SlideShare a Scribd company logo
1 of 4
Net Gain of Ecological Function Observed on
            Bainbridge Island Shorelines from 1997 to 2010
              Compiled from Hydraulic Project Approvals (HPAs) issued by the
                        Washington Department of Fish & Wildlife.

                       by Albert Greiner for Bainbridge Shoreline Homeowners
                              with editorial assistance by Ken Sethney


Summary

New construction, damage repair, and restoration projects undertaken since our city’s Shoreline
Management Master Program was enacted, have resulted in a significant gain of shoreline
ecological function. When combining the data from overwater structures, shoreline modifications
and restoration projects, we have seen the following gains over the last thirteen years:

      • 750 linear feet reduction of hard shoreline armoring

      • 1,536 square feet reduction of opaque overwater structures

      • 523 feet of creosote treated wood bulkhead have been replaced

      • 583 creosote treated pilings have been or will be removed

      • 4,036 cubic yards of sand & gravel will nourish beaches

      • 28,518 square feet of native vegetation have been planted

      • 125,676 square feet of tideland have been or will be restored

      • 196,020 square feet of eelgrass have been or will be planted


Conclusion

“No net loss” was not the standard in 1996, but it is today. It is clear that existing policies are
more than adequate to mitigate loss and provide substantial gains.

During their presentation at City Hall, Department of Ecology representatives made it clear that
“no net loss” can be applied to an entire jurisdiction rather than a single project. Doing so
spreads the incentives for and benefits of restoration across the entire island instead of focusing
on individual homeowners or project developers.




Tuesday, March 1, 2011 c                           
                                              1 of 4
Docks and Overwater Structures

        • 52 HPAs were issued from 1997 to 2010

        • 8,796 square feet of opaque dock deck was replaced with grated deck

        • 7,260 square feet of new opaque deck was installed

        • 1,772 square feet of new grated deck was installed

        • 283 creosote treated pilings were removed

        • 381 non-toxic pilings were installed


According to the Army Corps. of Engineers, Washington Department of Fish & Wildlife (WDFW),
and local planners, grated decking is better than opaque decking. Since 1996, we have seen a
net reduction of 1,536 square feet of opaque overwater structures.1

While examining the HPA documents, we observed that most decks and floats are less than 60
feet long. The area of the island’s tidelands extending 60 feet from the ordinary high water mark
is approximately 16,790,400 square feet.2

New overwater structures, both opaque and grated, total 9,032 square feet.3 This constitutes a
change of about 0.054% or 5.4 hundredths of one percent in thirteen years, or 4 thousandths of
one percent per year.

That amounts to one square foot of new dock surface for every 1,859 square feet of tideland
area 60 feet from the OHWM.



          Summary:         Any loss of ecological function caused by such a minute yearly change is
                           far outweighed by the net reduction in opaque overwater structures.




1   7,260 square feet - 8,796 square feet = -1,536 square feet
2   53 miles X 5,280 feet/mile X 60 feet = 16,790,400 square feet
3   1,772 square feet + 7,260 square feet = 9,032 square feet

Tuesday, March 1, 2011 c                               
                                       2 of 4
Shoreline Modifications

We found shoreline modification permits for bulkhead repairs, removals, replacement and
installations, plus restoration permits for private shorelines.

        • 68 permits were issued from 1997 to 2010 4

        • 1,690 linear feet of new rock bulkhead was installed

        • 507 linear feet of soft armoring was installed

        • 405 linear feet of concrete bulkhead was replaced by lower reflectivity rock bulkhead

        • 523 feet of creosote treated wood bulkhead was replaced by rock bulkhead

        • 17,036 square feet of tideland gained due to bulkhead removals & landward relocations

        • 2,806 linear feet of beach was improved by installing large woody debris

        • 5,018 square feet of native vegetation was restored

        • 4,036 cubic yards of beach nourishment (aka “fish
          mix”) has been required as mitigation over various time
          periods

                This is equal to 230 tandem wheeled dump truck loads,
                        enough to spread 4.5 inches of sand and gravel
                                   over the island’s entire tideland area.


