This Slideshare speaks about the RainWater Harvesting Implemented in Brigade Millennium, one of the earliest high-rise buildings in South of Bangalore. It was Presented by Mr.Shankar Rao (Refurb India), during the Water workshop for Apartment Communities organised by ApartmentADDA on 25-Feb-2012.

It details on the challenges faced while installing the system and also highlights on a solution which is a fully Automated system called "Innovative Hydraulic Activation System". Thus by employing this method Brigade Millennium was able to utilise the Rainwater more effectively.

Check the link here for more details on water workshops by ApartmentADDA
http://apartmentadda.com/blog/water-workshop-for-apartments-report/

Published in: Real Estate, Technology, Business
  • Be the first to comment

RainWater Harvesting in Brigade Millennium

  1. 1. Rain Water Harvesting System at Brigade Millenium (Cassia Block) - Shankar Rao. Refurb India. (refurb_india@yahoo.com) As presented in “The Water Workshop for Apartment Communities” Organized by ApartmentADDA.com
  2. 3. <ul><li>One of the earliest high rise apartment blocks in South Bangalore. </li></ul><ul><li>The 5 blocks named after flowers: </li></ul><ul><li>Cassia </li></ul><ul><li>Mayflower </li></ul><ul><li>Magnolia </li></ul><ul><li>Laburnum </li></ul><ul><li>Jacaranda </li></ul>
  3. 4. <ul><li>All 16 storey-tall with roof catchment of 2200 sq.m except for Laburnum. </li></ul><ul><li>Today’s presentation is about : </li></ul><ul><li>CASSIA BLOCK </li></ul>
  4. 5. Rainwater Disposal – Pre RWH <ul><li>Roof top water from 15 th /16 th floor. </li></ul><ul><li>Down pipes 27 nos. led down chutes in the building center to Basement. </li></ul><ul><li>Down pipes connected to 7 exit pipes. </li></ul><ul><li>Rainwater flows out to Municipal drain/STP/open wells. </li></ul>
  5. 6. FLOW CHART – STORE & USE
  6. 7. FLOW CHART – STORE & USE
  7. 8. The Challenge <ul><li>Topography of Cassia not conducive for direct flow to ground sumps. </li></ul><ul><li>Necessitates pumping from Basement level. </li></ul><ul><li>Transit storage became mandatory. </li></ul><ul><li>Rains – unpredictable in timing, duration and intensity. </li></ul><ul><li>Manual monitoring/Control/Action undependable. </li></ul>
  8. 9. The Solution - Fully automatized system <ul><li>PHASE I: </li></ul><ul><li>Programmable logic control to start/stop pumping depending upon flow/storage status. </li></ul>
  9. 10. The Solution - Fully automatized system <ul><li>PHASE II: </li></ul><ul><li>Action to meet the following ‘what if’ emergencies: </li></ul><ul><li>Filter block leading to Column Water Build-up. </li></ul><ul><li>Basement tanks full & ground sumps full and rain continues. </li></ul>
  10. 11. The Solution - Fully automatized system <ul><li>REMEDIES: </li></ul><ul><li>Bypass valves made to change flow status. </li></ul><ul><li>Manual intervention for the above ruled out. </li></ul><ul><li>Self-operated mechanism activated – How? </li></ul>
  11. 12. The Solution - Fully automatized system <ul><li>INNOVATIVE HYDRAULIC ACTIVATION SYSTEM: </li></ul><ul><li>No electric power is required, hence no dependence on power supply. </li></ul><ul><li>Water pressure available from roof top tank invoked. </li></ul>
  12. 13. The Solution - Fully automatized system <ul><li>MECHANISM EMPLOYED: </li></ul><ul><li>A) Incase of tank overflow, </li></ul><ul><li>a float valve moves up & </li></ul><ul><li>opens water flow from roof top. </li></ul><ul><li>This action hydraulically moves </li></ul><ul><li>the bypass valves appropriately. </li></ul>
  13. 14. The Solution - Fully automatized system <ul><li>B) Incase of a Filter block, </li></ul><ul><li> hydrostatic pressure builds up, </li></ul><ul><li> activating a spring-loaded lever, </li></ul><ul><li> thus opening the inlet valve; </li></ul><ul><li> Pressure activates hydraulically </li></ul><ul><li> to move bypass valves to </li></ul><ul><li> appropriate position. </li></ul>
  14. 15. Rainwater Utilization <ul><li>BWSSB stipulates 70-75% water utilization from roof top catchment. </li></ul><ul><li>Open paved catchment – no stipulation. </li></ul>
  15. 16. CATCHMENT AND RAIN YIELD AT CASSIA Type Total area in sq.m Storage & use Recharge Total harvested % Used A B C B+C Roof top 2200 1870 210 2080 95 Paved open 2800 0 1440 1440 51 Unpaved 687 0 500 500 73 TOTAL 5687 1870 2150 4020 72
  16. 17. Rainwater Utilization