SlideShare a Scribd company logo
1 of 19
Lecture 7 - Concrete
Objectives:-
1.To learn the units of measurement of concrete.
2.To relate the measurement as per clauses in
SMM2
3.To determine the classification of sizes for
slabs.
Outcomes:-
1.Able to differentiate the different clauses used
for the measurement of concrete
2.Able to write down the dimensions based on
the drawings.
Unit of measurement
• Measurement to be in
m3 or volume for all
structural members.
Clause F3.3 Isolated foundation base
• 1. To identify the
footing.
• 2. To include the
number.
Foundation - Footing
Clause F3.4 - Casings
• 1. Concrete support to
hand railing.
• 2. Measurement to
include the number of
support.
Steel railing
Concrete support
Clause F3.5 ground beams
• Concrete for ground
beams must not be
group with other
members like stump
and footings.
Ground beams
Stump
Footing
Clause F.3.6 Casing to steel ground beam
• Concrete casing is
needed to provide
protection to the steel
beam.
Concrete casing
Steel beam
Clause F2,F3. 8 & 9 Beds and suspended
slabs
• Measurement of slab
shall be under the
following categories:-
• A. Not exceeding 100mm.
• B. 100mm to 150mm
• C. 150mm to 300mm.
• D. Exceeding 300mmGround floor slab
1st
. Floor slab
Clause F.3.10 Troughed slab
• Slab of this shape
must be separated
and named as
troughed slab.
• To state overall
thickness.
A (overall thickness)
b
Coffered / troughed slab
Clause F.3.11 Upstand, kerbs
• These are smaller
structures whereby
the construction
would be slower and
more laborious.
Upstand
Kerb
Coping
Low wall
Clause F.3.12 Walls
• Reinforced concrete
wall is a structure to
prevent landslide or
movement of earth to
a lower level.
Retaining wall
Kicker
Hill
Clause F.3.12 Fascia and fins.
• These are beams are
very thin in thickness
and mainly served as
decorative surface
and sun shading.
• The construction of
these beams is very
difficult due to the
thinness.
Fascia beam
Fins
Clause F.3.16 steps and staircases
• These structure is very
difficult to construct
due to the different
sizes and drops.
Staircase
Steps
Clause F.3.17 Tops and cheeks of
dormers
• As the construction of
the small structure is
in a very high level
and involved very
delicate job the cost
could be high.
Dormers
Clause F.3.19 Machine bases
• The construction of
plinth shall mean the
support of a machine
like a water pump or
the water tank
support.
Water tank
Concrete plinth
Concrete slab
Clause F.3.20 Filling to pockets.
• 1. Volume of void
exceeding 0.10m3 to
be measured in m3
and to state how
many number.
• 2. Volume less than
0.10m3 to be
enumerated
irrespective of sizes.
R.C. slab with pockets of voids to be filled.
Clause F.4.2 Joints.
• Casting of large panel
slabs shall be in panels
and the joints could
include waterstop,
expansion or
compression joints
and be measured in
meters.
R.C .slab cast in panels
A B
C D
Airport runway
• Construction of
runway for planes
must be strong and
durable.
The concrete slab must be flexible to withstand the
contraction and expansion.
Expansion joints
Clause F.7.3 Guniting
• It is a slope improvement
system to prevent the
slope from failing.
• The concrete is splayed
to the surface of the
slope and the
measurement is in m2
stating the thickness.

More Related Content

What's hot

DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMAnep Botak
 
Solid Ground Floors
 Solid Ground Floors  Solid Ground Floors
Solid Ground Floors Luke D'Arcy
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achahAisyah Asyikin
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantitiesBt Lee
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second editionBt Lee
 
Building Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSBuilding Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSJing Fan Koh
 
Industrialised Building Solution
Industrialised Building SolutionIndustrialised Building Solution
Industrialised Building SolutionLee Wan Xuan
 
Int walls finishes to list
Int walls finishes to list Int walls finishes to list
Int walls finishes to list Jeanne Hoo
 
B.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsB.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsCarmen Chan
 
Wblff (1)
Wblff (1)Wblff (1)
Wblff (1)ahmong4
 
Pwd 203 a rev2007
Pwd 203 a rev2007Pwd 203 a rev2007
Pwd 203 a rev2007shimz2287
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compileTimun Loh
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building Systemjisunfoo
 
