  1. 1. SHAMIANA Project Software Project Management Project Abhinav Kamal 2010007 Debashish Bagg 2010298 Under the guidance of Prof. H. Halve Page1
  2. 2. Table of ContentsTable of Contents ............................................................................................................................................... 2Business Case..................................................................................................................................................... 4 Introduction .................................................................................................................................................... 4 Business Objective ......................................................................................................................................... 4 Current Situation and Problem/ opportunity statement .................................................................................. 4 Critical Assumption and Constraints ............................................................................................................. 5 Analysis of Options and Recommendations .................................................................................................. 5 Preliminary project requirements ................................................................................................................... 6 Budget estimates and financial analysis......................................................................................................... 6 Schedule estimates ......................................................................................................................................... 7 Potential risks ................................................................................................................................................. 7Project Charter ................................................................................................................................................... 8 Project Title:................................................................................................................................................... 8 Start Date: Aug 15th, 2011.............................................................................................................................. 8 Projected Finish Date: .................................................................................................................................... 8 Budget Information ........................................................................................................................................ 8 Project Manager ............................................................................................................................................. 8 Project Objectives: ......................................................................................................................................... 8 Approach:....................................................................................................................................................... 8 Roles and responsibilities: ............................................................................................................................. 9Project Scope Statement .................................................................................................................................... 9 Project Justification........................................................................................................................................ 9 Project characteristics and Requirements: ..................................................................................................... 9 Project management related deliverables:.................................................................................................... 10 Project Success Criteria ............................................................................................................................... 10Financial Analysis of the Project ..................................................................................................................... 11WBS for dart project ........................................................................................................................................ 13Detail schedule for implementation of dart project.......................................................................................... 21Human Resource Allocation Plan .................................................................................................................... 24 Roles and Responsibilities ........................................................................................................................... 24 Page2 Project Manager (PM) (1 position): ............................................................................................................. 24
