LAPORAN KEMAJUAN PROJEK NO.19 ‘MAC 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMAL...
ADTEC TAIPING LOKASI PROJEK
BANGUNAN  PENTADBIRAN BENGKEL   TEK. MAKLUMAT & JAMIN KUALITI DEWAN BESAR PUSAT SUMBER   DEWAN KULIAH LOBI  UTAMA KAFETERI...
KEMAJUAN KERJA FIZIKAL   JADUAL  :  84.22% SEBENAR  :  68.03% KESELURUHAN  :  -16.19%  TARIKH LAPORAN  : 11 MAC 2009
KEMAJUAN KERJA KEWANGAN   JADUAL  :  86.30% SEBENAR  :  68.81% KESELURUHAN  : -17.49% @ 136 HARI (LEWAT ) TARIKH LAPORAN :...
 
KEMAJUAN KERJA FIZIKAL - DEWAN BESAR BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 97.222% 65.52% - 31.70% MAC 09’ 9...
DEWAN BESAR
DEWAN BESAR
KEMAJUAN KERJA FIZIKAL – LOBI  BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 82.83% 78.68% -4.15% MAC 09’ 95.00% 89....
LOBI UTAMA
KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 83.03% 66.39% -16.64% MAC ...
DEWAN KULIAH UTAMA
KEMAJUAN KERJA FIZIKAL –  PUSAT SUMBER/PERPUSTAKAAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 93.37% 84.41% -8.9...
PUSAT SUMBER / PERPUSTAKAAN
KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBER BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 91.35% 77.52%...
BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
KEMAJUAN KERJA FIZIKAL - KAFETARIA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 84.36% 89.11% -4.75% MAC 09’ 94.82%...
KAFETERIA
KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMAT BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 85.84% 81.62% -4.2...
BENGKEL TEKNOLOGI MAKLUMAT
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 78.05% 8...
BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 79.39% ...
BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 76.14% 7...
BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 80.11% 77.74% -2...
BENGKEL KEJ. JAMINAN KUALITI
KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIK BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 79.37% 78.27% -1.10%...
BENGKEL MIKRO ELEKTRONIK
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 90.43% 95.76% 5.33% MAC 09’...
KUARTERS KELAS ‘B’
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 88.42% 95.12% 6.70% MAC 09’...
KUARTERS KELAS ‘C’
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 84.31% 94.25% 9.94% MAC 0...
KUARTERS KELAS ‘C’ + ‘D’
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F  ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DEL...
KUARTERS KELAS ‘F’ ( 4 TINGKAT )
KUARTERS KELAS ‘F’ ( 5 TINGKAT )
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G  (1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELA...
KUARTERS KELAS ‘G’ ( 5 TINGKAT )
KUARTERS KELAS ‘G’ ( 4 TINGKAT )
KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 98.16% 94.87% -3.29% MAC 09’ 98.3...
DEWAN MAKAN
KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & B BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 86.42% 91.05% 4.63% MAC 0...
ASRAMA LELAKI A & B
KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & D BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 81.04% 93.81% 12.77% M...
ASRAMA PEREMPUAN C & D
KEMAJUAN KERJA FIZIKAL - SURAU BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 77.94% 78.73% 0.79% MAC 09’ 86.10% 84.0...
SURAU
KEMAJUAN KERJA FIZIKAL - ASTAKA BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 91.60% 87.62% 3.98% MAC 09’ 9...
BANGUNAN SOKONGAN   ASTAKA
KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 91.00% 99.77% 8.77% M...
