
 

Viewers also liked (20)

SAP FI AP: Configuration & End User Guide
SAP FI AP: Configuration & End User GuideSAP FI AP: Configuration & End User Guide
SAP FI AP: Configuration & End User Guide
 
SAP Configuration Guide for Functional Modules (Based on IDES)
SAP Configuration Guide for Functional Modules (Based on IDES)SAP Configuration Guide for Functional Modules (Based on IDES)
SAP Configuration Guide for Functional Modules (Based on IDES)
 
SAP MM Configuration - Real Project Documentation
SAP MM Configuration - Real Project DocumentationSAP MM Configuration - Real Project Documentation
SAP MM Configuration - Real Project Documentation
 
SAP FI AP: End User Guide for Beginners
SAP FI AP: End User Guide for BeginnersSAP FI AP: End User Guide for Beginners
SAP FI AP: End User Guide for Beginners
 
SAP FICO BBP Sample Document PDF NEW!
SAP FICO BBP Sample Document PDF NEW!SAP FICO BBP Sample Document PDF NEW!
SAP FICO BBP Sample Document PDF NEW!
 
SAP FI Asset Accounting: End User Guide for Beginners
SAP FI Asset Accounting: End User Guide for BeginnersSAP FI Asset Accounting: End User Guide for Beginners
SAP FI Asset Accounting: End User Guide for Beginners
 
LSMW Tutorial (Spanish Espanol)
LSMW Tutorial (Spanish Espanol)LSMW Tutorial (Spanish Espanol)
LSMW Tutorial (Spanish Espanol)
 
SAP PM Master Data Training Guide
SAP PM Master Data Training GuideSAP PM Master Data Training Guide
SAP PM Master Data Training Guide
 
SAP FI-AR TCODES & MENU PATHS
SAP FI-AR TCODES & MENU PATHSSAP FI-AR TCODES & MENU PATHS
SAP FI-AR TCODES & MENU PATHS
 
SAP PM Training Manual - www.sapdocs.info
SAP PM Training Manual - www.sapdocs.infoSAP PM Training Manual - www.sapdocs.info
SAP PM Training Manual - www.sapdocs.info
 
SAP Basis Training Material | www.sapdocs.info
SAP Basis Training Material | www.sapdocs.infoSAP Basis Training Material | www.sapdocs.info
SAP Basis Training Material | www.sapdocs.info
 
SAP SD Certification (C_TSCM62_66) Preparation Training Notes
SAP SD Certification (C_TSCM62_66) Preparation Training NotesSAP SD Certification (C_TSCM62_66) Preparation Training Notes
SAP SD Certification (C_TSCM62_66) Preparation Training Notes
 
Variant Configuration in SAP PP: Beginner's Guide
Variant Configuration in SAP PP: Beginner's GuideVariant Configuration in SAP PP: Beginner's Guide
Variant Configuration in SAP PP: Beginner's Guide
 
SAP FI AR: End User Guide for Beginners
SAP FI AR: End User Guide for BeginnersSAP FI AR: End User Guide for Beginners
SAP FI AR: End User Guide for Beginners
 
Authorisation Concept In SAP | http://sapdocs.info
Authorisation Concept In SAP | http://sapdocs.infoAuthorisation Concept In SAP | http://sapdocs.info
Authorisation Concept In SAP | http://sapdocs.info
 
SAP FI-AP TCODES & MENU PATHS
SAP FI-AP TCODES & MENU PATHSSAP FI-AP TCODES & MENU PATHS
SAP FI-AP TCODES & MENU PATHS
 
ABAP Basico para Consultores Funcionales
ABAP Basico para Consultores FuncionalesABAP Basico para Consultores Funcionales
ABAP Basico para Consultores Funcionales
 
SAP HR Time Management User Guide | www.sapdocs.info
SAP HR Time Management User Guide | www.sapdocs.infoSAP HR Time Management User Guide | www.sapdocs.info
SAP HR Time Management User Guide | www.sapdocs.info
 
SAP PP End User Document - www.sapdocs.info
SAP PP End User Document - www.sapdocs.infoSAP PP End User Document - www.sapdocs.info
SAP PP End User Document - www.sapdocs.info
 
Variant Configurition in SAP: Beginners Guide | www.sapdocs.info
Variant Configurition in SAP: Beginners Guide | www.sapdocs.infoVariant Configurition in SAP: Beginners Guide | www.sapdocs.info
Variant Configurition in SAP: Beginners Guide | www.sapdocs.info
 

Similar to SAP PP MRP Guide for Beginners

TPS Basics Trg Material (NXPowerLite)
TPS Basics Trg Material (NXPowerLite)TPS Basics Trg Material (NXPowerLite)
TPS Basics Trg Material (NXPowerLite)Himanshu Pandya
 
Cin fi v1_by_guntupalliharikrishna
Cin fi v1_by_guntupalliharikrishnaCin fi v1_by_guntupalliharikrishna
Cin fi v1_by_guntupalliharikrishnaHari Krishna
 
1BM_S4CLD2302_BPD_EN_US.docx
1BM_S4CLD2302_BPD_EN_US.docx1BM_S4CLD2302_BPD_EN_US.docx
1BM_S4CLD2302_BPD_EN_US.docxnavinsurya3
 
Zero breakdown solution for lg_taehwa
Zero breakdown solution for lg_taehwaZero breakdown solution for lg_taehwa
Zero breakdown solution for lg_taehwaVaibhav Sharma
 
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-infoMBA, MSc, Alberto Castellano
 
Sdl software presentation
Sdl software presentationSdl software presentation
Sdl software presentationMdRezaUrRahman2
 
Software presentation
Software presentationSoftware presentation
Software presentationMdRezaUrRahman2
 