  3. 3. Design Engineer (DE) (1 position): ............................................................................................................. 24 Implementation Manager (IM) (1 position): ................................................................................................ 24Risk Management ............................................................................................................................................ 26 Risk Identification........................................................................................................................................ 26 Qualitative Risk Analysis ............................................................................................................................ 26 List of Prioritized Risks: .............................................................................................................................. 27 Risk Response Planning ............................................................................................................................... 27 Risk Monitoring and Control ....................................................................................................................... 28 Page3
  4. 4. Business CaseIntroduction SHAMIANA – The Short Film Club is a part of „Two Plus Productions‟ has been in the forefront inthe business of short film exhibition and distribution for the last nine years and is now actively producingshort films. SHAMIANA is a very unique initiative that has gathered a huge following for itself in a shortspan. With over 3 million people (and growing) across various countries following the club, it‟s soonbecoming into a cult. They are into business of screening some of the best award-winning short films everproduced including Oscar winners, National Award winners, Golden Globe winners, Cannes winners,Berlinale winners, etc. They have showcased approximately 1000 films in the last 3 years. SHAMIANA is on its way to becoming the biggest brand in the alternative space of short films andwith the way the film club has taken off in the last ONE YEAR (reaching out to over 3 million across thecountry). SHAMIANA has already attracted some powerful associations like, MICROMAX MOBILES,ZYDUS WELLNESS, CLEARTRIP.COM, and other tie-ups across the country including Times Card,Radio Mirchi, etc.Business Objective SHAMIANA has been growing for the last few years phenomenally. To expand its reach and imprintits existence in the essence of customers SHAMIANA has to take leaps into the business of marketing itselfwhich it has not done so actively. SHAMIANA has been active on the front of marketing through itsfacebook page and its own webpage. To actively involve customers who visit its web pages SHAMIANA looks to create a few web basedgamming applications. A few though of applications were developing of a web based Dart application or inanimated movie application that would captivate the customer‟s application and also allow the spread theknowhow of SHAMIANA to other friend and users connected to present customer on facebook. Facebook is chose to be the base of launch of this application as its perceived to be most cheapestand booming platform to communicate with customers from the point of view of SHAMIANA.Current Situation and Problem/ opportunity statement With the advent of information technology and world moving to a internet dependentcommunication platform there has been many web based marketing platform that has been available in themarket today. Facebook is one of the communication platforms for marketing. Page4
  5. 5. SHAMIANA is one of the initiatives that have a very short reach of 9 cities in the whole country.There cities span Delhi, Bangalore, Mumbai, Ahmadabad, Pune, Baroda, Goa etc. Each of these expansionand knowhow lets SHAMIANA to expand to a new customer base and hence to a different territory ofcustomers and hence allowing growth in number of customers. SHAMIANA has found that facebook a very ardent platform of communicating and captivating thecustomer‟s attention. This project if successful would provide a gamut of benefits as follows: 1. Free promotion: This application if successful would help in achieving free promotion. 2. Exponential spread of knowledge about the firm: As the application is basically targeted to be launched on facebook as a platform, with the help of data sharing features that facebook allows it can be easily passed on to from one friend to another and hence improve the overall knowledge about SHAMIANA. 3. Market survey: This if successful would also help in launching different region based market survey such that it can be expanded into different geographic location across the country. 4. Easily accessible. 5. Increase of visibility of SHAMIANA 6. Customer engagement: These applications will allow to have a direct engagement of customer.Critical Assumption and Constraints The proposed dart application must be a valuable asset for SHAMIANA in terms of increasing itsvisibility and reach into customer base. It also needs to be able to perform customer engagement on apositive note. It should not adversely affect the customer base in terms of depleting the existing base of itscustomers. The most deathly constraint that SHAMIANA faces being only 3 years old is that of financing thepresent development. The funds that has been allocated by SHAMIANA for the current development is50,000 INR.Analysis of Options and Recommendations There are three options for addressing this opportunity: 1. Do nothing. SHAMIANA is doing well, and might be able to continue to operate without thisnew project. The rate at which number of customers has been growing is phenomenon at the present stage.This project is based on the fact that facebook is a vast platform of promotional activity and helps to rope innew customers if they are made to be involved into some application. (i.e. the application on facebook areeasy ways to rope in the customer involvement) Page5
