9. Project Brief
Pinnacle
Spire
Project Name The Burj Tower
Communication (L160)
Duration 47Months (Feb. ’05 ~ Dec. ’08)
Office (L153)
Cost 876,000,000 USD
Observatory
(L123)
Owner EMAAR Properties
Residence (L108)
Floors Above 160 floors
THE BURJ TOWER
R
Height Above 800m
Usage Hotel, Residence
Hotel Residence, Office
T
Hotel (L39)
B
10. Project Brief
.Client Emaar Properties PJSC
.Consultants
Project Manager Turner Construction Int’l
Int’l.
Design Skidmore, Owings & Merill (SOM)
THE BURJ TOWER
R
Supervision Hyder Consulting
Quantity Surveyor DG Jones Int’l
Int l.
T
.Construction Period
B
01 Feb 2005 – 30 Dec 2008
11. Figures & Quantities
Some salient figures and quantities:
g q
•Total height of the tower : More than 800 M
•Gross area tower : 279,000 sq. M
•Gross area podium : 186,000 sq. M
•Total concrete quantity tower : 145,000 cubic M
145 000
THE BURJ TOWER
R
•Total concrete quantity podium : 115,000 cubic M
•Overall concrete quantity : 260,000 cubic M
T
•Overall rebar quantity : 34,000 tons
B
14. Structural Overview
Hotel R id i l
H l Residential
Floor plan
THE BURJ TOWER
B T R
Typical Floor Plan
15. Structural Overview
Tower Seismic D i
T S i i Design
• 500 year Event
y
• Wind Typically Governs
• Seismic Only Governs near Top
THE BURJ TOWER
B T R
16. Structural Overview
Predicted Wind Drift
• Location Elevation Drift
(m)
( ) (
(mm))
Top Communications +604.9 1450
• Top Office +569.7 1250
• Observatory +442.1 750
THE BURJ TOWER
R
• Top Residential +375.3 540
T
• 50 year wind event
B
17. THE BURJ TOWER
B T R Structural Overview
3D View Under Construction
18. Sequence of Work
Typical Work Sequence
wing-A
A
C-1 C-3
[Section A-A]
C-2
wing-C
A wing-
wing
B
[Work Sequence]
Level 0
Level 1
Le el -1
THE BURJ TOWER
R
3 to 5 levels below 2 levels below
Level -2
Level -3
Level -4
2 levels below
T
Level -5
5
6 to 8 levels below
Level -6 3levels below
Level -7 Wing Wing Corridor Corner Slab
Level -8 Slab Slab
B
Level -9
9 Center Lobby Slab
Nose Slab Wing Corewall Center Corewall Corner Slab
19. Sequence of Work
Work Sequence & Shoring Plan
Day 0 Day 1 Day 2 Day 3
: Con’c Pouring : Slab formwork : Slab formwork : Con’c Pouring
: Rebar Installation
: MEP
N+1
N+0
Form Form
Additional Form
N-1 Raking Shore
THE BURJ TOWER
R
Form
N-2
1/2 of
1/2 of Raking 1/2 of Raking Raking
Shore Shore Shore
T
N-3
N3
2/3 of
2/3 of Prop
N-4 Prop
1/3 of
B
2/3 of Prop
Prop
N-5
Tower Slab Formwork
20. Cranage & Hoisting
Overall Equipments Layout
. Tower Crane - 3 nos.
T/C#M1 : Favco M440D (25ton)
T/C#M2 : Favco M380D (25ton)
( )
T/C#M3 : Favco M220D (11ton)
Pump#1~#3
. Hoist - 14 cages
Phase 1 (Ground ~ L100) : H/C#1 #4 (8
Ph (G d H/C#1~#4 (8cages)
) T/C#M2 T/C#M3
Phase 2 (L100 ~ L142) : H/C#5~#6 (4 cages)
Phase 3 (L142 ~ SL2) : H/C#7 (2 cages)
Jump Hoist : Jump#1, Jump#2 (2 cages)
p p , p ( g )
H/C#3~4
H/C#3 4
THE BURJ TOWER
R
H/C#7
. Concrete Pump - 4 nos.