The net permitted gain of 1,690 feet of angular rock armoring is 0.6% of the island’s 53 miles of
shoreline.5 This is slightly more than 1/16th of an inch per foot of shoreline, and amounts to an
armoring rate of 130 feet per year.

Approximately 50 percent of Bainbridge Island’s shoreline has been modified in the past.6 At
130 feet per year, it would take 1,076 years to modify the remaining 50 percent if it were lawful
to do so.7 However, this ignores the restoration projects mentioned below which have (or will)
result in a 750 foot net reduction of shoreline armoring.


          Summary:         Any loss of ecological function caused by such a minute yearly change is
                           far outweighed by moving structures landward, installation of soft
                           armoring and woody debris, and beach nourishment requirements.




4   We noted a large spike in bulkhead repairs following the severe 2005-6 winter storm.
5   1,690 feet / ( 53 miles x 5,280 feet/mile ) = .006 = 0.6%
6   Herrera, Addendum to the Summary of Science Report for Bainbridge Island, pg 14
7   50% x (( 53 miles x 5,280 feet/mile ) / 130 feet/year ) = 1,076 years

Tuesday, March 1, 2011 c                                 
                                     3 of 4
Shoreline Restoration

The following were observed from sources reporting shoreline restorations on Bainbridge Island.
Most are classified as active projects. Blakely Harbor Park restoration goals are included but
that project is still being studied as to feasibility. We were unable to find data on the Waterfront
Park shoreline restoration, so bulkhead removal and shoreline restoration for that project is not
included in the following numbers.

      • 2,440 linear feet of shoreline armoring removed

      • 108,640 square feet of tidelands/marsh restored

      • 870 cubic yards of debris removed from tidelands

      • 23,500 square feet of nearshore vegetation restored to native species

      • 196,020 square feet of eelgrass planed

      • 300+ creosote treated pilings removed

      • 435 linear feet of shoreline received large woody debris

      • 265 feet of jetty to be removed (Blakely)

      • 2,750 square foot structure to be removed (Blakely)


        Summary:           Restoration is intended to cause a net gain of ecological function. With
                           limited information, we have been able to track these significant gains.


Limitations of Data Included

      • Hydraulic Project Approval (HPA) data was furnished under a public records request
        made to the Department of Fish and Wildlife.

      • All shoreline work requires an HPA before any city permit may be issued.

      • Many HPAs are not specific as to tideland gains, so only those gains cited or calculable
        from applications are included. There are more gains than totaled here.

      • Many HPOs do not specify numbers of piles removed, so only those pilings enumerated
        are included. More pilings have been removed than totaled here.

      • The permits mentioned were HPA permits, not Bainbridge Island city permits.

      • HPA permits do not show completion dates, so there is no confirmation that the
        permitted work was actually completed.

      • Personal communication from a COBI staff member indicates COBI has no reliable way
        of reporting project completion.


Tuesday, March 1, 2011 c                             
                                            4 of 4

More Related Content

What's hot

Cowell Beach Overview 11/14
Cowell Beach Overview 11/14Cowell Beach Overview 11/14
Cowell Beach Overview 11/14Matt Kuhn
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationFairfax County
 
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Ekonnect
 
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...Michael Hewitt, GISP
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Fairfax County
 
Municipal Adaptations to Create Resilient Beach Communities
Municipal Adaptations to Create Resilient Beach CommunitiesMunicipal Adaptations to Create Resilient Beach Communities
Municipal Adaptations to Create Resilient Beach CommunitiesSMRPC
 
Independent Review of Hydrological Issues: Deloro Mine Site
Independent Review of Hydrological Issues: Deloro Mine SiteIndependent Review of Hydrological Issues: Deloro Mine Site
Independent Review of Hydrological Issues: Deloro Mine SiteLOWaterkeeper
 
Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014Fairfax County
 
Getting to know_your_watershed_bass_river
Getting to know_your_watershed_bass_riverGetting to know_your_watershed_bass_river
Getting to know_your_watershed_bass_riverCapeCodCommission
 
Swim Drink Fish Canada submission for relicensing written hearing for the Del...
Swim Drink Fish Canada submission for relicensing written hearing for the Del...Swim Drink Fish Canada submission for relicensing written hearing for the Del...
Swim Drink Fish Canada submission for relicensing written hearing for the Del...LOWaterkeeper
 