OPTIMIZATION IN MES BY IMPLEMENTING SMART ANDON SYSTEM FOR PRODUCTIVITY ENHAN...
OPTIMIZATION IN MES BY IMPLEMENTING SMART ANDON SYSTEM FOR PRODUCTIVITY ENHAN...OPTIMIZATION IN MES BY IMPLEMENTING SMART ANDON SYSTEM FOR PRODUCTIVITY ENHAN...
OPTIMIZATION IN MES BY IMPLEMENTING SMART ANDON SYSTEM FOR PRODUCTIVITY ENHAN...IRJET Journal
 
Material Resource Planning
Material Resource PlanningMaterial Resource Planning
Material Resource PlanningBiswajit Ghosh
 
IRJET - Acet Sports Alert
IRJET - Acet Sports AlertIRJET - Acet Sports Alert
IRJET - Acet Sports AlertIRJET Journal
 
SAP Demand Management
SAP Demand ManagementSAP Demand Management
SAP Demand ManagementRahul Shukla
 
Sap seminar prince
Sap seminar princeSap seminar prince
Sap seminar princePrince Bhanwra
 
Sap seminar prince
Sap seminar princeSap seminar prince
Sap seminar princePrince Bhanwra
 
IRJET - Implementation of TPM Philosophy on Critical Paint Shop Machine
IRJET - Implementation of TPM Philosophy on Critical Paint Shop MachineIRJET - Implementation of TPM Philosophy on Critical Paint Shop Machine
IRJET - Implementation of TPM Philosophy on Critical Paint Shop MachineIRJET Journal
 

Similar to SAP PP MRP Guide for Beginners (20)

TPS Basics Trg Material (NXPowerLite)
TPS Basics Trg Material (NXPowerLite)TPS Basics Trg Material (NXPowerLite)
TPS Basics Trg Material (NXPowerLite)
 
Sap pp-user-manual
Sap pp-user-manualSap pp-user-manual
Sap pp-user-manual
 
Cin fi v1_by_guntupalliharikrishna
Cin fi v1_by_guntupalliharikrishnaCin fi v1_by_guntupalliharikrishna
Cin fi v1_by_guntupalliharikrishna
 
Just in time (jit) and lean production
Just in time (jit) and lean productionJust in time (jit) and lean production
Just in time (jit) and lean production
 
jit
jitjit
jit
 
1BM_S4CLD2302_BPD_EN_US.docx
1BM_S4CLD2302_BPD_EN_US.docx1BM_S4CLD2302_BPD_EN_US.docx
1BM_S4CLD2302_BPD_EN_US.docx
 
Zero breakdown solution for lg_taehwa
Zero breakdown solution for lg_taehwaZero breakdown solution for lg_taehwa
Zero breakdown solution for lg_taehwa
 
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
17085700 sap-pp-materials-requirement-planning-http-sapdocs-info
 
SD CIN.ppt
SD CIN.pptSD CIN.ppt
SD CIN.ppt
 
Sdl software presentation
Sdl software presentationSdl software presentation
Sdl software presentation
 
Software presentation
Software presentationSoftware presentation
Software presentation
 
OPTIMIZATION IN MES BY IMPLEMENTING SMART ANDON SYSTEM FOR PRODUCTIVITY ENHAN...
OPTIMIZATION IN MES BY IMPLEMENTING SMART ANDON SYSTEM FOR PRODUCTIVITY ENHAN...OPTIMIZATION IN MES BY IMPLEMENTING SMART ANDON SYSTEM FOR PRODUCTIVITY ENHAN...
OPTIMIZATION IN MES BY IMPLEMENTING SMART ANDON SYSTEM FOR PRODUCTIVITY ENHAN...
 
Material Resource Planning
Material Resource PlanningMaterial Resource Planning
Material Resource Planning
 
IRJET - Acet Sports Alert
IRJET - Acet Sports AlertIRJET - Acet Sports Alert
IRJET - Acet Sports Alert
 
SAP Demand Management
SAP Demand ManagementSAP Demand Management
SAP Demand Management
 
Nosheen Pathan
Nosheen PathanNosheen Pathan
Nosheen Pathan
 
Sap seminar prince
Sap seminar princeSap seminar prince
Sap seminar prince
 
Sap seminar prince
Sap seminar princeSap seminar prince
Sap seminar prince
 
BRD- MAINTENANCE
BRD- MAINTENANCEBRD- MAINTENANCE
BRD- MAINTENANCE
 
IRJET - Implementation of TPM Philosophy on Critical Paint Shop Machine
IRJET - Implementation of TPM Philosophy on Critical Paint Shop MachineIRJET - Implementation of TPM Philosophy on Critical Paint Shop Machine
IRJET - Implementation of TPM Philosophy on Critical Paint Shop Machine
 

More from sapdocs. info

SAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.infoSAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.infosapdocs. info
 
SAP CO Configuration Guide - Exclusive Document
SAP CO Configuration Guide - Exclusive DocumentSAP CO Configuration Guide - Exclusive Document
SAP CO Configuration Guide - Exclusive Documentsapdocs. info
 
ABAP for Beginners - www.sapdocs.info
ABAP for Beginners - www.sapdocs.infoABAP for Beginners - www.sapdocs.info
ABAP for Beginners - www.sapdocs.infosapdocs. info
 
Exclusive SAP Basis Training Book | www.sapdocs.info
Exclusive SAP Basis Training Book | www.sapdocs.infoExclusive SAP Basis Training Book | www.sapdocs.info
Exclusive SAP Basis Training Book | www.sapdocs.infosapdocs. info
 
SAP Plant Maintenance Training Material | www.sapdocs.info
SAP Plant Maintenance Training Material | www.sapdocs.infoSAP Plant Maintenance Training Material | www.sapdocs.info
SAP Plant Maintenance Training Material | www.sapdocs.infosapdocs. info
 
SAP FICO General Ledger EndUser Training | www.sapdocs.info
SAP FICO General Ledger EndUser Training | www.sapdocs.infoSAP FICO General Ledger EndUser Training | www.sapdocs.info
SAP FICO General Ledger EndUser Training | www.sapdocs.infosapdocs. info
 