Building Technology Project 1
Building Technology Project 1Building Technology Project 1
Building Technology Project 1zerospaces_
 

What's hot (20)

DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAMDIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
DIFFERENCE BETWEEN CONTRACT FORM JKR 203A & PAM
 
Solid Ground Floors
 Solid Ground Floors  Solid Ground Floors
Solid Ground Floors
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
Boq piling works
Boq   piling worksBoq   piling works
Boq piling works
 
industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achah
 
Ibs score
Ibs scoreIbs score
Ibs score
 
ECA form
ECA formECA form
ECA form
 
Standard bill of quantities
Standard bill of quantitiesStandard bill of quantities
Standard bill of quantities
 
Smm2 second edition
Smm2 second editionSmm2 second edition
Smm2 second edition
 
Building Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBSBuilding Technology I : Project 1 : IBS
Building Technology I : Project 1 : IBS
 
Industrialised Building Solution
Industrialised Building SolutionIndustrialised Building Solution
Industrialised Building Solution
 
Int walls finishes to list
Int walls finishes to list Int walls finishes to list
Int walls finishes to list
 
B.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building SystemsB.tech Project 1 - Industrialised Building Systems
B.tech Project 1 - Industrialised Building Systems
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
Wblff (1)
Wblff (1)Wblff (1)
Wblff (1)
 
Pwd 203 a rev2007
Pwd 203 a rev2007Pwd 203 a rev2007
Pwd 203 a rev2007
 
Eca presentation-compile
Eca presentation-compileEca presentation-compile
Eca presentation-compile
 
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATIONINDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
INDUSTRIALISED BUILDING SYSTEMS & MODULAR COORDINATION
 
Industrialised Building System
Industrialised Building SystemIndustrialised Building System
Industrialised Building System
 
Building Technology Project 1
Building Technology Project 1Building Technology Project 1
Building Technology Project 1
 

Viewers also liked

KA6564 Assignment 1
KA6564 Assignment 1KA6564 Assignment 1
KA6564 Assignment 1armada7000
 
Stucture large span area
Stucture large span areaStucture large span area
Stucture large span areaAbhishek Mewada
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle SlabAkshay Gawade
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
Quantity surveyor (ici+itd)
Quantity surveyor (ici+itd)Quantity surveyor (ici+itd)
Quantity surveyor (ici+itd)ALISON TANG
 
Excavation2014a-Lecture1
Excavation2014a-Lecture1Excavation2014a-Lecture1
Excavation2014a-Lecture1Anne Allan
 
Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Anne Allan
 
Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )Lee Pei Gie
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Anne Allan
 
Building construction ii report (1)
Building construction ii report  (1)Building construction ii report  (1)
Building construction ii report (1)Chong jiayi
 
Formwork by chakamba john
Formwork by chakamba johnFormwork by chakamba john
Formwork by chakamba johnJohn Chakamba
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantitiesalanchong88
 
How do you takeoff a staircase?
How do you takeoff a staircase?How do you takeoff a staircase?
How do you takeoff a staircase?Duc Tran Xuan
 
design of staircase
design of staircasedesign of staircase
design of staircasevasu.chawla
 
Assignment 1 Site Visit Report
Assignment 1 Site Visit ReportAssignment 1 Site Visit Report
Assignment 1 Site Visit Reportarmada7000
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of QuantitiesNatalie Reid
 

Viewers also liked (20)

How to pour concrete
How to pour concreteHow to pour concrete
How to pour concrete
 
KA6564 Assignment 1
KA6564 Assignment 1KA6564 Assignment 1
KA6564 Assignment 1
 
Formwork
FormworkFormwork
Formwork
 
Stucture large span area
Stucture large span areaStucture large span area
Stucture large span area
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
 
Folded plate structure
Folded plate structureFolded plate structure
Folded plate structure
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Quantity surveyor (ici+itd)
Quantity surveyor (ici+itd)Quantity surveyor (ici+itd)
Quantity surveyor (ici+itd)
 
Excavation2014a-Lecture1
Excavation2014a-Lecture1Excavation2014a-Lecture1
Excavation2014a-Lecture1
 
Excavation 2014a-Lecture2
Excavation 2014a-Lecture2Excavation 2014a-Lecture2
Excavation 2014a-Lecture2
 
Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )Bill of Quantities ( Door and Window )
Bill of Quantities ( Door and Window )
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3
 
