ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310

1,502 views

Published on

Published in: Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
1,502
On SlideShare
0
From Embeds
0
Number of Embeds
5
Actions
Shares
0
Downloads
63
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide
  • Notes: 46% or 1.3 million of total population of the country live only in 0.3% of total land of the country. The reason is that remaining territory of the country lacks engineering infrastructure, jobs, schools and hospitals thus people have a tendency to move to UB.
  • Notes: Total population of the capital city (UB) is projected to increase to 2 million people if we don’t manage the mechanical growth through planning.
  • Notes:
    MCUD = Ministry of Construction and Urban Development
    MEDS = Ministry of Education, Culture and Science
  • Notes:
    39% or 471k people live in apartment buildings while 61% or 736k people live in ger area, which means 22% more people live in gers than apartment. But ger area (79%) covers almost 4 times higher land than apartment area (21%). If people who live in ger areas move in to apartments as planned in UB Master Plan 2020, some of the issues such as traffic jam and air pollution will be reduced.
  • ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310

    1. 1. The project presentation of the Capital city Cooperation offer 1, JUNE 2014
    2. 2. POPULATION 1.3 million (46% of Mongolia) TERRITORY 4700 km2 (0.3% of Mongolia) GDP ₮ 8 784 666 mil. (63% of Mongolia) LOANS 84% of Mongolia AUTOMOBILE 59% of Mongolia SAVINGS 83% of Mongolia UB CITY STATISTICS
    3. 3.  INVESTMENT PROJECT ARRANGEMENT /CITY BUDGET/ /million tugrug/ 95 837,8 45% 48 393,9 23% 39 680,0 19% 10 577,0 5% 9 924,1 5% 6 502,6 3% URBANIZATION, INFRACTRUCTURE BRANCH SOCIAL BRANCH AUTO ROAD BRANCH TRANSPORTATION BRANCH STATE SERVICE LANDSCAPING, GREEN AREA
    4. 4.  2020 2030 It is projected that population of the capital city will be 50.3% of total population of the country in order to ensure national security, water resource and keep balance of nature and ecology. Population of Mongolia - 2020 3,162 UB region 1,534 /48,5%/ Other 4 region 1,628 /51,5%/ Population of Mongolia - 2030 3,501 UB region 1,763 /50,3%/ Other 4 region 1738 /49,7%/ UB REGIONAL POPULATION PROSPECT /thousands/ № Name of the city, town 2010 /statistics/ Planned population Population Households 2020 % 2030 % 1 Ulaanbaatar /Metropolitan/ 1058,129 264,311 1235,5 80,5 1400.0 79.4 2 Suburbs 103,656 30,106 298,5 19,4 363.0 20.6 Total population of capital city 1161,785 294,416 1534,0 1763.0 UB REGIONAL POPULATION PROSPECT 4
    5. 5. Needs About 16 bilion USD for Implementation of the Master Plan of Ulaanbaatar ULAANBAATAR MASTER PLAN 2020
    6. 6.  Capital city budget MCUD /State budget/ MEDS /State budget/ Projects started in 2013 Projects to be done in 2014 Capital city budget ULAANBAATAR MASTER PLAN 2020
    7. 7.  GER DISTRICT Apartment area 5,857 Ha (21%) 61% 736.0 people 39% 470.6 people Apartment buildings Ger area Ger area 21,823 Ha (79%) 7
    8. 8.  Яармаг Шинэ төв Сонсголон Гурвалжин Bayankhoshuu Selbe Хотын хуучин төв Амгалан Financed by ADB with a 1.5$ million technical assistance, investment program project for developing subcenters Bayankhoshuu, Selbe is ready. The mission of the program is to build a network in sub-centers that has economic opportunity, housing and urban infrastructure services with healthy, safe, comfortable and favorable condition “ULAANBAATAR URBAN SERVICES AND GER AREAS DEVELOPMENT INVESTMENT PROGRAM”
    9. 9. Baganuur district (1,5 khoroo) 17 khoroo Sukhbaatar district 15 khoroo 9,10,11,12 khoroo 13,14 khorоо 8,16 khoroo 12 khoroо 2 khoroo 2,4 khorоо Bayanzurkhdistrict Khan-Uul district (4 khoroo)7district 34khoroo Population:69072 10,11 khoroo 11 khoroo Bayangol district 7,8 khoroo 7 khoroo 9,10,11 khoroo 13, 15 khoroo Chingeltei district 5,6,7 khoroo 10 khoroo Songinokhairkhandistrict 1,2,20 khoroo 30 khoroo 28 khoroo RE-PLANNING THE GER AREAS