HR ABAP Technical Overview | http://sapdocs.info/
HR ABAP Technical Overview | http://sapdocs.info/HR ABAP Technical Overview | http://sapdocs.info/
HR ABAP Technical Overview | http://sapdocs.info/sapdocs. info
 
SAP Accounts Reveivable Introduction | http://sapdocs.info
SAP Accounts Reveivable Introduction | http://sapdocs.infoSAP Accounts Reveivable Introduction | http://sapdocs.info
SAP Accounts Reveivable Introduction | http://sapdocs.infosapdocs. info
 
SAP Accounts Reveivable Functions | http://sapdocs.info
SAP Accounts Reveivable Functions | http://sapdocs.infoSAP Accounts Reveivable Functions | http://sapdocs.info
SAP Accounts Reveivable Functions | http://sapdocs.infosapdocs. info
 
SAP Accounts Reveivable Financial Transaction | http://sapdocs.info
SAP Accounts Reveivable Financial Transaction | http://sapdocs.infoSAP Accounts Reveivable Financial Transaction | http://sapdocs.info
SAP Accounts Reveivable Financial Transaction | http://sapdocs.infosapdocs. info
 
SAP Accounts Reveivable Customer Master | http://sapdocs.info
SAP Accounts Reveivable Customer Master | http://sapdocs.infoSAP Accounts Reveivable Customer Master | http://sapdocs.info
SAP Accounts Reveivable Customer Master | http://sapdocs.infosapdocs. info
 
SAP Accounts Reveivable SAP Documents | http://sapdocs.info
SAP Accounts Reveivable SAP Documents | http://sapdocs.infoSAP Accounts Reveivable SAP Documents | http://sapdocs.info
SAP Accounts Reveivable SAP Documents | http://sapdocs.infosapdocs. info
 
SAP Accounts Payable Payment | http://sapdocs.info
SAP Accounts Payable Payment | http://sapdocs.infoSAP Accounts Payable Payment | http://sapdocs.info
SAP Accounts Payable Payment | http://sapdocs.infosapdocs. info
 

More from sapdocs. info (13)

SAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.infoSAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
SAP ECC 6.0 PM Configuration Manual - www.sapdocs.info
 
SAP CO Configuration Guide - Exclusive Document
SAP CO Configuration Guide - Exclusive DocumentSAP CO Configuration Guide - Exclusive Document
SAP CO Configuration Guide - Exclusive Document
 
ABAP for Beginners - www.sapdocs.info
ABAP for Beginners - www.sapdocs.infoABAP for Beginners - www.sapdocs.info
ABAP for Beginners - www.sapdocs.info
 
Exclusive SAP Basis Training Book | www.sapdocs.info
Exclusive SAP Basis Training Book | www.sapdocs.infoExclusive SAP Basis Training Book | www.sapdocs.info
Exclusive SAP Basis Training Book | www.sapdocs.info
 
SAP Plant Maintenance Training Material | www.sapdocs.info
SAP Plant Maintenance Training Material | www.sapdocs.infoSAP Plant Maintenance Training Material | www.sapdocs.info
SAP Plant Maintenance Training Material | www.sapdocs.info
 
SAP FICO General Ledger EndUser Training | www.sapdocs.info
SAP FICO General Ledger EndUser Training | www.sapdocs.infoSAP FICO General Ledger EndUser Training | www.sapdocs.info
SAP FICO General Ledger EndUser Training | www.sapdocs.info
 
HR ABAP Technical Overview | http://sapdocs.info/
HR ABAP Technical Overview | http://sapdocs.info/HR ABAP Technical Overview | http://sapdocs.info/
HR ABAP Technical Overview | http://sapdocs.info/
 
SAP Accounts Reveivable Introduction | http://sapdocs.info
SAP Accounts Reveivable Introduction | http://sapdocs.infoSAP Accounts Reveivable Introduction | http://sapdocs.info
SAP Accounts Reveivable Introduction | http://sapdocs.info
 
SAP Accounts Reveivable Functions | http://sapdocs.info
SAP Accounts Reveivable Functions | http://sapdocs.infoSAP Accounts Reveivable Functions | http://sapdocs.info
SAP Accounts Reveivable Functions | http://sapdocs.info
 
SAP Accounts Reveivable Financial Transaction | http://sapdocs.info
SAP Accounts Reveivable Financial Transaction | http://sapdocs.infoSAP Accounts Reveivable Financial Transaction | http://sapdocs.info
SAP Accounts Reveivable Financial Transaction | http://sapdocs.info
 
SAP Accounts Reveivable Customer Master | http://sapdocs.info
SAP Accounts Reveivable Customer Master | http://sapdocs.infoSAP Accounts Reveivable Customer Master | http://sapdocs.info
SAP Accounts Reveivable Customer Master | http://sapdocs.info
 
SAP Accounts Reveivable SAP Documents | http://sapdocs.info
SAP Accounts Reveivable SAP Documents | http://sapdocs.infoSAP Accounts Reveivable SAP Documents | http://sapdocs.info
SAP Accounts Reveivable SAP Documents | http://sapdocs.info
 
SAP Accounts Payable Payment | http://sapdocs.info
SAP Accounts Payable Payment | http://sapdocs.infoSAP Accounts Payable Payment | http://sapdocs.info
SAP Accounts Payable Payment | http://sapdocs.info
 

Recently uploaded

International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
MemorĂĄndum de Entendimiento (MoU) entre Codelco y SQM
MemorĂĄndum de Entendimiento (MoU) entre Codelco y SQMMemorĂĄndum de Entendimiento (MoU) entre Codelco y SQM
MemorĂĄndum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Call Us đŸ“Č8800102216📞 Call Girls In DLF City Gurgaon
Call Us đŸ“Č8800102216📞 Call Girls In DLF City GurgaonCall Us đŸ“Č8800102216📞 Call Girls In DLF City Gurgaon
Call Us đŸ“Č8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMintel Group
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607dollysharma2066
 

Recently uploaded (20)

