ADTEC REPORT 16 MAY 2009

799 views

Published on

Published in: Technology, Business
  • Be the first to comment

  • Be the first to like this

ADTEC REPORT 16 MAY 2009

  1. 1. LAPORAN KEMAJUAN PROJEK NO.21 ‘MEI 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B
  2. 2. ADTEC TAIPING LOKASI PROJEK
  3. 3. BANGUNAN PENTADBIRAN BENGKEL TEK. MAKLUMAT & JAMIN KUALITI DEWAN BESAR PUSAT SUMBER DEWAN KULIAH LOBI UTAMA KAFETERIA MIKRO ELEKTRONIK KOMPOSIT PLASTIK M&E PLANT ROOM 1 TNB SUB STATION SERAMIK M&E PLANT ROOM 2 GARAJ KENDERAAN ASRAMA LELAKI ASRAMA PEREMPUAN DEWAN MAKAN SURAU KELAS F KELAS G KUARTERS B, C, C&D PELAN TAPAK ADTEC TAIPING
  4. 4. KEMAJUAN KERJA FIZIKAL JADUAL : 79.69 % SEBENAR : 80.28 % KESELURUHAN : 0.60 % TARIKH LAPORAN : 16 MEI 2009
  5. 5. KEMAJUAN KERJA KEWANGAN JADUAL : 79.06 % SEBENAR : 79.61 % KESELURUHAN : 0.55 % TARIKH LAPORAN : 16 MEI 2009
  6. 7. KEMAJUAN KERJA FIZIKAL - DEWAN BESAR BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100% 85.77% - 14.23% MEI 09’ 88.35% 92.38% 4.03% MECHANICAL PLANNED ACTUAL AIR COND 89.36% 85.00% FIRE FIGHTING 63.03% 86.28% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 98.05% 87.50% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 90.00% LPS NA NA PA 40.54% 51.35% SMATV 28.33% 35.18% CCTV NA NA ICT 0.00% 0.76%
  7. 8. DEWAN BESAR
  8. 9. DEWAN BESAR
  9. 10. KEMAJUAN KERJA FIZIKAL – LOBI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 94.30% -5.70% MEI 09’ 98.92% 94.90% -4.02% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 93.11% 100.00% SUBMAIN CABLE 90.77% 100.00% DB 75.00% 100.00% LUMINAIRE 81.78% 100.00% MAIN S/BOARD NA NA LPS NA NA PA NA NA SMATV NA NA CCTV 73.63% 32.69% ICT NA NA
  10. 11. LOBI UTAMA
  11. 12. KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.45% 81.81% -17.64% MEI 09’ 92.24% 91.71% -0.52% MECHANICAL PLANNED ACTUAL AIR COND 89.71% 90.00% FIRE FIGHTING 72.55% 75.06% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 97.65% 100.00% SUBMAIN CABLE 90.60% 100.00% DB 75.00% 100.00% LUMINAIRE 83.76% 95.00% MAIN S/BOARD 75.00% 90.00% LPS 85.82% 92.01% PA 36.40% 48.82% SMATV NA NA CCTV NA NA ICT 0.00% 29.98%
  12. 13. DEWAN KULIAH UTAMA
  13. 14. KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 91.94% -8.06% MEI 09’ 95.30% 95.38% 0.09% MECHANICAL PLANNED ACTUAL AIR COND 88.44% 85.00% FIRE FIGHTING 38.38% 78.47% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 96.33% 95.00% SUBMAIN CABLE 90.32% 95.00% DB 85.00% 100.00% LUMINAIRE 84.09% 98.00% MAIN S/BOARD 85.00% 90.00% LPS 88.34% 96.92% PA 43.31% 54.45% SMATV 76.21% 73.61% CCTV NA NA ICT 13.59% 17.42%
  14. 15. PUSAT SUMBER / PERPUSTAKAAN
  15. 16. KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBER BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 88.93% -11.07% MEI 09’ 92.72% 92.73% 0.01% MECHANICAL PLANNED ACTUAL AIR COND 86.99% 89.96% FIRE FIGHTING 45.23% 40.30% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 97.36% 95.00% SUBMAIN CABLE 91.48% 92.00% DB 85.00% 100.00% LUMINAIRE 69.62% 95.00% MAIN S/BOARD 75.00% 90.00% LPS 86.00% 90.85% PA 20.34% 37.23% SMATV 69.40% 68.28% CCTV 2.36% 1.06% ICT 9.65% 12.59%
