Welcome to a webinar on
Procuring for Agile :
thoughts on what good
looks like
by the
Introduction
▪ Order follows that of our
recently published white
paper, which is
downloadable from APM
website.
▪ Key poi...
Who are we?
’Bukola Feyistan is a project professional with over 16 years of
experience in UK central government, working ...
Why this paper and how was it
developed ?
▪ Topic identified by C&P SIG as worthy of a white
paper, but not just for IT pr...
Why the need for a White Paper?
▪ Traditional legal drafting likes certainty and
precision: everything is tied down.
▪ Pro...
#projectingthefuture
Trends Traditional Transformational
Setup Detailed design approved before execution
Broad vision of o...
Procuring for Agile:
The traditional approaches
1. Fixed price contracts:
2. Time & Materials.
and nothing in-between !
Th...
What other trends were you aware
of which informed your thinking?
▪ A move towards more benefits / outcome-based
projects ...
Some caveats
The White Paper is:
▪ not just for IT projects
▪ not based around using any specific agile methodology
▪ for ...
Before an organisation procures for
agile, it needs to address …
▪ Provider selection: whether it is willing to select on ...
Is your project suitable for Agile?
X
X
X
X
X
X
X
X
X
3=1x3 36=9x4 Total = 39 / 50
X
What does an Agile Contract look like?
Our Top Ten …
1. It is designed collaboratively with the (potential)
Provider(s), s...
5. The conditions of contract are high-level with greater detail
is in the requirement docs which can be changed.
6. Detai...
9. Liability is for failing to act with ‘reasonable skill and care’,
not ‘fit for purpose’. Points 1 to 8 imply you are bu...
Preparing the Contract
1. Get your decision making in order so that you can instruct
the right Task fast enough for the Pr...
Preparing the Contract
5. Project Owners must own the agile process … so must be
heavily involved in writing the ‘how’ doc...
Selecting the Provider
▪ MEAT is a challenge, but mainly in the mind!
▪ Need to sell that the right people, organisation a...
Managing the Contract &
Delivering the Work
1. Do your thinking early … see previous slides!
2. Collaboration & agile are ...
4. Collaboration is not just about ‘behaviours’, but also
infrastructure. E.g.
– booked-in regular meetings and ‘time-out’...
Upcoming SlideShare
Loading in …5
×

Procuring for agile: thoughts on what good looks like webinar, 23 April 2020

Procuring for agile: thoughts on what good looks like webinar
Thursday 23 April 2020

presented by
Dr Jon Broome, Olubukola Feyisetan, John Lake, Jason Sprague, Will Webster
The link to the write up page and resources of this webinar:
https://www.apm.org.uk/news/procuring-for-agile-thoughts-on-what-good-looks-like-webinar/