International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
MemorĂĄndum de Entendimiento (MoU) entre Codelco y SQM
MemorĂĄndum de Entendimiento (MoU) entre Codelco y SQMMemorĂĄndum de Entendimiento (MoU) entre Codelco y SQM
MemorĂĄndum de Entendimiento (MoU) entre Codelco y SQM
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Call Us đŸ“Č8800102216📞 Call Girls In DLF City Gurgaon
Call Us đŸ“Č8800102216📞 Call Girls In DLF City GurgaonCall Us đŸ“Č8800102216📞 Call Girls In DLF City Gurgaon
Call Us đŸ“Č8800102216📞 Call Girls In DLF City Gurgaon
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Market Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 EditionMarket Sizes Sample Report - 2024 Edition
Market Sizes Sample Report - 2024 Edition
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Call Us ➄9319373153▻Call Girls In North Goa
Call Us ➄9319373153▻Call Girls In North GoaCall Us ➄9319373153▻Call Girls In North Goa
Call Us ➄9319373153▻Call Girls In North Goa
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607FULL ENJOY Call girls in Paharganj Delhi | 8377087607
FULL ENJOY Call girls in Paharganj Delhi | 8377087607
 

SAP PP MRP Guide for Beginners

  • 1. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 1 SAP USER TRAINING DOCUMENT MRP By Kanti Kumar
  • 2. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 2 Experts agree that you get the most from your ERP software when users become accepting, comfortable, and proficient performing the new business processes the software supports. In other words, much of the success of a multi- million dollar ERP implementation depends on the people using the system for day-to-day work. Our Aims and Ideals To train you on higher level in SAP ERP, that is our aim.
  • 3. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 3 MRP Process in SAP System We run MRP for generating Vendor Schedules. This document will show process in SAP for Production plan to material receive from vendors through SAP system. First we focus on Production Plan. We receive Schedules from our Customers as: Schedule from Maruti for July 2nd For Night OE & Spare Schedule Both Plant (Manesar & Gurgaon)
  • 4. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 4 Other Customers and spare parts Schedule will be provided by Mr. Bharat.
  • 5. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 5 On the basis of these delivery schedules Production Plan will be prepared. RTM and Paint Shop for Unit 1 and Unit 2 Production plan prepared by Mr. Uday. Mr. Uday will fill Production plan in these sheets. Mr. R.K. Gupta should help for preparation Production Plan for Unit 2 for RTM products. Production Plan (RTM and Paint Shop) for Unit 1 Production Plan (RTM and Paint Shop) for Unit 2
  • 6. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 6 TCM Production Plan for Unit 1 and Unit 2 will be prepared by Mr. Satybir. Mr. Satybir will fill Production plan in these sheets. Mr. R.K. Gupta should help for preparation Production Plan for Unit 2 for RTM products. Production Plan (TCM) for Unit 1 Production Plan (TCM) for Unit 2
  • 7. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 7 PIM Production Plan for Unit 1 will be prepared by Mr. Satybir. Mr. Satybir will fill Production plan in this sheet: Production Plan (PIM) for Unit 1 We are running our PIM machines only on Electricity so daily planning is not possible for PIM department. We are taking monthly planning from PIM. Preparation to run MRP in SAP System: These are the main points for run smooth MRP. 1. Inventory: Now our Physical and SAP system Inventory is matching. 2. Open Purchase Requisition: When we will run MRP old PR will be deleted automatically. 3. Open Purchase Orders: We will close old Purchase Orders. 4. Open Schedule Lines in Scheduling Agreements. 5. Open Production Orders: We will close all old unused Production Orders (TECO). 6. Open Planned Orders: We will close old Planned Orders. 7. Reorganizing Independent Requirements 8. Independent Requirements reorganization 9. Recorg. Independent Requirements 10. Delete Planned Independent Requirements 11. Create (Planned Independent Requirements ) Production Plan in SAP System Finally Run MRP with MD02
  • 8. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 8 2. Open Purchase Requisition: When we will run MRP open Purchase Requisition will be closed automatically. Manually created Open Purchase Requisition will be closed with this. We will close Open Purchase requisition on both NTF Unit 1 and Unit 2. Tcode: ZPR_DELETE 3. Open Purchase Orders: We should close open Purchase Orders. For getting list of open Purchase Orders these TCODE will be used. ME2M, ME2L, ME2N 1) Make delivered quantity equal to order qty. 2) Block PO line items 3) Delete line items if there is no open GR’s or invoices. 4) Open Purchase orders will be close for both NTF Unit 1 and NTF Unit 2.
  • 9. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 9 4. Open Schedule Lines in Scheduling Agreements. We will get the list of open Scheduling Lines in Schedule Agreements. Open Schedule Lines should be close for both NTF Unit 1 and NTF Unit 2 plants. TCODE: ZOPENSHL This is the list of open Schedule Lines. We should close these Schedule Lines in SAP System. These Schedule Lines should not appear. These Schedule Lines are the vendor Schedules and we should receive these materials in last month but not received and schedule lines are pending. Now close schedule line in Scheduling Agreement.
  • 10. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 10 TCODE: ME38 Enter Scheduling Agreement Number and press enter key.
  • 11. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 11 5. Open Production Orders: We should close open production orders. For getting open production orders TCODE: COOIS Delete Qty.
  • 12. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 12
  • 13. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 13 Take the list of Open production orders. Open production order for (TECO) closing. TCODE: CO02
  • 14. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 14
  • 15. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 15 Save the production Order. If Quantity of open Production Orders is high then we should close in mass. TCODE: COHV
  • 16. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 16
  • 17. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 17
  • 18. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 18 Other condition for getting open Production Orders
  • 19. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 19 Select layout as Standard Layout and press Select All tab right side on order screen. Select Mass Processing Tab.
  • 20. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 20 Select Technical Complete and press copy button then press execute button. 6. Open Planned Orders
  • 21. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 21 For getting list of open Planned order and delete open planned order this tcode required. TCODE: MD16
  • 22. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 22 Press Select All as per below given screen.
  • 23. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 23 Press Delete All. All Open Planned Orders from NTF Unit 1 and NTF Unit 2 should delete from the SAP System.
  • 24. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 24 7. Reorganizing Independent Requirements (Run for NTF Uint1 and NTF Unit2) TCODE: MD74 Press to for run this utility. It will show this type of results.
  • 25. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 25 8. Independent Requirements reorganization (Run for NTF Uint1 and NTF Unit2) TCODE: MD75 Press to for run this utility. It will show this type of results
  • 26. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 26 9. Recorg. Independent Requirements (Run for NTF Uint1 and NTF Unit2) TCODE: MD76 Press to for run this utility. It will show this type of results
