The ideal Agile world describes dedicated Teams that implement a negotiable scope in fixed iterations to meet a moving target. The real world is usually more complex, and often requires interaction with projects and processes that have very different and “non-Agile” characteristics. This webinar describes the conduct of Agile governance for hybrid projects that contain very different types of processes. We will review the very real drivers that lead to these hybrid environments, and look at practical techniques for making hybrid projects successful.

Published in: Business, Technology
  • Be the first to comment

Agile Governance for Hybrid Programs

  1. 1. SM RAGE Agile Governance for Hybrid Programs Kevin Thompson, PhD, PMP, ACP, CSP, CSM The leader in training and consulting for project management and agile development
  2. 2. Who cPrime? Who isis cPrime? ENGAGED FOR YOUR SUCCESS Copyright 2013, cPrime Inc. 2 2
  3. 3. Who Are You? 1) Have you read the RAGESM paper, Recipes for Agile Governance in the Enterprise: The Enterprise Web? 2) What fraction of your business initiatives involve hybrid programs? 3) Which of these best characterizes the products you develop? 4) Are you a member of PMI or the Scrum Alliance? Copyright 2013, cPrime Inc. 3 3
  4. 4. Start Communicating! • View our previous RAGESM webinars: • ―Principles for Agile Governance in the Enterprise‖ • ―Introduction to Agile Portfolio Governance‖ • Download the white paper “Recipes for Agile Governance in the Enterprise (RAGE): The Enterprise Web.” • Email: agileexpert@cprime.com • Social media: #RAGEwebinar Copyright 2013, cPrime Inc. 4 4
  5. 5. After the webinar… • We will send directions to collect the PDU you will earn from attending this webinar • We will also send links to the recorded webinar and all RAGESM resources • Please hold your questions until the end of the presentation Copyright 2013, cPrime Inc. 5 5
  6. 6. About Our Presenter Kevin Thompson Kevin Thompson, Ph.D., has a doctorate in Physics from Princeton University, and extensive background in managing software development projects. He specializes in training individuals, teams, and organizations in agile development. Dr. Thompson helps companies make the challenging transition to agile development by working with development teams and business stakeholders to identify their needs, define the right process for the business, determine the steps needed to implement the process, and work through the steps successfully. Dr. Thompson has Project Management Professional (PMP), Agile Certified Practitioner (ACP), Scrum Master (CSM), and Scrum Practitioner (CSP) certifications. Copyright 2013, cPrime Inc. 6 6
  7. 7. What will You Learn Today? • Fundamentals of planning & executing hybrid programs • How to create a Release Plan • How to manage dependencies and changes • How to evaluate progress towards objectives • This approach incorporates Principles of Agile Governance • Download ―Recipes for Agile Governance: The Enterprise Web‖ from www.cprime.com for much more detail Copyright 2013, cPrime Inc. 7 7
  8. 8. Review: Agile Governance Governance: The formalization and exercise of repeatable decision-making practices • Governance = how to decide what to do • Agile Governance is an Agile style of governance • Enables rapid decisions, based on lightweight artifacts developed with minimum effort • Applicable to any process (Agile, Plan-Driven, Hybrid, etc.) Governance Recipe: A mildly prescriptive and customizable technique for making a specific type of decision Copyright 2013, cPrime Inc. 8 8
  9. 9. Review: How the Principles Work Together Recipes have Standard Elements, including Common Role Types and Categories of Governance Points. We organize deliverables at each level into a small number of coarseGranularity items, which we rank by value, and for which our estimates for effort, value, etc. should be Good Enough for the current need, and no better. Work is always completed to a Definition of Done, and the Handoff from source to receiver is accomplished through sustained interaction over time. Download Recipes for Agile Governance: The Enterprise Web from www.cprime.com for much more detail Copyright 2013, cPrime Inc. 9 9