Coastal management integrated and sustainable management
Coastal management   integrated and sustainable managementCoastal management   integrated and sustainable management
Coastal management integrated and sustainable managementMrOH
 
Reconstructing Water Levels in the Lake Michigan Basin from Embayed Lakes
Reconstructing Water Levels in the Lake Michigan Basin from Embayed LakesReconstructing Water Levels in the Lake Michigan Basin from Embayed Lakes
Reconstructing Water Levels in the Lake Michigan Basin from Embayed LakesSERC at Carleton College
 
Nov 16 2016 nps presentation west pond[2995]
Nov 16 2016 nps presentation west pond[2995]Nov 16 2016 nps presentation west pond[2995]
Nov 16 2016 nps presentation west pond[2995]ecowatchers
 
Royal Lake Dredging and Restoration
Royal Lake Dredging and RestorationRoyal Lake Dredging and Restoration
Royal Lake Dredging and RestorationFairfax County
 

What's hot (20)

2015 State of Buzzards Bay
2015 State of Buzzards Bay2015 State of Buzzards Bay
2015 State of Buzzards Bay
 
Cowell Beach Overview 11/14
Cowell Beach Overview 11/14Cowell Beach Overview 11/14
Cowell Beach Overview 11/14
 
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake RestorationPohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
Pohick Creek Watershed: Dam Rehabilitation Dredging and Lake Restoration
 
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
Lake Restoration Projects Being Undertaken by BDA_Bangalore Development Autho...
 
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
Dizak, Earth Conservancy, "AMD Treatment Alternatives and Reclamation of Mine...
 
Clad agm sepa_lorna
Clad agm sepa_lornaClad agm sepa_lorna
Clad agm sepa_lorna
 
Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration Woodglen Lake Dredging and Restoration
Woodglen Lake Dredging and Restoration
 
Municipal Adaptations to Create Resilient Beach Communities
Municipal Adaptations to Create Resilient Beach CommunitiesMunicipal Adaptations to Create Resilient Beach Communities
Municipal Adaptations to Create Resilient Beach Communities
 
Independent Review of Hydrological Issues: Deloro Mine Site
Independent Review of Hydrological Issues: Deloro Mine SiteIndependent Review of Hydrological Issues: Deloro Mine Site
Independent Review of Hydrological Issues: Deloro Mine Site
 
Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014Royal Lake Dredging and Restoration Project Update-June 2014
Royal Lake Dredging and Restoration Project Update-June 2014
 
Getting to know_your_watershed_bass_river
Getting to know_your_watershed_bass_riverGetting to know_your_watershed_bass_river
Getting to know_your_watershed_bass_river
 
Swim Drink Fish Canada submission for relicensing written hearing for the Del...
Swim Drink Fish Canada submission for relicensing written hearing for the Del...Swim Drink Fish Canada submission for relicensing written hearing for the Del...
Swim Drink Fish Canada submission for relicensing written hearing for the Del...
 
Coastal management integrated and sustainable management
Coastal management   integrated and sustainable managementCoastal management   integrated and sustainable management
Coastal management integrated and sustainable management
 
Reconstructing Water Levels in the Lake Michigan Basin from Embayed Lakes
Reconstructing Water Levels in the Lake Michigan Basin from Embayed LakesReconstructing Water Levels in the Lake Michigan Basin from Embayed Lakes
Reconstructing Water Levels in the Lake Michigan Basin from Embayed Lakes
 
Navy Region Southwest Water Conservation - U.S. Navy
Navy Region Southwest Water Conservation -  U.S. NavyNavy Region Southwest Water Conservation -  U.S. Navy
Navy Region Southwest Water Conservation - U.S. Navy
 
The Shifting Sands of Noosa
The Shifting Sands of Noosa The Shifting Sands of Noosa
The Shifting Sands of Noosa
 
Nov 16 2016 nps presentation west pond[2995]
Nov 16 2016 nps presentation west pond[2995]Nov 16 2016 nps presentation west pond[2995]
Nov 16 2016 nps presentation west pond[2995]
 
