SlideShare a Scribd company logo
1 of 51
SUBMITED BY- SUBMITED TO-ANKIT 
SINGH DR. S.N. SACHDEVA 
M.TECH (TRANSPORTATION ENGINEERING) SECTION HEAD (TRANSPORTATION ENGINEERING) 
ROLL NUMBER- 3140715 DEPARTMENT OF CIVIL ENGINEERING 
NIT KURUKSHETRA NIT KURUKSHETRA
What is bridge? 
A structure which provides a passage over a gap 
without closing the opening which is beneath that gap. 
The passage may be due to railway , roadway , canal & 
natural river etc. 
Initially the naturally available materials such as stone 
and timber were extensively used for bridges but now 
days artificial materials such as cement concrete & 
steel are utilized more in the construction of bridge.
RIVER BRIDGE CANAL BRIDGE 
ROADWAY BRIDGE RAILWAY BRIDGE
History of bridge in india. 
During the king “harshavardhna” or even before him 
india appears to have a good highway system & such 
highways had a number of bridge. 
“firoze shah” who ruled the delhi in mid 14th century 
built a number of canal & bridges. 
“portuguese” in 16th and 17th century built many old 
arch masonary bridges in “goa”. 
One of oldest stone slab bridge still in use across the 
river “cauvery” at “srirangapatnam” bulit by “tippu 
sultan”.
Cauvery bridge 
CAUVERY BRIDGE 
Vidhyasagar setu 
VIDYASAGAR SETHU
A number of cable stayed bridges has been built in 
india in past two decades. The major one is 
“vidhyasagar sethu” across “hooghly” at “kolkata” & 
“nalini bridge” on river “jamuna” at “allahabad”. 
Inidian railways build a number of large steel arch 
bridge in “j & k”. 
BRO has erceted a cable stayed bridge in early part of 
this milleium which is claimed to be only bridge of the 
type at highest altitude in the world at the time of 
construction. 
ECONOMY IN BRIDGE CONSTRUCTION 
Can be achived by using proper materials , effective 
supervission & economic method of construction etc.
Planning of a bridge 
There are few steps in planning of a bridge 
Study the need for the bridge 
Assess traffic requirement 
Location study 
Study of alternatives 
Short listing feasible alternatives 
Developing plans for alternatives including materials etc 
preliminary design and costing 
Evaluation of alternative , risk analysis and final choice 
Finding resources , detailed survey & design 
Implementation of design , fixing agency, construction and 
commissioning, preparing estimates.
Site selection of bridge 
Depends upon 
Foundations conditions 
Clearance requirements 
Length of the bridge 
Width of the bridge 
Live load on the bridge 
Initial cost 
Operation and maintenance 
appearance
Classification of bridge 
A single construction of bridge can be classified in many 
ways but we have a general classification of bridge. 
MASONARY ARCH BRIDGE 
Probably first category of bridge to be involved. 
Aesthetically superior to slab bridges. 
Consist of a arch shape slab supported on two apposite wall & it was 
adopted earlier for small of 3 to 15m in masonry & extended up to 519m in 
steel & 305m in concrete has been built in the world. 
PIPE CULVERT 
Consist of a pipe barrel under the embankment with protection works at 
the entry and exit. 
It is suitable for cross drainage flow on relatively flat terrain & in this 
discharge is limited & it has negligible maintenance.
MASANORY ARCH BRIDGE 
PIPE CULVERT
SLAB BRIDGE 
Simplest type of construction. 
Adopted for small bridges and culverts. 
Span is between 10-20m. 
Concrete slab cast monolithically over longitudinal girder. 
No. of longitudinal girders depends upon the width of road. 
PLATE GIRDER BRIDGE 
Span ranges 10 to 60m. 
Can be extending up to 250m in continuous construction. 
TRUSS BRIDGE 
Span 30 to 375m in simply supported case. 
Span 30 to 550m in cantilever combination ca
SLAB BRIDGE 
PLATE GIRDER BRIDGE 
TRUSS BRIDGE
SUSPENSSION BRIDGE 
Made up of high tensile steel cables strung in form of a catenary to which 
the deck is attached by steel suspenders which are made up of steel 
rods/members/cables. 
Deck can be of timber , concrete or steel spanning across the stiffening 
girders transmitting loads to suspenders. 
CABLE STAYED BRIDGE 
Similar to suspenssion bridge except that there will be no suspenders in the 
cable stayed bridges . 
A number of cables are streched from support tower directly connected the 
decking. 
OTHER IMPORTANT CLASSIFICATION OF BRIDGE 
Based upon type of structural arrangement. 
I-girder bridge 
Plate girder bridge
SUSPENSION BRIDGE 
CABLE STAYED BRIDGE
truss girder bridge 
Suspenssion bridge 
Based upon structural action or nature of superstructure action 
Simply supported span bridge 
Continuous span bridge 
Cantilever bridge 
Arch bridge 
Rigid frame bridge 
Based upon type of connections 
Riveted bridge 
Welded bridge 
Bolted bridge 
Pinned bridge
Based upon floor action 
Deck type bridge 
Through type bridge 
Semi –through type bridge or pony bridge 
Double deck bridge-used in rail cum road bridge 
Based upon movement of structural parts of the bridge 
Fixed(permanent) bridge 
Movable bridge 
can opened either horizontally or vetically so as allow the river or channel 
traffic to pass. 
Based upon purpose of bridge 
Road bridge 
Railway bridge 
Padestrain bridge
Based upon loading 
Irc class aa loading bridge 
Irc class a loading bridge 
Irc class b bridge 
Base upon span length 
Culver – up to span length 6m 
Minor bridge – up to span length 6 to 30m. 
Major bridge – up to span length over 30m. 
LOAD FOR DESIGN OF BRIDGE 
1. Dead load 
Aggregate weight of complete structure elements such as deck, wearing 
coat, parapets, stiffeners and utilities. 
It does not changes its direction and magnitude with respect to the passage 
of time.
2. LIVE LOAD 
Includes vehicle live load That are moving on the bridge. 
IRC has categorized standards of vehicle live load as under three 
following category which is- 
(a) IRC CLASS AA LOADING 
Treated as heavy loading and all NH & SH and industrial areas’s 
bridge are designed for only IRC class AA loading. 
If a bridge designed for IRC class AA loading then it will 
automatically satisfied IRC class A & class B loading. 
It has two pattern of loading 
(i) tracked type (ii) wheeled type 
(b) IRC CLASS A LOADING 
Generally Treated as standard loading for permanent bridges. 
Having eight axles with a total length of 25m.
IRC CLASS AA LOADING 
IRC CLASS AA LOADING
IRC CLASS A LOADING
IRC CLASS B LOADING 
Used for temporary bridges. 
It is a light loading as compard to all other loading. 
CLASS 70R LOADING 
Not used in our country it is used only in US. 
3.Impact load 
It is account for the dynamic effects of sudden loading 
of a vehicle on bridge structure. 
It is calculated by multiplying the live load with an 
impact factor. 
The impact factor is calculated as the IRC-6 suggested 