Related Audiobooks

Free with a 30 day trial from Scribd

See all
  • Be the first to comment

  • Be the first to like this

Procuring for agile: thoughts on what good looks like webinar, 23 April 2020

  1. 1. Welcome to a webinar on Procuring for Agile : thoughts on what good looks like by the
  2. 2. Introduction ▪ Order follows that of our recently published white paper, which is downloadable from APM website. ▪ Key points from the white paper are in the slide set. ▪ But discussing and amplifying the text, not regurgitating it as you can read the guide. & Agenda
  3. 3. Who are we? ’Bukola Feyistan is a project professional with over 16 years of experience in UK central government, working with teams that deliver change to the public. John Lake is secretary of the SIG and has a career spanning 30+ years in technical, project and general management, predominantly within the high-technology sector. He is currently an independent contracting Project Manager. Dr Jon Broome – chair of the SIG, a trustee director of the APM and managing consultant of leading edge projects consulting. He has advised on contracting arrangements and issues for complex projects and programmes up to £16.5bn for last 20+ years. Jason Sprague is a managing consultant for ASE Consulting. He specialises in transformation having worked within some of the largest change projects in the UK bringing together technology, commercial and organisational culture. Will Webster is Head of IT for APM who recently awarded an ‘agile contract’ to improve our website. He has previous experience of agile.
  4. 4. Why this paper and how was it developed ? ▪ Topic identified by C&P SIG as worthy of a white paper, but not just for IT projects – the world is speeding up & wanting benefits delivered earlier ▪ Held a workshop early last year and got lots of info, examples and insight from 27 odd participants ▪ Seven of us formed a working group and developed a white paper on it, published in Feb this year. ▪ Three of the working group were from an IT background and been involved in ‘full-on’ agile projects.
  5. 5. Why the need for a White Paper? ▪ Traditional legal drafting likes certainty and precision: everything is tied down. ▪ Procurement likes to get to contract with a ‘fixed’ priced. BUT ▪ The world, not just IT, is moving too fast: we live in a VUCA (Volatile, Uncertain, Complex, Ambiguous) world I.e. the world often does not fit the traditional legal and procurement way of doing things.
  6. 6. #projectingthefuture Trends Traditional Transformational Setup Detailed design approved before execution Broad vision of outcomes. Iterative approach: test and learn Leadership Defined network, specific outputs Loose network, common aspirations Stakeholder management Support for a defined plan Jointly developing ‘the what and why’ Budgets and plans Use external comparisons to ensure realistic goals Avoided detailed plans too early. Test and learn Risk management Detailed risk register and contingency plans Focus on big issues e.g. customer behaviour, delivery pace Commercial/procurement ‘Big bang’ Experimental, incremental Key skillsets and mindsets Specific technical skills, esp. programme management – applied rigorously Transformational leadership, organisation design, digital leadership, communications, tailored governance and review; applied flexibly, embracing change How might the profession change?
  7. 7. Procuring for Agile: The traditional approaches 1. Fixed price contracts: 2. Time & Materials. and nothing in-between ! The Guide is intended to address this big gap for projects on the agile side of the waterfall/agile spectrum.
  8. 8. What other trends were you aware of which informed your thinking? ▪ A move towards more benefits / outcome-based projects (as opposed to delivering to a technical spec) which is reflected in contracts ▪ A move towards greater collaboration and longer- term relationships, which needs to be reflected in win-win commercial and hence contractual relationships.
  9. 9. Some caveats The White Paper is: ▪ not just for IT projects ▪ not based around using any specific agile methodology ▪ for projects on the agile side of the agile/waterfall spectrum i.e. they have mostly agile characteristics ▪ not encouraging the abandonment of good project management practice: Agile actually calls for slicker programme management ▪ presupposing that a procurement and contracting approach which is in harmony with agile working has got to be more helpful than one that doesn’t.
  10. 10. Before an organisation procures for agile, it needs to address … ▪ Provider selection: whether it is willing to select on tech competence, collaborative ability and input costs ? ▪ Governance & decision-making: fluid selection & instructing of sprints/projects so Provider can work efficiently. ▪ Legal considerations: lighter, more flexible shorter contracts with a greater focus on the ‘how’ versus the ‘what’. ▪ Projects controls: a lighter more iterative approach ▪ Skills and culture: see above and a collaborative approach ▪ Wider buy-in: the inputs to the team may need to change. ▪ Leadership buy-in: otherwise the above won’t happen.
  11. 11. Is your project suitable for Agile? X X X X X X X X X 3=1x3 36=9x4 Total = 39 / 50 X