    10. 10.  RAILBUS Will be open on June 6th 2014 300 million tugrug decided from the Municipality. NUMBER OF SITS: 136 PEOPLE TOTAL NUMBER OF PASSENGERS: 350-400 PEOPLE NUMBER OF TRAVELS: AMONG 1 ROAD PER DAY 3 TIMES AMONG DUAL ROAD PER DAY 6 TIMES SPEED: 100KM/HOUR TIME: TOLGOIT-AMGALAN 47 MIN AMGALAN-TOLGOIT 45 MIN SERVICE WORK TEAM: 4 PEOPLE
    11. 11.  BUS RAPID TRANSIT /BRT/ • INTEGRATED PLANNING
    12. 12.  6.6 km: Underground 6.2 km: Soaring 4.9 km: Soaring Tootal length 17.7 km • Establish a legal framework in relation to the construction of a subway in the city of Ulaanbaatar • In 2014, in preparation for construction of a subway in the city of Ulaanbaatar, will conduct the work such as drafting a plan, detailed engineering studies, assessment of environmental impact and determining the cost of the project. ULAANBAATAR – METRO PROJECT
    13. 13.  WORK NOTE 1 “Ulaanbaatar New City Hall” project is implemented to build in 6th khoroo of the Songinokhairkhan district, which general plan is approved by City Council of Ulaanbaatar. City council 7/29 decree, 2013 2 On June 7th, 2013, the tender for companies and enterprise that will complete the construction was announced. Batch Number Redevelopment of ger area project-2013/8 3 The Mayor of Ulaanbaatar city ratified that “Halla Gonsol” company is selected for the project from 5 companies. Mayor’s A/761 th charge, 12/Aug/2013 4 The task force is established by Mayor’s 783th charge on August 19th, 2013. Held 15 meetings 5 The task force worked and acquainted with the re-planning project in Korea, agreed mutually about the type of financing, type of agreement, energy efficient, environmental friendly and containing national patterns. 12/Sep/2013 6 The Mayor requested to Prime Minister Mr. N.Altankhuyag for supporting of implementation the new administrative center of the city’s construction project. By 01/788 official letter and by himself, 18/March/2014 7 Presented at a meeting of government and recognized by Government. 28/March/2014 THE PROJECT OF ULAANBAATAR NEW CITY HALL
    14. 14.
    15. 15.  “New complex of the cities administration: Building of the City Consul of Ulaanbaatar /6 floor/; Building of the Center acceptance for the citizen /2 floor/; Governor office of the UB city, Subsidiary agencies /20 floor/; Sport hall /1 floor/ consists of these 4 basic buildings. For implementing this project from 9,2 hectare square planed building 13%, 57% landscaping square, 30% road, parking place. Total building square is 50,000м2 potentially 1429 officers can work here. Building of the Center acceptance for the citizen potentially consists of 100 kindergarten, at once can accept 200 people, 100 people can served by library. Regarding the technology should contain energy saving (eco-friendly), advanced smart technology (intelligent building), veracious for the public (openness, transparency), national features style. ABOUT THE BUILDING
    16. 16.  Working title Halla Gonsol /dollars/ Construction 38,917,465 Land 6,827,625 Equipment 10,241,438 Electricity 10,525,922 Public tied house operation 9,956,956 Sum 76,469,406 Drawing 2,294,082 Total 78,763,488 Construction value, cost statement
    17. 17.  FINANCING STRUCTURE OF PROJECT MUB Customer bank Contractor bankHalla Gonsol Financing (Credit / Bond) Collateral, Sponsion Financing (non-project company) Monthly bill (Monthly payment claims/IPC approvals) Letters of credit or bonds (due within 3 years from the date of commissioning)
    18. 18. Hui Doloon Hudag is a beautiful green valley where Mongolians used to celebrate its great Summer Festival and located 32 km westward on the main road to the Western province from UB central Chingis Khan square. “Mongol Naadam Complex” situated in Hui Doloon Hudag
    19. 19. The “Mongol Naadam Complex” plans to construct the following buildings in its 13600 square m land.
    20. 20.  Construction works planned from 2014 to 2020 1. Arena for horse racing 2. Stadium 3. Open stadium for archery 4. Ankle bone shooting tent 5. Road along with horse race route 6. Ski and Snowboard camps 7. Complex for horse racing 8. Sport center for the capital city dwellers 9. Horse symbol 10. Archery symbol 11. Wrestler symbol 12. Car park 1 2 3 4 5 6 7 8 9 10 11 12