Pump#1~#3 (Ground Level) : High Pressure H/C#5~6
T
Pump#4 (L124) for Secondary Pumping
P #4 f S d P i
H/C#1~2
. Concrete Placing Boom - 4 nos.
CPB#1. for Center core : 32m Boom
B
T/C#M1
CPB#2~#4. for Wing core : 28m Boom
21. Cranage & Hoisting
Tower Crane – Installation Method
Con’c Placing
g
T/C#M2 T/C#M3 Boom
M380D M220D
Climbing
Core wall form
3rd Bracket
Installation
THE BURJ TOWER
R
Installation
Height : 48m
Top
collar
T
T/C#M1 :
M440D
Clamping Height
B
: 15.5 ~ 17m
Bottom
collar
22. Cranage & Hoisting
Tower Crane - Dismantling Method TO O SP R
P F I E
T/ STE E +704. 9
EL L:
SP RE LEV 8 BA
I EL SE
T/ STE E +691. 3
EL L:
SP RE LEV 7 BA
I EL SE
T/ STE E +681. 7
EL L:
SP RE LEV 6 BA
I EL SE
T/ STE E +668. 9
EL L:
SP RE LEV 5 - M ZZA
I EL E
T/ STE E +665. 7
EL L:
SP RE LEV 5 - M ZZA
I EL E
T/ STE E +659. 3
EL L:
SP RE LEV 5
I EL
T/ STE E +656. 1
EL L:
SP RE LEV 4 - M ZZA
I EL E
T/ STE E +652. 9
EL L:
Multi Step Method
p 1st Station
23
22
21
SP RE LEV 4
I EL
T/ STE E +646. 4
I
EL L:
SP RE LEV 3 - M ZZA
EL E
T/ STE E +640. 0
EL L:
20
19 SP RE LEV 3
I EL
T/ STE E +633. 6
EL L:
- 1st Station : L161
18
SP RE LEV 2 - M ZZA
I EL E
T/ STE E +627. 2
EL L:
17
16
SP RE LEV 2 - M ZZA
I EL E
T/ STE E +620. 8
EL L:
15 SP RE LEV 2
I EL
W
T/ STE E +617. 6
EL L:
SP RE LEV 1 - M ZZA
I EL E
14 T/ STE E +614. 4
EL L:
2nd
13
- Station: L99
LE VEL 162 / SP R LEV
I E
T/ SLA EL: +608. 0
B
12
11
LE VEL 161
T/ SLA EL: +601. 9
B
10
LEVEL 160
8
LEVEL 159
3nos. Recovery Crane
y LEVEL 158
7
6
5
LEVEL 157 4
3
- Favco 242R, Ogawa OT4520, Favco SDD3/10 LEVEL 156
LEVEL 155
2
1
LEVEL 154
LEVEL 153
LEVEL 152
LEVEL 151
LEVEL 150
LEVEL 149
LEVEL 148
LEVEL 147
THE BURJ TOWER
R
LEVEL 145
LEVEL 143
LEVEL 142
LEVEL 141
LEVEL 140
LEVEL 135
T
LEVEL 130
LEVEL 125
LEVEL 120
LEVEL 115
B
LEVEL 110
2nd Station
LEVEL 105
S6 S5 S4 S3 S2 S1
4500 4500 4500 4500 4500
LEVEL 100
LEVEL 99
23. Cranage & Hoisting
TO O S RE
P F PI
T/ S L EL: +704. 9
TEE
S RE LE L 8 B E
PI VE AS
T/ S L EL: +691. 3
TEE
S RE LE L 7 B E
PI VE AS
T/ S L EL: +681. 7
TEE
S RE LE L 6 B E
PI VE AS
T/ S L EL: +668. 9
TEE
S RE LE L 5 - M
PI VE EZZA N
NI E2
T/ S L EL: +665. 7
TEE
S RE LE L 5 - M
PI VE EZZA N
NI E1
T/ S L EL: +659. 3
TEE
S RE LE L 5
PI VE
T/ S L EL: +656. 1
TEE
S RE LE L 4 - M
PI VE EZZA N
NI E
T/ S L EL: +652. 9
TEE TO O SPI RE
P F
T/ STEEL EL: +704.
