ITS Design Manual Overview
Purpose• So designers can create concept to  complete plan set and spec package for  MDOT ITS projects or other municipal ...
Typical ITS design elements• Electrical power location• Fiber optic communications infrastructure• Dynamic Message Signs (...
Design Manual Organization•   1    –    Introduction•   2    –    General Design Guidelines•   3     –   Power Source Desi...
Introduction• Project Development Process• Use SEMP for SEA then Design Manual  for plan development• SEMP refers to proje...
General design guidelinesProvides overall guidance for preliminary placement – Details in Sections 3 – 12• Concept Develop...
Deployment guidance                      7
General design guidelines steps• General Device Placement• Before Field Visit• While On Field Visit• Guardrail Considerati...
Power Source Design• Starts in Concept phase• Early Coordination Required• What to show on plans• What are demarcation loc...
ITS Communications Design• Conduit / Fiber Optic Cable Placement Guidelines  •   Freeways  •   Urban Arterials  •   Rural ...
Fiber Allocation• Communications Path• Strategies:  • Existing vs. New Device Cases; Daisy Chain  • How Many Drops / Pair•...
Communication Design Examples                              Typical PTZ Camera                           Connected to encod...
ITS Device Design Sections• Goal / Concept• Gives Special Provision #, and refers to plan  sheets / detail sheets that may...
TMC Design• Equipment Room Layout• Equipment Rack Elevations and  Equipment Interconnections• Operations Area Layout• Elec...
Smart Work Zones• Guidelines and Process• Special Provisions
PS&E Assembly• Includes plans, standard specs, all special provisions,  NTBs, construction cost estimates, all approved  a...
ROADWAY/BRIDGE DESIGN TASKS                                 ITS DESIGN TASKS    PHASE A: RIGHT-OF-WAY PLANS              S...
SHEET DESCRIPTION                                                             WORKING NUMBER(S)Title Sheet                ...
DMS Details – includes elevation- and plan-view clearance diagrams        DMS-1, DMS-2… DMS-n   and other details for each...
Appendices• A – Plans Checklist – What is needed  for 50% - 100% Submittals• B – Model Sheets• C – Typical Label Formats• ...
Upcoming SlideShare
Loading in …5
×

MDOT ITS Design Manual

1,068 views

Published on

Presentation on the development of a design manual for Mississippi Dept of Transportation's Intelligent Transportation Systems group.

Published in: Technology, Business
0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total views
1,068
On SlideShare
0
From Embeds
0
Number of Embeds
5
Actions
Shares
0
Downloads
10
Comments
0
Likes
0
Embeds 0
No embeds

No notes for slide
  • General Device Placement: Following concept review – conduct field inspectionReview project location, device locations, conduit routing, power sourcesDevice placement criteria:Field conditionsMaintenance accessibilityAbility to route comm to devicesPower accessibilityDevice protection – existing guardrailMotorist protection (addition of guardrail or use of breakaway supports) Before Field Visit:To Do list to optimize data recordingA copy of complete set of plans (base map)Check with District office on any prior roadway plans or aerial photographyContact MDOT Project Manager to arrange access to existing facilitiesWhile on Field Visit:Safety first – high visibility clothingConfirm existing device locations – i.e. poles, cabinets, signs, overhead structures and other fixed roadway features that may be used as a proposed device reference pointNote guardrail length at candidate device locationsDon’t use small signs or guardrail ends as references as they may be damageUse mile markersReference signs and significant interchange signs should be noted and displayed on plans.Guardrail ConsiderationsTry to place devices such that new guardrail not needed. Follow AASHTO Roadside Design Manual and MDOT Roadway Design Manual for guardrail design. Situations that occur on ITS Freeway Projects: Extending Existing GuardrailClosing the gap between two runs of guardrailShortening the guardrail post spacingNew strain pole placed behind existing guardrail – verify existing guardrail meets all current standardsMust consider existing object that is being protected and new support to be installed. The appropriate length needs to be designed both upstream and downstream of the objectsWhen Guardrail is extended the anchor at the end is removed, new guardrail added and new anchor must be installed to current standards.If new guardrail is close to upstream or downstream existing – make judgment on whether closing the gap to create one continuous guardrail is appropriateShortening the post spacing – the offset behind guardrail to pole or object should be 4 ft or more to allow for deflectionIf offset can't be achieved review standards to determine allowable min post spacingIn extreme cases a barrier wall may be required.
  • Coordinate early with power companies on power source locationsWhat to show on plans Power source location and POW routing on plans - Show station for proposed power service locationThis power service location is the Demarc. b/t MDOT and the power company
  • Placement Guidelines give more of an overviewField Location Considerations gives details on spacing, #s, etc. - specific requirements that affect the number and way things are shown on the plan sheets. These sections are included throughout the manual in chapters of the other devices / ITS components
  • Goal / Concept – what the device is for and how it fits in with MDOT operations – information that is helpful to the designer when doing an ITS design. Includes placement Guidelines for the three different area types and additional field location consideration that should be used for placement.
  • Contract Plans Include:Content, Sequencing & NumberingProject IDRevisionsModel SheetsStandard LegendStandard Details
  • Typical Workflow:ITS design may be standalone or incorporated into larger set of plansTypical workflow applicable for standalone ITS projects but also shows how ITS design is integrated into development of MDOT roadway/bridge projects.
  • MDOT ITS Design Manual