    21. 21.  STADIUM 40.000 capacity stadium designed for football and other mass sport events shall take place. In future during national Great Holiday Naadam it will be major arena for wrestling and other sport and mass events.
    22. 22.  Arena for Horse Racing VERSION 1 /DESIGN/ 200Х34Х24М SIZE 40.000 CAPACITY HALF OPEN ARENA, WITH METAL AND CONCRETE COVER, ON THE LOWER FLOOR SERVICE CENTER, EXHIBITION HALL, CONFERENCE HALL AND VIP ROOM.
    23. 23.  Complex for horse racing: There will be built 40.000 seats stadium with capacity to allow betting through the internet. In this stadium: House for horse breeding Service center Shop for horse racing sport Restaurant
    24. 24.  Open Stadium for Archery competitions: On 3 square km land, will be built arena with capacity for 3000 viewers and 600 archery sportsmen. There also will be mounted large tent with seats for 1000 spectators and where simultaneously can compete 64 teams in ankle bone shooting.
    25. 25.  Ankle bone shooting tent There also will be mounted large tent for ankle bone shooting competition for 1000 spectators and where simultaneously can compete 64 teams in ankle bone shooting.
    26. 26.  Ski and Snowboard Camps There is plan to construct skiing center for international competitions on 100 square m land. It shall have capacity to serve in one day for 3000 people. There will be arena also for snowboarding and other types of winter sports.
    27. 27.  МММмМ Sport center for the capital city dwellers: 1. Office 2. Warehouse 3. Security office 4. Hotel 5. Ger camp 6. Water slide 7. Conference hall 8. Spa sauna 9. Play grounds 10. Green house for flowers warehouse Ger camp Play grounds Water slide Hotel Massage Spa Sauna
    28. 28.  10th khoroo of Khan-Uul district Model project of Morindavaa area Project  Action Plan of Governor and Mayor of Ulaanbaatar city, 2013-2016  City goals for economic and social 2014,  The Ulaanbaatar city urban planning policy “ Master Plan “ up to 2020 ,  Action plan documents of the development trend up to 2030,  City land management plan 2014,  On 30th May, 2013, the City Council based on the №10/39th resolution “Domestic demand for defining the location of land to citizens".
    29. 29.  New municipal land “CITY TOWN” Propoesd land Center of Ulaanbaatar
    30. 30.  “BAYANGOL DOWNHILL” 1st khoroo of Songinokhairkhan district 6800 apartments Propoesd land Military town area Center of city
    31. 31.  HOUSING SUPPLY /2030/ Total of 215000 household People who can afford direct payment People who can afford mortgage with advanced payment People who live abroad People without savings -with permanent income -rural residences From total of 215 000 housing required household current statistic shows that 70% /140 000/ household will be involved in HOCK program.
    32. 32.  Авто худалдааны төв орчим FIRST INTENDING LOCATIONS
    33. 33.  NORTH SIDE OF THE YARMAG SPORT COMPLEX KHAN-UUL district, 16th khoroo /959 family, 3836 people/
    34. 34.   According the partial overall planning nearly Buyant-Uhaa scheduled consists of 9 buildings, 15 floors, one-two entrances  Regarding the buildings all the first floors and the buildings grounded along the mean road from first to third floors should be used for service.  For the outside parking space planned openly 300, inside 400 cars, totally provide 70% of the family. NORTH SIDE OF THE YARMAG SPORT COMPLEX KHAN-UUL district, 16th khoroo /959 family, 3836 people/
    35. 35.  NORTH SIDE OF THE YARMAG SPORT COMPLEX KHAN-UUL district, 16th khoroo /959 family, 3836 people/
    36. 36.  “BAYANGOL DOWNHILL” 1st khoroo of Songinokhairkhan district 6800 apartments
    37. 37.  “BIO-SONGINO” KHAN-UUL DISTRICT 12 khoroo /household:2837, population:11348/
    38. 38.  “BIO-SONGINO” KHAN-UUL DISTRICT 12 khoroo /household:2837, population:11348/
    39. 39.  Finance diagram China exim bank Shanghai group Apartment Ulaanbaatar NOSK House holder Housing fund Mongolia China Pay back Ulaanbaatar • Land • Infrastructure • School • Kindergarten • Hospital Chinese side • Investment • Construct a building • Commercial center NOSK • Acquisition • Order /From citizen/
    40. 40.  THANK YOU FOR WATCHING OUR PRESENTATION

    ×