Project Scope of Work                                                  1                                   (E) 10th Street...
Laney College                           2      Athletic Field            &   Field House Project               Presented b...
Background & Priority                               3 Lake Merritt BART                                           Lake Mer...
Project Team / Cordoba’s Role                                              4                              Owner           ...
Project Scope of Work                                                  5                                   (E) 10th Street...
Inc. # 1: New Solar-Powered Parking Lot Structure   6
Inc. # 2: New Baseball Field   7
Inc. #3 Athletic Field House   8
First Floor- 12,000 sq.ft.   9
Second Floor- 5,500 sq.ft.   10
Final Project Cost                      11                    $18 Million   This cost included five (5) Approved Change Or...
Project Highlights                               12  Completed November 2011  Design-Build  LEED® Gold Certified  $1.9...
Upcoming SlideShare
Loading in …5
×

Laney College Athletic Field & Field House Project

2,045 views

Published on

In November 2011, the Peralta Community College District celebrated the completion of the new Design-Build, state-of-the-art, LEED® Gold Certified Athletic Field & Field House Project on the Laney College campus in Oakland, California. This assignment is particularly significant because it is the first design/build project of any kind undertaken by the District.

Published in: Business, Education
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
2,045
On SlideShare
0
From Embeds
0
Number of Embeds
532
Actions
Shares
0
Downloads
5
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Laney College Athletic Field & Field House Project

  1. 1. Project Scope of Work 1 (E) 10th Street (E) 5th Street (E) Football Field Increment #2“Baseball Field” Increment #3 “Field House” Increment #1 “Parking Lot”
  2. 2. Laney College 2 Athletic Field & Field House Project Presented by: Nawar Al Juburi LEED® Green AssociateAssistant Construction Manager/Field Engineer Cordoba Corporation Northern California Regional Office 500 12th Street, Suite 330 Oakland, CA 94607
  3. 3. Background & Priority 3 Lake Merritt BART Lake Merritt StationInterstate Highway 880 Eagles North(To Downtown Football Field San Francisco ) Laney College Laney College Campus Athletic Filed & Field House Interstate Highway Peralta Community880 South (To Oakland College District Office International Airport) STRATEGIC PROJECT LOCATION
  4. 4. Project Team / Cordoba’s Role 4 Owner (PERALTA COMMUNITY COLLEGE DISTRICT) Construction Management (CORDOBA CORPORATION ) Design-Build Entity Architect of Record(GILBANE BUILDING COMPANY ) (GOULD EVANS BAUM THORNLEY, INC.)
  5. 5. Project Scope of Work 5 (E) 10th Street (E) 5th Street (E) Football Field Increment #2“Baseball Field” Increment #3 “Field House” Increment #1 “Parking Lot”
  6. 6. Inc. # 1: New Solar-Powered Parking Lot Structure 6
  7. 7. Inc. # 2: New Baseball Field 7
  8. 8. Inc. #3 Athletic Field House 8
  9. 9. First Floor- 12,000 sq.ft. 9
  10. 10. Second Floor- 5,500 sq.ft. 10
  11. 11. Final Project Cost 11 $18 Million This cost included five (5) Approved Change Orders 1.50% Unforeseen Conditions 1% E&O 2%Owner Request
  12. 12. Project Highlights 12 Completed November 2011 Design-Build LEED® Gold Certified $1.9 million Photovoltaic Collection System Minimum of 340,000 kilowatt hours per year 100% of the peak energy demand of the Field House 75% of the annual power consumption This translates into $350k in savings within the first 5 years of the buildings use

×