Kenedy County GCD, Mary Sahs
Kenedy County GCD, Mary SahsKenedy County GCD, Mary Sahs
Kenedy County GCD, Mary Sahs
 
Royal Lake Dredging and Restoration
Royal Lake Dredging and RestorationRoyal Lake Dredging and Restoration
Royal Lake Dredging and Restoration
 
EdgeW
EdgeWEdgeW
EdgeW
 

Similar to Cumulative Impact Summary 1997-2010 HPAs

Cumulative Impact Net Gain
Cumulative Impact Net GainCumulative Impact Net Gain
Cumulative Impact Net GainBSH Admin
 
Cumulative Impact of Armoring Reduction
Cumulative Impact of Armoring ReductionCumulative Impact of Armoring Reduction
Cumulative Impact of Armoring ReductionBSH Admin
 
Babson Court Outfall Restoration
Babson Court Outfall RestorationBabson Court Outfall Restoration
Babson Court Outfall RestorationFairfax County
 
Martecchini great marsh symposium presentation duxbury beach - 11-13-2014
Martecchini great marsh symposium presentation   duxbury beach - 11-13-2014Martecchini great marsh symposium presentation   duxbury beach - 11-13-2014
Martecchini great marsh symposium presentation duxbury beach - 11-13-2014greenbelt82
 
Boston Engineering and Design Poster
Boston Engineering and Design PosterBoston Engineering and Design Poster
Boston Engineering and Design PosterThomas Bryce
 
Responses to Public Comments About Beach Restoration at Quogue
Responses to Public Comments About Beach Restoration at QuogueResponses to Public Comments About Beach Restoration at Quogue
Responses to Public Comments About Beach Restoration at QuogueQuogueBeaches
 
Harvest Green Project Completion
Harvest Green Project CompletionHarvest Green Project Completion
Harvest Green Project CompletionFairfax County
 
Lazy Creek Court Outfall Restoration
Lazy Creek Court Outfall RestorationLazy Creek Court Outfall Restoration
Lazy Creek Court Outfall RestorationFairfax County
 
Bay Crest Dredging Presentation 1-24-2024
Bay Crest Dredging Presentation 1-24-2024Bay Crest Dredging Presentation 1-24-2024
Bay Crest Dredging Presentation 1-24-2024marygracekamis
 
Realities of Beach Restoration in Quogue
Realities of Beach Restoration in QuogueRealities of Beach Restoration in Quogue
Realities of Beach Restoration in QuogueQuogueBeaches
 
Wetland and Stream Crossing Impacts of Proposed M-83
Wetland and Stream Crossing Impacts of Proposed M-83Wetland and Stream Crossing Impacts of Proposed M-83
Wetland and Stream Crossing Impacts of Proposed M-83redaphid
 
Crestmont circle outfall restoration
Crestmont circle outfall restorationCrestmont circle outfall restoration
Crestmont circle outfall restorationFairfax County
 
Dannenbaum Engineering - River Update 9-19-2015
Dannenbaum Engineering - River Update 9-19-2015Dannenbaum Engineering - River Update 9-19-2015
Dannenbaum Engineering - River Update 9-19-2015law138
 
4210 final presentation
4210 final presentation4210 final presentation
4210 final presentationCeciliaEargle
 
Green Hollow Court Outfall Restoration
Green Hollow Court Outfall RestorationGreen Hollow Court Outfall Restoration
Green Hollow Court Outfall RestorationFairfax County
 
Barnack Drive Outfall Restoration Project Completion
Barnack Drive Outfall Restoration Project CompletionBarnack Drive Outfall Restoration Project Completion
Barnack Drive Outfall Restoration Project CompletionFairfax County
 
Jamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdfJamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdfecowatchers
 

Similar to Cumulative Impact Summary 1997-2010 HPAs (20)

Orlando 2015
Orlando 2015Orlando 2015
Orlando 2015
 
Cumulative Impact Net Gain
Cumulative Impact Net GainCumulative Impact Net Gain
Cumulative Impact Net Gain
 
Cumulative Impact of Armoring Reduction
Cumulative Impact of Armoring ReductionCumulative Impact of Armoring Reduction
Cumulative Impact of Armoring Reduction
 