which are discussed below.
Impact factor for IRC CLASS A loading 
If=A/(B+L) 
Where If=Impact factor 
A=constant( 4.5 for RCC bridge & 9.0 for STEEL bridge) 
B=constant (6.0 for RCC bridge & 13.5 for STEEL bridge) 
L= effective span 
Impact factor IRC CLASS AA loading & CLASS 70R loading 
for span < 9m 
(a) Tracked vehicle- 25% for span upto 5m & reducing to 10% for span 
upto 9m. 
(b) Wheeled vehicle-25% for span upto 9m. 
for span > 9m 
(a) Tracked vehicle-for RCC bridge 10% upto 40m & as per graph for span 
>40m . For steel bridge 10% for all span. 
(b) Wheeled vehicle-for RCC bridge 25% upto 12m & as per graph for 
span >12m. For steel bridges 25% for span upto 23m & as per graph for 
span > 23m.
4. Centrifugal force 
consider for bridge constructed on horizontal curve. 
Considered to act at a height of 1.2m above the level of carriage way. 
C=WV2 
127 R 
Where c=centrifugal force in KN 
w=live in KN 
v=speed of vehicle in KMPH 
R= radius of horizontal curve in M. 
5.Wind load 
Assumed as horizontal forces on an area which are- 
For DECK structure- area of floor slab and railing 
For a through or half through structure- area of elevation of the windward 
tress flows half the area of elevation above the deck slab. 
Considered as acting at 15m above the roadway and have the following 
values 
highway ordinary bridges – 3.0 KN per meter 
highway bridges carrying framework- 4.5 KN per meter.
6. Longitudinal forces 
Forces result from vehicle braking or acceletrating while travelling on 
bridge. 
As the vehicle brakes the load of the vehicle is transferred from its 
wheels to bridge deck. 
IRC specifies a longitudinal forces of 20% is appropraite of live load 
and the force is applied at 1.2m above the level of deck. 
7.Seismic forces 
Depends upon geographical location of the bridge. 
These are the temparory forces act for the short duration. An 
earthquake forces is the fuction of following. 
(a) Dead load of structure Calculated as- F= ahW 
(b) Ground motion where F=horizontal forces owing to earthquake 
(c) Period of vibration ah=seismic coefficients for respective regions 
(d) Nature of soil W=DL+LL acting above the section
Some basic points regarding WSM and LSM 
Working Stress Method 
The Stresses in an element is obtained from the working loads and compared with 
permissible stresses. 
The method follows linear stress-strain behaviour of both the materials. 
Modular ratio can be used to determine allowable stresses. For bridge construction in 
case of WSM the Modular ratio is constant 10. 
Material capabilities are under estimated to large extent. Factor of safety are used in 
working stress method. 
The member is considered as working stress. 
Ultimate load carrying capacity cannot be predicted accurately. 
The main drawback of this method is that it results in an uneconomical section. 
All kind of major structure or important structure like bridge construction & tank 
construction (rectangular tank & intz tank etc.) is still usually designed by only WSM. 
Limit State Method 
The stresses are obtained from design loads and compared with design strength. 
In this method, it follows linear strain relationship but not linear stress relationship (one 
of the major difference between the two methods of design). 
The ultimate stresses of materials itself are used as allowable stresses. 
The material capabilities are not under estimated as much as they are in working stress 
method. Partial safety factors are used in limit state method.
T-BEAM BRIDGE 
This is most commonly adopted type of bridge for span range of 10 to 25m. 
It is so name because the main longitudinal girder are designed as T-beam 
which is integral part of deck slab cast monolithically with the deck slab. 
Simply supported T-beam spans of over 25m are rare as the dead load then 
becomes too heavy. However there is a bridge have single span of 35m named 
“ Advice bridge” in “Goa”. 
In other words we can say T-beam bridge is the combination of [ deck slab with 
longitudinal girders & cross girders ] superstructure & [piers , abutment & 
foundations] substructure.
COMPONENT OF A T-BEAM BRIDGE 
Deck slab 
Cantilever portion 
Longitudinal girders 
Cross girders 
Abutments & piers 
Bearing 
Foundations
Design of deck slab 
It is designed by either “effective width method” or by “Pigeauds curve 
method” as bending moment calculation. 
After calculation of bending moment we provide reinforcement and 
then do check for shear as accordance by WSM mtehod of RCC design. 
Normal depth of deck slab is very from 350mm to 500mm. 
EFFECTIVE WIDTH METHOD 
It is applicable when the slab is designed by assuming its a one way slab 
or supported only on two apposite edge or a very long slab supported 
on all four edge. 
Effective width is the width of wheel imprint on deck perpendicular to 
the movement of vehicle that is actually bears the load of wheel tyre it 
is calculated by following expressions. 
FOR SIMPLY SUPPORTED CASE 
beff.=k x(1-x/L) + bw 
FOR CANTILEVER CASE 
beff=1.2x + bw
Where beff= effective widht of dispersion 
k = constant depend upon b/L (widht/length) ratio specified in IRC-6. 
X=Distance of center of gravity of wheel from the nearest support in case of simply 
supported and distance of center of gravity of wheel From the cantilever phase. in 
case of 
L= effective span of bridge in case of simply supported and clear span in case of 
cantilever. 
bw= w+2h (width of wheel + 2 thickness of wearing coat) 
EFFECTIVE LENGTH OF DISPERSION 
In the same manner as effective width of dispersion there is also a effective length of 
dispersion measured along the direction of movement of vehicle. 
calculated as- for both simply supported case as well as cantilever case 
dispersion length= length of tyre contact + 2(overall thickness of deck including 
wearing coat) 
LEFF.= B + 2(D+2h) where Leff.=effective length of dispersion 
d=overall thickness of bridge deck 
h=thickness of wearing coat
Pigeauds method 
short span(B) & long span(L) bending moment coeeficients are read 
from curves developed by M. Pigeaud. 
Used for only 2-way slab design or slabs supported along four edges 
with restrained corners and subjected to symmetrically placed loads 
distributed over some well defined area. 
Curves developed for thin plates using the elastic flexural theory. 
However their use has been extended to concrete slab too. 
Poision’s ratio of 0.15 is considered. 
The short span(B) & long span (L) bending moment is calculated by 
following expressions. 
short span B.M.=W(m1 +0.15m2) along the widht(B) of slab. 
long span B.M.=W(0.15m1 +m2) along the length (L) of slab.
Design of cantilever slab portion 
It designed by effective width method only. The cantilever slab portion 