  • 27. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 27 10.Delete Planned Independent Requirements We enters production plan on daily basis for run MRP. For enter next month production plan we should delete old Planned Independent requirement (production plan). TCODE: MD62 We should delete all of these entries.
  • 28. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 28 Data Selection in the fields: The select of data in these fields is very important. (1) Product Group: We have created two main product groups. TCODE: MC84 NTFUNIT1: For enter production planning for NTF Unit 1
  • 29. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 29 NTFUNIT2: For enter production planning for NTF Unit 2 For display all Product Group we will use this Tcode. TCODE: MC85
  • 30. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 30 We want to see the Members of Product Group then user this: TCODE: MC85 For NTFUNIT1 (Manesar Plant) product Group these are the members: For NTFUNIT2 (Neemrana Plant) product Group these are the members:
  • 31. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 31 For Add or change the Materials in product Group Members we will use this tcode. TCODE: MC86
  • 32. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 32
  • 33. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 33 Add the Material and plant in the list and before save it press “Distribute proportns” Now Press save button for save material in product group member list. Other Fields Data Selection for delete and enter production Plan: Please check all marked fields according to document. Enter planning horizon date according you production plan.
  • 34. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 34 Create Planned Independent Requirements (Enter Production Plan): TCODE: MD61 Enter Daily Production Plan and save.
  • 35. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 35 The below screen is the production planning cycle
  • 36. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 36 Create Planned Independent Requirements MD61 Check In Stock Requirement List MD04 Online Single Item Multi Level Multi Items Order Confirmation & Scrap (FINAL) CO15 Excess Goods Issue for production Orders Release Order 1. Check Material Availability 2. Check Capacity Availability Convert Planned Order into Production Order Rework Confirmation Partial Confirmation Rework Goods Receipt to FG Store (SPF1) Sales Order Background Capacity Availability Check Finite Scheduling Transfer into Operative Planning LTP MD4C CO40 or MD04 > Enter Pld Order no >OK > Save > Prod order no generated Planning Run MD02 CO02 > Click Material Button > Click Capacity Button CO02 Click on Green FLAG button and SAVE MB1A (Store Department) > movement type - 261 > Production Oder No. MB31 Movement type 101,Sto. Loc. SPF1
  • 37. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 37 PLANNING RUN (MRP RUN) Def: The execution of materials planning for all materials or assemblies that have the nessary entries in the planning file. Planning File: A file that contains a list of all materials for which a change relevant to requirements planning has occurred and that are automatically flagged for planning. If such a change has taken place, the entry in the planning file is performed automatically. We need not do anything as everything is done automatically but to check planning file the TCODE is MZD21. For this type of ne change planning, only materials that change relecant to MRP in the period are planned in the planning run. There are several types of planning run. 1. Total planning on-line TCODE = MD01 2. Single item-multi level TCODE = MD02 3. Single item – single level TCODE = MD03 4. Total planning back-ground TCODE = MD04 Here we run MRP back-ground every week once but we may require running MRP foreground sometimes for single item. TCODE: MD02
  • 38. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 38 Enter the material to which planning is required. MRP Control Parameters. Processing Key: Enter NETCH Create purchase req: Select 2 for purchase requisition in the opening period. Delivery Schedules: Select 3 for schedule lines. Create MRP list : Enter 1 for MRP List. Planning Mode : Re-explode BOM and routing. Scheduling : Lead time Scheduling and capacity planning. Process Control Parameters Tick Also plan Unchanged components. Tick display results before they are saved. Tick display material list. After entering the above details press enter. You get notification that “please check input parameters”. Again press enter.MRP run will takes place and you can observe the following screen. Press Save button.
  • 39. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 39 First Select “Proceed without stopping” radio button and then Press Continue Tab
  • 40. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 40 Press Material Tab on the screen for getting Material List.
  • 41. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 41 We get the information of all the dependent materials. Planned orders are created for items that are not available on date. For in-house production dependent requirements we get planned orders and for external procurements items we get either planned order or purchase requisitions depending upon the time availability of converting planned orders to purchase requisitions in opening period. The MRP controller will check the planning result and make changes if required in dates and quantities. The system carries out the following processes in the planning run: 1) The system checks the planning file. During this process, the system checks whether a material is to be planned due to a change relevant to MRP, and how to proceed if there are already existing procurement proposals. 2) The system calculates net requirements for every material. For this calculation, the system checks whether the requirements are covered by the warehouse stock and dispatched receipts from Purchasing or Production. If the requirements cannot be covered, the system creates a procurement proposal. 3) The system calculates procurement quantities. When doing this, the system takes into account the selected lot-sizing procedure and, if necessary, scrap and rounding values. 4) The system carries out the scheduling in order to calculate the start and finish dates for the procurement proposals. 5) The system determines the type of procurement proposal. Dependent upon the defined setting, planned orders, purchase requisitions or delivery schedules are created by the system for a material. 6) For every procurement proposal of an assembly, the system explodes the BOM and determines the dependent requirements. 7) During the planning run, the system recognizes critical situations that have to be assessed manually in the planning result by the work scheduler. The system creates exception messages and, if necessary, checks rescheduling.
  • 42. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 42 Stock Requirement List: In this list we can see all planned orders, Ind. Requirement and Vendor Schedule lines. TCODE: MD04
  • 43. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 43 Master Data: Material Master We should enter correct Master data in SAP system. This is to inform you all who are creating new Material Master Data, Routing or BOM (with similar components and work centers), are not adapting standard procedures. After creating Material in Material Master, problem occurs at the time of production order creation or material consumption or report generation. The easiest and simplest way to create a Material Master data is to copy from the old material or routing or BOM and edit wherever necessary so that chances of committing errors can be reduced. So I am requesting you all who are responsible for master data creation, let us not invent the wheel again. Use Simplest way to create a Material in Material Master Data is to copy from the old materials. Some views are very important for run MRP. Please check these views: MRP1 MRP2 MRP3 MRP4 Accounting Costing Enter old Material number for Copy the material.