  6. 6. 2. Purchase of external software: There are many off shelf facebook and flash application likeangry birds and lord of Ultimatum etc. that are available for free and some for a minimal cost. ButSHAMIANA‟s motto to build application is not only to get customers involved with it but to drag them intoknowing and getting involved with SHAMIANA as a whole. So these off shelf application either will nothelp or will need to be highly customized to suit for the same. 3. Design and implement by Vendor: The new intranet based application could be outsourced to anexternal vendor who would then code and develop the front end of the project. Hardware required for theproject would be outsourced initially to some server hosting client. In accordance to the changes in the futurescenario of success of the software these might be a server buying decision. Based on discussions with SHAMIANA, we believe that option 3 is the best option to work onthough the costing seems to be on a bit higher end.Preliminary project requirements The main features of the facebook based application include the following: 1. Eye catching graphics to catch customer‟s attention immediately. 2. Allow upload of photograph or brown photo on web to serve as the basis of Dart application developed. 3. Application needs to be easy and light to be loaded on computer with basic requirement. 4. Also needs to have records and display personalized records on global basis.Budget estimates and financial analysis Actual heading Cost Estimation Cost of leasing hardware 5000-6000 INR /annum Cost of code development 20,000-25,000 INR Cost of front end development 25,000 INR Maintenance cost 2000 INR/ month The project has a potential to fetch in customer from varied background and varied taste andpreferences. Hence the amount of intangible branding that the application can develop is huge. In terms ofadding the number of customers on an average of 400/ month and if the conversion of customers onfacebook to real life is approximately 10% that gives be 40 customs/ month. i.e. approximately 500customers per year that is a huge potential of growth. All these values are just data that are found from a Page6
  7. 7. survey that is circulated internal in many Google and facebook group and hence the data could be higher thandenoted value.Schedule estimates Activity Time estimates Requirement estimation and analysis 10 days Estimate of Flash ware preparation 20 days +5 days Estimate of coding and implementation 30 days + 10 days Hard ware deal finalizing 10 days Final testing and go live 10 days +5 days Total 50 days + 10 days The project on rough estimates seems to be completed in a span of two months but the client had arequirement of completing it in a month that seems infeasible on the face.Potential risks There are several risks involved with this project. The foremost risk is moving of customer baseaway from facebook. There could be technology advancement in the domain of internet web basedapplication that may make developed application obsolete and un-acceptable to the web browser. The mainbusiness risk is investing the time and money into this project and not realizing the projected organizationalwise benefits. Page7
  8. 8. Project CharterProject Title: Dart application for SHAMIANAStart Date: Aug 15th, 2011.Projected Finish Date: Initial launch of this project is going to be within 2 months of start date.Budget Information The organization needs to allocate 50,000 INR for this project. The majority of costs for this projectwill be payment to vendors developing different parts of the project. The amount mentioned above does notinclude cost like server space leasing cost and also regular maintenance and update cost. An initial estimateprovides a total of 60 days of work will be needed for completion of the project.Project Manager Debashish Bagg and Abhinav Kamal will share this responsibility.Project Objectives: Develop a new facebook based / web based application that would help customers to connect to thework done by SHAMIANA more effectively. The web application will be a basic dart on to which you canupload specific photos or browse from friends thus playing a interactive application that involves thecustomer. It also has potential of capturing the customer responses that would give ques about continuing orscraping the present application development going further.Approach: 1. Develop a survey to determine critical features of the web based dart that needs to be developed and the respective application linkages that are needed. 2. Research software to provide features needed along with the hardware that would support the same. 3. Develop a dart application soliciting a great deal of user feedback 4. Determine a way to measure the value of application and the value that is added by the application to SHAMIANA. Page8