slab portion usually carries the KERB , HANDRAILS , FOOTHPATH if 
provided and a part of carriageway. 
The critical section for bending moment is the vertical section at the 
junction of the cantilever portion and the end of longitudinal girder. 
The design bending moment for cantilever slab portion is calculated as 
the sum of 0.2 times of dead load bending moment plus 0.3 times of 
live load bending moment. 
design moment= 0.2 dead load BM + 0.3 live load BM
Design of longitudinal girder 
There are 3 method of design of longitudinal girder 
(a) courbon’s method 
(b) Hendry-jaegar method 
(c) Morice and little version of huyon and massonnet method 
In india the courbon’s method is standerized for design of longitudinal 
girder. 
normal size of longitudinal girder is (300×1200)mm 
Courbon’s method 
According to his theory no flexural of transverse deck is possible 
because of presence of infinitely rigid diaphragms ( cross girder or 
cross beam) and a concentrated load instead of one pushing down 
only nearly girders , causes equal deflection of all girders. 
The design bending moment for longitudinal girder is calculated with 
the help of rection factor or distribution coefficient which is calculated 
by following expressions given by courbon.
Where W=ecentric concentrated load 
n= no. of longitudinal girder 
e=ecentricity of the wheel load from center line of the deck 
x1=distance of girder under considerations from central axis of the beam 
Σx2 = sum of distance of longitudinal girders from the centre line of deck 
LIMITATIONS OF COURBON’S METHOD O THEORY 
(a) span-width ratio should be between 2 to 4. 
(b) Atleast five symmetrical cross girder connecting the longitudinal girders 
(c) The minimum depth of cross girder should be atleast ¾ depth of longitudinal 
girder.
Design of cross girder 
Provided mainly to stiffen the girders and to reduce torssion in the 
exterior girders. 
Another function of the cross beam is to equalize the deflections of the 
girders carrying heavy loading with those of the girders with less 
loading. 
This is particularly important when the design loading consist of 
concentrated wheel loads such as IRC CLASS AA Loading to be placed 
in most unfavourable positions. 
The thickness of cross beams should not be less than the minimum 
thickness of the webs of longitudinal girders. 
The depth of the end cross girders should be such as to permit access 
for inspection of bearings and to facilitate positionings of jacks for 
lifting of superstructure for replacement of bearings. 
normally we use same size as that of longitudinal girders. 
Dead load bending moment is computed considering a trapezoidal 
distribution of weight of deck slab and wearing coarse. 
The live load bending moment is calculated as the bending moment 
calculated simply for a beam.
TYPICAL EXAMPLE OF CROSS GIRDER DEAL LOAD B.M. CALCULATION
PIERS 
A support of concrete or masonry for superstructure of bridge. 
The base of a pier may rest directly over firm round or it may be 
supported on piles. 
Center line of pier normally coincide with the center line of the 
superstructure. The dimensions of the top of a pier depends on 
distances between girder(longitudinal girder) and distance required to 
provide for the expansion of girder , size of bearing etc. 
IRC 40 gives minimum top width of pier and abutment. 
Basic Types of Bridge Piers
Design loads for piers 
a) dead load of superstructure 
b) Dead load of pier 
c) Live load on superstructure 
d) Lateral forces perpendicular to centerline of superstructure (wind portion on 
pier above water level , presure due to water , wave action of current) 
e) Longitudinal forces parllel to the direction of the bridge (includes braking of 
vehicles , tractive force of vehicle (high in case of train)). 
f) Seismic force. 
ABUTMENTS 
An abutment is a structure that support one end of a bridge in other word 
we can say that it is a structure located at the end & at the beginning of a 
bridge. 
Functions of abutment 
a) Support the bridge deck at end. 
b) Retain the embankment of approaching road. 
c) Connected the approach road to the bridge deck.
Basic Types of Bridge Abutments – 
Wall & Counterfort 
Wall Abutment Counterfor 
t
Basic Types of Bridge Abutments – 
Open Type
Types of Wall Abutments
Forces acting on abutment 
Dead load due to superstructure 
Live load on superstructure 
Self weight of abutment 
Longitudinal forces (traction and boiling) 
Earth presure due to soil embankment 
Design of abutment 
Hieght- Kept equal to hieght of pier 
Abutment- provided with a better of 1 in 3 to 1 in 6 or it may be stepped down 
Abutment width- top width according to space needed by the single bearing and bottom 
width 0.4 to 0.5 times of height of abutment 
Length- minimum equal to width of bridges 
Abutment cap- thickness 450 to 600 mm. 
Stability of abutment 
It should be chack and safe against the following- 
Oveturning 
Sliding 
Ecentricity of resultant with respect to center of the base 
Maximum base presure or earth presure .
BEARING 
Bearing are mechanical arrangement provided in the superstructure to transmit 
the load to the sub- structure. Thus it is a via media between superstructure and 
sub-structure which transmit the load from superstructure in such a manner 
that bearing stresses induced in the subset are within permissible limits. 
Purpose of bearings 
To absorb movements of girder 
To distribute load on a large area 
To keep compressive stress within safe limits 
To simplify the procedure in design 
To take up the vertical movement due to sinking of the the support. 
Type or category of bearing 
Free bearing or expansion bearing 
free to slide or move or roll and thus it allows longitudinal movement of girder. 
Fixed bearing 
it allows free angular movement and it does not permit any longitudinal 
movement of the girder
Free bearing or expansion bearing are of following type- 
RC rocker expansion bearing 
Elastomeric bearing 
Steel roller –cum rocker bearing 
Sliding own rocker bearing 
Sliding plate bearing 
Fixed bearing are of following type- 
Rocker bearing 
Steel hinge 
Steel rocker bearing 
RC rocker fixed bearing 
FORCES ON BEARING 
(1)Reactive forces (2) longitudinal forces (3)uplift forces (4)transverse forces 
MATERILAS FOR BEARING 
(1)Cast steel (2)mild steel (3) lead (4)RCC (5)Rubber (6)Tar paper (7) Kraft 
paper
BASIS FOR SELECTION OF BEARING 
a) High vertical load taking capability. 
b) Rotational capability. 
c) Good seismic resistance 
d) Overall cost (initial, maintenance) should be low. 
e) Capability to resist external horizontal forces. 
f) Aesthetic considerations.
Typical view of complete T-Beam bridge construction arrangement 
REFERENCE- 
“D.J. VICTOR” 
THANK YOU 
(for giving your valuable time)