BANGUNAN SOKONGAN   M&E PLANT ROOM – PUSAT SUMBER
BANGUNAN SOKONGAN   M&E PLANT ROOM - BENGKEL
DECORATIVE FENCE
BANGUNAN SOKONGAN   GARAJ KENDERAAN
ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
WAKAF
LALUAN BERBUMBUNG
OPEN PLAZA
KERJA INFRA – JALAN UTAMA
GELANGGANG PERMAINAN
M&E INSTALLATION
M&E INSTALLATION
M&E INSTALLATION
BENGKEL MIKROELEKTRONIK – CLEAN ROOM
BENGKEL MIKROELEKTRONIK – CLEAN ROOM
<ul><li>SEKIAN TERIMA KASIH </li></ul>
Upcoming SlideShare
Loading in …5
×

Adtec Pre No.19 Mac 09

705 views

Published on

Published in: Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
705
On SlideShare
0
From Embeds
0
Number of Embeds
18
Actions
Shares
0
Downloads
7
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide

Adtec Pre No.19 Mac 09

  1. 1. LAPORAN KEMAJUAN PROJEK NO.19 ‘MAC 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B
  2. 2. ADTEC TAIPING LOKASI PROJEK
  3. 3. BANGUNAN PENTADBIRAN BENGKEL TEK. MAKLUMAT & JAMIN KUALITI DEWAN BESAR PUSAT SUMBER DEWAN KULIAH LOBI UTAMA KAFETERIA MIKRO ELEKTRONIK KOMPOSIT PLASTIK M&E PLANT ROOM 1 TNB SUB STATION SERAMIK M&E PLANT ROOM 2 GARAJ KENDERAAN ASRAMA LELAKI ASRAMA PEREMPUAN DEWAN MAKAN SURAU KELAS F KELAS G KUARTERS B, C, C&D PELAN TAPAK ADTEC TAIPING
  4. 4. KEMAJUAN KERJA FIZIKAL JADUAL : 84.22% SEBENAR : 68.03% KESELURUHAN : -16.19% TARIKH LAPORAN : 11 MAC 2009
  5. 5. KEMAJUAN KERJA KEWANGAN JADUAL : 86.30% SEBENAR : 68.81% KESELURUHAN : -17.49% @ 136 HARI (LEWAT ) TARIKH LAPORAN : 11 MAC 2009
  6. 7. KEMAJUAN KERJA FIZIKAL - DEWAN BESAR BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 97.222% 65.52% - 31.70% MAC 09’ 99.12% 74.17% - 24.95% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 50.00% FIRE FIGHTING 100.00% 39.77% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 85.00% SUBMAIN CABLE 100.00% 75.00% DB 100.00% 0.00% LUMINAIRE 100.00% 0.00% MAIN S/BOARD 100.00% 0.00% LPS NA NA PA 100.00% 31.81% SMATV 100.00% 25.00% CCTV NA NA ICT 100.00% 0.00%
  7. 8. DEWAN BESAR
  8. 9. DEWAN BESAR
  9. 10. KEMAJUAN KERJA FIZIKAL – LOBI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 82.83% 78.68% -4.15% MAC 09’ 95.00% 89.22% -5,78% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 0.00% LUMINAIRE 100.00% 0.00% MAIN S/BOARD NA NA LPS NA NA PA 100.00% 65.37% SMATV NA NA CCTV 100.00% 65.37% ICT NA NA
  10. 11. LOBI UTAMA
  11. 12. KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 83.03% 66.39% -16.64% MAC 09’ 94.20% 74.34% -19.87% MECHANICAL PLANNED ACTUAL AIR COND 62.86% 75.00% FIRE FIGHTING 86.64% 3.87% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 56.25% 75.00% DB 100.00% 0.00% LUMINAIRE 0.00% 50.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 83.13% PA 100.00% 28.96% SMATV NA NA CCTV NA NA ICT 100.00% 0.00%
  12. 13. DEWAN KULIAH UTAMA
  13. 14. KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 93.37% 84.41% -8.96% MAC 09’ 96.79% 85.99% -10.80% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 75.00% FIRE FIGHTING 79.40% 29.24% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 0.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 77.33% PA 100.00% 41.75% SMATV 100.00% 68.59% CCTV NA NA ICT 40.84% 0.00%
  14. 15. PUSAT SUMBER / PERPUSTAKAAN