    1. 1. ITS Design Manual Overview
    2. 2. Purpose• So designers can create concept to complete plan set and spec package for MDOT ITS projects or other municipal ITS projects.• Uniform guidelines and design criteria for ITS elements implemented on MS urban freeways, rural freeways, urban arterials and rural roadways.• Manual doesn’t address specific details designers encounter, so must confirm assumptions with ITS Program Manager.
    3. 3. Typical ITS design elements• Electrical power location• Fiber optic communications infrastructure• Dynamic Message Signs (DMS)• Closed-Circuit Television (CCTV) system• Radar Detection System (RDS)• Video Detection System (VDS)• Road Weather Information System (RWIS)• Highway Advisory Radio (HAR)• Communications Hut building and equipment• Transportation Management Center (TMC) equipment
    4. 4. Design Manual Organization• 1 – Introduction• 2 – General Design Guidelines• 3 – Power Source Design and Placement• 4 – ITS Communications Design• 5 – Dynamic Message Sign Design• 6 – Closed Circuit Television System (CCTV) Design• 7 – Radar Detection System Design• 8 – Video Detection System (VDS) Design• 9 – ROAD Weather Information System Design• 10 – Highway Advisory Radio Design• 11 – HUT Building Design• 12 – HUT Equipment Design• 13 – Traffic Management Center Design• 14 - Smart Work Zones• 15 – PS&E Assembly for ITS Projects• 16 – Appendices
    5. 5. Introduction• Project Development Process• Use SEMP for SEA then Design Manual for plan development• SEMP refers to project development process: • 1) Develop Concept of Operations • 2) Develop system requirements • 3) Develop Project SEA • 4) Detailed Design – this manual• Steps in Chapter 14 – key are design concept and SEA
    6. 6. General design guidelinesProvides overall guidance for preliminary placement – Details in Sections 3 – 12• Concept Development • Meet w/ District & ITS staff for scope and limits. • Research other planned projects and coordinate with others • Use aerials or plan sheets showing existing alignment and can obtain field control for scaling• Concept Review
    7. 7. Deployment guidance 7
    8. 8. General design guidelines steps• General Device Placement• Before Field Visit• While On Field Visit• Guardrail Considerations
    9. 9. Power Source Design• Starts in Concept phase• Early Coordination Required• What to show on plans• What are demarcation locations• When you may need transformer• Urban vs. Rural area Considerations• Verify obstacles for routing
    10. 10. ITS Communications Design• Conduit / Fiber Optic Cable Placement Guidelines • Freeways • Urban Arterials • Rural • Other Agencies • Wireless and Least Broadband• Field Location Considerations for Fiber / Conduit • Cable Pull boxes and Electrical Pull Boxes• Options • Cable Type, Construction, Fiber Mode, Count, Reel to Reel Splicing, Conduit Types• Fiber Allocation• Communications Design Examples
    11. 11. Fiber Allocation• Communications Path• Strategies: • Existing vs. New Device Cases; Daisy Chain • How Many Drops / Pair• Which Fibers are Used• Switch Selection ITS Field HUT/Control Drop Cable Trunk Cable Device Center
    12. 12. Communication Design Examples Typical PTZ Camera Connected to encoder and IP network P T Z SP 650 Composite Cable Power Data (232/422/485) Video Surge Block Video Encoder DATA SP 662 Network Cable Switch Spare Jumper spliced to (A or B) Rose and Aqua on Orange SP 658 trunk buffer Type 5 Pull box 12 count drop cable splice to orange trunk Fiber Trunk (72 SM Standard)
    13. 13. ITS Device Design Sections• Goal / Concept• Gives Special Provision #, and refers to plan sheets / detail sheets that may be required• Placement Guidelines • Urban Freeways • Urban Arterial Streets and Highways • Rural• Field Location Considerations• Additional Sections for additional documentation as needed (DMS Types for Example)
    14. 14. TMC Design• Equipment Room Layout• Equipment Rack Elevations and Equipment Interconnections• Operations Area Layout• Electrical and Environmental Infrastructure• Construction Coordination
    15. 15. Smart Work Zones• Guidelines and Process• Special Provisions