S RE LE L 4
PI VE
T/ S L EL: +646. 4
TEE
S RE LE L 3 - M
PI VE EZZA N
NI E
T/ S L EL: +640. 0
TEE
S RE LE L 3
PI VE
T/ S L EL: +633. 6
TEE
S RE LE L 2 - M
PI VE EZZA N
NI E2 SPI R LEVEL 8 BAS
E
T/ S L EL: +627. 2
TEE
T/ STEEL EL: +691.
S RE LE L 2 - M
PI VE EZZA N
NI E1
T/ S L EL: +620. 8
TEE
W S RE LE L 2
PI VE
T/ S L EL: +617. 6
TEE
S RE LE L 1 - M
PI VE EZZA N
NI E
T/ S L EL: +614. 4
TEE
SPI R LEVEL 7 BAS
E
LEV 162 / SPI RE LEV 1
EL EL T/ STEEL EL: +681.
T/ SLAB E +608. 0
L:
Step 1 : Main T/C Dismantling
LEV 161
EL
T/ SLAB E +601. 9
L:
10
LEVEL 160
8
LEVEL 159 SPI R LEVEL 6 BAS
E
7
T/ STEEL EL: +668.
6
LEVEL 158 SPI R LEVEL 5 - M
E
1) Main T/C Descending to L161
T/ STEEL EL: +665.
5
LEVEL 157 4
3
SPI R LEVEL 5 - M
E
T/ STEEL EL: +659.
LEVEL 156 2
SPI R LEVEL 5
E
1 T/ STEEL EL: +656.
LEVEL 155
2) Main T/C Dismantled to L99 by Favco 242R
SPI R LEVEL 4 - M
E
T/ STEEL EL: +652.
LEVEL 154
LEVEL 153
LEVEL 152 SPI R LEVEL 4
E
T/ STEEL EL: +646.
LEVEL 151
3) Dismantled Components moved to Ground LEVEL 150
LEVEL 149
LEVEL 148
SPI R LEVEL 3 - M
E
T/ STEEL EL: +640.
LEVEL 147 SPI R LEVEL 3
E
T/ STEEL EL: +633.
by Ogawa OT4520
y g LEVEL 145
Favco
THE BURJ TOWER
R
SPI R LEVEL 2 - M
E
T/ STEEL EL: +627.
LEVEL 143
LEVEL 142
LEVEL 141
242R W
SPI R LEVEL 2 - M
E
T/ STEEL EL: +620.
SPI R LEVEL 2
E
T/ STEEL EL: +617.
LEVEL 140 SPI R LEVEL 1 - M
E
T/ STEEL EL: +614.