Building construction ii report (1)
Building construction ii report  (1)Building construction ii report  (1)
Building construction ii report (1)
 
Formwork by chakamba john
Formwork by chakamba johnFormwork by chakamba john
Formwork by chakamba john
 
Sgp4813 measurement of quantities
Sgp4813 measurement of quantitiesSgp4813 measurement of quantities
Sgp4813 measurement of quantities
 
How do you takeoff a staircase?
How do you takeoff a staircase?How do you takeoff a staircase?
How do you takeoff a staircase?
 
design of staircase
design of staircasedesign of staircase
design of staircase
 
Stairs
StairsStairs
Stairs
 
Assignment 1 Site Visit Report
Assignment 1 Site Visit ReportAssignment 1 Site Visit Report
Assignment 1 Site Visit Report
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of Quantities
 

Similar to Concrete 2014a-Lecture7

Concrete2014a-Lecture6
Concrete2014a-Lecture6Concrete2014a-Lecture6
Concrete2014a-Lecture6Anne Allan
 
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGSEARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGSMohd Danish
 
Design example of a six storey building project report
Design example of a six storey building project reportDesign example of a six storey building project report
Design example of a six storey building project reportPraba Haran
 
Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Parham Farhadpoor
 
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGSEARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGSMohd Danish
 
Reinforced Concrete Frame Structure
Reinforced Concrete Frame Structure Reinforced Concrete Frame Structure
Reinforced Concrete Frame Structure Tantish QS, UTM
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxsydneyaugust1
 
Mat foundation
Mat foundationMat foundation
Mat foundationshuvo293
 
Design of Retaining Wall
Design of Retaining WallDesign of Retaining Wall
Design of Retaining WallAnanthakumar75
 
Types of pile according to their composition
Types of pile according to their compositionTypes of pile according to their composition
Types of pile according to their compositionMdDiluarHossain1
 

Similar to Concrete 2014a-Lecture7 (20)

Ce 6601 qb
Ce 6601 qbCe 6601 qb
Ce 6601 qb
 
Concrete2014a-Lecture6
Concrete2014a-Lecture6Concrete2014a-Lecture6
Concrete2014a-Lecture6
 
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGSEARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
 
Civil drawing detail
Civil drawing detailCivil drawing detail
Civil drawing detail
 
Design example of a six storey building project report
Design example of a six storey building project reportDesign example of a six storey building project report
Design example of a six storey building project report
 
Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1Sem 1 degree ct assignment 1
Sem 1 degree ct assignment 1
 
Water tank 1
Water tank 1Water tank 1
Water tank 1
 
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGSEARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
EARTHQUAKE SAFE CONSTRUCTION OF MASONRY BUILDINGS
 
Reinforced Concrete Frame Structure
Reinforced Concrete Frame Structure Reinforced Concrete Frame Structure
Reinforced Concrete Frame Structure
 
Boq sample
Boq sampleBoq sample
Boq sample
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
5th batch.pptx
5th batch.pptx5th batch.pptx
5th batch.pptx
 
Lesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptxLesson 3 Floor screeds _suspended floors.pptx
Lesson 3 Floor screeds _suspended floors.pptx
 
Mat foundation
Mat foundationMat foundation
Mat foundation
 
advanced construction
advanced constructionadvanced construction
advanced construction
 
Design of Retaining Wall
Design of Retaining WallDesign of Retaining Wall
Design of Retaining Wall
 
SPECIFICATION
SPECIFICATIONSPECIFICATION
SPECIFICATION
 
Formwork
FormworkFormwork
Formwork
 
Types of pile according to their composition
Types of pile according to their compositionTypes of pile according to their composition
Types of pile according to their composition
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 

Recently uploaded

ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptJohnWilliam111370
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.elesangwon
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptxmohitesoham12
 
Secure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech LabsSecure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech Labsamber724300
 
Forming section troubleshooting checklist for improving wire life (1).ppt
Forming section troubleshooting checklist for improving wire life (1).pptForming section troubleshooting checklist for improving wire life (1).ppt
Forming section troubleshooting checklist for improving wire life (1).pptNoman khan
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfManish Kumar
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdfsahilsajad201
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTSneha Padhiar
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESkarthi keyan
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Communityprachaibot
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
STATE TRANSITION DIAGRAM in psoc subject
STATE TRANSITION DIAGRAM in psoc subjectSTATE TRANSITION DIAGRAM in psoc subject
STATE TRANSITION DIAGRAM in psoc subjectGayathriM270621
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Sumanth A
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfisabel213075
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsResearcher Researcher
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSneha Padhiar
 