    16. 16. PS&E Assembly• Includes plans, standard specs, all special provisions, NTBs, construction cost estimates, all approved agreements with railroads, utilities, and municipalities, the proposal assembly and the utility and ROW certificates.• Ch 15 of Roadway Design Manual• Typical Workflow• Contract Plans• Specs • Special Provisions • NTBs• Cost Estimates• ITS-Related Permits & MOAs/MOUs
    17. 17. ROADWAY/BRIDGE DESIGN TASKS ITS DESIGN TASKS PHASE A: RIGHT-OF-WAY PLANS SYSTEMS ENGINEERING & PRELIMINARY ITS PLANSAttend Roadway/Bridge Scoping Meeting Attend ITS Scoping Meeting w/ ITS Program DirectorPrepare/Submit Conceptual Plans Prepare/Submit Draft Systems Engineering Analysis (SEA)Attend Conceptual Plans Review Meeting Prepare/Submit Draft Preliminary (50%) ITS Plans *, Specifications List and Planning-Level Const. Cost EstimatePrepare/Submit Preliminary R.O.W. Plans Attend Review Meeting w/ ITS Program DirectorPrepare/Submit Field Inspection Plans Prepare/Submit Final SEA & Preliminary (50%) ITS Plans *, Specifications List and Planning-Level Const. Cost EstimateAttend Field Inspection Coordinate with ITS Program Director to develop all required permits (e.g., rail crossings) and MOUs with other agenciesPrepare/Submit Final R.O.W. Plans If above tasks are not completed in conjunction with Phase A: Right-of-Way Plans, the designer shall complete within first 90 days of Phase B. If a stand-alone ITS project, the designer shall complete all tasks in accordance with the mutually agreed project schedule. PHASE B: CONTRACT PLANS FINAL ITS PLANS & SPECIFICATIONSAttend Roadway/Bridge Design ConferencePrepare/Submit Office Review Plans Prepare/Submit ITS Office Review Plans, Specs. & Estimate (95% Submittal)Attend Roadway/Bridge Office Review Attend ITS Office Review w/ ITS Program DirectorPrepare/Submit Final Contract Plans Prepare/Submit Final ITS Plans *, Specifications & Estimate(Roadway/Bridge PS&E Assembly) (PS&E Assembly)
    18. 18. SHEET DESCRIPTION WORKING NUMBER(S)Title Sheet -Detailed Index & ITS Legend DI-1General Notes GN-1Summary of Quantities – recap of all project quantities SQ-1, SQ-2… SQ-nEstimated Quantities – sheet-by-sheet & other special qty. tabulations EQ-1, EQ-2… EQ-nProject Location Plan – serves as key map for ITS Plan Sheets LP-1ITS Plan Sheets: Mainline – identify route/street name and station limits ITS-1, ITS-2… ITS-n Additional route/street names and station limits, as required ITS-p, ITS-q… ITS-zSpecial Design Sheets: Aerial-Supported Conduit – structure attachment details ASC-1, ASC-2… ASC-n Cabinet Details – details for Type A, B or C cabinets, where req’d. CAB-1, CAB-2… CAB-n CCTV Details – details for pole- or structure-mounted CCTV cameras CCTV-1, CCTV-2… CCTV-n DMS Details – includes elevation- and plan-view clearance diagrams DMS-1, DMS-2… DMS-n and other details for each overhead and roadside DMS installation Erosion Control Plan – misc. notes/details, as req’d. by project scope EC-1, EC-2… EC-n Equipment Details – structure attachment details ED-1, ED-2… ED-n Fiber Optic Details – includes details for conduit trenching & boring; FO-1, FO-2… FO-n
    19. 19. DMS Details – includes elevation- and plan-view clearance diagrams DMS-1, DMS-2… DMS-n and other details for each overhead and roadside DMS installation Erosion Control Plan – misc. notes/details, as req’d. by project scope EC-1, EC-2… EC-n Equipment Details – structure attachment details ED-1, ED-2… ED-n Fiber Optic Details – includes details for conduit trenching & boring; FO-1, FO-2… FO-n pull boxes; termination cabinets; FO cable splicing, storage & mgmt. HAR Details – coverage area, system details & sign details HAR-1, HAR-2… HAR-n Electrical Details – misc. notes/details pertaining to power service POW-1, POW-2… POW-n RDS Details – pole- and structure-mounted radar detector details RDS-1, RDS-2… RDS-n Traffic Control Plan – misc. notes/details, as req’d. by project scope TC-1, TC-2… TC-n Traffic Control Details – misc. sheets furnished by RWD Division TCP-__ Other detail sheets – as required by project scope -Standard Roadway Design and/or Bridge Design Drawings: Note: Standard drawings to be chosen from list, based on project scope. -
    20. 20. Appendices• A – Plans Checklist – What is needed for 50% - 100% Submittals• B – Model Sheets• C – Typical Label Formats• D – Special Provisions (latest at time of design manual published version)• E – Example Notice to Bidder Documents

    ×