More Related Content

What's hot

Ductile detailing IS 13920
Ductile detailing IS 13920Ductile detailing IS 13920
Ductile detailing IS 13920INTEZAAR ALAM
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineeringHalcrow
 
Working Stress Method v/s Limit State Method
Working Stress Method v/s Limit State MethodWorking Stress Method v/s Limit State Method
Working Stress Method v/s Limit State MethodMachenLink
 
Well foundations
Well foundationsWell foundations
Well foundationsganesh6561
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)RAMPRASAD KUMAWAT
 
Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C BeamAr. Aakansha
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTUVATSAL PATEL
 
Limit state, working stress, ultimate load method - Detailed Concept
Limit state, working stress, ultimate load method - Detailed ConceptLimit state, working stress, ultimate load method - Detailed Concept
Limit state, working stress, ultimate load method - Detailed ConceptCivil Insider
 
SINGLY REINFORCED BEAM
SINGLY REINFORCED BEAM SINGLY REINFORCED BEAM
SINGLY REINFORCED BEAM Pavan Kumar
 
Counterfort Retaining Wall
Counterfort Retaining WallCounterfort Retaining Wall
Counterfort Retaining WallKaizer Dave
 
About Bridge pier.
About Bridge pier.About Bridge pier.
About Bridge pier.Tajul Islam
 

What's hot (20)

Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
Ductile detailing IS 13920
Ductile detailing IS 13920Ductile detailing IS 13920
Ductile detailing IS 13920
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Working Stress Method v/s Limit State Method
Working Stress Method v/s Limit State MethodWorking Stress Method v/s Limit State Method
Working Stress Method v/s Limit State Method
 
Well foundations
Well foundationsWell foundations
Well foundations
 
Design of columns as per IS 456-2000
Design of columns as per IS 456-2000Design of columns as per IS 456-2000
Design of columns as per IS 456-2000
 
Components of railway track
Components of railway trackComponents of railway track
Components of railway track
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
 
Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C Beam
 
Bridge Rule
Bridge RuleBridge Rule
Bridge Rule
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
 
Pile Foundations
Pile FoundationsPile Foundations
Pile Foundations
 
Limit state, working stress, ultimate load method - Detailed Concept
Limit state, working stress, ultimate load method - Detailed ConceptLimit state, working stress, ultimate load method - Detailed Concept
Limit state, working stress, ultimate load method - Detailed Concept
 