  • 44. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 44 MRP 1 View: MRP 2 View
  • 45. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 45 MRP 3 View MRP 4 View
  • 46. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 46 Account 1 View S: Standard price for Finished and semi-finished goods. V: Moving price for Raw Materials Enter or Check Profit Center
  • 47. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 47 Purchasing View Please check Unit of measure/EANs in Purchasing View -> Additional Data Tab.
  • 48. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 48 WORK SCHEDULING View Issue Storage Location: In the case of a material produced in-house, this is the key of the storage location that is copied to the planned order or production order. Production Scheduler: Scheduler responsible for a material in production activity control. The production scheduler determines how capacity requirements are calculated for a material during a scheduling run. Production Scheduling Profile: Profile that you can use to Specify that certain business transactions are carried out in parallel in a production order / process order (you can, for example, create and release an order at the same time, or release an order and print the shop papers) Trigger an automatic goods receipt Specify an overall profile for capacity leveling Serial No Profile: The data grouped under a four-digit identification code that defines the conditions and operations for assigning serial numbers for serialized materials.
  • 49. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 49 The serial number profile must be entered in the master record of the material for which the items are assigned serial numbers. Batch entry: Defines when batches have to be determined. We have the following options The batches can be determined when the goods issue is posted. The batches must be entered in the order before it is released. The batches must be entered in the order before the goods issue is posted, but not necessarily before the order is released The batches are determined automatically when the order is released Batch management: Specifies whether the material is managed in batches. In house production time in days(Lot size dependant): Set up and tear down time: Specifies the number of workdays needed to set up and tear down the various work centers where the material is processed. This value is the total of the setup and teardown times. The setup and teardown time is independent of the order quantity. Processing time: Specifies the time needed to process the material in the operations at the different work centers. The processing time depends on the order quantity. Base quantity: Quantity to which the in house production time and the processing time of the material relate. We can also upload this data from routings. When we maintain values for lot size dependent in-house production time in days we have to carefully enter the values because it should be always equal or greater than the timings from routings, otherwise the system will reduce the operation timings even though our intension is not that.
  • 50. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 50 Maintain MRP 2 View storage location in MMSC. TCODE: MMSC
  • 51. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 51 PRODUCTION VERSION MAINTENANCE IN MATERIAL MASTER Production version is the combination of BOM’s and Routings and should be maintained in the material master under the following conditions. Mainly this PV is used in the finished goods material master. Consider GYPSY HARD TOP for example. There are two versions of hard top we make for GYPSY, they are Milky white and Olive Green with the same item code for ex.93610m83F00-26U. When we create production order without creating PV, system will select Alternate BOM 1 and Routing Group 1 for this item. Since we have two different BOM’s for this item (two colors) we should have an option to choose one that we manufacture and here it is not possible. Also while planning material procurement it is difficult to plan for Alternate BOM 2 materials. So PV is must in such case. When there is a difference of operation times for two different items of same item code, it is difficult to select which process we adopt to manufacture the item or if there more than one process available to make an item ( such as alternate routing) it is only possible with PV. Here is a demo to create the PV in material master for item 93610M83F00-26U Create different BOM’s for 93610M83F00-26U, such as alt BOM1 and alt BOM2. Create different routings for 93610M83F00-26U (if required). Now in the material master MRP 4 View click on PV Here we need to create version as 0001, 0002 and so on along with validity Here I am creating version 0003 as test 1 and click on details and the following screen appears. Fill the details such as lot size, valid from and to date, task list type and alternate BOM as under
  • 52. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 52 Click on check and you should get the following screen. If both task list and BOM exists check status will become green as under
  • 53. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 53 Continue and create as many versions as needed and save. One another configuration setting required in material master is in MRP 4 tab page Select 2 0r 3 in BOM selection method. This is how we have to maintain PV for different items with same item code. As there is a need to maintain PV I am providing this document to all the users who create the material master.
  • 54. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 54 BOM: Bill of Material Creation and updating is the responsibility of Engineering Department. For getting change document (changes in the BOM) follow this process: Go To Environment Tab and press Change Document:
  • 55. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 55 Press Document Overview All change documents: Click on the doc. No. for getting details.
  • 56. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 56 Where-Used List: Materials This Tcode shows the materials used in BOM component. TCODE: CS15 List of all components where this material is using.
  • 57. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 57 Multi-Level BOM Report: Menu Transaction Code ZPP_BOM
  • 58. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 58
  • 59. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 59 For Searching Raw Material used in BOM Enter Raw Material in (For material List BOM Component)
  • 60. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 60 Creation of Routing T-code: CA01 Pic. Shows the initial screen of creation of routings and the T-code is CA01. We have to enter the material code for which we are going to create routing in the Material field. We have to enter plant (7777). Go to Header of the routing.
  • 61. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 61 Enter the task list description. Enter the task list usage as production. Enter the status as 4 which indicate this routing or task list is released (general). Enter the lot size if anything is applicable. Come back the initial screen. Position the cursor on the operations field and enter.
  • 62. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 62 The operations screen appears. The operational increment is 10 by default. Enter the work center assigned to the operation, in work center field. Enter the control key in the field CO. The control key determines which business transactions should be executed for the object that belongs to the task list or order. The business transactions are whether the operations are included in scheduling. Costing automatic goods receipt, mile stone conformation etc. Enter the description of each operation. Enter the base quantity, by default system takes 1. Enter the Standard values (for ex. setup, labor etc).The standard values are planned values for executing an operation. Standard values are used in costing, scheduling, and capacity planning to calculate costs, execution times, and capacity requirements. The setup operation is not depended upon the quantity but all other operations are depended upon the operation quantity. Ex. Set up time =45min (die change).There we don’t enter any machine or labor time.