  9. 9. Roles and responsibilities:Name Role Position Contact InformationDebashish Bagg Project Manager Debashish. bagg@gmail.comAbhinav Kamal Project Manager abhinav.kamal@gmail.comProject Scope StatementProject Justification SHAMIANA, requested this project to assist the company in meeting its marketing and hence itsgrowth goals. The new web based application will increase visibility of the company‟s expertise to currentand potential customers though increased involvement of customer with application of SHAMIANA page. Itwill also help improve visibility and customer involvement hence spreading of customer base. The budgetfor the project is 50,000 INR and will be deployed to software development by the external vendor.Estimated benefits are at least additional 500 customers each year.Project characteristics and Requirements: 1. Photos and dart background upload: The application needs to allow uploading photos or browsing through friend‟s photos to fix dart background. 2. User submissions: Users submissions and their scores needs to be recorded by the program and needs to be globally available. 3. Requests for articles: The application needs to be able to post the recent happenings on the customers page so as to attract other non customers get attached to the application and hence to SHAMIANA as a whole. 4. The “Refer to a friend” feature must be user-friendly and capable of soliciting user to forward the application link to his/ her friends in a proper format. This should also be able to show friend circle wise highest to inculcate high level of involvement among people/ customers. 5. Security: The application must not breach the internal security provided by facebook. It also needs to ensure that there is a proper security that the data in the application is not leaked unless intended by the user itself. 6. The intranet site must be light in terms of coding and hence be available on a basic web browser than asking for a heavier processing at the client side.. Page9
  10. 10. Project management related deliverables: Business case, charter, scope statement, WBS, schedule, cost baseline, final project presentation,lessons-learned report, and any other documents required to manage the project.Project Success Criteria Our goal is to complete this project within two months for no more than INR 50,000. The projectsponsor, SHAMIANA, has emphasized the importance of the project paying for itself within one year afterthe web application is complete. To meet this marketing goal, the web application must have strong userinputs. We must also develop a method for capturing the benefits while the web application is beingdeveloped, tested, and after it is rolled out. If the project takes a little longer to complete or costs a little morethan planned, the firm will still view it as a success if it has a good payback and helps promote the firm‟simage and draw the increased number of audience as its the goal of the application. Page10
  11. 11. Financial Analysis of the Project Following template is utilized to calculate the estimation of human resources as per function pointanalysis and data generate is as below. SUMMARY Project Identification Customer Name SHAMIANA Dart application for Project Name SHAMIANA Project Code Analyst Debashish Bagg Date Summary Estimates Unadjusted Function Point Count 28 From FP worksheet Processing Complexity Adjustment Factor 1.22 From PCA worksheet Adjusted Function Point Count (AFP) 34 Calculated: (FP*PCA) Calibration Factor (CF) 1 See note Total Function Point Measure (TFP) 34 Calculated: (AFP*CF) Delivery Rate (DR) in FPs/person month 1 See note Days per person-month (DPM) 4 See note High Level Effort Estimate (in person-days) 137 Calculated: (TFP/DR) * DPM The above summary can be further detailed in the following tables. INTERNAL LOGICAL FILES (ILFs) # of # of Complexity List of files DETs RETs Low Average High Notes and Assumptions Data file storing scores 2 5 1 0 0 global counter Summary 1 0 0 EXTERNAL INTERFACE FILES (EIFs) # of # of Complexity List of files DETs RETs Low Average High Notes and Assumptions interface to webpage 2 1 1 0 0 help files 1 1 1 0 0 Summary 2 0 0 Page11
  12. 12. EXTERNAL INPUTS (EIs) # of # of Complexity List of inputs DETs FTRs Low Average High Notes and Assumptions User name 2 1 1 0 0 User friend list 1 30 0 1 0 Tagged Summary 1 1 0 UNADJUSTED FUNCTION POINT COUNT (FP)Function Type Functional Complexity Count Weight Function Points (FPs) FP %Internal Logical Files (ILFs) Low 1 7 7 Average 0 10 0 High 0 15 0 25%External Interface Files (EIFs) Low 2 5 10 Average 0 7 0 High 0 10 0 36%External Inputs (EIs) Low 1 3 3 Average 1 4 4 High 0 6 0 25%External Outputs (EOs) Low 1 4 4 Average 0 5 0 High 0 7 0 14%External Queries (EQs) Low 0 3 0 Average 0 4 0 High 0 6 0 0% Total Unadjusted Function Point Count 28 100% VALUE ADJUSTMENT FACTOR (VAF) Degree of General Systems Characteristics Description Influence (0-5) 1. Data Communications 5 The application is online 2. Distributed Processing 4 It has to be distributed calculation 3. Performance 3 Heavily Used 4. Configuration 3 5. Transaction Rates 4 6. Online Data Entry 5 Design for End User Page12 7. Efficiency 4 8. Online Update 5 update is online