SINGLY REINFORCED BEAM
SINGLY REINFORCED BEAM SINGLY REINFORCED BEAM
SINGLY REINFORCED BEAM
 
Counterfort Retaining Wall
Counterfort Retaining WallCounterfort Retaining Wall
Counterfort Retaining Wall
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Bridge foundation
Bridge foundationBridge foundation
Bridge foundation
 
About Bridge pier.
About Bridge pier.About Bridge pier.
About Bridge pier.
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 

Similar to Design of t beam bridge using wsm(2)

DESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREDESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREbabji syed
 
Bridge
Bridge Bridge
Bridge illpa
 
introductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfintroductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfabhinavbharat9
 
Introductiontobridges07 08-090507223401-phpapp02-converted
Introductiontobridges07 08-090507223401-phpapp02-convertedIntroductiontobridges07 08-090507223401-phpapp02-converted
Introductiontobridges07 08-090507223401-phpapp02-convertednaveen kumar
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptJoeBankerS1
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptJoeBankerS1
 
Transport enggineering
Transport enggineeringTransport enggineering
Transport enggineeringAparna Sharma
 
Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Mohamed Yassin
 
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...SalmanRabbani5
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
bridges-140101030123-phpapp02.pdf
bridges-140101030123-phpapp02.pdfbridges-140101030123-phpapp02.pdf
bridges-140101030123-phpapp02.pdfabhinavbharat9
 
project-1.pptx
project-1.pptxproject-1.pptx
project-1.pptxSpidra1
 
Design and Analysis of a Girder Bridge for Highway Structures Using Sap 2000
Design and Analysis of a Girder Bridge for Highway Structures Using Sap 2000Design and Analysis of a Girder Bridge for Highway Structures Using Sap 2000
Design and Analysis of a Girder Bridge for Highway Structures Using Sap 2000ijtsrd
 
challanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areaschallanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areasSwapnali Kunjir
 

Similar to Design of t beam bridge using wsm(2) (20)

DESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDUREDESIGN OF T BEAM BRIDGE PROCEDURE
DESIGN OF T BEAM BRIDGE PROCEDURE
 
Bridge
Bridge Bridge
Bridge
 
introductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfintroductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdf
 
Introductiontobridges07 08-090507223401-phpapp02-converted
Introductiontobridges07 08-090507223401-phpapp02-convertedIntroductiontobridges07 08-090507223401-phpapp02-converted
Introductiontobridges07 08-090507223401-phpapp02-converted
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.ppt
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.ppt
 
Transport enggineering
Transport enggineeringTransport enggineering
Transport enggineering
 
Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)Bridge construction (RC girder bridges)
Bridge construction (RC girder bridges)
 
report
reportreport
report
 
Bridge Engg
Bridge Engg Bridge Engg
Bridge Engg
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
unit-5-bridge-engg-components-classification-data-collection-site-selection-e...
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
bridges-140101030123-phpapp02.pdf
bridges-140101030123-phpapp02.pdfbridges-140101030123-phpapp02.pdf
bridges-140101030123-phpapp02.pdf
 
bridges overview.pdf
bridges overview.pdfbridges overview.pdf
bridges overview.pdf
 
BRIDGE OVERVIEW
BRIDGE OVERVIEWBRIDGE OVERVIEW
BRIDGE OVERVIEW
 
Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
project-1.pptx
project-1.pptxproject-1.pptx
project-1.pptx
 
Design and Analysis of a Girder Bridge for Highway Structures Using Sap 2000
Design and Analysis of a Girder Bridge for Highway Structures Using Sap 2000Design and Analysis of a Girder Bridge for Highway Structures Using Sap 2000
Design and Analysis of a Girder Bridge for Highway Structures Using Sap 2000
 
challanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areaschallanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areas
 

Design of t beam bridge using wsm(2)