  • 63. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 63 The Next operation if it is done in machine work center we have to enter machine time and if labor works then enters labor time. In the Assembly work center where there is only labor involves enter labor time. These timings are called standard values and used in calculation of capacities, scheduling and costing functions. Component allocations: We have to assign materials to operations. The procedure is.. 1) Click on component allocations and select materials and click on new assignment. In the operation details all the operations are displayed. Select and assign materials to operations and save. The routing is saved with group and group counter. If we have similar routings for several materials we can copy the routings .The procedure is described below.
  • 64. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 64 Enter the material to which the routing is to be created and click on copy from and selct routing from the pop up screen. We get the below screen. Fill up the material name from which we want to copy the routings and click on copy and we get the operations copied. We can edit for changes.
  • 65. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 65 Creation of Work Centers An organizational unit that defines where and when an operation must be performed The work center has an available capacity. Work centers can be: Machines People Production lines The initial screen of the work center is given below. The T-Code to create work center is CR01.change CR02,DisplayCR03. We have to enter the plant and name of the work center and work center category. Ex: Plant =7777 Name of the Work center: LRTM Work Center Category: 0001=machine,0003=Labor
  • 66. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 66 We can copy work center from Different plants or in the same plant if they have got identical characteristics. Work Center is having 5 views. 1) basic data2) default values3) capacities4) scheduling and 5) costing The basic data screen as follows We need to enter the description of work centered: RTM work center. Person responsible: the person who is responsible for that work center. Usage: Key to control in which type of Routings we use work centers. Here it is 009=all task list types. Standard value key: Key defining and giving a dimension (for example, time or area) to one of up to six standard values. We use the parameter ID to determine the key word for a standard value, such as setup, machine or labor. We assign values to the standard values in the task list.
  • 67. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 67 Default Values Screen Control key: Determines which business transactions should be executed for the object that belongs to the routing or order. We have discussed about control key in routing, but if we tick in Ref.ID this is copied for an operation otherwise what is given in routing or task list is considered. No. of time tickets: Number of time tickets to be printed for an operation. This entry is only taken into account if time tickets are to be printed according to the operation control key. The value from the work center is the default in the routing. No. of Conformation slips: Number of confirmation slips to be printed for an operation or an activity. The system prints confirmations if the control key for the operation or activity has been set. The value from the work center is the default in the routing.
  • 68. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 68 Capacities In capacities screen we have to enter the formulas for setup requirements, processing requirements and other requirements if necessary. The formulas you can find by using drop down menu .The capacity category we have to enter if it is the machine category or labor category. A machine can have labor capacity, (crew working on that machine)can be entered as additional capacity in the same view. We need to enter data in another screen for capacities.
  • 69. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 69 Capacity planner grp: Key referring to the capacity planner group, which is responsible for planning this capacity. Factory calendar ID: IN Active version: The active version of available capacity is used as a basis for scheduling. The different versions allow you to maintain several available capacities at the same time. Base Unit of measure: Unit in which available capacity is maintained Standard available capacity: We have to define the available capacity(start time, finish time ,length of breaks and no. of individual capacities).By entering these values we get standard available capacity. Planning details: We define whether the work center capacities are relevant to finite scheduling, can be used by several operations and for long term planning. Scheduling In the capacity category we enter the main category of the work center. Set up formula, processing formula: Here we assign formula in view of scheduling Location group: Define where this work center is located.
  • 70. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 70 Work dimension, Work Unit: Define work dimension and units of work as TIME and HR. Capacities in scheduling: Capacities relevant to scheduling point of view
  • 71. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 71 COSTING We have to assign the activity types and the relevant formulas for costing purpose.
  • 72. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 72 Reference operation set A type of routing that comprises of a series of operations that recur frequently. It is used to create a routing. A reference operation set cannot be used directly in production. A reference operation set has the same structure as a routing. We cannot assign a material to be produced to a reference operation set. The T-Code to create reference operation set is CA11. This is the default screen of the reference operation set. Group: Here we can assign numeric key if it is required to combine several task lists. Otherwise system will assign internal number automatically. Click on header icon. System will display header for reference operation set.
  • 73. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 73 Group counter: This key and the task list group uniquely identify a routing. By default it is 1. We need to fill the task list description. Usage: Enter 1 for production. Status: Enter 4 for released (general). Enter the lot size if it is required and enter the unit of measure. After entering data in above fields click operations. The operations screen is similar as routing operations screen. After entering values in operations screen save the reference operation set. The message will be displayed as below. Reference operation set was saved with group (ex.) 50000014.
  • 74. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 74 Trigger Points A trigger point is an object that can be assigned to an operation in order to trigger a function. The T-code for creation of trigger points is CO31. Trigger points can trigger functions, If the status of an operation changes When an operation is confirmed, in this case the user decides whether the function is triggered. The default screen for creation of trigger points We have to enter the name of the trigger point. The following screen appears.