  10. 10. Review: Levels of Governance • Classic perspective • Project: Temporary endeavor to deliver a fixed scope • Program: Collection of linked projects • Portfolio: Group of Programs/Projects to be managed together • Classic definitions don’t map well to Agile world, but… • Hierarchical organization is still relevant. • Our levels for Agile Governance • Project Level: Refers to work of a single Team, which is a persistent grouping of people • Program Level: Refers to the collaboration between Teams • Portfolio Level: Refers to the development and management of business Initiatives that lead to program- and project-level work Copyright 2013, cPrime Inc. 10 10
  11. 11. Levels of Governance Copyright 2013, cPrime Inc. 11 11
  12. 12. The Teams in the Program • Two Software Teams • They write software, to be deployed in Production environment • They mostly interact with each other • They depend on IT for key milestones in next Release • IT Department • Manages procurement, configuration of hardware and software products • Supplies hardware, software, services to software development Teams • Builds, maintains, deploys applications to Production environment Copyright 2013, cPrime Inc. 12 12
  13. 13. The Processes • Software Teams follow Scrum process • Work must be planned against a calendar • Work can be divided into short cycles • Teams can start and finish deliverables in each cycle • IT follows a plan-driven process • Work must be planned against a calendar • Unique, one-off projects are common and have varying lengths • Work cannot be divided into short cycles in which deliverables are started and finished Copyright 2013, cPrime Inc. 13 13
  14. 14. The Objective • Deliver first release of Web application for an onlinedating service • First release has minimum-marketable feature set • Time to market more important than feature richness Copyright 2013, cPrime Inc. 14 14
  15. 15. Program Governance Summary • Requirements Development • • Release Planning • • The Program Manager facilitates the Release Planning meeting for the Scrum Teams and IT personnel, who develop an initial Release plan for the Stories and IT milestones. Execution during the Release Cycle • • The Area Product Owner defines the Release goals. Team Product Owners and Team Members write Stories to define the specific deliverables, review them in Backlog Grooming meetings, and revise after. An IT Project Manager meets with the Teams over time to understand the deliverables IT needs to deliver for the Release. The Program Manager facilitates twice-weekly Scrum-of-Scrums meetings, where ScrumMasters and the IT Project Manager identify and respond to cross-Team issues as they arise. Validation for Release to Production • The Area Product Owner facilitates the Release Review meeting at the end of the Release cycle, to work with the Team Product Owners, Program Manager, and IT Project Manager to confirm that the Release candidate satisfies the Release Definition of Done. Copyright 2013, cPrime Inc. 15 15
  16. 16. Backlog Grooming Meeting • Purpose: Ensure Product Backlog is ready for planning • Team Product Owner facilitates • When: 1—2 hours per week • Who: Team, Team Product Owner • Actions in meeting • Provide feedback on clarity, quality, acceptance criteria, dependencies, ranking of Stories • Identify ―holes‖ (esp. technical) for which Stories must be written • Break Epics into Stories • Do long-term technical (architecture / infrastructure) planning • Follow-up actions • Team, Product owner write or revise Stories, as needed Copyright 2013, cPrime Inc. 16 16
  17. 17. Release Planning Meeting • Purpose: Develop Initial Release Plan • Program Manager facilitates • When: 1—4 weeks before start of Release cycle • Who: Program Manager, Area Product Owner, Team Product Owners, ScrumMasters, Team Members, IT Project Manager,… Agenda 1. 2. 3. 4. 5. Copyright 2013, cPrime Inc. 6. 7. Teams lay out Stories, Epics (―Items‖) in preferred sequence Teams quickly provide adequate estimates for Items not yet estimated (e.g., Planning Poker, Affinity Estimation) Teams map Items to Sprints – Stories do not cross Sprint boundaries, but Epics may Teams collaborate to identify, sequence dependencies Teams collaborate to identify missing Items, create, and incorporate them into the plan IT Project Manager collaborates on timing of IT milestones All agree on ―Definition of Done‖ (exit criteria) for Release 17 17