Babson Court Outfall Restoration
Babson Court Outfall RestorationBabson Court Outfall Restoration
Babson Court Outfall Restoration
 
Martecchini great marsh symposium presentation duxbury beach - 11-13-2014
Martecchini great marsh symposium presentation   duxbury beach - 11-13-2014Martecchini great marsh symposium presentation   duxbury beach - 11-13-2014
Martecchini great marsh symposium presentation duxbury beach - 11-13-2014
 
Boston Engineering and Design Poster
Boston Engineering and Design PosterBoston Engineering and Design Poster
Boston Engineering and Design Poster
 
Responses to Public Comments About Beach Restoration at Quogue
Responses to Public Comments About Beach Restoration at QuogueResponses to Public Comments About Beach Restoration at Quogue
Responses to Public Comments About Beach Restoration at Quogue
 
Harvest Green Project Completion
Harvest Green Project CompletionHarvest Green Project Completion
Harvest Green Project Completion
 
Lazy Creek Court Outfall Restoration
Lazy Creek Court Outfall RestorationLazy Creek Court Outfall Restoration
Lazy Creek Court Outfall Restoration
 
Bay Crest Dredging Presentation 1-24-2024
Bay Crest Dredging Presentation 1-24-2024Bay Crest Dredging Presentation 1-24-2024
Bay Crest Dredging Presentation 1-24-2024
 
Realities of Beach Restoration in Quogue
Realities of Beach Restoration in QuogueRealities of Beach Restoration in Quogue
Realities of Beach Restoration in Quogue
 
Wetland and Stream Crossing Impacts of Proposed M-83
Wetland and Stream Crossing Impacts of Proposed M-83Wetland and Stream Crossing Impacts of Proposed M-83
Wetland and Stream Crossing Impacts of Proposed M-83
 
Crestmont circle outfall restoration
Crestmont circle outfall restorationCrestmont circle outfall restoration
Crestmont circle outfall restoration
 
Dannenbaum Engineering - River Update 9-19-2015
Dannenbaum Engineering - River Update 9-19-2015Dannenbaum Engineering - River Update 9-19-2015
Dannenbaum Engineering - River Update 9-19-2015
 
4210 final presentation
4210 final presentation4210 final presentation
4210 final presentation
 
Green Hollow Court Outfall Restoration
Green Hollow Court Outfall RestorationGreen Hollow Court Outfall Restoration
Green Hollow Court Outfall Restoration
 
ESTC 2011 Presentation by Scott Liggett, Beach Renourishment
ESTC 2011 Presentation by Scott Liggett, Beach RenourishmentESTC 2011 Presentation by Scott Liggett, Beach Renourishment
ESTC 2011 Presentation by Scott Liggett, Beach Renourishment
 
Making Connections Across Our Watersheds
Making Connections Across Our WatershedsMaking Connections Across Our Watersheds
Making Connections Across Our Watersheds
 
Barnack Drive Outfall Restoration Project Completion
Barnack Drive Outfall Restoration Project CompletionBarnack Drive Outfall Restoration Project Completion
Barnack Drive Outfall Restoration Project Completion
 
Jamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdfJamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdf
 

More from BSH Admin

PRSM Petition For Review
PRSM Petition For ReviewPRSM Petition For Review
PRSM Petition For ReviewBSH Admin
 
Dennis Reynolds Legal Implications of SMP Update
Dennis Reynolds Legal Implications of SMP UpdateDennis Reynolds Legal Implications of SMP Update
Dennis Reynolds Legal Implications of SMP UpdateBSH Admin
 
Kitsap draft smp conforming w highlights-1
Kitsap draft smp   conforming w highlights-1Kitsap draft smp   conforming w highlights-1
Kitsap draft smp conforming w highlights-1BSH Admin
 
Sandy Mackie on Restoration vs. Mitigation
Sandy Mackie on Restoration vs. MitigationSandy Mackie on Restoration vs. Mitigation
Sandy Mackie on Restoration vs. MitigationBSH Admin
 
What does state law say about shoreline regulations?
What does state law say about shoreline regulations?What does state law say about shoreline regulations?
What does state law say about shoreline regulations?BSH Admin
 