  • 1. SUBMITED BY- SUBMITED TO-ANKIT SINGH DR. S.N. SACHDEVA M.TECH (TRANSPORTATION ENGINEERING) SECTION HEAD (TRANSPORTATION ENGINEERING) ROLL NUMBER- 3140715 DEPARTMENT OF CIVIL ENGINEERING NIT KURUKSHETRA NIT KURUKSHETRA
  • 2. What is bridge? A structure which provides a passage over a gap without closing the opening which is beneath that gap. The passage may be due to railway , roadway , canal & natural river etc. Initially the naturally available materials such as stone and timber were extensively used for bridges but now days artificial materials such as cement concrete & steel are utilized more in the construction of bridge.
  • 3. RIVER BRIDGE CANAL BRIDGE ROADWAY BRIDGE RAILWAY BRIDGE
  • 4. History of bridge in india. During the king “harshavardhna” or even before him india appears to have a good highway system & such highways had a number of bridge. “firoze shah” who ruled the delhi in mid 14th century built a number of canal & bridges. “portuguese” in 16th and 17th century built many old arch masonary bridges in “goa”. One of oldest stone slab bridge still in use across the river “cauvery” at “srirangapatnam” bulit by “tippu sultan”.
  • 5. Cauvery bridge CAUVERY BRIDGE Vidhyasagar setu VIDYASAGAR SETHU
  • 6. A number of cable stayed bridges has been built in india in past two decades. The major one is “vidhyasagar sethu” across “hooghly” at “kolkata” & “nalini bridge” on river “jamuna” at “allahabad”. Inidian railways build a number of large steel arch bridge in “j & k”. BRO has erceted a cable stayed bridge in early part of this milleium which is claimed to be only bridge of the type at highest altitude in the world at the time of construction. ECONOMY IN BRIDGE CONSTRUCTION Can be achived by using proper materials , effective supervission & economic method of construction etc.
  • 7. Planning of a bridge There are few steps in planning of a bridge Study the need for the bridge Assess traffic requirement Location study Study of alternatives Short listing feasible alternatives Developing plans for alternatives including materials etc preliminary design and costing Evaluation of alternative , risk analysis and final choice Finding resources , detailed survey & design Implementation of design , fixing agency, construction and commissioning, preparing estimates.
  • 8. Site selection of bridge Depends upon Foundations conditions Clearance requirements Length of the bridge Width of the bridge Live load on the bridge Initial cost Operation and maintenance appearance
  • 9. Classification of bridge A single construction of bridge can be classified in many ways but we have a general classification of bridge. MASONARY ARCH BRIDGE Probably first category of bridge to be involved. Aesthetically superior to slab bridges. Consist of a arch shape slab supported on two apposite wall & it was adopted earlier for small of 3 to 15m in masonry & extended up to 519m in steel & 305m in concrete has been built in the world. PIPE CULVERT Consist of a pipe barrel under the embankment with protection works at the entry and exit. It is suitable for cross drainage flow on relatively flat terrain & in this discharge is limited & it has negligible maintenance.
  • 10. MASANORY ARCH BRIDGE PIPE CULVERT
  • 11. SLAB BRIDGE Simplest type of construction. Adopted for small bridges and culverts. Span is between 10-20m. Concrete slab cast monolithically over longitudinal girder. No. of longitudinal girders depends upon the width of road. PLATE GIRDER BRIDGE Span ranges 10 to 60m. Can be extending up to 250m in continuous construction. TRUSS BRIDGE Span 30 to 375m in simply supported case. Span 30 to 550m in cantilever combination ca
  • 12. SLAB BRIDGE PLATE GIRDER BRIDGE TRUSS BRIDGE
  • 13. SUSPENSSION BRIDGE Made up of high tensile steel cables strung in form of a catenary to which the deck is attached by steel suspenders which are made up of steel rods/members/cables. Deck can be of timber , concrete or steel spanning across the stiffening girders transmitting loads to suspenders. CABLE STAYED BRIDGE Similar to suspenssion bridge except that there will be no suspenders in the cable stayed bridges . A number of cables are streched from support tower directly connected the decking. OTHER IMPORTANT CLASSIFICATION OF BRIDGE Based upon type of structural arrangement. I-girder bridge Plate girder bridge
  • 14. SUSPENSION BRIDGE CABLE STAYED BRIDGE
  • 15. truss girder bridge Suspenssion bridge Based upon structural action or nature of superstructure action Simply supported span bridge Continuous span bridge Cantilever bridge Arch bridge Rigid frame bridge Based upon type of connections Riveted bridge Welded bridge Bolted bridge Pinned bridge
  • 16. Based upon floor action Deck type bridge Through type bridge Semi –through type bridge or pony bridge Double deck bridge-used in rail cum road bridge Based upon movement of structural parts of the bridge Fixed(permanent) bridge Movable bridge can opened either horizontally or vetically so as allow the river or channel traffic to pass. Based upon purpose of bridge Road bridge Railway bridge Padestrain bridge
  • 17. Based upon loading Irc class aa loading bridge Irc class a loading bridge Irc class b bridge Base upon span length Culver – up to span length 6m Minor bridge – up to span length 6 to 30m. Major bridge – up to span length over 30m. LOAD FOR DESIGN OF BRIDGE 1. Dead load Aggregate weight of complete structure elements such as deck, wearing coat, parapets, stiffeners and utilities. It does not changes its direction and magnitude with respect to the passage of time.
  • 18. 2. LIVE LOAD Includes vehicle live load That are moving on the bridge. IRC has categorized standards of vehicle live load as under three following category which is- (a) IRC CLASS AA LOADING Treated as heavy loading and all NH & SH and industrial areas’s bridge are designed for only IRC class AA loading. If a bridge designed for IRC class AA loading then it will automatically satisfied IRC class A & class B loading. It has two pattern of loading (i) tracked type (ii) wheeled type (b) IRC CLASS A LOADING Generally Treated as standard loading for permanent bridges. Having eight axles with a total length of 25m.
  • 19. IRC CLASS AA LOADING IRC CLASS AA LOADING
  • 20. IRC CLASS A LOADING
  • 21. IRC CLASS B LOADING Used for temporary bridges. It is a light loading as compard to all other loading. CLASS 70R LOADING Not used in our country it is used only in US. 3.Impact load It is account for the dynamic effects of sudden loading of a vehicle on bridge structure. It is calculated by multiplying the live load with an impact factor. The impact factor is calculated as the IRC-6 suggested which are discussed below.
