Ballou Senior High School
SIT team update
20 June 2013
Exterior Rendering
2
Exterior Rendering
3
Exterior Rendering
4
Brick and Metal Panel
Exterior Rendering
5
Exterior Rendering
6
Exterior Rendering
7
29 May 2013
Third Floor
29 May 2013
Second Floor
29 May 2013
First Floor
Progress Photos
SIT team update
20 June 2013
Aerial Photo prior to demolition (01/19/2013)
29 May 2013
Aerial Photo – Major Demolition Complete 03/10/2013
29 May 2013
Aerial Photo – Building Pads and Shoring in Progress
29 May 2013
Aerial Photo – Building Pads, Shoring, and Retainign Walls in Progress
29 May 2013
Excavation complete Cafeteria, Auto Tech, and Kitchen
29 May 2013
Site Retaining Walls on 4th St, near Band / Auditorium
29 May 2013
Caissons in progress, 40% complete, 60’ deep underground
29 May 2013
Steel Piles for Site Retaining Walls, 2nd St
29 May 2013
Caisson rebar cage being lowered into the ground
29 May 2013
Aerial Photo – June 15, 2013
29 May 2013
Construction Schedule
Upcoming SlideShare
Loading in …5
×

Ballou Senior High School Construction Update

2,089 views

Published on

Published in: Education, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
2,089
On SlideShare
0
From Embeds
0
Number of Embeds
799
Actions
Shares
0
Downloads
11
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Ballou Senior High School Construction Update

  1. 1. Ballou Senior High School SIT team update 20 June 2013
  2. 2. Exterior Rendering 2
  3. 3. Exterior Rendering 3
  4. 4. Exterior Rendering 4 Brick and Metal Panel
  5. 5. Exterior Rendering 5
  6. 6. Exterior Rendering 6
  7. 7. Exterior Rendering 7
  8. 8. 29 May 2013 Third Floor
  9. 9. 29 May 2013 Second Floor
  10. 10. 29 May 2013 First Floor
  11. 11. Progress Photos SIT team update 20 June 2013
  12. 12. Aerial Photo prior to demolition (01/19/2013)
  13. 13. 29 May 2013 Aerial Photo – Major Demolition Complete 03/10/2013
  14. 14. 29 May 2013 Aerial Photo – Building Pads and Shoring in Progress
  15. 15. 29 May 2013 Aerial Photo – Building Pads, Shoring, and Retainign Walls in Progress
  16. 16. 29 May 2013 Excavation complete Cafeteria, Auto Tech, and Kitchen
  17. 17. 29 May 2013 Site Retaining Walls on 4th St, near Band / Auditorium
  18. 18. 29 May 2013 Caissons in progress, 40% complete, 60’ deep underground
  19. 19. 29 May 2013 Steel Piles for Site Retaining Walls, 2nd St
  20. 20. 29 May 2013 Caisson rebar cage being lowered into the ground
  21. 21. 29 May 2013 Aerial Photo – June 15, 2013
  22. 22. 29 May 2013 Construction Schedule

×