  15. 16. KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBER BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 91.35% 77.52% -13.83% MAC 09’ 96.07% 83.49% -12.58% MECHANICAL PLANNED ACTUAL AIR COND 95.68% 50.00% FIRE FIGHTING 81.99% 40.30% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 77.50% SUBMAIN CABLE 100.00% 75.00% DB 100.00% 0.00% LUMINAIRE 100.00% 30.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 72.59% PA 100.00% 19.15% SMATV 100.00% 62.46% CCTV 99.86% 2.13% ICT 82,62% 0.00%
  16. 17. BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
  17. 18. KEMAJUAN KERJA FIZIKAL - KAFETARIA BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 84.36% 89.11% -4.75% MAC 09’ 94.82% 93.88% -0.95% MECHANICAL PLANNED ACTUAL AIR COND 76.19% 0.00% FIRE FIGHTING 14.60% 6.32% KITCHEN EQUIP. 45.48% 0.00% LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 0.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD NA NA LPS 75.13% 66.47% PA 100.00% 27.35% SMATV 99.59% 60.35% CCTV NA NA ICT 100.00% 0.00%
  18. 19. KAFETERIA
  19. 20. KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMAT BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 85.84% 81.62% -4.22% MAC 09’ 95.07% 84.50% -10.56% MECHANICAL PLANNED ACTUAL AIR COND 57.23% 50.00% FIRE FIGHTING 100.00% 15.93% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 50.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 87.01% PA 100.00% 42.43% SMATV 100.00% 70.94% CCTV 97.59% 33.71% ICT 29.05% 0.00%
  20. 21. BENGKEL TEKNOLOGI MAKLUMAT
  21. 22. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 78.05% 86.03% 7.98% MAC 09’ 88.52% 90.27% 1.75% MECHANICAL PLANNED ACTUAL AIR COND 56.66% 75.00% FIRE FIGHTING 49.72% 34.03% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 62.86% 75.00% DUST CONTROL NA NA PROCESS COOLING 35.30% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 47.06% 85.00% DB 0.00% 0.00% LUMINAIRE 0.00% 75.00% MAIN S/BOARD 0.00% 0.00% LPS 86.70% 91.49% PA 85.81% 56.22% SMATV NA NA CCTV 77.25% 49.69% ICT 17.49% 1.34%
  22. 23. BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
  23. 24. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 79.39% 83.64% 4.25% MAC 09’ 87.48% 91.18% 3.70% MECHANICAL PLANNED ACTUAL AIR COND 62.87% 75.00% FIRE FIGHTING 67.96% 32.95% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 68.57% 75.00% DUST CONTROL 48.77% 23.77% PROCESS COOLING 50.33% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 58.22% 85.00% DB 0.00% 0.00% LUMINAIRE 35.71% 75.00% MAIN S/BOARD 35.71% 0.00% LPS 81.02% 82.52% PA 83.73% 48.47% SMATV NA NA CCTV 92.94% 50.54% ICT 15.86% 1.16%
  24. 25. BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
  25. 26. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 76.14% 79.96% 3.82% MAC 09’ 81.17% 90.55% 9.38% MECHANICAL PLANNED ACTUAL AIR COND 41.99% 75.00% FIRE FIGHTING 43.45% 33.30% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 77.14% 75.00% DUST CONTROL 16.46% 8.86% PROCESS COOLING 41.29% 0.00% ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 72.22% 85.00% DB 0.00% 0.00% LUMINAIRE 0.00% 75.00% MAIN S/BOARD 0.00% 0.00% LPS 76.32% 89.38% PA 97.72% 49.95% SMATV NA NA CCTV 74.79% 57.16% ICT 23.12% 1.58%
  26. 27. BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