  16. 17. BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
  17. 18. KEMAJUAN KERJA FIZIKAL - KAFETARIA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 96.14% -03.86% MEI 09’ 98.36% 98.71% 0.08% MECHANICAL PLANNED ACTUAL AIR COND 75.55% 100.00% FIRE FIGHTING 54.69% 70.73% KITCHEN EQUIP. 27.61% 34.00% LPG INSTALL. 0.00% 0.00% COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 90.94% 100.00% LUMINAIRE 94.07% 100.00% MAIN S/BOARD NA NA LPS 75.13% 88.81% PA 30.39% 43.51% SMATV 67.06% 66.02% CCTV NA NA ICT 0.00% 0.00%
  18. 19. KAFETERIA
  19. 20. KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMAT BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.67% 89.84% -9.82% MEI 09’ 93.95% 95.49% 1.54% MECHANICAL PLANNED ACTUAL AIR COND 79.15% 89.24% FIRE FIGHTING 29.88% 15.93% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 97.22% 95.00% SUBMAIN CABLE 94.32% 100.00% DB 93.83% 100.00% LUMINAIRE 84.21% 100.00% MAIN S/BOARD 75.00% 90.00% LPS 89.76% 96.80% PA 54.28% 61.18% SMATV 78.82% 73.97% CCTV 37.46% 20.60% ICT 4.29% 9.58%
  20. 21. BENGKEL TEKNOLOGI MAKLUMAT
  21. 22. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.20% 94.41% -4.79% MEI 09’ 96.82% 95.67% -1.14% MECHANICAL PLANNED ACTUAL AIR COND 88.70% 88.41% FIRE FIGHTING 45.37% 45.37% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 81.45% 85.00% DUST CONTROL NA NA PROCESS COOLING 0.00% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 75.00% 100.00% LUMINAIRE 94.28% 100.00% MAIN S/BOARD 75.00% 90.00% LPS 92.90% 96.80% PA 62.47% 64.97% SMATV 75.18% 74.39% CCTV 55.21% 30.36% ICT 9.90% 14.40%
  22. 23. BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
  23. 24. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.13% 94.65% -4.48% MEI 09’ 97.05% 95.65% -1.40% MECHANICAL PLANNED ACTUAL AIR COND 61.02% 78.34% FIRE FIGHTING 43.93% 32.95% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 81.45% 85.00% DUST CONTROL 31.69% 77.29% PROCESS COOLING 0.00% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 94.29% 100.00% MAIN S/BOARD 61.95% 90.00% LPS 84.99% 93.25% PA 53.85% 59.26% SMATV 75.26% 75.20% CCTV 56.15% 30.88% ICT 16.58% 11.59%
  24. 25. BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
  25. 26. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 98.21% 92.30% -5.91% MEI 09’ 95.12% 94.67% -0.46% MECHANICAL PLANNED ACTUAL AIR COND 86.19% 85.00% FIRE FIGHTING 41.34% 33.30% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 81.45% 85.00% DUST CONTROL 10.44% 72.95% PROCESS COOLING 0.00% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 98.53% 100.00% SUBMAIN CABLE 94.89% 95.00% DB 78.00% 100.00% LUMINAIRE 90.95% 100.00% MAIN S/BOARD 85.00% 90.00% LPS 90.99% 96.49% PA 53.24% 60.41% SMATV 73.29% 74.70% CCTV 63.51% 34.93% ICT 16.96% 22.29%
  26. 27. BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