  12. 12. What does an Agile Contract look like? Our Top Ten … 1. It is designed collaboratively with the (potential) Provider(s), so that you utilise their experience and it will work for them. 2. The focus is on the ‘how’ it will be delivered, not the ‘what’, because the ‘what’ won’t be fully defined and will evolve over time. The ‘how’ embraces change, rather than fights it. 3. Each sprint is instructed as a Task, not as a new contract, so that it can be delivered within a contract. 4. The contract describes the standard technical, management and administrative requirements with only the specifics in the Task Order.
  13. 13. 5. The conditions of contract are high-level with greater detail is in the requirement docs which can be changed. 6. Detail of both the ‘how and ‘what’ in the contract is ‘just sufficient’ to provide a framework, but not over- prescriptive to stifle innovation and creativity. 7. Payment is primarily based on input costs, but supplemented by performance measures which are related to the desired outcomes/benefits within the Provider’s influence. 8. The emphasis is on ‘carrots’, not ‘sticks’. Contractual ‘sticks’ encourage hiding of problems and blame to avoid liability. “A lack of sticks enables teams to fail fast and openly and then move on”. 9. What does an Agile Contract look like? Our Top Ten …
  14. 14. 9. Liability is for failing to act with ‘reasonable skill and care’, not ‘fit for purpose’. Points 1 to 8 imply you are buying a service not a product. If liability is ‘fit for purpose’, the Client will have to spend too much time defining that purpose and the Provider being clear about what it is taking on and not finishing each sprint until absolutely sure it’s met that standard. 10. The ‘how’ is based on collaboration with a presumption of trust in competence, integrity and empathy to each others needs. A lack of trust means more administration and defensive behaviours. What does an Agile Contract look like? Our Top Ten …
  15. 15. Preparing the Contract 1. Get your decision making in order so that you can instruct the right Task fast enough for the Provider to not have resource doing nothing. It needs to align with the project controls and feedback process. 2. Put stakeholder engagement at the heart of the decision- making cycle whoever those stakeholder are. 3. Establish how success criteria and any incentives will be set: research clearly indicates joint setting works best, but their needs to be a framework to do this. Decision making, stakeholder and risk assessment feed into this. 4. Contractual-ise the critical agile methods be it systems, the organisational structure &/or people of the Provider – so need to design the contract to incorporate the provider’s ‘how’ (its agile method) into it. Precedence?
  16. 16. Preparing the Contract 5. Project Owners must own the agile process … so must be heavily involved in writing the ‘how’ documents and project managed in order not to revert to type. 6. Bring subject-matter experts with you so need to be briefed and project managed in order not to revert to type e.g. overly prescriptive technically or excessive remedies 7. Allow for change over the duration of the relationship so much of the ‘how’ will not be in the conditions of contract but can be changed. It may that different types of contract are need over the duration of the relationship & are connected by an over-arching framework type contract. 8. Pay for insight, information and decisions once the Provider is selected for two reasons: you pay for it anyway and it will be given willingly by the delivery team. State this upfront.
  17. 17. Selecting the Provider ▪ MEAT is a challenge, but mainly in the mind! ▪ Need to sell that the right people, organisation and processes/systems will give best value, not the illusion of lowest tender Price for undefined & changing deliverables. ▪ For example: – how will their organisational structure combine with yours; – what systems, process and procedures will they will use; will they replace, work alongside or integrate with yours; and – who will they provide with evidence both of technical capability and collaborative/ agile ability. ▪ Ideally, these can be expressed as contractual commitments and incorporated into the contract.
  18. 18. Managing the Contract & Delivering the Work 1. Do your thinking early … see previous slides! 2. Collaboration & agile are a means to an end, not the end. I.e. together you make better & faster decisions due to strong project controls, more rapid and honest feedback, and greater realism about risk. This does not mean you sweep hard issues under the carpet. 3. Agile needs to be nurtured, not just in the delivery team but across the organisation that feeds into the delivery team. Leadership needs to step up.
  19. 19. 4. Collaboration is not just about ‘behaviours’, but also infrastructure. E.g. – booked-in regular meetings and ‘time-out’ workshops for continuous improvement of effectiveness & efficiency. – shared & common databases, planning tools and reporting standards – video-conferencing if located remotely etc. 5. ‘Just sufficient’ governance so that Tasks can be instructed in a timely manner & performance evaluated without undue bureaucracy. 6. Governance of the ‘how’ (not just the ‘what’), so that the ‘how’ evolves in a controlled way as the relationship evolves = more management time, less admin, improved benefits! Managing the Contract & Delivering the Work

×