  13. 13. 9. Complex Processing 4 average on processing complexity Usable in Other has to be reusable to be moved to other 10. Applications 4 coding if needed 11. Installation Ease 3 12. Operational Ease 4 13. Multiple Sites 5 on website and facebook 14. Facilitate Change 4 needs to allow change Total Degree of Influence (TDI) 57 Calculated (sum of the above) Value Adjustment Factor (VAF) 1.22 Calculated ((TDI*0.01)+0.65)WBS for dart project1. Dart project 1.1. Design of web application Interface (MAAC) 1.1.1. Interface specification 1.1.1.1. Functional specification 1.1.1.1.1. Interface for web browser 1.1.1.1.1.1. Create mock interface for web browser 1.1.1.1.1.2. Conduct design review internal to the team 1.1.1.1.1.3. Get design reviewed by stakeholders 1.1.1.1.1.3.1. Get design reviewed by mock users 1.1.1.1.1.4. Take consensus for the design 1.1.1.1.1.5. Create a final functional specification 1.1.1.1.1.6. Obtain individual signoff 1.1.1.1.2. Interface for mobile browser (can run simultaneously with 1.1.1.1.1) 1.1.1.1.2.1. Create mock interface for web browser 1.1.1.1.2.2. Conduct design review internal to the team 1.1.1.1.2.3. Get design reviewed by stakeholders 1.1.1.1.2.3.1. Get design reviewed by mock users 1.1.1.1.2.4. Take consensus for the design 1.1.1.1.2.5. Create a final functional specification 1.1.1.1.2.6. Obtain individual signoff 1.1.1.1.2.6.1. Signoff for interface from SHAMIANA representative body and mock users 1.1.1.2. Technical specifications (TAVARI PVT. LTD) 1.1.1.2.1. Develop the technical specifications based on the previous signoff document 1.1.1.2.2. Review the technical specifications Page13 1.1.1.2.3. Obtain signoff from respective stakeholders 1.1.1.2.3.1. Signoff of the SHAMIANA representation
  14. 14. 1.1.1.2.3.2. Signoff of mock users if required1.1.2. SQL Database specification (TAVARI PVT. LTD) 1.1.2.1. Develop technical specifications 1.1.2.2. Review technical specifications 1.1.2.2.1. Review by the project team 1.1.2.3. Review by external expert (SHAMIANA ) 1.1.2.4. Rework technical specification 1.1.2.5. Obtain team signoff 1.1.2.5.1. Obtain signoff of the project team 1.1.2.6. Obtain signoff of the external expert if he is a stakeholder (SHAMIANA )1.1.3. Interfaces (TAVARI PVT. LTD) 1.1.3.1. Technical specifications 1.1.3.1.1. Determine data import/ export elements 1.1.3.1.2. Design Interface 1.1.3.1.3. Obtain signoff of the respective stakeholders 1.1.3.1.3.1. Obtain signoff of the project team 1.1.3.2. Obtain signoff of the external expert if he is a stakeholder (SHAMIANA )1.1.4. Reports (TAVARI PVT. LTD) 1.1.4.1. Functional specification report 1.1.4.1.1. Collect user requirement data 1.1.4.1.1.1. Define data elements 1.1.4.1.1.1.1. Define null or initial values if any on the screen 1.1.4.1.1.1.2. Define relative values for users i.e. any history to be maintained 1.1.4.1.1.2. Define frequency of use 1.1.4.1.1.3. Define sessions 1.1.4.1.2. Design reports 1.1.4.1.2.1. Design and develop the functional specifications 1.1.4.1.2.2. Document relationship/ flow from functional specification to technical specification 1.1.4.1.2.3. Design and develop the detailed design document 1.1.4.1.2.4. Flow from detailed design specification to test plans 1.1.4.1.2.5. Design and develop the initial testing plan 1.1.4.1.2.6. Design and develop the integration testing plan 1.1.4.1.3. Deliver the acceptance testing plan 1.1.4.1.4. Review report design with project team 1.1.4.1.5. Deliver final functional specifications Page14 1.1.4.1.5.1. Deliver the functional specifications
  15. 15. 1.1.4.1.5.2. Deliver the detailed design document 1.1.4.1.5.3. Deliver the initial testing plan 1.1.4.1.5.4. Deliver the integration testing plan 1.1.4.1.5.5. Deliver the acceptance testing plan 1.1.4.1.6. Obtain signoff of the respective stakeholders 1.1.4.1.6.1. Obtain signoff of the project team 1.1.4.2. Obtain signoff of the external expert if he is a stakeholder (SHAMIANA ) 1.1.4.2.1.1.1.2. Procurement (TAVARI PVT. LTD) 1.2.1. Planning software needs 1.2.1.1. Determine software needs 1.2.1.2. Make software selection 1.2.2. Float the design specification to respective software vendors 1.2.2.1. Float above technical specification development 1.2.3. Get quotation from software providers 1.2.4. Compare the quotations 1.2.4.1. Compare the quotation price 1.2.4.2. Compare vendor history 1.2.4.3. Compare add on features if any 1.2.4.4. Compare the comparability and customization requirement 1.2.4.5. Compare the software provided on basis of relative ease of maintenance cost 1.2.5. Take an decision of which vendor to be accepted 1.2.6. vendor visit 1.2.6.1. Discuss with the vendor to avoid any communication gap in the specification 1.2.6.2. Discuss the broad aspects of the project 1.2.6.3. Finalize the vendor contact and date of delivery. 1.2.6.4. If failed go to step 1.2.3 for next best vendor 1.2.7. Communicate to get the software on board and start with customization 1.2.7.1. Deadline communications and reporting 1.2.7.1.1. Check with the detailed design document for specification 1.2.7.1.2. Check with testing and reporting at each stage 1.2.7.2. Involve respective stakeholders in the decision process 1.2.7.3. If failed go to step 1.2.3 for next best vendor1.3. Customization (TAVARI PVT. LTD) 1.3.1. Installation of software 1.3.1.1. Procure the soft ware 1.3.1.2. Install the software on the existing hardware Page15 1.3.2. Initial testing and validation of the software and its features