  18. 18. Example: Release Definition of Done • No P0 or P1 defects • No more than 15 P2 defects • Value of Release candidate justifies a Production deployment • Prerequisites for handoff to IT are confirmed by IT and Engineering to have been satisfied Copyright 2013, cPrime Inc. 18 18
  19. 19. Stories and Milestones Blue Team Stories Size User Creates Account 5 User Personal Info 5 User Logs In 5 User Search Profiles 5 CC Gateway 8 User Message to Profile 8 User Gives CC Info 3 User Reads Message 3 CC Data Secure Storage 8 User Replies to Message 8 User Logs Out 3 User Emailed re: Msg 3 Total Green Team Stories 32 Milestones for IT Department Size Total 39 Day of Release Cycle Reconfigure Firewall to enable access to CC Gateway for development 0 Deliver DB Server 8 Deliver Mail Server 12 Copyright 2013, cPrime Inc. 19 19
  20. 20. Initial Release Plan Blue Team: CC Gateway is new and high-risk, so put at front of Sprint 1 to allow time to deal with issues. Enable account creation and access next, to make work easier for Green Team. Sprint 1 CC Gateway User Personal Info Reconfigure Firewall Sprint 2 User Creates Account User Logs In User Search Profiles User Message to Profile Deliver DB Server Deliver Mail Server Sprint 3 User Logs Out User Emailed re: Msg CC Data Secure Storage User Gives CC Info User Reads Message User Replies to Message Green Team: Ranking by workflow is natural, and gives IT time to deliver the Mail Server before it is needed. Will mock user-account objects at start. Copyright 2013, cPrime Inc. 20 20
  21. 21. Scrum-of-Scrums Meeting • Purpose: Identify and address cross-Team issues • Program Manager facilitates • When: Twice weekly (more or less often, as needed) • Who: Program Manager, ScrumMasters, IT Project Manager Agenda • Each person describes  What my Team is doing that may affect other Teams  What issues my Team needs help to resolve • Resolve issues in meeting, if possible • Identify follow-up actions and owners • Follow-up actions • Resolve problems, revise schedule as needed Copyright 2013, cPrime Inc. 21 21
  22. 22. Revision at Start of Sprint 1 Blue Team: IT can’t reconfigure corporate firewall to enable development access to credit-card gateway before Sprint 1. Defer ‘CC Gateway’ to Sprint 2. Sprint 1 User Creates Account Sprint 2 User Logs In User Personal Info CC Gateway User Search Profiles User Message to Profile Reconfigure Firewall Deliver DB Server Deliver Mail Server CC Data Secure Storage User Emailed re: Msg Sprint 3 User Logs Out User Reads Message User Gives CC Info User Replies to Message Green Team: No change needed. Actually more convenient to have Login earlier than for original plan. Copyright 2013, cPrime Inc. 22 22
  23. 23. Burn-Up Chart: End of Sprint 1 Sprint 1 Sprint 2 Sprint 3 No guarantee, but progress is consistent with completion of planned Release scope Copyright 2013, cPrime Inc. 23 23
  24. 24. Revision at Start of Sprint 2 Blue Team: Firewall fixed, but IT will be late delivering DB server for CC data storage. Defer ‘CC Data Secure Storage’ to Sprint 3. Sprint 1 Sprint 2 Sprint 3 User Logs In User Creates Account User Personal Info CC Gateway User Gives CC Info CC Data Secure Storage User Logs Out User Search Profiles User Message to Profile User Reads Message User Replies to Message User Emailed re: Msg Reconfigure Firewall Deliver DB Server Deliver Mail Server Green Team: IT delivery of email server will be late. Defer ‘User Emailed re: Msg’ to Sprint 3. Copyright 2013, cPrime Inc. 24 24
  25. 25. Burn-Up Chart: End of Sprint 2 Sprint 1 Sprint 2 Sprint 3 The trend looks good. Completion of planned Release scope is likely. Copyright 2013, cPrime Inc. 25 25
  26. 26. Final at Start of Sprint 3 Blue Team: No change needed. Sprint 1 Sprint 2 Sprint 3 User Logs In User Creates Account User Personal Info CC Gateway User Gives CC Info CC Data Secure Storage User Logs Out User Search Profiles User Message to Profile User Reads Message User Replies to Message User Emailed re: Msg Reconfigure Firewall Deliver DB Server Deliver Mail Server Green Team: No change needed. Copyright 2013, cPrime Inc. 26 26
  27. 27. Burn-Up Chart: End of Release Cycle Sprint 1 Sprint 2 Sprint 3 The planned Release scope was completed Copyright 2013, cPrime Inc. 27 27