  27. 28. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.71% 91.02% -8.70% MEI 09’ 94.30% 95.17% -0.87% MECHANICAL PLANNED ACTUAL AIR COND 58.17% 59.54% FIRE FIGHTING 23.90% 21.39% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 81.45% 85.00% DUST CONTROL 38.25% 60.33% PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 96.41% 95.00% SUBMAIN CABLE 92.64% 95.00% DB 92.64% 90.00% LUMINAIRE 67.10% 85.00% MAIN S/BOARD 30.09% 90.00% LPS 84.35% 96.20% PA 41.16% 53.00% SMATV 45.52% 54.97% CCTV 44.98% 24.74% ICT 3.77% 0.00%
  28. 29. BENGKEL KEJ. JAMINAN KUALITI
  29. 30. KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIK BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 98.51% 90.05% -8.47% MEI 09’ 92.86% 94.80% 1.94% MECHANICAL PLANNED ACTUAL AIR COND 89.48% 87.17% FIRE FIGHTING 22.33% 11.16% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 81.45% 85.00% DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 97.65% 95.00% SUBMAIN CABLE 90.51% 90.00% DB 50.09% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 88.47% 96.70% PA 52.12% 58.72% SMATV 61.66% 64.98% CCTV 58.47% 32.16% ICT 0.00% 0.00%
  30. 31. BENGKEL MIKRO ELEKTRONIK
  31. 32. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 96.79% -3.21% MEI 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 100.00% LPS 100.00% 95.68% PA NA NA SMATV 35.86% 48.48% CCTV 37.80% 20.79% ICT 100.00% 90.00%
  32. 33. KUARTERS KELAS ‘B’
  33. 34. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 96.94% -3.06% MEI 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 95.78% PA NA NA SMATV 27.51% 42.76% CCTV NA NA ICT 98.03% 62.02%
  34. 35. KUARTERS KELAS ‘C’
  35. 36. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 96.38% -3.62% MEI 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 100.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 100.00% 96.33% PA NA NA SMATV 35.86% 48.48% CCTV NA NA ICT 100.00% 90.00%
  36. 37. KUARTERS KELAS ‘C’ + ‘D’
  37. 38. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.68% 94.20% -5.48% MEI 09’ 97.14% 98.49% 1.36% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 100.00% 90.00% LPS 92.69% 96.98% PA NA NA SMATV 81.76% 80.03% CCTV NA NA ICT 96.04% 90.36%
  38. 39. KUARTERS KELAS ‘F’ ( 4 TINGKAT )
  39. 40. KUARTERS KELAS ‘F’ ( 5 TINGKAT )
  40. 41. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G (1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.33% 93.98% -5.35% MEI 09’ 97.58% 98.48% 0.90% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 100.00% 100.00% MAIN S/BOARD 86.52% 90.00% LPS 100.00% 96.98% PA NA NA SMATV 81.76% 80.03% CCTV NA NA ICT 98.74% 96.73%
  41. 42. KUARTERS KELAS ‘G’ ( 5 TINGKAT )
  42. 43. KUARTERS KELAS ‘G’ ( 4 TINGKAT )
  43. 44. KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 97.34% -2.66% MEI 09’ 99.42% 99.60% 0.18% MECHANICAL PLANNED ACTUAL AIR COND 83.40% 95.00% FIRE FIGHTING 36.66% 70.31% KITCHEN EQUIP. 27.61% 34.00% LPG INSTALL. 0.00% 0.00% COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 98.00% SUBMAIN CABLE 98.49% 98.00% DB 93.59% 90.00% LUMINAIRE 100.00% 80.00% MAIN S/BOARD 100.00% 90.00% LPS 98.91% 97.32% PA 56.87% 61.20% SMATV 67.06% 71.44% CCTV NA NA ICT 100.00% 1.40%
  44. 45. DEWAN MAKAN