  • 22.
  • 23. Impact factor for IRC CLASS A loading If=A/(B+L) Where If=Impact factor A=constant( 4.5 for RCC bridge & 9.0 for STEEL bridge) B=constant (6.0 for RCC bridge & 13.5 for STEEL bridge) L= effective span Impact factor IRC CLASS AA loading & CLASS 70R loading for span < 9m (a) Tracked vehicle- 25% for span upto 5m & reducing to 10% for span upto 9m. (b) Wheeled vehicle-25% for span upto 9m. for span > 9m (a) Tracked vehicle-for RCC bridge 10% upto 40m & as per graph for span >40m . For steel bridge 10% for all span. (b) Wheeled vehicle-for RCC bridge 25% upto 12m & as per graph for span >12m. For steel bridges 25% for span upto 23m & as per graph for span > 23m.
  • 24.
  • 25. 4. Centrifugal force consider for bridge constructed on horizontal curve. Considered to act at a height of 1.2m above the level of carriage way. C=WV2 127 R Where c=centrifugal force in KN w=live in KN v=speed of vehicle in KMPH R= radius of horizontal curve in M. 5.Wind load Assumed as horizontal forces on an area which are- For DECK structure- area of floor slab and railing For a through or half through structure- area of elevation of the windward tress flows half the area of elevation above the deck slab. Considered as acting at 15m above the roadway and have the following values highway ordinary bridges – 3.0 KN per meter highway bridges carrying framework- 4.5 KN per meter.
  • 26. 6. Longitudinal forces Forces result from vehicle braking or acceletrating while travelling on bridge. As the vehicle brakes the load of the vehicle is transferred from its wheels to bridge deck. IRC specifies a longitudinal forces of 20% is appropraite of live load and the force is applied at 1.2m above the level of deck. 7.Seismic forces Depends upon geographical location of the bridge. These are the temparory forces act for the short duration. An earthquake forces is the fuction of following. (a) Dead load of structure Calculated as- F= ahW (b) Ground motion where F=horizontal forces owing to earthquake (c) Period of vibration ah=seismic coefficients for respective regions (d) Nature of soil W=DL+LL acting above the section
  • 27. Some basic points regarding WSM and LSM Working Stress Method The Stresses in an element is obtained from the working loads and compared with permissible stresses. The method follows linear stress-strain behaviour of both the materials. Modular ratio can be used to determine allowable stresses. For bridge construction in case of WSM the Modular ratio is constant 10. Material capabilities are under estimated to large extent. Factor of safety are used in working stress method. The member is considered as working stress. Ultimate load carrying capacity cannot be predicted accurately. The main drawback of this method is that it results in an uneconomical section. All kind of major structure or important structure like bridge construction & tank construction (rectangular tank & intz tank etc.) is still usually designed by only WSM. Limit State Method The stresses are obtained from design loads and compared with design strength. In this method, it follows linear strain relationship but not linear stress relationship (one of the major difference between the two methods of design). The ultimate stresses of materials itself are used as allowable stresses. The material capabilities are not under estimated as much as they are in working stress method. Partial safety factors are used in limit state method.
  • 28. T-BEAM BRIDGE This is most commonly adopted type of bridge for span range of 10 to 25m. It is so name because the main longitudinal girder are designed as T-beam which is integral part of deck slab cast monolithically with the deck slab. Simply supported T-beam spans of over 25m are rare as the dead load then becomes too heavy. However there is a bridge have single span of 35m named “ Advice bridge” in “Goa”. In other words we can say T-beam bridge is the combination of [ deck slab with longitudinal girders & cross girders ] superstructure & [piers , abutment & foundations] substructure.
  • 29. COMPONENT OF A T-BEAM BRIDGE Deck slab Cantilever portion Longitudinal girders Cross girders Abutments & piers Bearing Foundations
  • 30. Design of deck slab It is designed by either “effective width method” or by “Pigeauds curve method” as bending moment calculation. After calculation of bending moment we provide reinforcement and then do check for shear as accordance by WSM mtehod of RCC design. Normal depth of deck slab is very from 350mm to 500mm. EFFECTIVE WIDTH METHOD It is applicable when the slab is designed by assuming its a one way slab or supported only on two apposite edge or a very long slab supported on all four edge. Effective width is the width of wheel imprint on deck perpendicular to the movement of vehicle that is actually bears the load of wheel tyre it is calculated by following expressions. FOR SIMPLY SUPPORTED CASE beff.=k x(1-x/L) + bw FOR CANTILEVER CASE beff=1.2x + bw
  • 31. Where beff= effective widht of dispersion k = constant depend upon b/L (widht/length) ratio specified in IRC-6. X=Distance of center of gravity of wheel from the nearest support in case of simply supported and distance of center of gravity of wheel From the cantilever phase. in case of L= effective span of bridge in case of simply supported and clear span in case of cantilever. bw= w+2h (width of wheel + 2 thickness of wearing coat) EFFECTIVE LENGTH OF DISPERSION In the same manner as effective width of dispersion there is also a effective length of dispersion measured along the direction of movement of vehicle. calculated as- for both simply supported case as well as cantilever case dispersion length= length of tyre contact + 2(overall thickness of deck including wearing coat) LEFF.= B + 2(D+2h) where Leff.=effective length of dispersion d=overall thickness of bridge deck h=thickness of wearing coat
  • 32. Pigeauds method short span(B) & long span(L) bending moment coeeficients are read from curves developed by M. Pigeaud. Used for only 2-way slab design or slabs supported along four edges with restrained corners and subjected to symmetrically placed loads distributed over some well defined area. Curves developed for thin plates using the elastic flexural theory. However their use has been extended to concrete slab too. Poision’s ratio of 0.15 is considered. The short span(B) & long span (L) bending moment is calculated by following expressions. short span B.M.=W(m1 +0.15m2) along the widht(B) of slab. long span B.M.=W(0.15m1 +m2) along the length (L) of slab.
  • 33.
  • 34.
  • 35.