  28. 28. Release Review Meeting • Purpose: Ensure product is ready for release to Production • Area Product Owner facilitates • When: End of Release cycle • Who: Area and Team Product Owners, Program Manager, IT Project Manager • Actions in meeting • Review Release Definition of Done to confirm release readiness  Review business objectives to confirm value justifies release  Quality is sufficient  Technical pre-requisites for deployment have been satisfied • Area Product Owner makes Go/No-go decision • Follow-up actions • Program Manager communicates decision, initiates handoff, to IT department, as appropriate Copyright 2013, cPrime Inc. 28 28
  29. 29. Summary of Cross-Team Roles Area Product Owner • Defines Release Goals • Minimum Feature Set • Works with Team Product Owners to clarify requirements Program Manager • Ensures cross-Team planning, collaboration are done well • Runs Release Planning, Scrum-of-Scrums meetings Project Manager (IT) • Brings Scrum Teams’ requirements to IT Department • Creates and updates IT work schedule Copyright 2013, cPrime Inc. 29 29
  30. 30. Summary of Scrum Team Roles ScrumMaster • Does whatever is needed to make Team as productive as possible • Acts as Servant Leader • Owns process (enforces, tracks, expedites problem resolution) • Runs Daily Scrum, Sprint Planning, Retrospective Meetings • Often a Project Manager Team • Self-organizes crossfunctional members to implement, test features • Software & test engineers, database architects, UI developers, etc. • Owns estimates, tasks, assignments Team Product Owner • • • • • Is Team’s sole source of truth for requirements and priorities Owns requirements (new features, bug fixes) and ranking Works with Area Product Owner to define & rank user-facing features Collaborates with Team to ensure proper implementation Often a Product Manager, Business Analyst Copyright 2013, cPrime Inc. 30 30
  31. 31. Summary of Recipes Recipe Participants Decisions & Actions Backlog Grooming Meeting Team Product Owner, Team Identify changes required for the Product Backlog (revise, add, delete Stories) Release Planning Meeting Area & Team Product Owners, Program Manager, IT Project Manager, ScrumMasters, Teams Program Manager facilitates. Teams and IT Project Manager devise Release Plan that satisfies Release goals and dependencies. Scrum-ofScrums Meeting Program Manager, ScrumMasters, IT Project Manager Each describes possible impact of Team’s work, impacts discovered that require assistance. All identify how to address impacts. Copyright 2013, cPrime Inc. 31 31
  32. 32. Summary of Recipes Recipe Participants Decisions & Actions Release Readiness Review Meeting Area & Team Product owners, Program Manager, IT Project Manager Area Product Owner facilitates review to confirm product satisfies Release Definition of Done, make Go/No-go decision for deployment. Release Definition of Done Area Product Owner, Program Manager, IT Project Manager Defines requirements that must be satisfied before product can be released for production deployment. Guides development, and is used in Release Readiness Review meeting. Copyright 2013, cPrime Inc. 32 32
  33. 33. Which Agile Governance Principles are Used? Most of them! 1. 2. 3. 4. 5. 6. 7. Standardization of Recipe Elements Common Role Types Categories of Governance Points “Good Enough” is Good Enough Granularity Definition of Done Handoffs Copyright 2013, cPrime Inc. Download ―Recipes for Agile Governance: The Enterprise Web‖ from www.cprime.com for much more detail 33 33
  34. 34. Conclusion • Program-level governance for hybrid processes means • Developing, planning requirements across all Teams and processes • Adapting to issues that arise during development • Our hybrid Program governance is conducted with • Roles: Area & Team Product Owners, Program Manager, ScrumMasters, Teams, IT Project Manager • Ceremonies: Backlog Grooming, Release Planning, Scrum-ofScrums, Release Readiness Review Meetings • Artifacts: Stories, Release Definition of Done • Tracking and Metrics: Burn-Up Chart • Key insights • Breaking scope into small deliverables (Stories) is key to our ability to adapt to unexpected changes Copyright 2013, cPrime Inc. 34 34
  35. 35. Question & Answer Copyright 2013, cPrime Inc. 35 35

×