  45. 46. KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & B BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 97.10% -2.90% MEI 09’ 98.70% 99.43% 0.73% MECHANICAL PLANNED ACTUAL AIR COND 51.93% 75.00% FIRE FIGHTING 39.40% 38.83% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 98.47% 99.50% SUBMAIN CABLE 92.53% 95.00% DB 76.93% 75.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 90.00% LPS 94.22% 97.48% PA 64.19% 66.13% SMATV 60.98% 67.30% CCTV 37.44% 20.59% ICT 79.41% 79.22%
  46. 47. ASRAMA LELAKI A & B
  47. 48. KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & D BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 99.99% 97.67% -2.32% MEI 09’ 98.95% 99.37% 0.52% MECHANICAL PLANNED ACTUAL AIR COND 44.80% 75.00% FIRE FIGHTING 67.44% 46.61% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 98.41`% 99.50% SUBMAIN CABLE 94.66% 95.00% DB 75.95% 75.00% LUMINAIRE 92.74% 90.00% MAIN S/BOARD 100.00% 90.00% LPS 98.08% 97.64% PA 59.38% 63.54% SMATV 60.98% 67.30% CCTV 35.21% 19.36% ICT 85.90% 82.44%
  48. 49. ASRAMA PEREMPUAN C & D
  49. 50. KEMAJUAN KERJA FIZIKAL - SURAU BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 98.65% 92.10% -6.55% MEI 09’ 95.20% 92.10% 0.69% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 89.00% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 95.52% 100.00% SUBMAIN CABLE 93.11% 100.00% DB 100.00% 100.00% LUMINAIRE 52.31% 100.00% MAIN S/BOARD 85.00% 90.00% LPS 88.76% 96.24% PA 29.36% 44.39% SMATV NA NA CCTV NA NA ICT NA NA
  50. 51. SURAU
  51. 52. KEMAJUAN KERJA FIZIKAL - ASTAKA BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY APRIL 09’ 100.00% 98.86% -1.14% MEI 09’ 99.80% 99.83% 0.04% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 82.47% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 100.00% SUBMAIN CABLE 100.00% 100.00% DB 100.00% 100.00% LUMINAIRE 98.67% 100.00% MAIN S/BOARD 100.00% 100.00% LPS 85.72% 93.89% PA 38.16% 49.36% SMATV NA NA CCTV NA NA ICT NA NA
  52. 53. BANGUNAN SOKONGAN ASTAKA
  53. 54. KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY MEI 09’ 100.00% 100.00% 0.00% MECHANICAL PLANNED ACTUAL AIR COND 96.91% 88.04% FIRE FIGHTING 32.54% 29.75% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 95.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 0.00% LUMINAIRE 89.07% 85.00% MAIN S/BOARD 28.42% 100.00% LPS NA NA PA NA NA SMATV NA NA CCTV NA NA ICT NA NA
  54. 55. BANGUNAN SOKONGAN M&E PLANT ROOM – PUSAT SUMBER
  55. 56. BANGUNAN SOKONGAN M&E PLANT ROOM - BENGKEL
  56. 57. DECORATIVE FENCE
  57. 58. BANGUNAN SOKONGAN GARAJ KENDERAAN
  58. 59. ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
  59. 60. WAKAF
  60. 61. LALUAN BERBUMBUNG
  61. 62. OPEN PLAZA
  62. 63. KERJA INFRA – JALAN UTAMA
  63. 64. GELANGGANG PERMAINAN
  64. 65. GELANGGANG PERMAINAN - TENIS
  65. 66. VINYL FLOORING : CLEANROON
  66. 67. VINYL FLOORING : BENGKEL
  67. 68. ACOUSTIC WALL : DEWAN BESAR
  68. 69. ACOUSTIC WALL & CEILING : DEWAN KULIAH
  69. 70. KITCHEN HOOD : CAFETERIA
  70. 71. KABINET DAPUR : KUATERS KELAS G
  71. 72. PERABUT ASRAMA PELAJAR
  72. 73. <ul><li>SEKIAN TERIMA KASIH </li></ul>

×