  16. 16. 1.3.2.1. Front end testing 1.3.2.1.1. Browser front end testing 1.3.2.1.1.1. Verify design and functionality 1.3.2.1.1.2. Perform unit testing 1.3.2.1.1.3. Perform integration testing 1.3.2.1.1.4. Perform acceptance testing 1.3.2.1.1.4.1. Perform load testing (if needed) 1.3.2.1.1.4.2. Perform connectivity testing (if needed) 1.3.2.1.1.5. Obtain signoff from the testing team and end users 1.3.2.1.1.6. Note and communicate the customizations needed 1.3.2.1.1.7. Signoff test plan for vendor 1.3.2.1.2. Mobile frontend testing 1.3.2.1.2.1. Verify design and functionality 1.3.2.1.2.2. Perform unit testing 1.3.2.1.2.3. Perform integration testing 1.3.2.1.2.4. Perform acceptance testing 1.3.2.1.2.4.1. Perform load testing (if needed) 1.3.2.1.2.4.2. Perform connectivity testing (if needed) 1.3.2.1.2.5. Obtain signoff from the testing team and end users 1.3.2.1.2.6. Note and communicate the customizations needed 1.3.2.1.2.7. Signoff test plan for vendor1.3.2.2. SQL database testing 1.3.2.2.1. Verify design/ data elements 1.3.2.2.2. Verify the relationships 1.3.2.2.3. Perform integration testing 1.3.2.2.4. Perform User acceptance testing 1.3.2.2.4.1. Acceptance testing in terms of load 1.3.2.2.4.2. Acceptance testing in terms of integrity etc 1.3.2.2.5. Obtain user signoff1.3.2.3. Interface 1.3.2.3.1. Verify design and functionality 1.3.2.3.2. Perform Integration Testing 1.3.2.3.3. Perform User Acceptance Testing 1.3.2.3.4. Obtain signoff from the testing team and end users 1.3.2.3.5. Note and communicate the customizations needed 1.3.2.3.6. Signoff test plan for vendor1.3.2.4. Reports Page16 1.3.2.4.1. Verify design and functionality
  17. 17. 1.3.2.4.2. Perform Integration test 1.3.2.4.3. Perform User Acceptance Testing 1.3.2.4.4. Obtain signoff from the testing team and end users 1.3.2.4.5. Note and communicate the customizations needed 1.3.2.4.6. Signoff test plan for vendor1.3.3. Implement the required customization 1.3.3.1. Front End 1.3.3.1.1. Mock user front end 1.3.3.1.1.1. Customize Web pages 1.3.3.1.1.2. Conduct Unit testing 1.3.3.1.1.3. Review web page design and functionality 1.3.3.1.1.4. Get final user to test 1.3.3.1.1.5. Rework if needed for the same 1.3.3.1.2. Web front end 1.3.3.1.2.1. Customize Web pages 1.3.3.1.2.2. Conduct Unit testing 1.3.3.1.2.3. Review web page design and functionality 1.3.3.1.2.4. Get final user to test 1.3.3.1.2.5. Rework if needed for the same 1.3.3.1.3. Mobile front end 1.3.3.1.3.1. Customize Web pages 1.3.3.1.3.2. Conduct Unit testing 1.3.3.1.3.3. Review web page design and functionality 1.3.3.1.3.4. Get final user to test 1.3.3.1.3.5. Rework if needed for the same 1.3.3.2. SQL Database 1.3.3.2.1. Identify the customization in relationships of the tables 1.3.3.2.2. Build the database schemas 1.3.3.2.3. Build each data element if needed 1.3.3.2.4. Build database tables 1.3.3.2.5. Review tables with project team and external expert 1.3.3.3. Interface 1.3.3.3.1. Customize interfaces where ever needed 1.3.3.3.2. Conduct unit testing of import and export functionality 1.3.3.3.3. Sign off for interface customization 1.3.3.4. Reports 1.3.3.4.1. Code custom reports Page17 1.3.3.4.2. Test custom reports
  18. 18. 1.3.3.4.3. Review 1.3.3.4.3.1. Review the reports with required stakeholders if needed 1.3.3.4.3.2. Review the reports with project team 1.3.3.4.3.3. Rework if there are changes needed 1.3.3.4.4. Sign off custom reports development 1.3.3.5. Track customization at every stage through different reporting mechanism1.3.4. Final testing and validation of the software and its features 1.3.4.1. Front end testing 1.3.4.1.1. Browser front end testing 1.3.4.1.1.1. Verify design and functionality 1.3.4.1.1.2. Perform unit testing 1.3.4.1.1.3. Perform integration testing 1.3.4.1.1.4. Perform acceptance testing 1.3.4.1.1.4.1. Perform load testing (if needed) 1.3.4.1.1.4.2. Perform connectivity testing (if needed) 1.3.4.1.1.5. Obtain signoff from the testing team and end users 1.3.4.1.1.6. Note and communicate the customizations needed 1.3.4.1.1.7. Signoff test plan for vendor 1.3.4.1.2. Mobile frontend testing 1.3.4.1.2.1. Verify design and functionality 1.3.4.1.2.2. Perform unit testing 1.3.4.1.2.3. Perform integration testing 1.3.4.1.2.4. Perform acceptance testing 1.3.4.1.2.4.1. Perform load testing (if needed) 1.3.4.1.2.4.2. Perform connectivity testing (if needed) 1.3.4.1.2.5. Obtain signoff from the testing team and end users 1.3.4.1.2.6. Note and communicate the customizations needed 1.3.4.1.2.7. Signoff test plan for vendor 1.3.4.2. SQL database testing 1.3.4.2.1. Verify design/ data elements 1.3.4.2.2. Verify the relationships 1.3.4.2.3. Perform integration testing 1.3.4.2.4. Perform User acceptance testing 1.3.4.2.4.1. Acceptance testing in terms of load 1.3.4.2.4.2. Acceptance testing in terms of integrity etc 1.3.4.2.5. Obtain user signoff 1.3.4.3. Interface Page18 1.3.4.3.1. Verify design and functionality