  • 36. Design of cantilever slab portion It designed by effective width method only. The cantilever slab portion slab portion usually carries the KERB , HANDRAILS , FOOTHPATH if provided and a part of carriageway. The critical section for bending moment is the vertical section at the junction of the cantilever portion and the end of longitudinal girder. The design bending moment for cantilever slab portion is calculated as the sum of 0.2 times of dead load bending moment plus 0.3 times of live load bending moment. design moment= 0.2 dead load BM + 0.3 live load BM
  • 37. Design of longitudinal girder There are 3 method of design of longitudinal girder (a) courbon’s method (b) Hendry-jaegar method (c) Morice and little version of huyon and massonnet method In india the courbon’s method is standerized for design of longitudinal girder. normal size of longitudinal girder is (300×1200)mm Courbon’s method According to his theory no flexural of transverse deck is possible because of presence of infinitely rigid diaphragms ( cross girder or cross beam) and a concentrated load instead of one pushing down only nearly girders , causes equal deflection of all girders. The design bending moment for longitudinal girder is calculated with the help of rection factor or distribution coefficient which is calculated by following expressions given by courbon.
  • 38.
  • 39. Where W=ecentric concentrated load n= no. of longitudinal girder e=ecentricity of the wheel load from center line of the deck x1=distance of girder under considerations from central axis of the beam Σx2 = sum of distance of longitudinal girders from the centre line of deck LIMITATIONS OF COURBON’S METHOD O THEORY (a) span-width ratio should be between 2 to 4. (b) Atleast five symmetrical cross girder connecting the longitudinal girders (c) The minimum depth of cross girder should be atleast ¾ depth of longitudinal girder.
  • 40. Design of cross girder Provided mainly to stiffen the girders and to reduce torssion in the exterior girders. Another function of the cross beam is to equalize the deflections of the girders carrying heavy loading with those of the girders with less loading. This is particularly important when the design loading consist of concentrated wheel loads such as IRC CLASS AA Loading to be placed in most unfavourable positions. The thickness of cross beams should not be less than the minimum thickness of the webs of longitudinal girders. The depth of the end cross girders should be such as to permit access for inspection of bearings and to facilitate positionings of jacks for lifting of superstructure for replacement of bearings. normally we use same size as that of longitudinal girders. Dead load bending moment is computed considering a trapezoidal distribution of weight of deck slab and wearing coarse. The live load bending moment is calculated as the bending moment calculated simply for a beam.
  • 41. TYPICAL EXAMPLE OF CROSS GIRDER DEAL LOAD B.M. CALCULATION
  • 42. PIERS A support of concrete or masonry for superstructure of bridge. The base of a pier may rest directly over firm round or it may be supported on piles. Center line of pier normally coincide with the center line of the superstructure. The dimensions of the top of a pier depends on distances between girder(longitudinal girder) and distance required to provide for the expansion of girder , size of bearing etc. IRC 40 gives minimum top width of pier and abutment. Basic Types of Bridge Piers
  • 43. Design loads for piers a) dead load of superstructure b) Dead load of pier c) Live load on superstructure d) Lateral forces perpendicular to centerline of superstructure (wind portion on pier above water level , presure due to water , wave action of current) e) Longitudinal forces parllel to the direction of the bridge (includes braking of vehicles , tractive force of vehicle (high in case of train)). f) Seismic force. ABUTMENTS An abutment is a structure that support one end of a bridge in other word we can say that it is a structure located at the end & at the beginning of a bridge. Functions of abutment a) Support the bridge deck at end. b) Retain the embankment of approaching road. c) Connected the approach road to the bridge deck.
  • 44. Basic Types of Bridge Abutments – Wall & Counterfort Wall Abutment Counterfor t
  • 45. Basic Types of Bridge Abutments – Open Type
  • 46. Types of Wall Abutments
  • 47. Forces acting on abutment Dead load due to superstructure Live load on superstructure Self weight of abutment Longitudinal forces (traction and boiling) Earth presure due to soil embankment Design of abutment Hieght- Kept equal to hieght of pier Abutment- provided with a better of 1 in 3 to 1 in 6 or it may be stepped down Abutment width- top width according to space needed by the single bearing and bottom width 0.4 to 0.5 times of height of abutment Length- minimum equal to width of bridges Abutment cap- thickness 450 to 600 mm. Stability of abutment It should be chack and safe against the following- Oveturning Sliding Ecentricity of resultant with respect to center of the base Maximum base presure or earth presure .
  • 48. BEARING Bearing are mechanical arrangement provided in the superstructure to transmit the load to the sub- structure. Thus it is a via media between superstructure and sub-structure which transmit the load from superstructure in such a manner that bearing stresses induced in the subset are within permissible limits. Purpose of bearings To absorb movements of girder To distribute load on a large area To keep compressive stress within safe limits To simplify the procedure in design To take up the vertical movement due to sinking of the the support. Type or category of bearing Free bearing or expansion bearing free to slide or move or roll and thus it allows longitudinal movement of girder. Fixed bearing it allows free angular movement and it does not permit any longitudinal movement of the girder
  • 49. Free bearing or expansion bearing are of following type- RC rocker expansion bearing Elastomeric bearing Steel roller –cum rocker bearing Sliding own rocker bearing Sliding plate bearing Fixed bearing are of following type- Rocker bearing Steel hinge Steel rocker bearing RC rocker fixed bearing FORCES ON BEARING (1)Reactive forces (2) longitudinal forces (3)uplift forces (4)transverse forces MATERILAS FOR BEARING (1)Cast steel (2)mild steel (3) lead (4)RCC (5)Rubber (6)Tar paper (7) Kraft paper
  • 50. BASIS FOR SELECTION OF BEARING a) High vertical load taking capability. b) Rotational capability. c) Good seismic resistance d) Overall cost (initial, maintenance) should be low. e) Capability to resist external horizontal forces. f) Aesthetic considerations.
  • 51. Typical view of complete T-Beam bridge construction arrangement REFERENCE- “D.J. VICTOR” THANK YOU (for giving your valuable time)