PSP Vital Signs
PSP Vital SignsPSP Vital Signs
PSP Vital SignsBSH Admin
 
Slide show with audio
Slide show with audioSlide show with audio
Slide show with audioBSH Admin
 
Residential Development and Buffers
Residential Development and BuffersResidential Development and Buffers
Residential Development and BuffersBSH Admin
 
Six BIG Problems with the SMP update.
Six BIG Problems with the SMP update.Six BIG Problems with the SMP update.
Six BIG Problems with the SMP update.BSH Admin
 
Save a salmon, lose your life savings.
Save a salmon, lose your life savings.Save a salmon, lose your life savings.
Save a salmon, lose your life savings.BSH Admin
 
Save a salmon, lose your life savings.
Save a salmon, lose your life savings.Save a salmon, lose your life savings.
Save a salmon, lose your life savings.BSH Admin
 
Rockaway Beach Road Erosion Control
Rockaway Beach Road Erosion ControlRockaway Beach Road Erosion Control
Rockaway Beach Road Erosion ControlBSH Admin
 
SMP Update Calendar 032911
SMP Update Calendar 032911SMP Update Calendar 032911
SMP Update Calendar 032911BSH Admin
 
Rockaway Slip Sliding Away
Rockaway Slip Sliding AwayRockaway Slip Sliding Away
Rockaway Slip Sliding AwayBSH Admin
 
Rockaway Beach Road Erosion Control
Rockaway Beach Road Erosion ControlRockaway Beach Road Erosion Control
Rockaway Beach Road Erosion ControlBSH Admin
 
DOE Role in SMP Update
DOE Role in SMP UpdateDOE Role in SMP Update
DOE Role in SMP UpdateBSH Admin
 
DOE Nonconforming Uses
DOE Nonconforming UsesDOE Nonconforming Uses
DOE Nonconforming UsesBSH Admin
 

More from BSH Admin (17)

PRSM Petition For Review
PRSM Petition For ReviewPRSM Petition For Review
PRSM Petition For Review
 
Dennis Reynolds Legal Implications of SMP Update
Dennis Reynolds Legal Implications of SMP UpdateDennis Reynolds Legal Implications of SMP Update
Dennis Reynolds Legal Implications of SMP Update
 
Kitsap draft smp conforming w highlights-1
Kitsap draft smp   conforming w highlights-1Kitsap draft smp   conforming w highlights-1
Kitsap draft smp conforming w highlights-1
 
Sandy Mackie on Restoration vs. Mitigation
Sandy Mackie on Restoration vs. MitigationSandy Mackie on Restoration vs. Mitigation
Sandy Mackie on Restoration vs. Mitigation
 
What does state law say about shoreline regulations?
What does state law say about shoreline regulations?What does state law say about shoreline regulations?
What does state law say about shoreline regulations?
 
PSP Vital Signs
PSP Vital SignsPSP Vital Signs
PSP Vital Signs
 
Slide show with audio
Slide show with audioSlide show with audio
Slide show with audio
 
Residential Development and Buffers
Residential Development and BuffersResidential Development and Buffers
Residential Development and Buffers
 
Six BIG Problems with the SMP update.
Six BIG Problems with the SMP update.Six BIG Problems with the SMP update.
Six BIG Problems with the SMP update.
 
Save a salmon, lose your life savings.
Save a salmon, lose your life savings.Save a salmon, lose your life savings.
Save a salmon, lose your life savings.
 
Save a salmon, lose your life savings.
Save a salmon, lose your life savings.Save a salmon, lose your life savings.
Save a salmon, lose your life savings.
 