  19. 19. 1.3.4.3.2. Perform Integration Testing 1.3.4.3.3. Perform User Acceptance Testing 1.3.4.3.4. Obtain signoff from the testing team and end users 1.3.4.3.5. Note and communicate the customizations needed 1.3.4.3.6. Signoff test plan for vendor 1.3.4.4. Reports 1.3.4.4.1. Verify design and functionality 1.3.4.4.2. Perform Integration test 1.3.4.4.3. Perform User Acceptance Testing 1.3.4.4.4. Obtain signoff from the testing team and end users 1.3.4.4.5. Note and communicate the customizations needed 1.3.4.4.6. Signoff test plan for vendor1.4. Test runs (TAVARI PVT. LTD) 1.4.1. Create system documentation 1.4.1.1. Assemble functional specification document 1.4.1.2. Assemble technical specification documents 1.4.1.3. Develop system flowcharts 1.4.1.4. Make proper documentation for the source code (in form of comments etc) 1.4.1.5. Deliver the source code 1.4.1.6. Complete system documentation manual 1.4.1.7. Get the document created by respective user and technical expert 1.4.1.8. Rework and baseline the changes that are suggested in system manual 1.4.2. Create test run materials 1.4.2.1. Assemble functional specifications 1.4.2.2. Develop “As Is” and “To be” documentations 1.4.2.3. Update business process 1.4.2.3.1. Write new business process 1.4.2.3.2. Obtain user signoff 1.4.2.4. Complete system documentation manual 1.4.2.5. Get the document created by respective user and technical expert 1.4.2.6. Rework and baseline the changes that are suggested in system manual1.5. Project closure (TAVARI PVT. LTD) 1.5.1. Closure of project 1.5.2. Closure of contract with the vendor 1.5.3. Final project backup 1.5.4. Project review and lessons learnt documented 1.5.5. Final project signoff Page191.6. Post project (TAVARI PVT. LTD)
  20. 20. 1.6.1. Post project maintenance 1.6.1.1. Verify the project functionality 1.6.1.2. Verify the acceptance functionality1.6.2. Regular update/ patches 1.6.2.1. Verify the project versions of software update 1.6.2.2. Check and update the software installed 1.6.2.3. Make changes and update the software 1.6.2.4. Make required changes to custom code (if necessary) for each update of the software Page20
  21. 21. Detail schedule for implementation of dartprojectThe timeline for the project and present completion status of the project is as follows: Serial No Task Name Start Date End Date Days Prev. Task % done Assigned To Design of web 08/16/11 08/23/11 6 100% debashish bagg application 1 Interface Front End 08/16/11 08/17/11 2 100% Interface 2 specification SQL Database 08/18/11 08/19/11 2 2 100% 3 specification 4 Interfaces 08/18/11 08/22/11 3 2, 3FF 100% 5 Reports 08/23/11 08/23/11 1 2, 4FF +1 day 100% 6 Procurement 08/26/11 10/27/11 45 60% abhinav kamal Planning 08/26/11 08/26/11 1 1FS +2 days 100% 7 software needs Float the design 08/29/11 08/31/11 3 7 100% specification to respective 8 software vendors Get quotation 09/01/11 09/05/11 3 8FF +3 days 100% from software 9 providers Compare the 09/06/11 09/06/11 0.5 9 100% 10 quotations Take an 09/07/11 09/07/11 0.5 10 100% decision of which vendor to be 11 accepted 12 vendor visit 09/08/11 09/08/11 1 11 100% Communicate 09/09/11 10/27/11 35 11FS +1 day 50% to get the software on board and start with 13 customization 14 Customization 11/01/11 11/03/11 3 debashish bagg Installation of 11/01/11 11/01/11 1 6FS +2 days 15 software Initial testing 11/02/11 11/02/11 1.5 15 and validation of the software and 16 its features Implement the 11/03/11 11/03/11 1.5 16 required 17 customization Final testing 11/02/11 11/03/11 2 17FF Page21 18 and validation of
  22. 22. the software and its features19 Test runs 08/24/11 09/09/11 13 100% abhinav Kamal Create system 08/24/11 08/30/11 5 1 100%20 documentation Create test run 09/05/11 09/09/11 5 20FS +3 days 100%21 materials22 Project closure 11/04/11 11/10/11 5 debashish bagg Closure of 11/04/11 11/04/11 1 1423 project Closure of 11/07/11 11/08/11 2 23 contract with the24 vendor Final project 11/04/11 11/07/11 2 1825 backup Project review 11/09/11 11/09/11 1.5 24, 25 and lessons learn26 documented Final project 11/10/11 11/10/11 1 2627 signoff28 Post project 11/11/11 11/11/11 1 abhinav kamal Post project 11/11/11 11/11/11 1 2229 maintenance Regular update/30 patches Page22
  23. 23. Software Project Management Final Project Report 23 Page
  24. 24. Software Project Management Final Project ReportHuman Resource Allocation PlanRoles and Responsibilities The roles and responsibilities for the Software Upgrade Project are essential to project success. Allteam members must clearly understand their roles and responsibilities in order to successfully perform theirportion of the project. For the Software Upgrade Project the following project team roles and responsibilitieshave been established:Project Manager (PM) (1 position): PM is responsible for the overall success of the Software DART Project. The PM must authorizeand approve all project expenditures. The PM is also responsible for approving that work activities meetestablished acceptability criteria and fall within acceptable variances. The PM will be responsible forreporting project status in accordance with the communications management plan. The PM will evaluate theperformance of all project team members and communicate their performance to functional managers. ThePM is also responsible for acquiring human resources for the project through coordination with functionalmanagers. The PM must possess the following skills: leadership/management, budgeting, scheduling, andeffective communication.Design Engineer (DE) (1 position): DE is responsible for gathering coding requirements for the Software DART Project. The DE isresponsible for all upgrade design, coding, and testing of the upgraded software. The DEs will assist theimplementation lead in the distribution and monitoring of the software upgrades throughout the networkinfrastructure. The DE will be responsible for timely status reporting to the PM as required by thecommunications management plan. The DEs may not authorize any project expenditures nor allocate anyresources without PM approval.Implementation Manager (IM) (1 position): The IM is responsible for the distribution, implementation, and monitoring of the new softwareupgrade. The IM is responsible for working with the DE to ensure all coding on new software conformswith organizational security regulations. The IM is responsible for coordination outage windows with eachdepartment to facilitate the rollout of the software upgrades with minimal/no disturbance to operations. The 24IM will report status to the PM in accordance with the project‟s communications management plan. Page
  25. 25. The following RACI chart shows the relationship between project tasks and team members. Anyproposed changes to project responsibilities must be reviewed and approved by the project manager.Changes will be proposed in accordance with the project‟s change control process. As changes are made allproject documents will be updated and redistributed accordingly. Project Manager Design Engineers Implementation Manager Design of web application Interface A R R Procurement/ Outsourcing A R C Customization A R Software Testing A R C Implementation A C R Project Closure A A C Post closure Activities A A IKey:R – Responsible for completing the workA – Accountable for ensuring task completion/sign offC – Consulted before any decisions are madeI – Informed of when an action/decision has been made Page25
  26. 26. Risk Management There may several risks involved during or after the completion of this project. Those risks need tobe identified and managed in order to make the project a success.Risk Identification Risk associated with this project can be categorized under following four heads: People risk: o Risk 1: Acceptance from the customers for whom the application is being designed and implemented in the first place o Risk 2: Finding appropriate coders for coding the back-end functions to be performed by the system. o Risk 3: Lack of inputs from the team members during the planning, execution and implementation of the project Technological risk: o Risk 4: Technical glitches faced by users while taking the test o Risk 5: Providing appropriate results to application user o Risk 6: Migration of platform from facebook to other if the target customer moves on Financial and Time risk: o Risk 7: Completing the project within the budget o Risk 8: Completing the project within allocated timeline Other risk: o Risk 9: Realizing the required MOV for the SHAMIANA‟s investmentQualitative Risk AnalysisThe above-identified risks have to prioritized, so that appropriate actions can be taken in case of occurrenceof those risks. Probability Low Medium HighImpactLow Risk 5 Risk 7, Risk 8 Risk 2, Risk 3 Page26
  27. 27. Medium Risk 9 Risk 4High Risk 1, Risk 6List of Prioritized Risks:Ranking Potential Risk1 Acceptance from the customers for whom the application is being designed and implemented in the first place2 Migration of platform from facebook to other if the target customer moves on3 Technical glitches faced by users while taking the test4 Finding appropriate coders for coding the back-end functions to be performed by the system5 Completion of the project with in allocated timeline6 Completing the project within the budget7 Migration of platform from facebook to other if the target customer moves on8 Realizing the required MOV for the Institute‟s investment9 Providing appropriate results to application userRisk Response PlanningIn order to manage the risks the following strategies and actions can be performed:Risk Strategy ActionAcceptance from the customers Risk There has to be a specific research that has been Mitigation done to actually zero down to a set of game that would be developed. This part is taken by SHAMIANA.Appropriate results Risk Through testing each module AvoidanceTechnical glitches Risk Use familiar hardware, and software available Avoidance Page27Finding appropriate coders Risk Approach the familiar coders or coders whose
  28. 28. Mitigation work is known.Time and cost constraints Risk Follow the WBS strictly and keep some slack for Mitigation the coding part, For cost also estimation is done on task and functional point basis .Realizing the required MOV Risk Promote the application as in ways possible TransferenceRisk Monitoring and Control The project team should be at all times aware of any of the above-identified risks and should followthe actions as stated in the previous table. In addition, the team should keep an open mind and keepidentifying any other risks while the execution and or implementation phase of this project. For the newlyidentified risks, the team members should follow the complete risk management process. Page28

×