  27. 28. KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITI BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 80.11% 77.74% -2.37% MAC 09’ 91.91% 83.93% -7.97% MECHANICAL PLANNED ACTUAL AIR COND 53.50% 55.00% FIRE FIGHTING 79.89% 14.81% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 100.00% 75.00% DUST CONTROL 71.70% 19.13% PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 82.50% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 85.00% LUMINAIRE 14.29% 45.00% MAIN S/BOARD 100.00% 0.00% LPS 91.41% 81.69% PA 100.00% 33.28% SMATV 98.53% 40.97% CCTV 86.29% 40.48% ICT 28.12% 0.00%
  28. 29. BENGKEL KEJ. JAMINAN KUALITI
  29. 30. KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIK BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 79.37% 78.27% -1.10% MAC 09’ 89.92% 87.86% -2.06% MECHANICAL PLANNED ACTUAL AIR COND 58.27% 50.00% FIRE FIGHTING 36.20% 11.16% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR 94.29% 75.00% DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 90.48% 85.00% DB 0.00% 7.00% LUMINAIRE 0.00% 45.00% MAIN S/BOARD 0.00% 0.00% LPS 83.20% 84.16% PA 98.98% 39.69% SMATV 80.65% 55.50% CCTV 88.56% 52.62% ICT 31.59% 0.00%
  30. 31. BENGKEL MIKRO ELEKTRONIK
  31. 32. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 90.43% 95.76% 5.33% MAC 09’ 95.86% 96.63% 0.77% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 90.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 90.40% PA NA NA SMATV 100.00% 32.27% CCTV 100.00% 34.02% ICT 100.00% 90.00%
  32. 33. KUARTERS KELAS ‘B’
  33. 34. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 88.42% 95.12% 6.70% MAC 09’ 95.03% 96.71% 1.68% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 90.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 0.00% LPS 98.44% 90.63% PA NA NA SMATV 100.00% 24.75% CCTV NA NA ICT 100.00% 62.02%
  34. 35. KUARTERS KELAS ‘C’
  35. 36. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’ BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 84.31% 94.25% 9.94% MAC 09’ 92.69% 96.33% 3.63% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 90.00% FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 100.00% 90.00% LUMINAIRE 100.00% 90.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 91.85% PA NA NA SMATV 100.00% 32.27% CCTV NA NA ICT 100.00% 90.00%
  36. 37. KUARTERS KELAS ‘C’ + ‘D’
  37. 38. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 77.45% 91.08% 13.63% MAC 09’ 85.15% 94.13% 8.98% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 52.38% 90.00% DB 0.00% 90.00% LUMINAIRE 0.00% 90.00% MAIN S/BOARD 0.00% 0.00% LPS 100.00% 88.80% PA NA NA SMATV 100.00% 73.58% CCTV NA NA ICT 100.00% 65.58%
  38. 39. KUARTERS KELAS ‘F’ ( 4 TINGKAT )
  39. 40. KUARTERS KELAS ‘F’ ( 5 TINGKAT )
  40. 41. KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G (1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT) BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 77.88% 92.63% 14.75% MAC 09’ 86.68% 93.87% 7.19% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING NA NA KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 90.00% DB 44.44% 90.00% LUMINAIRE 0.00% 90.00% MAIN S/BOARD 26.67% 0.00% LPS 100.00% 88.80% PA NA NA SMATV 100.00% 73.58% CCTV NA NA ICT 100.00% 69.85%
  41. 42. KUARTERS KELAS ‘G’ ( 5 TINGKAT )
  42. 43. KUARTERS KELAS ‘G’ ( 4 TINGKAT )