LEVEL 162 / SPI R E
T/ SLAB EL: +608. 0
LEVEL 135
L161 LEVEL 161
T/ SLAB EL: +601. 9
10
LEVEL 130 LEVEL 160
T
8
LEVEL 159
7
LEVEL 125
6
LEVEL 158
LEVEL 120
Main T/C 5
LEVEL 157 4
3
LEVEL 115 LEVEL 156 2
B
1
LEVEL 155
LEVEL 110
LEVEL 154
LEVEL 105
S6 S5 S4 S3 S2 S1
4500 4500 4500 4500 4500
LEVEL 100
LEVEL 99
24. Cranage & Hoisting
TO O S R
P F PI E
T/ STEE EL: +704. 9
L
S R LE
PI E VEL 8 B EAS
T/ STEE EL: +691. 3
L
S R LE
PI E VEL 7 B EAS
T/ STEE EL: +681. 7
L
S R LE
PI E VEL 6 B EAS
T/ STEE EL: +668. 9
L
S R LE
PI E VEL 5 - M EZZAN N
I E2
T/ STEE EL: +665. 7
L
S R LE
PI E VEL 5 - M EZZAN N
I E1
T/ STEE EL: +659. 3
L
S R LE
PI E VEL 5
1st Station
T/ STEE EL: +656. 1
L
S R LE
PI E VEL 4 - M EZZAN N
I E
T/ STEE EL: +652. 9
L TO O SPI RE
P F
T/ STEEL EL: +704. 9
S R LE
PI E VEL 4
T/ STEE EL: +646. 4
L
S R LE
PI E VEL 3 - M EZZAN N
I E
T/ STEE EL: +640. 0
L
S R LE
PI E VEL 3
T/ STEE EL: +633. 6
L
S R LE
PI E VEL 2 - M EZZAN N
T/ STEE EL: +627. 2
L
I E2 SPI R LEVEL 8 BASE
E
T/ STEEL EL: +691. 3
S R LE
PI E VEL 2 - M EZZAN N
I E1
T/ STEE EL: +620. 8
L
W S R LE
PI E VEL 2
T/ STEE EL: +617. 6
L
S R LE
PI E VEL 1 - M EZZAN N
I E
T/ STEE EL: +614. 4
L
SPI R LEVEL 7 BASE
E
LEVE 162 / S RE LE L 1
L PI VE T/ STEEL EL: +681. 7
T/ SLAB E +608. 0
L:
Step 2 : Favco 242R Dismantling
LEVE 161
L
T/ SLAB E +601. 9
L:
LEVEL 160
LEVEL 159 SPI R LEVEL 6 BASE
E
T/ STEEL EL: +668. 9
LEVEL 158 SPI R LEVEL 5 - M
E EZ
1) Favco SDD 3/10 Installed on L161
T/ STEEL EL: +665. 7
LEVEL 157
SPI R LEVEL 5 - M
E EZ
T/ STEEL EL: +659. 3
LEVEL 156
SPI R LEVEL 5
E
T/ STEEL EL: +656. 1
LEVEL 155
2) Favco 242R Dismantled to L99 by Favco SDD3/10
SPI R LEVEL 4 - M
E EZ
T/ STEEL EL: +652. 9
LEVEL 154
LEVEL 153
LEVEL 152 SPI R LEVEL 4
E
T/ STEEL EL: +646. 4
LEVEL 151
3) Dismantled Components moved to Ground LEVEL 150
LEVEL 149
LEVEL 148
SPI R LEVEL 3 - M
E EZ
T/ STEEL EL: +640. 0
LEVEL 147 SPI R LEVEL 3
E
T/ STEEL EL: +633. 6
by Ogawa OT4520.
OT4520 LEVEL 145
THE BURJ TOWER
R
SPI R LEVEL 2 - M
E EZ
T/ STEEL EL: +627. 2
LEVEL 143
SPI R LEVEL 2 - M
E EZ
T/ STEEL EL: +620. 8
LEVEL 142
LEVEL 141
LEVEL 140
Favco 242R W SPI R LEVEL 2
E
T/ STEEL EL: +617. 6
SPI R LEVEL 1 - M
E EZ
T/ STEEL EL: +614. 4
LEVEL 162 / SPI R L
E
T/ SLAB EL: +608. 0
LEVEL 135
L161 LEVEL 161
T/ SLAB EL: +601. 9
LEVEL 130
T
Favco
LEVEL 125
SDD3/10
LEVEL 120
LEVEL 115
B
LEVEL 110
2nd Station
LEVEL 105
S6 S5 S4 S3 S2 S1
4500 4500 4500 4500 4500
LEVEL 100
LEVEL 99