  • 75. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 75 We have to enter Trigger point usage: Grouping (standard) trigger points by their usage can have the following advantages: It becomes easier to locate similar trigger points When you enter a usage, the system lists all standard trigger points that have the same usage. It can display the type of function behind the trigger point. Trigger point Group: A combination of standard trigger points. We have click on the usage whether it is for triggering functions or used as release stop indicator and also the function which is to be activated. In the pic. Trig point functions checkbox is ticked. It means when the trigger point is activated and creates order with reference. Enter the system status and click on the status change triggering function. Activate once indicator: Use this indicator to specify that the milestone function can only be triggered once. Put the cursor on create order with reference and click on parameters. You can find the below screen
  • 76. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 76 We need to enter the system status, and status change as ‘+’,execute once indicator, group as well as group counter and order type as ‘Zp01’.(or any other rework order type). So when any order is partially confirmed the trigger point automatically triggers rework order or reference operation set depends on the setting what we have entered. If it triggers rework order the internal number assignment is done (the immediate no. of main production order is created with order type ZP01).We have to manually confirm the rework production order and goods movements and settlement is done for this to main production order.
  • 77. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 77 Production Resource Tools Production Resource/Tool (PRT) is a moveable operating resource used in production or plant maintenance. We can assign production resources and tools to the task lists and production orders for which they are required. Creation of PRT: T-code CF01 Enter the PRT name. Press enter.
  • 78. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 78 The screen follows Enter the status as 03 =released for production Task list usage =009 Base unit of measure = EA Plant =7777 Location=0001 Grouping key =2000 for fixtures. And press defaults
  • 79. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 79 You will see the following screen: Enter control key =1 Quantity formula =SAPF01 Usage value formula =SAPF02 Ref.date for start = 01 Ref. date for finish =04
  • 80. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 80 Go to extras and formula constants and you will find below screen. Enter the prt quantity and units as 2 nos and EA.
  • 81. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 81 Now we Closed these Movement Type: These (202,309,521) movement type is effecting our financial data and a lot of problems occurred in Balance sheet.
  • 82. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 82 Check Vendor Schedules: We should check vendor schedules with this Tcode. TCODE: ZOPENSHL These materials should receive on 23.07.2012 from respected vendors.
  • 83. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 83 Manually Created Schedule Lines: TCODE: YSLC
  • 84. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 84 In Scheduling Agreements Schedule Lines will be created by MRP. We closed manually creation of schedule lines in Vendor Scheduling Agreements. We closed Manually Creation of Production Orders. TCODE - CO01 Closed. On the basis of Production plan MRP will create planned orders and users will convert these planned orders in Production Orders. If there is any change in production plan we will change production plan in SAP system and run MRP again for getting planned orders and Procurement schedule lines. TCODE: MD04
  • 85. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 85 Select PldOrd and convert it in Production Order. User can convert total order qty. Or User can convert PartConvProdOrder
  • 86. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 86
  • 87. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 87 Scrap and rework doc TCODE: CO01 Order is created for 200 qty for 88912M68K00 Order conformation
  • 88. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 88 TCODE: CO15 Order is confirmed with 145 Nos , rework of 33 nos and rejection or scrap of 22 nos as shown in below screen and reason for variance in order quantity is also entered. Save confirmation. TCODE: MB31 GR is done for confirmed quantity only, that is 145 nos
  • 89. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 89 System show the screen below as deficit of order quantity 55 nos, ignore this message. After rework you can GR ( no conformation again) the quantity as shown below. Suzzest zero lines indicator as shown. Enter the rework order qty as 33 in the units of entry and save the order.
  • 90. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 90 Now the order quantity received is 178. do GR in MB31 screen for 22 nos in scrap storage location.
  • 91. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 91 The material in the Scrap store is scrapped by using 551 goods movement later in mb1a as below. TCODE: MB1A (Movement Type is 551)
  • 92. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 92 If you have created a Production orders and some change in BOM required. Engineering Department change in BOM and that change material are not effective in old production orders. This process will update BOM material in production orders after change in BOM. TCODE-CO02 Open production order in change mode.
  • 93. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 93 Go to Functions menu and Select Read PP master data.
  • 94. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 94 Click on check box “New BOM” and enter today’s date for explosion new/change BOM in production order.
  • 95. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 95 SAP TCODES FOR PRODUCTION USERS TCODE Description MM03 Display Material MMBE Stock Overview MM60 Material List CS03 Display Material BOM CS11 Explode BOM: Level by Level CS12 Explode BOM: Multi Level BOM CS13 Explode BOM: Summarized BOM CR01 Create Work Center CR02 Change Work Center CR03 Display Work Center CR11 Create Capacity CR12 Change Capacity CR13 Display Capacity CR05 Work Center List CA80 Work Center Where-Used CR15 Capacity Where-Used CR10 Work Center Change Document CA01 Create Routing CA02 Change Routing CA03 Display Routing CA12 Change Reference Operation Set CA13 Display Reference Operation Set MD61 Create Planned Independent Requirements MD62 Change Planned Independent Requirements MD63 Display Planned Independent Requirements MD4C Multilevel Order Report
  • 96. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 96 Evaluations MD04 Stock / Requirements List MD07 Collective access of stock / requirements list MD05 MRP List MD06 Collective access of MRP lists CO46 Order Progress Planned Order MD11 Create planned order MD12 Change planned order MD13 Display planned order MD16 Collective access of planned orders MD14 Individual conversion of planned order into MD15 Collective conversion of planned orders int MDVP Collective availability check CO01 Production order create (With Material) CO07 Production order create (Without Material) CO40 Production order create (From Planned Order) CO41 Collective convention of planned order CO08 Production order create (For Sales Order) COHV Mass Processing Production Orders COMAC Collective Availability check CO05N Release Production Orders CO04N Print Production Orders CO09 Availability Overwiew MB1A Enter Goods Issue MB31 Goods Receipt for order
  • 97. NTF (INDIA) PVT. LTD. User Training Document NTF Technik India Pvt. Ltd. 97 Reports COOIS Order Information System MCP7 Work Center Analysis MCP1 Operation Analysis MCP5 Material Analysis MCP3 Production Order Analysis MCRE Material Uses Analysis MCYJ Shop Floor Information System CO20 Orders Acc. to Order Number CO21 Orders for material CO22 Orders for MRP Controller CO23 Orders for Production Scheduler CO24 Missing Parts Info System CO27 Picking List CO28 Selection of Indiv. Objects List CO26 Order Information System