Recently uploaded (20)

ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptx
 
Secure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech LabsSecure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech Labs
 
Forming section troubleshooting checklist for improving wire life (1).ppt
Forming section troubleshooting checklist for improving wire life (1).pptForming section troubleshooting checklist for improving wire life (1).ppt
Forming section troubleshooting checklist for improving wire life (1).ppt
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdf
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Community
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
STATE TRANSITION DIAGRAM in psoc subject
STATE TRANSITION DIAGRAM in psoc subjectSTATE TRANSITION DIAGRAM in psoc subject
STATE TRANSITION DIAGRAM in psoc subject
 
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
Robotics-Asimov's Laws, Mechanical Subsystems, Robot Kinematics, Robot Dynami...
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdf
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending Actuators
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATIONSOFTWARE ESTIMATION COCOMO AND FP CALCULATION
SOFTWARE ESTIMATION COCOMO AND FP CALCULATION
 

Concrete 2014a-Lecture7

  • 1. Lecture 7 - Concrete Objectives:- 1.To learn the units of measurement of concrete. 2.To relate the measurement as per clauses in SMM2 3.To determine the classification of sizes for slabs. Outcomes:- 1.Able to differentiate the different clauses used for the measurement of concrete 2.Able to write down the dimensions based on the drawings.
  • 2. Unit of measurement • Measurement to be in m3 or volume for all structural members.
  • 3. Clause F3.3 Isolated foundation base • 1. To identify the footing. • 2. To include the number. Foundation - Footing
  • 4. Clause F3.4 - Casings • 1. Concrete support to hand railing. • 2. Measurement to include the number of support. Steel railing Concrete support
  • 5. Clause F3.5 ground beams • Concrete for ground beams must not be group with other members like stump and footings. Ground beams Stump Footing
  • 6. Clause F.3.6 Casing to steel ground beam • Concrete casing is needed to provide protection to the steel beam. Concrete casing Steel beam
  • 7. Clause F2,F3. 8 & 9 Beds and suspended slabs • Measurement of slab shall be under the following categories:- • A. Not exceeding 100mm. • B. 100mm to 150mm • C. 150mm to 300mm. • D. Exceeding 300mmGround floor slab 1st . Floor slab
  • 8. Clause F.3.10 Troughed slab • Slab of this shape must be separated and named as troughed slab. • To state overall thickness. A (overall thickness) b Coffered / troughed slab
  • 9. Clause F.3.11 Upstand, kerbs • These are smaller structures whereby the construction would be slower and more laborious. Upstand Kerb Coping Low wall
  • 10. Clause F.3.12 Walls • Reinforced concrete wall is a structure to prevent landslide or movement of earth to a lower level. Retaining wall Kicker Hill
  • 11. Clause F.3.12 Fascia and fins. • These are beams are very thin in thickness and mainly served as decorative surface and sun shading. • The construction of these beams is very difficult due to the thinness. Fascia beam Fins
  • 12. Clause F.3.16 steps and staircases • These structure is very difficult to construct due to the different sizes and drops. Staircase Steps
  • 13. Clause F.3.17 Tops and cheeks of dormers • As the construction of the small structure is in a very high level and involved very delicate job the cost could be high. Dormers
  • 14. Clause F.3.19 Machine bases • The construction of plinth shall mean the support of a machine like a water pump or the water tank support. Water tank Concrete plinth Concrete slab
  • 15. Clause F.3.20 Filling to pockets. • 1. Volume of void exceeding 0.10m3 to be measured in m3 and to state how many number. • 2. Volume less than 0.10m3 to be enumerated irrespective of sizes. R.C. slab with pockets of voids to be filled.
  • 16. Clause F.4.2 Joints. • Casting of large panel slabs shall be in panels and the joints could include waterstop, expansion or compression joints and be measured in meters. R.C .slab cast in panels A B C D
  • 17. Airport runway • Construction of runway for planes must be strong and durable.
  • 18. The concrete slab must be flexible to withstand the contraction and expansion. Expansion joints
  • 19. Clause F.7.3 Guniting • It is a slope improvement system to prevent the slope from failing. • The concrete is splayed to the surface of the slope and the measurement is in m2 stating the thickness.