  43. 44. KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 98.16% 94.87% -3.29% MAC 09’ 98.39% 96.95% -1.44% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 75.00% FIRE FIGHTING 100.00% 12.24% KITCHEN EQUIP. 42.73% 0.00% LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 50.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS 100.00% 88.67% PA 100.00% 51.18% SMATV 100.00% 60.35% CCTV NA NA ICT 100.00% 0.00%
  44. 45. DEWAN MAKAN
  45. 46. KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & B BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 86.42% 91.05% 4.63% MAC 09’ 92.69% 95.69% 3.00% MECHANICAL PLANNED ACTUAL AIR COND 100.00% 10.00% FIRE FIGHTING 100.00% 29.58% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 89.29% 86.25% SUBMAIN CABLE 0.00% 85.00% DB 0.00% 50.00% LUMINAIRE 0.00% 75.00% MAIN S/BOARD 0.00% 0.00% LPS 93.12% 85.86% PA 60.31% 54.28% SMATV 60.53% 54.88% CCTV 42.12% 31.69% ICT 98.57% 78.12%
  46. 47. ASRAMA LELAKI A & B
  47. 48. KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & D BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 81.04% 93.81% 12.77% MAC 09’ 90.09% 96.91% 6.82% MECHANICAL PLANNED ACTUAL AIR COND 17.86% 10.00% FIRE FIGHTING 46.33% 20.18% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 50.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS 93.12% 85.86% PA 60.31% 54.28% SMATV 60.53% 54.88% CCTV 42.12% 31.69% ICT 98.57% 78.12%
  48. 49. ASRAMA PEREMPUAN C & D
  49. 50. KEMAJUAN KERJA FIZIKAL - SURAU BANGUNAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 77.94% 78.73% 0.79% MAC 09’ 86.10% 84.06% -2.04% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 57.14% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 75.00% SUBMAIN CABLE 41.67% 75.00% DB NA NA LUMINAIRE 0.00% 0.00% MAIN S/BOARD 0.00% 0.00% LPS 65.01% 81.70% PA 87.81% 22.89% SMATV NA NA CCTV NA NA ICT NA NA
  50. 51. SURAU
  51. 52. KEMAJUAN KERJA FIZIKAL - ASTAKA BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY FEB 09’ 91.60% 87.62% 3.98% MAC 09’ 99.03% 98.95% -0.45% MECHANICAL PLANNED ACTUAL AIR COND NA NA FIRE FIGHTING 0.00% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. NA NA COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 85.00% DB 100.00% 0.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS 69.22% 37.93% PA 100.00% 28.62% SMATV NA NA CCTV NA NA ICT NA NA
  52. 53. BANGUNAN SOKONGAN ASTAKA
  53. 54. KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM BANGUNAN SOKONGAN MONTH PLANNED ACTUAL AHEAD / DELAY MAC 09’ 91.00% 99.77% 8.77% MECHANICAL PLANNED ACTUAL AIR COND 94.03% 77.59% FIRE FIGHTING 79.72% 0.00% KITCHEN EQUIP. NA NA LPG INSTALL. 0.00% 0.00% COMPRES. AIR NA NA DUST CONTROL NA NA PROCESS COOLING NA NA ELECTRICAL PLANNED ACTUAL WIRING 100.00% 90.00% SUBMAIN CABLE 100.00% 75.00% DB 100.00% 0.00% LUMINAIRE 100.00% 75.00% MAIN S/BOARD 100.00% 0.00% LPS NA NA PA NA NA SMATV NA NA CCTV NA NA ICT NA NA
  54. 55. BANGUNAN SOKONGAN M&E PLANT ROOM – PUSAT SUMBER
  55. 56. BANGUNAN SOKONGAN M&E PLANT ROOM - BENGKEL
  56. 57. DECORATIVE FENCE
  57. 58. BANGUNAN SOKONGAN GARAJ KENDERAAN
  58. 59. ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
  59. 60. WAKAF
  60. 61. LALUAN BERBUMBUNG
  61. 62. OPEN PLAZA
  62. 63. KERJA INFRA – JALAN UTAMA
  63. 64. GELANGGANG PERMAINAN
  64. 65. M&E INSTALLATION
  65. 66. M&E INSTALLATION
  66. 67. M&E INSTALLATION
  67. 68. BENGKEL MIKROELEKTRONIK – CLEAN ROOM
  68. 69. BENGKEL MIKROELEKTRONIK – CLEAN ROOM
  69. 70. <ul><li>SEKIAN TERIMA KASIH </li></ul>

×