Rockaway Beach Road Erosion Control
Rockaway Beach Road Erosion ControlRockaway Beach Road Erosion Control
Rockaway Beach Road Erosion Control
 
SMP Update Calendar 032911
SMP Update Calendar 032911SMP Update Calendar 032911
SMP Update Calendar 032911
 
Rockaway Slip Sliding Away
Rockaway Slip Sliding AwayRockaway Slip Sliding Away
Rockaway Slip Sliding Away
 
Rockaway Beach Road Erosion Control
Rockaway Beach Road Erosion ControlRockaway Beach Road Erosion Control
Rockaway Beach Road Erosion Control
 
DOE Role in SMP Update
DOE Role in SMP UpdateDOE Role in SMP Update
DOE Role in SMP Update
 
DOE Nonconforming Uses
DOE Nonconforming UsesDOE Nonconforming Uses
DOE Nonconforming Uses
 

Recently uploaded

Experience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendExperience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendFabwelt
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.NaveedKhaskheli1
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest2
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeAbdulGhani778830
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkbhavenpr
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdfGerald Furnkranz
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdfFIRST INDIA
 

Recently uploaded (8)

Experience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming TrendExperience the Future of the Web3 Gaming Trend
Experience the Future of the Web3 Gaming Trend
 
Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.Global Terrorism and its types and prevention ppt.
Global Terrorism and its types and prevention ppt.
 
IndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global NewsIndiaWest: Your Trusted Source for Today's Global News
IndiaWest: Your Trusted Source for Today's Global News
 
15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf15042024_First India Newspaper Jaipur.pdf
15042024_First India Newspaper Jaipur.pdf
 
Rohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for JusticeRohan Jaitley: Central Gov't Standing Counsel for Justice
Rohan Jaitley: Central Gov't Standing Counsel for Justice
 
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfkcomplaint-ECI-PM-media-1-Chandru.pdfra;;prfk
complaint-ECI-PM-media-1-Chandru.pdfra;;prfk
 
57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf57 Bidens Annihilation Nation Policy.pdf
57 Bidens Annihilation Nation Policy.pdf
 
16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf16042024_First India Newspaper Jaipur.pdf
16042024_First India Newspaper Jaipur.pdf
 

Cumulative Impact Summary 1997-2010 HPAs

  • 1. Net Gain of Ecological Function Observed on Bainbridge Island Shorelines from 1997 to 2010 Compiled from Hydraulic Project Approvals (HPAs) issued by the Washington Department of Fish & Wildlife. by Albert Greiner for Bainbridge Shoreline Homeowners with editorial assistance by Ken Sethney Summary New construction, damage repair, and restoration projects undertaken since our city’s Shoreline Management Master Program was enacted, have resulted in a significant gain of shoreline ecological function. When combining the data from overwater structures, shoreline modifications and restoration projects, we have seen the following gains over the last thirteen years: • 750 linear feet reduction of hard shoreline armoring • 1,536 square feet reduction of opaque overwater structures • 523 feet of creosote treated wood bulkhead have been replaced • 583 creosote treated pilings have been or will be removed • 4,036 cubic yards of sand & gravel will nourish beaches • 28,518 square feet of native vegetation have been planted • 125,676 square feet of tideland have been or will be restored • 196,020 square feet of eelgrass have been or will be planted Conclusion “No net loss” was not the standard in 1996, but it is today. It is clear that existing policies are more than adequate to mitigate loss and provide substantial gains. During their presentation at City Hall, Department of Ecology representatives made it clear that “no net loss” can be applied to an entire jurisdiction rather than a single project. Doing so spreads the incentives for and benefits of restoration across the entire island instead of focusing on individual homeowners or project developers. Tuesday, March 1, 2011 c 1 of 4
  • 2. Docks and Overwater Structures • 52 HPAs were issued from 1997 to 2010 • 8,796 square feet of opaque dock deck was replaced with grated deck • 7,260 square feet of new opaque deck was installed • 1,772 square feet of new grated deck was installed • 283 creosote treated pilings were removed • 381 non-toxic pilings were installed According to the Army Corps. of Engineers, Washington Department of Fish & Wildlife (WDFW), and local planners, grated decking is better than opaque decking. Since 1996, we have seen a net reduction of 1,536 square feet of opaque overwater structures.1 While examining the HPA documents, we observed that most decks and floats are less than 60 feet long. The area of the island’s tidelands extending 60 feet from the ordinary high water mark is approximately 16,790,400 square feet.2 New overwater structures, both opaque and grated, total 9,032 square feet.3 This constitutes a change of about 0.054% or 5.4 hundredths of one percent in thirteen years, or 4 thousandths of one percent per year. That amounts to one square foot of new dock surface for every 1,859 square feet of tideland area 60 feet from the OHWM. Summary: Any loss of ecological function caused by such a minute yearly change is far outweighed by the net reduction in opaque overwater structures. 1 7,260 square feet - 8,796 square feet = -1,536 square feet 2 53 miles X 5,280 feet/mile X 60 feet = 16,790,400 square feet 3 1,772 square feet + 7,260 square feet = 9,032 square feet Tuesday, March 1, 2011 c 2 of 4
  • 3. Shoreline Modifications We found shoreline modification permits for bulkhead repairs, removals, replacement and installations, plus restoration permits for private shorelines. • 68 permits were issued from 1997 to 2010 4 • 1,690 linear feet of new rock bulkhead was installed • 507 linear feet of soft armoring was installed • 405 linear feet of concrete bulkhead was replaced by lower reflectivity rock bulkhead • 523 feet of creosote treated wood bulkhead was replaced by rock bulkhead • 17,036 square feet of tideland gained due to bulkhead removals & landward relocations • 2,806 linear feet of beach was improved by installing large woody debris • 5,018 square feet of native vegetation was restored • 4,036 cubic yards of beach nourishment (aka “fish mix”) has been required as mitigation over various time periods This is equal to 230 tandem wheeled dump truck loads, enough to spread 4.5 inches of sand and gravel over the island’s entire tideland area. The net permitted gain of 1,690 feet of angular rock armoring is 0.6% of the island’s 53 miles of shoreline.5 This is slightly more than 1/16th of an inch per foot of shoreline, and amounts to an armoring rate of 130 feet per year. Approximately 50 percent of Bainbridge Island’s shoreline has been modified in the past.6 At 130 feet per year, it would take 1,076 years to modify the remaining 50 percent if it were lawful to do so.7 However, this ignores the restoration projects mentioned below which have (or will) result in a 750 foot net reduction of shoreline armoring. Summary: Any loss of ecological function caused by such a minute yearly change is far outweighed by moving structures landward, installation of soft armoring and woody debris, and beach nourishment requirements. 4 We noted a large spike in bulkhead repairs following the severe 2005-6 winter storm. 5 1,690 feet / ( 53 miles x 5,280 feet/mile ) = .006 = 0.6% 6 Herrera, Addendum to the Summary of Science Report for Bainbridge Island, pg 14 7 50% x (( 53 miles x 5,280 feet/mile ) / 130 feet/year ) = 1,076 years Tuesday, March 1, 2011 c 3 of 4
  • 4. Shoreline Restoration The following were observed from sources reporting shoreline restorations on Bainbridge Island. Most are classified as active projects. Blakely Harbor Park restoration goals are included but that project is still being studied as to feasibility. We were unable to find data on the Waterfront Park shoreline restoration, so bulkhead removal and shoreline restoration for that project is not included in the following numbers. • 2,440 linear feet of shoreline armoring removed • 108,640 square feet of tidelands/marsh restored • 870 cubic yards of debris removed from tidelands • 23,500 square feet of nearshore vegetation restored to native species • 196,020 square feet of eelgrass planed • 300+ creosote treated pilings removed • 435 linear feet of shoreline received large woody debris • 265 feet of jetty to be removed (Blakely) • 2,750 square foot structure to be removed (Blakely) Summary: Restoration is intended to cause a net gain of ecological function. With limited information, we have been able to track these significant gains. Limitations of Data Included • Hydraulic Project Approval (HPA) data was furnished under a public records request made to the Department of Fish and Wildlife. • All shoreline work requires an HPA before any city permit may be issued. • Many HPAs are not specific as to tideland gains, so only those gains cited or calculable from applications are included. There are more gains than totaled here. • Many HPOs do not specify numbers of piles removed, so only those pilings enumerated are included. More pilings have been removed than totaled here. • The permits mentioned were HPA permits, not Bainbridge Island city permits. • HPA permits do not show completion dates, so there is no confirmation that the permitted work was actually completed. • Personal communication from a COBI staff member indicates COBI has no reliable way of reporting project completion. Tuesday, March 1, 2011 c 4 of 4